SlideShare a Scribd company logo
1 of 16
Download to read offline
Data Centre Environments
CCS Commercial Overview Session 3
The Greening of the Data Centre
16th December 2008
Paul Mathews MInstSMM
Global Channel Manager
• The heartbeat of any business, designed to manage the flow, processing and
storage of information
• Must be reliable, secure and flexible to enable growth and reconfiguration
• A data centre can support small singular businesses through to thousands of
clients ecommerce facilities
• “A building or portion of a building whose primary function is to house a
computer room and its support areas,” according to TIA 942
Introduction to Data Centres
Energy usage in Data Centres
• Average 200 sq m computer room in a data centre uses 52 more times
electricity than an office LAN
• An average of 7500 kW hours per sq m / pa
• Present day servers generate around 2.5 kW of heat per sq m – this is
expected to rise to 10 kW as CPUs become densely populated
• A floor tile emits an average of 1.2 tonnes of carbon omissions pa
• Based on costs of £450.00 per sq m would result in savings over £9000 if
efficiency was improved by 10%
Energy wastage in Data Centres
• Huge financial industry burden and public policy environmental issue
• If a Data Centre could be 100% efficient, all electrical power would need to
reach the IT loads
• Real world environments see non-IT physical infrastructure devices
consuming power (manifested as heat), including:
- Transformers
- UPS
- Power wiring
- Fans
- Air conditioners
- Pumps
- Humidifiers
- Lighting
This all needs cooling (therefore
consumes more power)
Increased redundancy means
more energy required
Why are data centres inefficient?
• Over sizing of the physical infrastructure creates fixed losses of electrical
power and cooling systems
• Data Centre industry power and cooling usage worldwide wastes more than
60,000,000 megawatt-hours per year of electricity
• Data Centres typically run at 30-50% of capacity
• Losses in energy are proportional to overall electrical power ratings of a
system, regardless of IT load (so installations with light IT loads, fixed losses
of the physical infrastructure equipment often exceed IT load)
Example:
• Every 10 Watts of power delivered to a data centre loaded to 10% of its rated
capacity, only 1 Watt actually reaches the IT equipment, remaining 9 Watts
are lost to energy inefficiencies
• Generally, 50% of energy in data centres goes to IT Loads, the other 50% to
physical infrastructure equipment including electrical power devices
Data Centre Infrastructure Efficiency (DCiE)
• Data centres needs to become more green
• Measuring data centre efficiency is measured as the ratio of watts to the IT Load /
Watts to the data centre (DCIE)
• To maximise DCiE, efficiency measurements for the whole data centre should be
monitored and targeted for improvement in an ongoing strategy
DCiE Architecture (Data Centre Subsystem)
• IT Load
• Auxiliary devices
• Lights
• Humidifiers
• Chillers
• Pumps
• Heat Rejection
• CRAC
• Distribution Wiring
• Switchgear
• Generator
• PDU
• UPS
Data Centre Greening
Improvement Guidelines – Part 1
• Electrical power and cooling equipment not needed should not be energised
• Minimise over sizing where possible, so equipment operated within the
optimum region of efficiency
• Electrical power, cooling and lighting equipment should utilise up-to-date
technology to minimise power consumption
• Sub-systems used for redundancy should be optimised for their fractional
load capacity, not the full load efficiency
Data Centre Greening
Improvement Guidelines – Part 2
• Use a capacity management tool to manage the amount of electrical power
and cooling to the Data Centre, ensuring ‘stranded capacity’ is minimised
• To optimise the efficiency of zones/areas within the data centre, an integrated
physical configuration should control the system and not just one room
Example
Row-based cooling for racks should be integrated with IT racks, independent
from the room based cooling
• Integrate management systems to monitor and alert electrical consumption
levels that cause high inefficiency levels
Data Centre Greening
Improvement Guidelines – Part 3 Cabling
• Design cabling and racks to maximise air flow (use blanking panels in
cabinets, hot and cold aisle placement)
• Use pre-terminated cabling to reduce waste
• Consider optical fibre:
- kinder to the environment in manufacturing v copper
- bullet proof for longer life cycle
- components consume less power v copper
- higher bandwidth, extended distance (performance)
- cabling such as Connectix Starlight MTP reduces amount of cables and
improves air flow
Sizing the Data Centre
• Sizing the physical infrastructure inline with the IT Load will have the most
impact on electrical consumption
• Scalable physical infrastructures that can grow with IT Load offer the best
opportunity to limit electrical waste and costs
• A well designed, correctly sized physical infrastructure can eliminate up to
50% of the electrical bill in real-world installations
• So….. Design a modular, scalable physical infrastructure
Sub-system Greening
Part 1
• Scalable electrical power and cooling:
Helps increase efficiency in smaller data centres or data centres early in their
life form
Helps defer capital and operating costs until needed
• Row-based cooling:
Shortens the air flow path to improve predictability of air distribution
Perimeter CRACs operate at 80% efficient at 70% IT Load
Row-base CRACs operate at 95% efficient at 70% IT Load
Sub-system Greening
Part 2
• High-efficiency UPS
Current new products can improve efficiency by over 10% compared to
current installed UPS
• Capacity management tools
A mixture of tools and company regulations that implements a safe operating
system that is higher density and more efficient, designed to reduce capital
costs and energy bills
Energy Efficiency Best Practices
• Install blanking panels
• Coordinate CRAC Units
• Improve under floor airflow
• Implement hot and cold aisles
• Install sensors to monitor temperature
• Implement cold aisle or hot aisle containment
• Raise the temperature in the data centre (ASHRAE)
to improve electrical use
• Exploit ‘free cooling’
• Design new data centres and computer rooms using modular cooling
Additional information can be
found in the Gartner report ‘How
to Save a Million Kilowatt Hours
in your Data Centre’
Data Centre Whitepapers
• Data Centre Design Whitepaper
http://www.connectixcablingsystems.com/library/detail.cfm?item=10
Connectix Technical Articles
• Log on to www.connectixcablingsystems.com for full access to our data
centre and high speed LAN support articles
• Log on to www.connectixcablingsystems.com/events for details of our Data
Centre Design Principle Seminars run in association with The IET
IET Endorsed
Training
provider
CIBSE Continuing
Professional Development BICSI Continuing Education Credits

