SlideShare a Scribd company logo
1 of 26
PHẦN: I

CÁC BƯỚC THỰC HIỆN THI CÔNG
  PHẦN PIPING & MECHANICAL
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                        BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY


I.        CHUẨN BỊ CÁC VẤN ĐỀ PHỤC VỤ CHO THI CÔNG

     1.     ĐỌC HIỂU KỸ CÁC SPECIFICATION VÀ CÁC TÀI LIỆU PHỤC
            VỤ CHO THI CÔNG

           Scope Of Work.
           Applicable Codes & Standards.
           Project Document Numbering. H:LinkP.N.pdf
                                                   H:LinkP.N.pdf
           Data Sheet cho Valves và các thiết bị.
           Piping Design Specification.
           Piping Fabrication Specification. H:LinkP.F.S.pdf
                                                       H:LinkP.F.S.pdf
           Piping Specifications. H:LinkP.S.pdf
                                   H:LinkP.S.pdf
           Valve Specifications.
           Insulation Specification.
           Painting and Protective Coating Specification.
           Ngoài ra còn có rất nhiều Spec. cho các thiết bị như: Tanks,
            Pumps…v.v…
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY

2.     CHUẨN BỊ ĐẦY ĐỦ CÁC BẢNG VẼ (AFC) CẦN PHỤC VỤ
       CHO THI CÔNG

      Bảng vẽ P&ID. ..LinkP&ID.pdf
      Isometric AFC. ..LinkISO.AFC.pdf
      Piping GA Plan. ..LinkPL.dwg . ..LinkPL.H.bmp
      Pipe Support Detail AFC. ..LinkSP.D.pdf
      Pipe Support Location Plan. ..LinkSP.L.dwg
      Equipment Layout AFC. ..LinkE.L.pdf
      Fire Fighting, Safety Equipment Layout & Escape Route. ..LinkS.E.pdf
      Pipe Support Standard…vvv…..LinkSP.SD.pdf
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                 BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY



3.   VIẾT CÁC QUI TRÌNH DO PHẠM VI DỰ ÁN YÊU CẦU

    Piping Fabrication & Erection Procedure.

    Mechanical Equipment Installation Procedure.

    Valve Leak Test Procedure.

    Hydrotest & Flushing Procedure.

    Bolt Tensioning Procedure. ..LinkB.T.P.doc
    Acid Cleaning Procedure.
    Welding Procedure (QC)…
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY


4.   VẬT TƯ TIÊU HAO & CÁC VẤN ĐỀ KHÁC

    Dựa vào qui trình hàn, bản vẽ Isometric, khối lượng ống, khối lượng
     mối hàn và định mức để bốc tách khối lượng que hàn, đá cắt, đá
     mài… và order mua.
    Dựa vào bản vẽ P&ID và Isometric chia các gói Test Package cho
     Hydrotest.
    Bốc tách khối lượng vật tư tiêu hao cho Hydrotest để order mua.
    Rà soát lại các thiết bị dụng cụ phục vụ thi công sẵn có và order mua
     bổ sung số luợng còn thiếu hoặc theo yêu cầu đặt thù của dự án.
    Dựa vào số lượng Dia-inch và số lượng hệ thống để chia line, chia hệ
     và chia nhóm quản lý.
    Lập bảng theo dõi tình trạng chế tạo và lắp đặt piping (Piping
     Fabrication Control Sheet).
    Lập bảng theo dõi tình trạng xuất và sử dụng vật tư dự án (Material
     Control Sheet).
    Kiểm tra bảng vẽ AFC.
    Viết STQ… ..LinkSTQ.xls
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY


5.   BỐC TÁCH VẬ TƯ CHÍNH CHO DỰ ÁN (MTO)

    Dựa vào Isometric bốc tách MTO cho Pipe, Fitting & Valve.   ..LinkMTO.P.xls




    Piping Specialty List. ..LinkPS.L.pdf
    Dựa vào bản vẽ Pipe support bốc tách MTO cho Pipe support.     ..LinkM.S.xls




    Dựa vào bản vẽ thiết bị bốc tách MTO cho thiết bị.

    Dựa vào bản vẽ Safety Sign bốc tách MTO cho Safety Sign.

    Ngoài ra còn bốc tách MTO cho Insulation và một số vật tư khác
     nếu có…

    Issue MTO và cập nhật tình trạng để báo cáo tuần.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY



3.     YÊU CẦU MUA VẬT TƯ (RFQ) & ĐÁNH GIÁ KỸ THUẬT
       (TBE)

      Dựa vào MTO cần đi mua.
      Làm RFQ (Requirement for quotation) cho từng gói. ..LinkRFQ.pdf
      Làm Inter-memo và gửi kèm RFQ, MTO, Data-sheet, Specifications
       và các bảng vẽ cần thiết đến bộ phận mua sắm của dự án để gửi đếnn
       các Vendor chào giá & kỹ thuật. ..LinkI.M.doc
      Nhận các đề xuất kỹ thuật từ các Vendor thông qua bộ phận mua
       sắm. ..LinkT.P.pdf
      Làm TBC (Technical Bid Clarification) nếu cần. ..LinkTBC.doc
      Làm đánh giá TBE (Technical Bid Evaluation). ..LinkTBE.xls
      Làm Inter-memo gửi TBE gửi đến bộ phận mua sắm để chọn Vendor
       hợp lý nhất để mua vật tư.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                      BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY


II.   TRIỂN KHAI SHOP-DRAWINGS (IFC)

      1.   BẢN VẼ ISOMETRIC ..LinkISO.dwg
          Format form cho bản vẽ shop-drawing.
          Chuyển nội dung từ bảng vẽ AFC sang IFC.
          Đánh số mối hàn.
          Đánh số chi tiết đoạn cắt (Piece-mark).
          Chia spools và đánh ký hiệu những mối field weld (FW) hoặc field
           -fit weld (FFW, nếu hàn ở Offshore).
          Đánh số Spools.
          Dựa vào Pipedata tính chiều dài các đoạn cắt, lập bảng Cut Pipe
           Length ..LinkDP.doc
          Chọn qui trình hàn và các thông số cần thiết. ..LinkWPS.R.xls
          Ghi chú nội dung cần chú ý vào phần ghi chú.
          Issue bảng vẽ và cập nhật tình trạng vào “Register” để theo dõi và
           báo cáo tuần. ..LinkS.R.xls
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                 BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY


2.   BẢN VẼ PIPE SUPPORT DETAIL ..LinkPSP.dwg
    Tham khảo bảng vẽ Pipe support Standard.
    Chọn hướng nhìn.
    Vẽ hình dạng support theo các hướng nhìn.
    Vẽ hình trích dẫn cho những mối liên kết khó.
    Đánh số cho các chi tiết (member).
    Ghi ký hiệu mối hàn.
    Chọn gốc toạ độ.
    Dựa vào bảng vẽ Piece-mark Deck FramingPlan cho Secondary
     Beam chọn dầm liên kết và trục tham chiếu.
    Tính kích thước cho các chi tiết và kích thước tham chiếu.
    Lập bảng MTO.
    Ghi chú nội dung cần chú ý vào bảng vẽ.
    Issue bảng vẽ và cập nhật tình trạng vào Register để theo dõi và báo
     cáo tuần.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                 BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY



3.   BẢN VẼ LẮP ĐẶT THIẾT BỊ (Equipment Layout) ..LinkS.E.L.dwg

    Dựa vào bản vẽ chi tiết của thiết bị từ Vendor.
    Dựa vào bảng vẽ Layout của Structural.
    Dựa vào bảng vẽ Piping GA Plan.
    Kiểm tra toạ độ các Nozzle và đối chiếu với toạ độ đấu ống trên
     Isometric.
    Chọn gốc toạ độ chuẩn lắp đặt.
    Tính toán các kích thước lắp đặt.
    Gia cố support khi cần thiết.
    Lập bảng vẽ Shop Drawing Equipment Layout.
    Issue bảng vẽ và cập nhật tình trạng vào Register để theo dõi và báo
     cáo tuần.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                    BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY



4.   CUTTING PLAN

    Lập cutting plan cho cắt ống. ..LinkCP.P.pdf

         Xuất dữ liệu từ bảng pipe cutting length của bảng vẽ Isometric
          IFC ra Excel.
         Chọn lọc và tách các đoạn cắt theo từng loại vật tư. ..LinkX.DL.doc
         Dùng lệnh hổ trợ trong Autocad để chạy tự động Cutting Plan.
     lập cutting plan cho cắt pipe support. ..LinkCP.S.pdf
         Xuất dữ liệu từ bảng MTO của bảng vẽ pipe support detail IFC
          ra Excel.
         Các bước tiếp theo tương tự như lập Cutting plan cho cắt ống.
     Issue Cutting Plan và cập nhật tình trạng để báo cáo tuần.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                        BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY




III.        TRIỂN KHAI THI CÔNG

       1.   LẬP LỆNH SẢN XUẤT ..LinkLSX.DOC

           Dựa vào định mức.
           Dựa vào bảng vẽ thi công.
           Tính toán khối lượng công việc.
           Tính toán số luợng nhân công.
           Đưa ra ngày bắt đầu và kế thúc.
           Giao lệnh sản xuất & kèm theo bản vẽ thi công cho tổ thi công.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                 BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY



2.   XUẤT VẬT TƯ CHO THI CÔNG ..LinkM.C.S.xls
    Dựa vào bảng vẽ thi công.

    Dựa vào lệnh sản xuất.

    Lập phiếu xuất vật tư theo form mẫu phù hợp với từng loại vật tư:
        Vật tư do công ty mua. ..LinkY.CT.doc
        Vật tư do chủ đầu tư mua. ..LinkY.N.doc
    Nhận vật tư từ kho.

    Bàn giao vật tư cho từng tổ thi công. ..LinkB.G.xls
    Cập nhật tình trạng vật tư vào “Material Control Sheet” để theo dõi.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                 BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY




3.   TRIỂN KHAI CẮT ỐNG HOẶC PIPE SUPPORT

    Lập requet cho QC kiểm tra kích thước và lấy dấu trước khi cắt.
     ..LinkRD.xls


    Cắt ống hoặc support theo QC đã lấy dấu.

    Bàn giao các đoạn đã cắt cho từng tổ thi công.

    Cập nhật tình trạng để theo dõi.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                 BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY




4.   TRIỂN KHAI FIT-UP

    Mài Bevel các đầu ống, fitting hoặc vật tư pipe support. ..LinkB.V.doc
    Dùng đồ gá và các dụng cụ cần thiết để gá ống.

    Hàn đính các mối lắp. ..LinkFU.doc
    Kiểm tra khe hở và độ lệch mếp.

    Báo cáo khối luợng fit-up.

