SlideShare a Scribd company logo
1 of 3
Download to read offline
M1400 (Blue Devil 2) Airship Fact Sheet

1. The M1400 is the host aircraft for the Blue Devil 2 (BD2) sensor-to-sensor cueing
   and on-board processing payload. It the most complex U.S. airship ever built, and
   the largest U.S. airship (370’ long) built in over 50 years. The BD2 Program was
   initiated to provide a persistent intelligence, surveillance, and reconnaissance (ISR)
   capability to our Warfighters—over multiple days airborne vice hours currently flown
   by manned and unmanned ISR aircraft. It has the potential to be more than an
   order of magnitude more cost-effective than current ISR air and spacecraft. It's
   capabilities and potential as an ISR, comms relay, surrogate satellite, and/or other
   critical airborne functions are unmatched. The Blue Devil 2 Airship won the 2011
   Popular Science “Best of What's New” award. It is currently under contract by the
   U.S. Air Force.

2. From independent assessments, the prime contractor, Mav6 LLC, and its
   employees have performed exceptionally well, and in spite of the many challenges
   designing, developing, and building a new aircraft, they have accomplished an
   extraordinary feat—Mav6 will have gone from a clean sheet concept to first flight of
   the world’s largest UAV in less than two years.

3. The BD2 program is currently about 12 percent over budget, and projected to take
   approximately 8 months more than originally estimated to first flight. For a
   developmental aircraft this is an impressive accomplishment considering nominal
   ISR and UAV aircraft development programs take 4-5 years to go from design to
   first flight; are often years late; and significantly over cost. The BD2 program is
   approximately 90-95 percent complete, and first flight is projected to be NLT 31
   August 2012 with an additional $3M cost. To “deflate and crate” the M1400—
   essentially destroying it—will cost $2.6M. Even if it takes to September or October
   2012, as some in the Air Force believe it may take to get to first flight, it would cost
   less than $5M to get to that point. That would allow a demonstration of the
   capabilities and viability of today’s airship technology after having spent $143M+ on
   the entire program, and $65M on the M1400 airship development.

4. The initial BD2 contract was awarded to Mav6 in October 2010 for $137M from the
   Army Engineering Research & Development Center for a specific set of
   requirements. The program transitioned to the Air Force over the period from
   November 2010 to March 2011. At that time most of the contract dollars shifted to
   the Air Force, and an undefinitized contract for $86.2M was awarded from the Big
   Safari Systems Group (BSSG) program office. There was a 60-day delay in funding
   during this transition. That transition caused slips to the program schedule due to
   the associated delay in issuing key subcontracts to vendors and teammates.
   During this transition period and through July 2011 there were numerous changes
   and additions made by the BSSG to the BD2 requirements that included more
   stringent FAA airship certification than in the original contract or budgeted.
5. After the 60 day Army to Air Force transition funding delay, the Air Force did not
   definitize the BD2 contract with Mav6 for 11 months (in violation of the Federal
   Acquisition regulations). That created many difficulties for Mav6, a small business,
   due to incremental funding over that period. This caused BD2 programmatic
   disruptions, and on many occasions put Mav6 and their subcontractors at risk of a
   $3-4M loss. Additionally, as a result of Air Force delays in contract definitization,
   Mav6 was unable to collect profit for a period of 12 months, and often performed
   work at risk of losing profit to prevent having to stop work on the program. This was
   a major hardship for a small company, but indicates the degree of their commitment
   to provide this game-changing capability to the Department of Defense (DOD).

6. There were numerous attempts to terminate the program by the Air Force during the
   contract transition period from the Army to the Air Force. It is also important to note
   that the Air Force has openly stated they have no requirement for an airship and
   have exhibited actions to stop the program since early Fall of 2011. This is difficult
   to understand given that the M1400 airship is a lower cost, and much more
   effective, ISR solution relative to the more expensive Life Cycle Costs (LCC) and
   limited integration of sensors of existing fixed-wing ISR aircraft. In terms of “ISR
   payload times endurance” the BD2 can be more than 40 times more effective than
   the fixed-wing UAVs now being used to wide acclaim. The BD2 program survived
   through support from the Congress who understood the capability and value
   proposition potential of BD2.