More Related Content

What's hot

The Future Of Data Center Critical Power - GP100 eBook
The Future Of Data Center Critical Power - GP100 eBookThe Future Of Data Center Critical Power - GP100 eBook
The Future Of Data Center Critical Power - GP100 eBook
GE Energy Connections
 

What's hot (19)

Improving your PUE while consolidating into an existing live data center
Improving your PUE while consolidating into an existing live data centerImproving your PUE while consolidating into an existing live data center
Improving your PUE while consolidating into an existing live data center
 
Data center hvac
Data center hvacData center hvac
Data center hvac
 
greendatacenter
greendatacentergreendatacenter
greendatacenter
 
Data center power infrastructure
Data center power infrastructureData center power infrastructure
Data center power infrastructure
 
Datacenter101
Datacenter101Datacenter101
Datacenter101
 
How Green Is Your Data Center
How Green Is Your Data CenterHow Green Is Your Data Center
How Green Is Your Data Center
 
Express Computer
Express ComputerExpress Computer
Express Computer
 
Data Center Lessons Learned
Data Center Lessons LearnedData Center Lessons Learned
Data Center Lessons Learned
 
How Row-based Data Center Cooling Works
How Row-based Data Center Cooling WorksHow Row-based Data Center Cooling Works
How Row-based Data Center Cooling Works
 
Denison university success story schneider electric
Denison university success story schneider electricDenison university success story schneider electric
Denison university success story schneider electric
 
2009-dec02_APC
2009-dec02_APC2009-dec02_APC
2009-dec02_APC
 
Actual Time Online Thermal Mapping Of significant Components In Data Hub
Actual Time Online Thermal Mapping Of significant Components In Data Hub Actual Time Online Thermal Mapping Of significant Components In Data Hub
Actual Time Online Thermal Mapping Of significant Components In Data Hub
 
Green Data Centre for banks
Green Data Centre for banksGreen Data Centre for banks
Green Data Centre for banks
 
Data centre networking
Data centre networkingData centre networking
Data centre networking
 
legal mandates in green computing
legal mandates in green computinglegal mandates in green computing
legal mandates in green computing
 
The Future Of Data Center Critical Power - GP100 eBook
The Future Of Data Center Critical Power - GP100 eBookThe Future Of Data Center Critical Power - GP100 eBook
The Future Of Data Center Critical Power - GP100 eBook
 
DataCenter:: Infrastructure Presentation
DataCenter:: Infrastructure PresentationDataCenter:: Infrastructure Presentation
DataCenter:: Infrastructure Presentation
 
B7 merlin
B7 merlinB7 merlin
B7 merlin
 
Data Center Server Rack Strategies
Data Center Server Rack StrategiesData Center Server Rack Strategies
Data Center Server Rack Strategies
 