    Làm request cho QC kiểm tra fit-up. ..LinkRF.xls
    Cập nhật tình trạng fit-up vào “Piping Control Sheet” để theo dõi.
     ..LinkF.C.R.xls ..LinkWR.D.xls
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                 BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY



5.   TRIỂN KHAI HÀN ..LinkH.doc

    Chọn thợ hàn có tay nghề phù hợp với vật liệu cần hàn.

    Chọn qui trình hàn phù hợp với mối hàn cần hàn.

    Tiến hành hàn theo qui trình hàn cần tham khảo. ..LinkWPS.xls

    Báo cáo khối luợng hàn.

    Làm request cho QC kiểm tra visual. ..LinkRV.xls

    Đóng và treo Tagname cho từng spool theo bản vẽ Isometric.

    Cập nhật tình trạng hàn vào “Piping Control Sheet” để theo dõi.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                 BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY



6.   KIỂM TRA VISUAL MỐI HÀN (QC)

    Kiểm tra mối hàn bằng mắt (visual) để định chất lượng mối hàn
     (QC).

    Báo cáo kết quả visual (QC).

    Nhận báo cáo kết quả visual từ QC.

    Cập nhật tình trạng visual vào “Piping Control Sheet” để theo dõi.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                 BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY


7.   KIỂM TRA NDT MỐI HÀN (Nhà thầu phụ, QC & Production cùng
     thực hiện)

    Chuyển những spools cần RT đến bãi chup RT. (Pro.). ..LinkMR.doc
     ..LinkBG.xls

    Làm request NDT. (QC).

    Chụp RT mối hàn cho các spools. (Thầu phụ).

    MPI, DPI, PI hoặc UT mối hàn cho các spools. (Thầu phụ).

    MPI 10% đối với pipe support. (Thầu phụ).

    Báo cáo kết quả NDT. (Thầu phụ).

    Mang những spools đã chụp RT xong vào lại bãi thi công và cập
     nhật tình trạng NDT vào “Piping Control Sheet” để theo dõi. ..LinkMV.doc
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY


7.     GIA NHIỆT MỐI HÀN-PWHT (Nhà thầu phụ, QC & Production
       cùng thực hiện) ..LinkGN.doc
      Chuyển những spools có mối hàn sau khi đã RT lần 1 và cần gia
       nhiệt đến bãi gia nhiệt. (Pro.).

      Làm request cho gia nhiệt. (QC).

      Làm gia nhiệt. (Thầu phụ).

      Báo cáo kết quả gia nhiệt. (Thầu phụ).

      Làm RT lần 2. (Thầu phụ).

      Báo cáo kết quả RT lần 2. (Thầu phụ).

      Cập nhật tình trạng gia nhiệt & RT lần 2 vào “Piping Control Sheet”
       để theo dõi.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                 BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY


8.   SƠN SPOOLS VÀ PIPE SUPPORT

    QC dựa vào kết quả NDT issued list release các spools hoặc pipe
     support cần mang đi sơn.

    Chuyển những spools hoặc pipe support theo list release đến bãi sơn.

    Bàn giao các spools hoặc pipe support này cho bộ phận sơn. ..LinkBDS.doc
    Theo dõi tình trạng sơn.

    Mang những spools hoặc pipe support đã sơn xong về tập kết tại khu
     vực chuẩn bị lắp đặt.

    Ngoài ra một số thiết bị hoặc Valves mà Vendor chưa sơn hoặc sơn
     chưa đúng code thì cũng bàn giao cho bộ phận sơn để sơn lại.

    Cập nhật tình trạng sơn vào “Piping Control Sheet” để theo dõi.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                 BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY


9.   LẮP ĐẶT

    Trước tiên chuẩn bị đầy đủ các bảng đã nêu ở trên.
    Lập kế hoạch lắp đặt cho thiết bị và các đường ống.
    Thiết bị phải lắp trước để có cơ sở lắp & đấu nối các đường ống vào
     các Nozzles.
    Qui hoạch các thiết bị chính và hệ thống ống chính phải ưu tiên lắp
     trước.
    Lập lệnh sản xuất cho từng gói lắp đặt.
    Lập và đánh giá JSA cho các gói lắp đặt có nguy cơ nguy hiểm cao.
    Order các thiết bị và dụng cụ cần thiết để phục vụ lắp đặt.
    Đưa các thiết bị, spools và valves cần lắp vào vị trí.
    Cân chỉnh & Fit cố định thiết bị trước sau đó đấu nối các line ống
     vào các nozzles.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
               BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY



   Hàn cố định những chân hoặc support cho các thiết bị.
   Dùng bulông tạm để lắp tạm những mối nối bằng mặt bích.
   Dùng spools tạm để gá, lắp cho những vị trí valve hoặc thiết bị trên
    đường ống mà chưa về hoặc không yêu cầu lắp trước hydrotest.
   Fit-up và request yêu cầu kiểm tra fit-up những mối FW.
   Hàn, và request yêu cầu kiểm tra visual và làm NDT những mối
    FW.
   Cập nhật tình trạng fit-up, weld, NDT và số lượng spools lắp được
    vào Piping Control Sheet để theo dõi.
   Lắp những Stud-bolt, Gasket và Valves cần lắp trước hydrotest.
   Siết bulông cho những mối nối mặt bích cần thiết trước khi
    hydrotest. ..LinkX.BL.doc
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                  BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY



10.   HYDROTEST (HT)

     Chuẩn bị và update các gói thử trước khi test.
     Tiến hành cùng với QC đi line checking và lập “Punch List”.
     Clear những item thuộc “category A” trong Punch list trước khi HT.
     Tiến hành cùng QC và QC chủ đầu tư kiểm tra lại những item A đã
      được clear.
     Làm request đề nghị QC chủ đầu tư kiểm tra dự liệu trong test
      package, ký Chart Page và tiến hành làm chứng (witness) trong quá
      trình thử HT.
     Rửa sạch (Flushing) hệ thống ống cần test trước khi HT.
     Thử hydrotest. (Tuỳ theo yêu cầu của thiết kế một số gói thử có thể
      test bằng khí N2 hoặc service test mà thôi). ..LinkHT.doc
     Làm sạch lại và thổi khô hệ thống ống bằng khí nén.
     Ký nghiệm thu “check sheet” cho quá trình Flushing và thử HT.
     Cập nhật tình trạng hydrotest vào “Hydotest Register” để theo
      dõi. ..LinkH.R.xls
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                  BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY



11.   REINSTATEMENT ..LinkRT.doc
     Lắp hoàn thiện lại hệ thống sau khi hoàn thiện hydrotest xong.(tất cả
      dùng vật tư chính thức).
     Phối hợp với bộ phận E & I để nhận và lắp các thiết bị điện mà bộ
      phận piping phải lắp.
     Tiến hành siết bulông những mặt bích chưa siết trong quá trình HT
      theo đúng qui trình.
     Tiến hành clear toàn bộ những item thuộc “category B” trong punch
      list.
     Ký nghiệm thu những check sheet còn lại thuộc phần reinstatement
      cùng với QC và QC chủ đầu tư (kể cả những gói thiết bị).
     Bàn giao tất cả Test Package và công việc còn lại thuộc phần chạy
      thử (commissioning) cho bộ phận Re-com.
     Hổ trợ bộ phận re-com. thực hiện những công việc trong quá trình
      chạy thử mà theo yêu cầu từ bộ phận re-com.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
                  BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY



12.   CÔNG VIỆC HOÀN THIỆN CUỐI CÙNG

     Hoàn thiện những công việc còn tồn đọng lại sau khi các hệ thống đã
      chạy thử xong.
     Hoàn thiện những item còn tồn đọng cuối cùng thuộc “category C”
      trong punch list.
     Hoàn thiện những công việc “page work” còn tồn đọng cuối cùng.
     Phối hợp giữa các bộ phận re-com. và QC để bàn giao dự án cho chủ
      đầu tư.
     Kết thúc dự án.
HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN
           BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY




        “KẾT THÚC PHẦN I”

More Related Content

What's hot

Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Varun Patel
 
Introduction to piping.......PLEASE give your valuable comments if you like t...
Introduction to piping.......PLEASE give your valuable comments if you like t...Introduction to piping.......PLEASE give your valuable comments if you like t...
Introduction to piping.......PLEASE give your valuable comments if you like t...
Madhur Mahajan
 

What's hot (20)

Piping Design ppt.pdf
Piping Design ppt.pdfPiping Design ppt.pdf
Piping Design ppt.pdf
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
 
Basic piping
Basic pipingBasic piping
Basic piping
 
what is process piping
what is process pipingwhat is process piping
what is process piping
 
Introduction to piping.......PLEASE give your valuable comments if you like t...
Introduction to piping.......PLEASE give your valuable comments if you like t...Introduction to piping.......PLEASE give your valuable comments if you like t...
Introduction to piping.......PLEASE give your valuable comments if you like t...
 
Giáo Trình NAVISWORK Tiếng Việt
Giáo Trình NAVISWORK Tiếng ViệtGiáo Trình NAVISWORK Tiếng Việt
Giáo Trình NAVISWORK Tiếng Việt
 
Piping ppt1
Piping ppt1Piping ppt1
Piping ppt1
 
Piping presentation part ii 2
Piping presentation part ii 2Piping presentation part ii 2
Piping presentation part ii 2
 
Piping training-course
Piping training-coursePiping training-course
Piping training-course
 
ASME BOILER & PRESSURE SECTION VIII.ppt
ASME BOILER & PRESSURE SECTION VIII.pptASME BOILER & PRESSURE SECTION VIII.ppt
ASME BOILER & PRESSURE SECTION VIII.ppt
 
Piping Introduction
Piping IntroductionPiping Introduction
Piping Introduction
 
Constant Spring Supports Webinar
Constant Spring Supports WebinarConstant Spring Supports Webinar
Constant Spring Supports Webinar
 
Difference Between Piping and Pipeline -Piping vs pipeline
Difference Between Piping and Pipeline -Piping vs pipelineDifference Between Piping and Pipeline -Piping vs pipeline
Difference Between Piping and Pipeline -Piping vs pipeline
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technip
 
Introduction to piping design
Introduction to piping designIntroduction to piping design
Introduction to piping design
 
Piping Drawings Basics.pdf
Piping Drawings Basics.pdfPiping Drawings Basics.pdf
Piping Drawings Basics.pdf
 
Pipe & its wall thickness calculation
Pipe & its wall thickness calculationPipe & its wall thickness calculation
Pipe & its wall thickness calculation
 
Piping Fundamentals .pdf
Piping Fundamentals .pdfPiping Fundamentals .pdf
Piping Fundamentals .pdf
 
Piping presentation
Piping presentationPiping presentation
Piping presentation
 
Thuật ngữ và ký hiệu mối hàn.pdf
Thuật ngữ và ký hiệu mối hàn.pdfThuật ngữ và ký hiệu mối hàn.pdf
Thuật ngữ và ký hiệu mối hàn.pdf
 

Viewers also liked

Proper installation GRE
Proper installation  GREProper installation  GRE
Proper installation GRE
manx75
 