7. Some delays in the program can be attributed to the research and development
   nature of building the world’s most complex UAV. It has progressed from a concept
   in October 2010 to 90-95 percent complete by May 2012. Specifically, the M1400
   has experienced the following technical challenges: 1) production and testing of the
   four 40 foot by 30 foot tailfins. The tailfins recently (9 May 2012) passed a FAA test
   for 50 mph flight and were scheduled for testing to the full 80 mph on 30 May 2012;
   2) development and integration of the vehicle and flight control systems that include
   6 engines of three different types, and 26 airship flight control valves that are 7-8
   times the complexity of a large fixed-wing UAV (software delivery for the flight
   control system is 31 May 2012); and 3) integration of the numerous electrical boxes
   and wiring harnesses associated with the vehicle and flight control systems for a
   370 foot long aircraft (these boxes and harnesses are to be completed by 15-30
   June 2012.

8. In Jan 2012, Mav6 was accomplishing final development testing of the most robust
   onboard multi-intelligence payload architecture built for a UAV when the mission
   payload portion of the program was arbitrarily terminated by the Air Force. This
   leading-edge architecture designed by Mav6 included processing of six sensors
   (SIGINT, EO and IR) and the raw data and meta-data storage for these sensors in
   an innovative modular structure enabling rapid exchange of sensors to achieve ISR
   tailoring for changing situations. This combination of numbers of multi-intelligence
   sensors, open integration architecture, and modularity of capability to achieve
sensor-to-sensor tipping and cueing is a first for airborne ISR and a set of
    capabilities long sought after by the Department of Defense. It also included a
    SatCom data link, two direct downlink common data links, laser communications
    and Vortex/Rover that allowed access to the data from individual teams on the
    ground.

9. An independent U.S. government team spent 14-17 May 2012 viewing and
   evaluating all aspects of the M1400 airship in its location in North Carolina. The
   feedback after their evaluation of the airship was extremely positive citing
   exceptional architecture, excellent quality of workmanship and nothing
   insurmountable in getting to first flight and beyond.

10. On 23 May 2012 the Air Force issued a letter of direction to “deflate and crate” the
    M1400 by 30 Jun 2012. This is an arbitrary stop work date as approximately $55
    million remains in the FY12 DOD budget specified for BD2/M1400 development,
    demonstration, and deployment.

    Given the approximately $3-5 million required to get BD2 to first flight (2-3 percent
    of total cost already spent and approximately 5-9 percent of remaining BD2 FY12
    available funds in FY12 budget), and its potential to demonstrate over an order of
    magnitude increase in cost-effectiveness delivering ISR relative to conventional
    aircraft and space systems, OSD should work with Congress to move the program
    from the Air Force to another sponsor along with the $55M in the FY12 budget
    specified for BD2. These dollars will complete development and integration of the
    airship and a mission payload package enabling a full CONUS operational
    capabilities demonstration for one year.

    Acting AT&L Secretary Frank Kendall recently stated that DoD needs to overcome
    the inertia of "old think," and look at prototyping and experimentation to explore new
    technologies and capabilities that they enable. The M1400 airship equipped with
    any variety of payloads has the potential to do just that. Without a demonstration of
    its potential, deflating and destroying it, would be a significant lost opportunity for
    the Department of Defense, the American taxpayers, and our Warfighters.