Similar to Commercial Overview DC Session 3 The Greening Of The Data Centre

Commercial Overview DC Session 4 Introduction To Energy In The Data Centre
Commercial Overview   DC Session 4   Introduction To Energy In The Data CentreCommercial Overview   DC Session 4   Introduction To Energy In The Data Centre
Commercial Overview DC Session 4 Introduction To Energy In The Data Centre
paul_mathews
 
Commercial Overview SCS Session 1 Server Rack Strategies
Commercial Overview   SCS Session 1   Server Rack StrategiesCommercial Overview   SCS Session 1   Server Rack Strategies
Commercial Overview SCS Session 1 Server Rack Strategies
paul_mathews
 
MRI Energy-Efficient Cloud Computing
MRI Energy-Efficient Cloud ComputingMRI Energy-Efficient Cloud Computing
MRI Energy-Efficient Cloud Computing
Roger Rafanell Mas
 

Similar to Commercial Overview DC Session 3 The Greening Of The Data Centre (20)

Commercial Overview DC Session 4 Introduction To Energy In The Data Centre
Commercial Overview   DC Session 4   Introduction To Energy In The Data CentreCommercial Overview   DC Session 4   Introduction To Energy In The Data Centre
Commercial Overview DC Session 4 Introduction To Energy In The Data Centre
 
Commercial Overview SCS Session 1 Server Rack Strategies
Commercial Overview   SCS Session 1   Server Rack StrategiesCommercial Overview   SCS Session 1   Server Rack Strategies
Commercial Overview SCS Session 1 Server Rack Strategies
 
Modular Data Center Design
Modular Data Center DesignModular Data Center Design
Modular Data Center Design
 
Improvements in Data Center Management
Improvements in Data Center ManagementImprovements in Data Center Management
Improvements in Data Center Management
 
Virtualization for efficiency: by Kathrin Winkler, The green grid
Virtualization for efficiency: by Kathrin Winkler, The green gridVirtualization for efficiency: by Kathrin Winkler, The green grid
Virtualization for efficiency: by Kathrin Winkler, The green grid
 
Green ICT
Green ICTGreen ICT
Green ICT
 
Green IT
Green ITGreen IT
Green IT
 
Green cloud computing
Green cloud computingGreen cloud computing
Green cloud computing
 
PUE Reconsidered
PUE ReconsideredPUE Reconsidered
PUE Reconsidered
 
Aged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptxAged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptx
 
Build Energy Saving into Your Datacenter
Build Energy Saving into Your DatacenterBuild Energy Saving into Your Datacenter
Build Energy Saving into Your Datacenter
 
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRES
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRESCOMMON PROBLEMS AND CHALLENGES IN DATA CENTRES
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRES
 
A Cyber Physical Approach to a Combined Hardware-Software
A Cyber Physical Approach to a Combined Hardware-Software A Cyber Physical Approach to a Combined Hardware-Software
A Cyber Physical Approach to a Combined Hardware-Software
 
Showcase ppt ver 8
Showcase ppt ver 8Showcase ppt ver 8
Showcase ppt ver 8
 
Showcase ppt ver 8
Showcase ppt ver 8Showcase ppt ver 8
Showcase ppt ver 8
 
インドネシア JCM事業 FS報告会
インドネシア JCM事業 FS報告会インドネシア JCM事業 FS報告会
インドネシア JCM事業 FS報告会
 
The next wave of GreenIT
The next wave of GreenITThe next wave of GreenIT
The next wave of GreenIT
 
High Efficiency technologies for Data Centre Air Conditioning
High Efficiency technologies for  Data Centre Air ConditioningHigh Efficiency technologies for  Data Centre Air Conditioning
High Efficiency technologies for Data Centre Air Conditioning
 
MRI Energy-Efficient Cloud Computing
MRI Energy-Efficient Cloud ComputingMRI Energy-Efficient Cloud Computing
MRI Energy-Efficient Cloud Computing
 
Critical design elements for high power density data centers
Critical design elements for high power density data centersCritical design elements for high power density data centers
Critical design elements for high power density data centers
 

More from paul_mathews

CCCS Presentation - On Lda Oct 2010 Parts 1&2
CCCS Presentation  - On Lda Oct 2010 Parts 1&2CCCS Presentation  - On Lda Oct 2010 Parts 1&2
CCCS Presentation - On Lda Oct 2010 Parts 1&2
paul_mathews
 
Commercial Overview DC Session 2 Optical Fibre In The Data Centre
Commercial Overview   DC Session 2   Optical Fibre In The Data CentreCommercial Overview   DC Session 2   Optical Fibre In The Data Centre
Commercial Overview DC Session 2 Optical Fibre In The Data Centre
paul_mathews
 