Viewers also liked (10)

Bondstrand bonder training, rev 0 (ptsc m&c)
Bondstrand bonder training, rev 0 (ptsc m&c)Bondstrand bonder training, rev 0 (ptsc m&c)
Bondstrand bonder training, rev 0 (ptsc m&c)
 
Proper installation GRE
Proper installation  GREProper installation  GRE
Proper installation GRE
 
B gas painting-multiple-choice-1
B gas painting-multiple-choice-1B gas painting-multiple-choice-1
B gas painting-multiple-choice-1
 
presentation
presentationpresentation
presentation
 
National structural concrete_specification_for_building_construction
National structural concrete_specification_for_building_constructionNational structural concrete_specification_for_building_construction
National structural concrete_specification_for_building_construction
 
PAINT AND COATING TESTING MANUAL, 15th Edition - ASTM
PAINT AND COATING TESTING MANUAL, 15th Edition - ASTMPAINT AND COATING TESTING MANUAL, 15th Edition - ASTM
PAINT AND COATING TESTING MANUAL, 15th Edition - ASTM
 
Piping basics knowledge
Piping basics knowledgePiping basics knowledge
Piping basics knowledge
 
Question bank
Question bankQuestion bank
Question bank
 
all about Painting (definition, elements, types, styles, history of Philippi...
all about Painting  (definition, elements, types, styles, history of Philippi...all about Painting  (definition, elements, types, styles, history of Philippi...
all about Painting (definition, elements, types, styles, history of Philippi...
 
Piping components, materials, codes and standards part 1- pipe
Piping components, materials, codes and standards   part 1- pipePiping components, materials, codes and standards   part 1- pipe
Piping components, materials, codes and standards part 1- pipe
 

Similar to Phần ii các bước thực hiện thi công piping cho dự án

Quy dinh ky_thuat_thi_cong_va_nghiem_thu_coc_khoan_nhoi
Quy dinh ky_thuat_thi_cong_va_nghiem_thu_coc_khoan_nhoiQuy dinh ky_thuat_thi_cong_va_nghiem_thu_coc_khoan_nhoi
Quy dinh ky_thuat_thi_cong_va_nghiem_thu_coc_khoan_nhoi
image_verification
 
Giam sat lap dat thiet bi cong nghe va m&e
Giam sat lap dat thiet bi cong nghe va m&eGiam sat lap dat thiet bi cong nghe va m&e
Giam sat lap dat thiet bi cong nghe va m&e
tiendung pham
 
Thiết kế máy đột thủy lực.pdf
Thiết kế máy đột thủy lực.pdfThiết kế máy đột thủy lực.pdf
Thiết kế máy đột thủy lực.pdf
Man_Ebook
 
Thiết kế máy uốn ống.pdf
Thiết kế máy uốn ống.pdfThiết kế máy uốn ống.pdf
Thiết kế máy uốn ống.pdf
Man_Ebook
 
Cẩm nang thiết kế và sử dụng thiết bị đóng cắt.pdf
Cẩm nang thiết kế và sử dụng thiết bị đóng cắt.pdfCẩm nang thiết kế và sử dụng thiết bị đóng cắt.pdf
Cẩm nang thiết kế và sử dụng thiết bị đóng cắt.pdf
Man_Ebook
 

Similar to Phần ii các bước thực hiện thi công piping cho dự án (20)

Dinh-muc-du-toan-lap-dat-he-thong-ky-thuat-cua-cong-trinh
Dinh-muc-du-toan-lap-dat-he-thong-ky-thuat-cua-cong-trinhDinh-muc-du-toan-lap-dat-he-thong-ky-thuat-cua-cong-trinh
Dinh-muc-du-toan-lap-dat-he-thong-ky-thuat-cua-cong-trinh
 
Quy dinh ky_thuat_thi_cong_va_nghiem_thu_coc_khoan_nhoi
Quy dinh ky_thuat_thi_cong_va_nghiem_thu_coc_khoan_nhoiQuy dinh ky_thuat_thi_cong_va_nghiem_thu_coc_khoan_nhoi
Quy dinh ky_thuat_thi_cong_va_nghiem_thu_coc_khoan_nhoi
 
tài liệu cơ sở thiết kế nhà máy
tài liệu cơ sở thiết kế nhà máytài liệu cơ sở thiết kế nhà máy
tài liệu cơ sở thiết kế nhà máy
 
Luận văn: Đề xuất quy trình kiểm định tháp thép Viễn Thông, 9đ
Luận văn: Đề xuất quy trình kiểm định tháp thép Viễn Thông, 9đLuận văn: Đề xuất quy trình kiểm định tháp thép Viễn Thông, 9đ
Luận văn: Đề xuất quy trình kiểm định tháp thép Viễn Thông, 9đ
 
Biện Pháp Thi Công Hệ Điều Hòa Thông Gió
Biện Pháp Thi Công Hệ Điều Hòa Thông Gió Biện Pháp Thi Công Hệ Điều Hòa Thông Gió
Biện Pháp Thi Công Hệ Điều Hòa Thông Gió
 
Giam sat lap dat thiet bi cong nghe va m&e
Giam sat lap dat thiet bi cong nghe va m&eGiam sat lap dat thiet bi cong nghe va m&e
Giam sat lap dat thiet bi cong nghe va m&e
 
đồ áN cung cấp điện đại học điện lực 3683452
đồ áN cung cấp điện đại học điện lực 3683452đồ áN cung cấp điện đại học điện lực 3683452
đồ áN cung cấp điện đại học điện lực 3683452
 