    	
  

More Related Content

Viewers also liked

USCG Operations i the Arctic
USCG Operations i the ArcticUSCG Operations i the Arctic
USCG Operations i the Arctic
ICSA, LLC
 
Air Vice Marshal John Blackburn on 21st Century Force Design
Air Vice Marshal John Blackburn on 21st Century Force DesignAir Vice Marshal John Blackburn on 21st Century Force Design
Air Vice Marshal John Blackburn on 21st Century Force Design
ICSA, LLC
 
Brigadier General Chris Mills, Australian Army, New Approaches to Air Land In...
Brigadier General Chris Mills, Australian Army, New Approaches to Air Land In...Brigadier General Chris Mills, Australian Army, New Approaches to Air Land In...
Brigadier General Chris Mills, Australian Army, New Approaches to Air Land In...
ICSA, LLC
 

Viewers also liked (20)

Second Nuclear Age
Second Nuclear AgeSecond Nuclear Age
Second Nuclear Age
 
Learning from the F-16 Experience to Choose the Next Danish Combat Aircraft
Learning from the F-16 Experience to Choose the Next Danish Combat AircraftLearning from the F-16 Experience to Choose the Next Danish Combat Aircraft
Learning from the F-16 Experience to Choose the Next Danish Combat Aircraft
 
Preparing, Engaging and Prevailing in 21st Century Conflict
Preparing, Engaging and Prevailing in 21st Century ConflictPreparing, Engaging and Prevailing in 21st Century Conflict
Preparing, Engaging and Prevailing in 21st Century Conflict
 
Services
ServicesServices
Services
 
USCG Operations i the Arctic
USCG Operations i the ArcticUSCG Operations i the Arctic
USCG Operations i the Arctic
 
Airbus Defence and Space Perspective on Technological Development, June 2016
Airbus Defence and Space Perspective on Technological Development, June 2016Airbus Defence and Space Perspective on Technological Development, June 2016
Airbus Defence and Space Perspective on Technological Development, June 2016
 
Rear Admiral Kevin Scott
Rear Admiral Kevin ScottRear Admiral Kevin Scott
Rear Admiral Kevin Scott
 
Major General (Retired) Goldfein Presentation to Williams Foundation Seminar ...
Major General (Retired) Goldfein Presentation to Williams Foundation Seminar ...Major General (Retired) Goldfein Presentation to Williams Foundation Seminar ...
Major General (Retired) Goldfein Presentation to Williams Foundation Seminar ...
 
Brigadier Chris Mills on the future of Air-Land integration
Brigadier Chris Mills on the future of Air-Land integrationBrigadier Chris Mills on the future of Air-Land integration
Brigadier Chris Mills on the future of Air-Land integration
 
Professor Jakobsen on the Danish Way of War
Professor Jakobsen on the Danish Way of WarProfessor Jakobsen on the Danish Way of War
Professor Jakobsen on the Danish Way of War
 
Bold Alligator 2014: Composite Forces
Bold Alligator 2014: Composite ForcesBold Alligator 2014: Composite Forces
Bold Alligator 2014: Composite Forces
 
L3 Presentation at Williams Foundation Seminar on New Approaches to Air-Land ...
L3 Presentation at Williams Foundation Seminar on New Approaches to Air-Land ...L3 Presentation at Williams Foundation Seminar on New Approaches to Air-Land ...
L3 Presentation at Williams Foundation Seminar on New Approaches to Air-Land ...
 
Unmanned aerial systems
Unmanned aerial systemsUnmanned aerial systems
Unmanned aerial systems
 
Air Vice Marshal John Blackburn on 21st Century Force Design
Air Vice Marshal John Blackburn on 21st Century Force DesignAir Vice Marshal John Blackburn on 21st Century Force Design
Air Vice Marshal John Blackburn on 21st Century Force Design
 
Rockwell Collins Presentation to Williams Foundation Seminar on Air-Land Inte...
Rockwell Collins Presentation to Williams Foundation Seminar on Air-Land Inte...Rockwell Collins Presentation to Williams Foundation Seminar on Air-Land Inte...
Rockwell Collins Presentation to Williams Foundation Seminar on Air-Land Inte...
 