Commercial Overview DC Session 1 Introduction To Cabling Standards And Th...
Commercial Overview   DC Session 1   Introduction To Cabling Standards And Th...Commercial Overview   DC Session 1   Introduction To Cabling Standards And Th...
Commercial Overview DC Session 1 Introduction To Cabling Standards And Th...
paul_mathews
 

More from paul_mathews (8)

CCS Presentation Company Intro, DC Cabling & Racks, Future Trends
CCS Presentation   Company Intro, DC Cabling & Racks, Future TrendsCCS Presentation   Company Intro, DC Cabling & Racks, Future Trends
CCS Presentation Company Intro, DC Cabling & Racks, Future Trends
 
Connectix Commercial Overview Dc Session 8 Using The Fear Model To Design...
Connectix Commercial Overview   Dc Session 8   Using The Fear Model To Design...Connectix Commercial Overview   Dc Session 8   Using The Fear Model To Design...
Connectix Commercial Overview Dc Session 8 Using The Fear Model To Design...
 
CCS Presentation On Lda Oct 2010 (Compressed Pics) Parts 3 5
CCS Presentation   On Lda Oct 2010 (Compressed Pics) Parts 3 5CCS Presentation   On Lda Oct 2010 (Compressed Pics) Parts 3 5
CCS Presentation On Lda Oct 2010 (Compressed Pics) Parts 3 5
 
CCCS Presentation - On Lda Oct 2010 Parts 1&2
CCCS Presentation  - On Lda Oct 2010 Parts 1&2CCCS Presentation  - On Lda Oct 2010 Parts 1&2
CCCS Presentation - On Lda Oct 2010 Parts 1&2
 
Connectix Commercial Overview Dc Session 6 The European Code Of Conduct O...
Connectix Commercial Overview   Dc Session 6   The European Code Of Conduct O...Connectix Commercial Overview   Dc Session 6   The European Code Of Conduct O...
Connectix Commercial Overview Dc Session 6 The European Code Of Conduct O...
 
Connectix Commercial Overview Dc Session 5 The Uk Carbon Reduction Commit...
Connectix Commercial Overview   Dc Session 5   The Uk Carbon Reduction Commit...Connectix Commercial Overview   Dc Session 5   The Uk Carbon Reduction Commit...
Connectix Commercial Overview Dc Session 5 The Uk Carbon Reduction Commit...
 
Commercial Overview DC Session 2 Optical Fibre In The Data Centre
Commercial Overview   DC Session 2   Optical Fibre In The Data CentreCommercial Overview   DC Session 2   Optical Fibre In The Data Centre
Commercial Overview DC Session 2 Optical Fibre In The Data Centre
 
Commercial Overview DC Session 1 Introduction To Cabling Standards And Th...
Commercial Overview   DC Session 1   Introduction To Cabling Standards And Th...Commercial Overview   DC Session 1   Introduction To Cabling Standards And Th...
Commercial Overview DC Session 1 Introduction To Cabling Standards And Th...
 