587 qd bxd-dm-lap-dat
587 qd bxd-dm-lap-dat587 qd bxd-dm-lap-dat
587 qd bxd-dm-lap-dat
 
Robot hàn
Robot hànRobot hàn
Robot hàn
 
1172 qd bxd1373984361
1172 qd bxd13739843611172 qd bxd1373984361
1172 qd bxd1373984361
 
Thiết kế máy đột thủy lực.pdf
Thiết kế máy đột thủy lực.pdfThiết kế máy đột thủy lực.pdf
Thiết kế máy đột thủy lực.pdf
 
Thiết kế hệ thống HVAC cho doanh nghiệp
Thiết kế hệ thống HVAC cho doanh nghiệpThiết kế hệ thống HVAC cho doanh nghiệp
Thiết kế hệ thống HVAC cho doanh nghiệp
 
Thuyet minh bien phap thi cong
Thuyet minh bien phap thi congThuyet minh bien phap thi cong
Thuyet minh bien phap thi cong
 
[123doc] - tieu-chuan-ky-nang-nghe-gia-cong-va-lap-dung-ket-cau-thep.pdf
[123doc] - tieu-chuan-ky-nang-nghe-gia-cong-va-lap-dung-ket-cau-thep.pdf[123doc] - tieu-chuan-ky-nang-nghe-gia-cong-va-lap-dung-ket-cau-thep.pdf
[123doc] - tieu-chuan-ky-nang-nghe-gia-cong-va-lap-dung-ket-cau-thep.pdf
 
Quy trinh qlda
Quy trinh qldaQuy trinh qlda
Quy trinh qlda
 
Bmb brochure 2014
Bmb brochure 2014Bmb brochure 2014
Bmb brochure 2014
 
Thiết kế máy uốn ống.pdf
Thiết kế máy uốn ống.pdfThiết kế máy uốn ống.pdf
Thiết kế máy uốn ống.pdf
 
Cẩm nang thiết kế và sử dụng thiết bị đóng cắt.pdf
Cẩm nang thiết kế và sử dụng thiết bị đóng cắt.pdfCẩm nang thiết kế và sử dụng thiết bị đóng cắt.pdf
Cẩm nang thiết kế và sử dụng thiết bị đóng cắt.pdf
 
Bài giảng môn công nghệ chế tạo máy thiết kế đồ gá
Bài giảng môn công nghệ chế tạo máy thiết kế đồ gáBài giảng môn công nghệ chế tạo máy thiết kế đồ gá
Bài giảng môn công nghệ chế tạo máy thiết kế đồ gá
 
0. Bai mo dau.pdf
0. Bai mo dau.pdf0. Bai mo dau.pdf
0. Bai mo dau.pdf
 

More from Nguyen Tung (6)

Master slide for wis5
Master slide for wis5Master slide for wis5
Master slide for wis5
 
Mac thep kiem tra pha huy
Mac thep kiem tra pha huyMac thep kiem tra pha huy
Mac thep kiem tra pha huy
 
Welding consumable control
Welding consumable controlWelding consumable control
Welding consumable control
 
Tig tech
Tig techTig tech
Tig tech
 
Mig mag tech
Mig mag techMig mag tech
Mig mag tech
 
Mag tig welding (messer)
Mag tig welding (messer)Mag tig welding (messer)
Mag tig welding (messer)
 