Magic Carpet Landing System for F-18s
Magic Carpet Landing System for F-18sMagic Carpet Landing System for F-18s
Magic Carpet Landing System for F-18s
 
Airbus Defence and Space on UAS systems, June 2016
Airbus Defence and Space on UAS systems, June 2016Airbus Defence and Space on UAS systems, June 2016
Airbus Defence and Space on UAS systems, June 2016
 
NH90 Briefing, June 2016
NH90 Briefing, June 2016NH90 Briefing, June 2016
NH90 Briefing, June 2016
 
A330 MRTT Briefing, June 2016
A330 MRTT Briefing, June 2016A330 MRTT Briefing, June 2016
A330 MRTT Briefing, June 2016
 
Brigadier General Chris Mills, Australian Army, New Approaches to Air Land In...
Brigadier General Chris Mills, Australian Army, New Approaches to Air Land In...Brigadier General Chris Mills, Australian Army, New Approaches to Air Land In...
Brigadier General Chris Mills, Australian Army, New Approaches to Air Land In...
 

Similar to M1400 airship fact_sheet_25_may_12v2

GAO Report US Congress September 2013
 GAO Report US Congress September 2013 GAO Report US Congress September 2013
GAO Report US Congress September 2013
Dmitry Tseitlin
 
Rapid Development of a Rotorcraft UAV System - AHS Tech Specialists Meeting 2005
Rapid Development of a Rotorcraft UAV System - AHS Tech Specialists Meeting 2005Rapid Development of a Rotorcraft UAV System - AHS Tech Specialists Meeting 2005
Rapid Development of a Rotorcraft UAV System - AHS Tech Specialists Meeting 2005
Mark Hardesty
 
Adv_Low_Vis_Tech_B_English
Adv_Low_Vis_Tech_B_EnglishAdv_Low_Vis_Tech_B_English
Adv_Low_Vis_Tech_B_English
Brian O'Donnell
 
HighSpeed_Stealthy_PayloadFocused_VTOL_UAV
HighSpeed_Stealthy_PayloadFocused_VTOL_UAVHighSpeed_Stealthy_PayloadFocused_VTOL_UAV
HighSpeed_Stealthy_PayloadFocused_VTOL_UAV
Michael C. Becker
 
Executive Transport Detatchment Sigonella
Executive Transport Detatchment SigonellaExecutive Transport Detatchment Sigonella
Executive Transport Detatchment Sigonella
kingstonmj
 
End of Semester Design Report Final Version
End of Semester Design Report Final VersionEnd of Semester Design Report Final Version
End of Semester Design Report Final Version
Daniel Worts
 
Uas news digest (10 may 11)
Uas news digest  (10 may 11)Uas news digest  (10 may 11)
Uas news digest (10 may 11)
hagentd
 
A review of unmanned aerial vehicle and their morphing concepts evolution and
A review of unmanned aerial vehicle and their morphing concepts evolution andA review of unmanned aerial vehicle and their morphing concepts evolution and
A review of unmanned aerial vehicle and their morphing concepts evolution and
IAEME Publication
 

Similar to M1400 airship fact_sheet_25_may_12v2 (20)

GAO Report US Congress September 2013
 GAO Report US Congress September 2013 GAO Report US Congress September 2013
GAO Report US Congress September 2013
 
Rapid Development of a Rotorcraft UAV System - AHS Tech Specialists Meeting 2005
Rapid Development of a Rotorcraft UAV System - AHS Tech Specialists Meeting 2005Rapid Development of a Rotorcraft UAV System - AHS Tech Specialists Meeting 2005
Rapid Development of a Rotorcraft UAV System - AHS Tech Specialists Meeting 2005
 
Adv_Low_Vis_Tech_B_English
Adv_Low_Vis_Tech_B_EnglishAdv_Low_Vis_Tech_B_English
Adv_Low_Vis_Tech_B_English
 