Commercial Overview DC Session 3 The Greening Of The Data Centre

  • 1. Data Centre Environments CCS Commercial Overview Session 3 The Greening of the Data Centre 16th December 2008 Paul Mathews MInstSMM Global Channel Manager
  • 2. • The heartbeat of any business, designed to manage the flow, processing and storage of information • Must be reliable, secure and flexible to enable growth and reconfiguration • A data centre can support small singular businesses through to thousands of clients ecommerce facilities • “A building or portion of a building whose primary function is to house a computer room and its support areas,” according to TIA 942 Introduction to Data Centres
  • 3. Energy usage in Data Centres • Average 200 sq m computer room in a data centre uses 52 more times electricity than an office LAN • An average of 7500 kW hours per sq m / pa • Present day servers generate around 2.5 kW of heat per sq m – this is expected to rise to 10 kW as CPUs become densely populated • A floor tile emits an average of 1.2 tonnes of carbon omissions pa • Based on costs of £450.00 per sq m would result in savings over £9000 if efficiency was improved by 10%
  • 4. Energy wastage in Data Centres • Huge financial industry burden and public policy environmental issue • If a Data Centre could be 100% efficient, all electrical power would need to reach the IT loads • Real world environments see non-IT physical infrastructure devices consuming power (manifested as heat), including: - Transformers - UPS - Power wiring - Fans - Air conditioners - Pumps - Humidifiers - Lighting This all needs cooling (therefore consumes more power) Increased redundancy means more energy required
  • 5. Why are data centres inefficient? • Over sizing of the physical infrastructure creates fixed losses of electrical power and cooling systems • Data Centre industry power and cooling usage worldwide wastes more than 60,000,000 megawatt-hours per year of electricity • Data Centres typically run at 30-50% of capacity • Losses in energy are proportional to overall electrical power ratings of a system, regardless of IT load (so installations with light IT loads, fixed losses of the physical infrastructure equipment often exceed IT load) Example: • Every 10 Watts of power delivered to a data centre loaded to 10% of its rated capacity, only 1 Watt actually reaches the IT equipment, remaining 9 Watts are lost to energy inefficiencies • Generally, 50% of energy in data centres goes to IT Loads, the other 50% to physical infrastructure equipment including electrical power devices
  • 6. Data Centre Infrastructure Efficiency (DCiE) • Data centres needs to become more green • Measuring data centre efficiency is measured as the ratio of watts to the IT Load / Watts to the data centre (DCIE) • To maximise DCiE, efficiency measurements for the whole data centre should be monitored and targeted for improvement in an ongoing strategy
  • 7. DCiE Architecture (Data Centre Subsystem) • IT Load • Auxiliary devices • Lights • Humidifiers • Chillers • Pumps • Heat Rejection • CRAC • Distribution Wiring • Switchgear • Generator • PDU • UPS
  • 8. Data Centre Greening Improvement Guidelines – Part 1 • Electrical power and cooling equipment not needed should not be energised • Minimise over sizing where possible, so equipment operated within the optimum region of efficiency • Electrical power, cooling and lighting equipment should utilise up-to-date technology to minimise power consumption • Sub-systems used for redundancy should be optimised for their fractional load capacity, not the full load efficiency
  • 9. Data Centre Greening Improvement Guidelines – Part 2 • Use a capacity management tool to manage the amount of electrical power and cooling to the Data Centre, ensuring ‘stranded capacity’ is minimised • To optimise the efficiency of zones/areas within the data centre, an integrated physical configuration should control the system and not just one room Example Row-based cooling for racks should be integrated with IT racks, independent from the room based cooling • Integrate management systems to monitor and alert electrical consumption levels that cause high inefficiency levels
  • 10. Data Centre Greening Improvement Guidelines – Part 3 Cabling • Design cabling and racks to maximise air flow (use blanking panels in cabinets, hot and cold aisle placement) • Use pre-terminated cabling to reduce waste • Consider optical fibre: - kinder to the environment in manufacturing v copper - bullet proof for longer life cycle - components consume less power v copper - higher bandwidth, extended distance (performance) - cabling such as Connectix Starlight MTP reduces amount of cables and improves air flow
  • 11. Sizing the Data Centre • Sizing the physical infrastructure inline with the IT Load will have the most impact on electrical consumption • Scalable physical infrastructures that can grow with IT Load offer the best opportunity to limit electrical waste and costs • A well designed, correctly sized physical infrastructure can eliminate up to 50% of the electrical bill in real-world installations • So….. Design a modular, scalable physical infrastructure
  • 12. Sub-system Greening Part 1 • Scalable electrical power and cooling: Helps increase efficiency in smaller data centres or data centres early in their life form Helps defer capital and operating costs until needed • Row-based cooling: Shortens the air flow path to improve predictability of air distribution Perimeter CRACs operate at 80% efficient at 70% IT Load Row-base CRACs operate at 95% efficient at 70% IT Load
  • 13. Sub-system Greening Part 2 • High-efficiency UPS Current new products can improve efficiency by over 10% compared to current installed UPS • Capacity management tools A mixture of tools and company regulations that implements a safe operating system that is higher density and more efficient, designed to reduce capital costs and energy bills
  • 14. Energy Efficiency Best Practices • Install blanking panels • Coordinate CRAC Units • Improve under floor airflow • Implement hot and cold aisles • Install sensors to monitor temperature • Implement cold aisle or hot aisle containment • Raise the temperature in the data centre (ASHRAE) to improve electrical use • Exploit ‘free cooling’ • Design new data centres and computer rooms using modular cooling Additional information can be found in the Gartner report ‘How to Save a Million Kilowatt Hours in your Data Centre’
  • 15. Data Centre Whitepapers • Data Centre Design Whitepaper http://www.connectixcablingsystems.com/library/detail.cfm?item=10
  • 16. Connectix Technical Articles • Log on to www.connectixcablingsystems.com for full access to our data centre and high speed LAN support articles • Log on to www.connectixcablingsystems.com/events for details of our Data Centre Design Principle Seminars run in association with The IET IET Endorsed Training provider CIBSE Continuing Professional Development BICSI Continuing Education Credits