Phần ii các bước thực hiện thi công piping cho dự án

  • 1. PHẦN: I CÁC BƯỚC THỰC HIỆN THI CÔNG PHẦN PIPING & MECHANICAL
  • 2. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY I. CHUẨN BỊ CÁC VẤN ĐỀ PHỤC VỤ CHO THI CÔNG 1. ĐỌC HIỂU KỸ CÁC SPECIFICATION VÀ CÁC TÀI LIỆU PHỤC VỤ CHO THI CÔNG  Scope Of Work.  Applicable Codes & Standards.  Project Document Numbering. H:LinkP.N.pdf H:LinkP.N.pdf  Data Sheet cho Valves và các thiết bị.  Piping Design Specification.  Piping Fabrication Specification. H:LinkP.F.S.pdf H:LinkP.F.S.pdf  Piping Specifications. H:LinkP.S.pdf H:LinkP.S.pdf  Valve Specifications.  Insulation Specification.  Painting and Protective Coating Specification.  Ngoài ra còn có rất nhiều Spec. cho các thiết bị như: Tanks, Pumps…v.v…
  • 3. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 2. CHUẨN BỊ ĐẦY ĐỦ CÁC BẢNG VẼ (AFC) CẦN PHỤC VỤ CHO THI CÔNG  Bảng vẽ P&ID. ..LinkP&ID.pdf  Isometric AFC. ..LinkISO.AFC.pdf  Piping GA Plan. ..LinkPL.dwg . ..LinkPL.H.bmp  Pipe Support Detail AFC. ..LinkSP.D.pdf  Pipe Support Location Plan. ..LinkSP.L.dwg  Equipment Layout AFC. ..LinkE.L.pdf  Fire Fighting, Safety Equipment Layout & Escape Route. ..LinkS.E.pdf  Pipe Support Standard…vvv…..LinkSP.SD.pdf
  • 4. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 3. VIẾT CÁC QUI TRÌNH DO PHẠM VI DỰ ÁN YÊU CẦU  Piping Fabrication & Erection Procedure.  Mechanical Equipment Installation Procedure.  Valve Leak Test Procedure.  Hydrotest & Flushing Procedure.  Bolt Tensioning Procedure. ..LinkB.T.P.doc  Acid Cleaning Procedure.  Welding Procedure (QC)…
  • 5. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 4. VẬT TƯ TIÊU HAO & CÁC VẤN ĐỀ KHÁC  Dựa vào qui trình hàn, bản vẽ Isometric, khối lượng ống, khối lượng mối hàn và định mức để bốc tách khối lượng que hàn, đá cắt, đá mài… và order mua.  Dựa vào bản vẽ P&ID và Isometric chia các gói Test Package cho Hydrotest.  Bốc tách khối lượng vật tư tiêu hao cho Hydrotest để order mua.  Rà soát lại các thiết bị dụng cụ phục vụ thi công sẵn có và order mua bổ sung số luợng còn thiếu hoặc theo yêu cầu đặt thù của dự án.  Dựa vào số lượng Dia-inch và số lượng hệ thống để chia line, chia hệ và chia nhóm quản lý.  Lập bảng theo dõi tình trạng chế tạo và lắp đặt piping (Piping Fabrication Control Sheet).  Lập bảng theo dõi tình trạng xuất và sử dụng vật tư dự án (Material Control Sheet).  Kiểm tra bảng vẽ AFC.  Viết STQ… ..LinkSTQ.xls
  • 6. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 5. BỐC TÁCH VẬ TƯ CHÍNH CHO DỰ ÁN (MTO)  Dựa vào Isometric bốc tách MTO cho Pipe, Fitting & Valve. ..LinkMTO.P.xls  Piping Specialty List. ..LinkPS.L.pdf  Dựa vào bản vẽ Pipe support bốc tách MTO cho Pipe support. ..LinkM.S.xls  Dựa vào bản vẽ thiết bị bốc tách MTO cho thiết bị.  Dựa vào bản vẽ Safety Sign bốc tách MTO cho Safety Sign.  Ngoài ra còn bốc tách MTO cho Insulation và một số vật tư khác nếu có…  Issue MTO và cập nhật tình trạng để báo cáo tuần.
  • 7. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 3. YÊU CẦU MUA VẬT TƯ (RFQ) & ĐÁNH GIÁ KỸ THUẬT (TBE)  Dựa vào MTO cần đi mua.  Làm RFQ (Requirement for quotation) cho từng gói. ..LinkRFQ.pdf  Làm Inter-memo và gửi kèm RFQ, MTO, Data-sheet, Specifications và các bảng vẽ cần thiết đến bộ phận mua sắm của dự án để gửi đếnn các Vendor chào giá & kỹ thuật. ..LinkI.M.doc  Nhận các đề xuất kỹ thuật từ các Vendor thông qua bộ phận mua sắm. ..LinkT.P.pdf  Làm TBC (Technical Bid Clarification) nếu cần. ..LinkTBC.doc  Làm đánh giá TBE (Technical Bid Evaluation). ..LinkTBE.xls  Làm Inter-memo gửi TBE gửi đến bộ phận mua sắm để chọn Vendor hợp lý nhất để mua vật tư.
  • 8. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY II. TRIỂN KHAI SHOP-DRAWINGS (IFC) 1. BẢN VẼ ISOMETRIC ..LinkISO.dwg  Format form cho bản vẽ shop-drawing.  Chuyển nội dung từ bảng vẽ AFC sang IFC.  Đánh số mối hàn.  Đánh số chi tiết đoạn cắt (Piece-mark).  Chia spools và đánh ký hiệu những mối field weld (FW) hoặc field -fit weld (FFW, nếu hàn ở Offshore).  Đánh số Spools.  Dựa vào Pipedata tính chiều dài các đoạn cắt, lập bảng Cut Pipe Length ..LinkDP.doc  Chọn qui trình hàn và các thông số cần thiết. ..LinkWPS.R.xls  Ghi chú nội dung cần chú ý vào phần ghi chú.  Issue bảng vẽ và cập nhật tình trạng vào “Register” để theo dõi và báo cáo tuần. ..LinkS.R.xls
  • 9. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 2. BẢN VẼ PIPE SUPPORT DETAIL ..LinkPSP.dwg  Tham khảo bảng vẽ Pipe support Standard.  Chọn hướng nhìn.  Vẽ hình dạng support theo các hướng nhìn.  Vẽ hình trích dẫn cho những mối liên kết khó.  Đánh số cho các chi tiết (member).  Ghi ký hiệu mối hàn.  Chọn gốc toạ độ.  Dựa vào bảng vẽ Piece-mark Deck FramingPlan cho Secondary Beam chọn dầm liên kết và trục tham chiếu.  Tính kích thước cho các chi tiết và kích thước tham chiếu.  Lập bảng MTO.  Ghi chú nội dung cần chú ý vào bảng vẽ.  Issue bảng vẽ và cập nhật tình trạng vào Register để theo dõi và báo cáo tuần.