OnYourWing0002_eng
OnYourWing0002_engOnYourWing0002_eng
OnYourWing0002_eng
 
Usdod road map_2007-2032
Usdod road map_2007-2032Usdod road map_2007-2032
Usdod road map_2007-2032
 
Dod Unmanned Systems Roadmap 2007-2032
Dod Unmanned Systems Roadmap 2007-2032Dod Unmanned Systems Roadmap 2007-2032
Dod Unmanned Systems Roadmap 2007-2032
 
HighSpeed_Stealthy_PayloadFocused_VTOL_UAV
HighSpeed_Stealthy_PayloadFocused_VTOL_UAVHighSpeed_Stealthy_PayloadFocused_VTOL_UAV
HighSpeed_Stealthy_PayloadFocused_VTOL_UAV
 
Eye on Defence April 2018
Eye on Defence April 2018Eye on Defence April 2018
Eye on Defence April 2018
 
Market Assessment of Commercial Supersonic Aviation
Market Assessment of Commercial Supersonic AviationMarket Assessment of Commercial Supersonic Aviation
Market Assessment of Commercial Supersonic Aviation
 
Executive Transport Detatchment Sigonella
Executive Transport Detatchment SigonellaExecutive Transport Detatchment Sigonella
Executive Transport Detatchment Sigonella
 
Coming Late to the Party - Getting to Green on the Fly
Coming Late to the Party - Getting to Green on the FlyComing Late to the Party - Getting to Green on the Fly
Coming Late to the Party - Getting to Green on the Fly
 
Global Defense MRO - Air Platforms Market Report
Global Defense MRO - Air Platforms Market ReportGlobal Defense MRO - Air Platforms Market Report
Global Defense MRO - Air Platforms Market Report
 
Pratyaksha news
Pratyaksha newsPratyaksha news
Pratyaksha news
 
End of Semester Design Report Final Version
End of Semester Design Report Final VersionEnd of Semester Design Report Final Version
End of Semester Design Report Final Version
 
Eye on defence April 2017
Eye on defence April 2017Eye on defence April 2017
Eye on defence April 2017
 
2016 Next Gen ISR Velocity Group Presentation
2016 Next Gen ISR Velocity Group Presentation2016 Next Gen ISR Velocity Group Presentation
2016 Next Gen ISR Velocity Group Presentation
 
Gulfstream Aerospace
Gulfstream AerospaceGulfstream Aerospace
Gulfstream Aerospace
 
Uas news digest (10 may 11)
Uas news digest  (10 may 11)Uas news digest  (10 may 11)
Uas news digest (10 may 11)
 
FY2016 F-35 SAR
FY2016 F-35 SARFY2016 F-35 SAR
FY2016 F-35 SAR
 
A review of unmanned aerial vehicle and their morphing concepts evolution and
A review of unmanned aerial vehicle and their morphing concepts evolution andA review of unmanned aerial vehicle and their morphing concepts evolution and
A review of unmanned aerial vehicle and their morphing concepts evolution and
 

More from ICSA, LLC

More from ICSA, LLC (20)

Jack Rowley on USV Technologies
Jack Rowley on USV TechnologiesJack Rowley on USV Technologies
Jack Rowley on USV Technologies
 
Team osprey
Team ospreyTeam osprey
Team osprey
 
Presentation By Hugh Fraser
Presentation By Hugh FraserPresentation By Hugh Fraser
Presentation By Hugh Fraser
 
Presentation richard czumak
Presentation richard czumakPresentation richard czumak
Presentation richard czumak
 
Presentation By Air Vice Marshal (Retd.) Chris Deeble
Presentation By Air Vice Marshal (Retd.) Chris DeeblePresentation By Air Vice Marshal (Retd.) Chris Deeble
Presentation By Air Vice Marshal (Retd.) Chris Deeble
 
BG langford Presentation at Williams Foundation seminar October 24 2019
BG langford Presentation at Williams Foundation seminar October 24 2019BG langford Presentation at Williams Foundation seminar October 24 2019
BG langford Presentation at Williams Foundation seminar October 24 2019
 
AIRCDRE Phil Gordon on the Changing Character of Manouvre
AIRCDRE Phil Gordon on the Changing Character of ManouvreAIRCDRE Phil Gordon on the Changing Character of Manouvre
AIRCDRE Phil Gordon on the Changing Character of Manouvre
 
A Historical Perspective on Manoeuvre
A Historical Perspective on ManoeuvreA Historical Perspective on Manoeuvre
A Historical Perspective on Manoeuvre
 
Rebuild of Conventional Forces and implications for Training
Rebuild of Conventional Forces and implications for TrainingRebuild of Conventional Forces and implications for Training
Rebuild of Conventional Forces and implications for Training
 
Rebuild of Conventional Forces
Rebuild of Conventional ForcesRebuild of Conventional Forces
Rebuild of Conventional Forces
 
GATR HADR Efforts
GATR HADR EffortsGATR HADR Efforts
GATR HADR Efforts
 
Wing Commander Alison MacCarthy Brief
Wing Commander Alison MacCarthy BriefWing Commander Alison MacCarthy Brief
Wing Commander Alison MacCarthy Brief
 
Lt Col Beaumont Brief on Logistics
Lt Col Beaumont Brief on LogisticsLt Col Beaumont Brief on Logistics
Lt Col Beaumont Brief on Logistics
 
MBDA Briefing at Williams Foundation Seminar, April 11, 2019
MBDA Briefing at Williams Foundation Seminar, April 11, 2019MBDA Briefing at Williams Foundation Seminar, April 11, 2019
MBDA Briefing at Williams Foundation Seminar, April 11, 2019
 
Plan b
Plan bPlan b
Plan b
 
Far from the Sanctuaries: Sustaining a Fifth Generation Fight in the Indo-Pac...
Far from the Sanctuaries: Sustaining a Fifth Generation Fight in the Indo-Pac...Far from the Sanctuaries: Sustaining a Fifth Generation Fight in the Indo-Pac...
Far from the Sanctuaries: Sustaining a Fifth Generation Fight in the Indo-Pac...
 
Mike Tarlton Briefing to Williams Fondation Seminar on Joint Strike, August ...
Mike Tarlton Briefing to Williams Fondation  Seminar on Joint Strike, August ...Mike Tarlton Briefing to Williams Fondation  Seminar on Joint Strike, August ...
Mike Tarlton Briefing to Williams Fondation Seminar on Joint Strike, August ...
 
Air Marshal Atha, RAF, Presentation to Williams Foundation Seminar on Joint S...
Air Marshal Atha, RAF, Presentation to Williams Foundation Seminar on Joint S...Air Marshal Atha, RAF, Presentation to Williams Foundation Seminar on Joint S...
Air Marshal Atha, RAF, Presentation to Williams Foundation Seminar on Joint S...
 
James Heading Briefing to Williams Foundation Seminar on Joint Strike, August...
James Heading Briefing to Williams Foundation Seminar on Joint Strike, August...James Heading Briefing to Williams Foundation Seminar on Joint Strike, August...
James Heading Briefing to Williams Foundation Seminar on Joint Strike, August...
 
Dr. Tom Bussing Briefing to Williams Foundation Seminar on Joint Strike, Augu...
Dr. Tom Bussing Briefing to Williams Foundation Seminar on Joint Strike, Augu...Dr. Tom Bussing Briefing to Williams Foundation Seminar on Joint Strike, Augu...
Dr. Tom Bussing Briefing to Williams Foundation Seminar on Joint Strike, Augu...
 

Recently uploaded

The political system of the united kingdom
The political system of the united kingdomThe political system of the united kingdom
The political system of the united kingdom
lunadelior
 
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
Faga1939
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
hyt3577
 

Recently uploaded (20)

The political system of the united kingdom
The political system of the united kingdomThe political system of the united kingdom
The political system of the united kingdom
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf
 
Job-Oriеntеd Courses That Will Boost Your Career in 2024
Job-Oriеntеd Courses That Will Boost Your Career in 2024Job-Oriеntеd Courses That Will Boost Your Career in 2024
Job-Oriеntеd Courses That Will Boost Your Career in 2024
 
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
 
Politician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsPolitician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full Details
 
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
 
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
 
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
 
Group_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeGroup_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the trade
 
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkoEmbed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptx
 
422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdf
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
 

M1400 airship fact_sheet_25_may_12v2

  • 1. M1400 (Blue Devil 2) Airship Fact Sheet 1. The M1400 is the host aircraft for the Blue Devil 2 (BD2) sensor-to-sensor cueing and on-board processing payload. It the most complex U.S. airship ever built, and the largest U.S. airship (370’ long) built in over 50 years. The BD2 Program was initiated to provide a persistent intelligence, surveillance, and reconnaissance (ISR) capability to our Warfighters—over multiple days airborne vice hours currently flown by manned and unmanned ISR aircraft. It has the potential to be more than an order of magnitude more cost-effective than current ISR air and spacecraft. It's capabilities and potential as an ISR, comms relay, surrogate satellite, and/or other critical airborne functions are unmatched. The Blue Devil 2 Airship won the 2011 Popular Science “Best of What's New” award. It is currently under contract by the U.S. Air Force. 2. From independent assessments, the prime contractor, Mav6 LLC, and its employees have performed exceptionally well, and in spite of the many challenges designing, developing, and building a new aircraft, they have accomplished an extraordinary feat—Mav6 will have gone from a clean sheet concept to first flight of the world’s largest UAV in less than two years. 3. The BD2 program is currently about 12 percent over budget, and projected to take approximately 8 months more than originally estimated to first flight. For a developmental aircraft this is an impressive accomplishment considering nominal ISR and UAV aircraft development programs take 4-5 years to go from design to first flight; are often years late; and significantly over cost. The BD2 program is approximately 90-95 percent complete, and first flight is projected to be NLT 31 August 2012 with an additional $3M cost. To “deflate and crate” the M1400— essentially destroying it—will cost $2.6M. Even if it takes to September or October 2012, as some in the Air Force believe it may take to get to first flight, it would cost less than $5M to get to that point. That would allow a demonstration of the capabilities and viability of today’s airship technology after having spent $143M+ on the entire program, and $65M on the M1400 airship development. 4. The initial BD2 contract was awarded to Mav6 in October 2010 for $137M from the Army Engineering Research & Development Center for a specific set of requirements. The program transitioned to the Air Force over the period from November 2010 to March 2011. At that time most of the contract dollars shifted to the Air Force, and an undefinitized contract for $86.2M was awarded from the Big Safari Systems Group (BSSG) program office. There was a 60-day delay in funding during this transition. That transition caused slips to the program schedule due to the associated delay in issuing key subcontracts to vendors and teammates. During this transition period and through July 2011 there were numerous changes and additions made by the BSSG to the BD2 requirements that included more stringent FAA airship certification than in the original contract or budgeted.
  • 2. 5. After the 60 day Army to Air Force transition funding delay, the Air Force did not definitize the BD2 contract with Mav6 for 11 months (in violation of the Federal Acquisition regulations). That created many difficulties for Mav6, a small business, due to incremental funding over that period. This caused BD2 programmatic disruptions, and on many occasions put Mav6 and their subcontractors at risk of a $3-4M loss. Additionally, as a result of Air Force delays in contract definitization, Mav6 was unable to collect profit for a period of 12 months, and often performed work at risk of losing profit to prevent having to stop work on the program. This was a major hardship for a small company, but indicates the degree of their commitment to provide this game-changing capability to the Department of Defense (DOD). 6. There were numerous attempts to terminate the program by the Air Force during the contract transition period from the Army to the Air Force. It is also important to note that the Air Force has openly stated they have no requirement for an airship and have exhibited actions to stop the program since early Fall of 2011. This is difficult to understand given that the M1400 airship is a lower cost, and much more effective, ISR solution relative to the more expensive Life Cycle Costs (LCC) and limited integration of sensors of existing fixed-wing ISR aircraft. In terms of “ISR payload times endurance” the BD2 can be more than 40 times more effective than the fixed-wing UAVs now being used to wide acclaim. The BD2 program survived through support from the Congress who understood the capability and value proposition potential of BD2. 7. Some delays in the program can be attributed to the research and development nature of building the world’s most complex UAV. It has progressed from a concept in October 2010 to 90-95 percent complete by May 2012. Specifically, the M1400 has experienced the following technical challenges: 1) production and testing of the four 40 foot by 30 foot tailfins. The tailfins recently (9 May 2012) passed a FAA test for 50 mph flight and were scheduled for testing to the full 80 mph on 30 May 2012; 2) development and integration of the vehicle and flight control systems that include 6 engines of three different types, and 26 airship flight control valves that are 7-8 times the complexity of a large fixed-wing UAV (software delivery for the flight control system is 31 May 2012); and 3) integration of the numerous electrical boxes and wiring harnesses associated with the vehicle and flight control systems for a 370 foot long aircraft (these boxes and harnesses are to be completed by 15-30 June 2012. 8. In Jan 2012, Mav6 was accomplishing final development testing of the most robust onboard multi-intelligence payload architecture built for a UAV when the mission payload portion of the program was arbitrarily terminated by the Air Force. This leading-edge architecture designed by Mav6 included processing of six sensors (SIGINT, EO and IR) and the raw data and meta-data storage for these sensors in an innovative modular structure enabling rapid exchange of sensors to achieve ISR tailoring for changing situations. This combination of numbers of multi-intelligence sensors, open integration architecture, and modularity of capability to achieve
  • 3. sensor-to-sensor tipping and cueing is a first for airborne ISR and a set of capabilities long sought after by the Department of Defense. It also included a SatCom data link, two direct downlink common data links, laser communications and Vortex/Rover that allowed access to the data from individual teams on the ground. 9. An independent U.S. government team spent 14-17 May 2012 viewing and evaluating all aspects of the M1400 airship in its location in North Carolina. The feedback after their evaluation of the airship was extremely positive citing exceptional architecture, excellent quality of workmanship and nothing insurmountable in getting to first flight and beyond. 10. On 23 May 2012 the Air Force issued a letter of direction to “deflate and crate” the M1400 by 30 Jun 2012. This is an arbitrary stop work date as approximately $55 million remains in the FY12 DOD budget specified for BD2/M1400 development, demonstration, and deployment. Given the approximately $3-5 million required to get BD2 to first flight (2-3 percent of total cost already spent and approximately 5-9 percent of remaining BD2 FY12 available funds in FY12 budget), and its potential to demonstrate over an order of magnitude increase in cost-effectiveness delivering ISR relative to conventional aircraft and space systems, OSD should work with Congress to move the program from the Air Force to another sponsor along with the $55M in the FY12 budget specified for BD2. These dollars will complete development and integration of the airship and a mission payload package enabling a full CONUS operational capabilities demonstration for one year. Acting AT&L Secretary Frank Kendall recently stated that DoD needs to overcome the inertia of "old think," and look at prototyping and experimentation to explore new technologies and capabilities that they enable. The M1400 airship equipped with any variety of payloads has the potential to do just that. Without a demonstration of its potential, deflating and destroying it, would be a significant lost opportunity for the Department of Defense, the American taxpayers, and our Warfighters.