  • 10. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 3. BẢN VẼ LẮP ĐẶT THIẾT BỊ (Equipment Layout) ..LinkS.E.L.dwg  Dựa vào bản vẽ chi tiết của thiết bị từ Vendor.  Dựa vào bảng vẽ Layout của Structural.  Dựa vào bảng vẽ Piping GA Plan.  Kiểm tra toạ độ các Nozzle và đối chiếu với toạ độ đấu ống trên Isometric.  Chọn gốc toạ độ chuẩn lắp đặt.  Tính toán các kích thước lắp đặt.  Gia cố support khi cần thiết.  Lập bảng vẽ Shop Drawing Equipment Layout.  Issue bảng vẽ và cập nhật tình trạng vào Register để theo dõi và báo cáo tuần.
  • 11. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 4. CUTTING PLAN  Lập cutting plan cho cắt ống. ..LinkCP.P.pdf  Xuất dữ liệu từ bảng pipe cutting length của bảng vẽ Isometric IFC ra Excel.  Chọn lọc và tách các đoạn cắt theo từng loại vật tư. ..LinkX.DL.doc  Dùng lệnh hổ trợ trong Autocad để chạy tự động Cutting Plan.  lập cutting plan cho cắt pipe support. ..LinkCP.S.pdf  Xuất dữ liệu từ bảng MTO của bảng vẽ pipe support detail IFC ra Excel.  Các bước tiếp theo tương tự như lập Cutting plan cho cắt ống.  Issue Cutting Plan và cập nhật tình trạng để báo cáo tuần.
  • 12. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY III. TRIỂN KHAI THI CÔNG 1. LẬP LỆNH SẢN XUẤT ..LinkLSX.DOC  Dựa vào định mức.  Dựa vào bảng vẽ thi công.  Tính toán khối lượng công việc.  Tính toán số luợng nhân công.  Đưa ra ngày bắt đầu và kế thúc.  Giao lệnh sản xuất & kèm theo bản vẽ thi công cho tổ thi công.
  • 13. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 2. XUẤT VẬT TƯ CHO THI CÔNG ..LinkM.C.S.xls  Dựa vào bảng vẽ thi công.  Dựa vào lệnh sản xuất.  Lập phiếu xuất vật tư theo form mẫu phù hợp với từng loại vật tư:  Vật tư do công ty mua. ..LinkY.CT.doc  Vật tư do chủ đầu tư mua. ..LinkY.N.doc  Nhận vật tư từ kho.  Bàn giao vật tư cho từng tổ thi công. ..LinkB.G.xls  Cập nhật tình trạng vật tư vào “Material Control Sheet” để theo dõi.
  • 14. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 3. TRIỂN KHAI CẮT ỐNG HOẶC PIPE SUPPORT  Lập requet cho QC kiểm tra kích thước và lấy dấu trước khi cắt. ..LinkRD.xls  Cắt ống hoặc support theo QC đã lấy dấu.  Bàn giao các đoạn đã cắt cho từng tổ thi công.  Cập nhật tình trạng để theo dõi.
  • 15. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 4. TRIỂN KHAI FIT-UP  Mài Bevel các đầu ống, fitting hoặc vật tư pipe support. ..LinkB.V.doc  Dùng đồ gá và các dụng cụ cần thiết để gá ống.  Hàn đính các mối lắp. ..LinkFU.doc  Kiểm tra khe hở và độ lệch mếp.  Báo cáo khối luợng fit-up.  Làm request cho QC kiểm tra fit-up. ..LinkRF.xls  Cập nhật tình trạng fit-up vào “Piping Control Sheet” để theo dõi. ..LinkF.C.R.xls ..LinkWR.D.xls
  • 16. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 5. TRIỂN KHAI HÀN ..LinkH.doc  Chọn thợ hàn có tay nghề phù hợp với vật liệu cần hàn.  Chọn qui trình hàn phù hợp với mối hàn cần hàn.  Tiến hành hàn theo qui trình hàn cần tham khảo. ..LinkWPS.xls  Báo cáo khối luợng hàn.  Làm request cho QC kiểm tra visual. ..LinkRV.xls  Đóng và treo Tagname cho từng spool theo bản vẽ Isometric.  Cập nhật tình trạng hàn vào “Piping Control Sheet” để theo dõi.
  • 17. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 6. KIỂM TRA VISUAL MỐI HÀN (QC)  Kiểm tra mối hàn bằng mắt (visual) để định chất lượng mối hàn (QC).  Báo cáo kết quả visual (QC).  Nhận báo cáo kết quả visual từ QC.  Cập nhật tình trạng visual vào “Piping Control Sheet” để theo dõi.
  • 18. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 7. KIỂM TRA NDT MỐI HÀN (Nhà thầu phụ, QC & Production cùng thực hiện)  Chuyển những spools cần RT đến bãi chup RT. (Pro.). ..LinkMR.doc ..LinkBG.xls  Làm request NDT. (QC).  Chụp RT mối hàn cho các spools. (Thầu phụ).  MPI, DPI, PI hoặc UT mối hàn cho các spools. (Thầu phụ).  MPI 10% đối với pipe support. (Thầu phụ).  Báo cáo kết quả NDT. (Thầu phụ).  Mang những spools đã chụp RT xong vào lại bãi thi công và cập nhật tình trạng NDT vào “Piping Control Sheet” để theo dõi. ..LinkMV.doc
  • 19. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 7. GIA NHIỆT MỐI HÀN-PWHT (Nhà thầu phụ, QC & Production cùng thực hiện) ..LinkGN.doc  Chuyển những spools có mối hàn sau khi đã RT lần 1 và cần gia nhiệt đến bãi gia nhiệt. (Pro.).  Làm request cho gia nhiệt. (QC).  Làm gia nhiệt. (Thầu phụ).  Báo cáo kết quả gia nhiệt. (Thầu phụ).  Làm RT lần 2. (Thầu phụ).  Báo cáo kết quả RT lần 2. (Thầu phụ).  Cập nhật tình trạng gia nhiệt & RT lần 2 vào “Piping Control Sheet” để theo dõi.
  • 20. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 8. SƠN SPOOLS VÀ PIPE SUPPORT  QC dựa vào kết quả NDT issued list release các spools hoặc pipe support cần mang đi sơn.  Chuyển những spools hoặc pipe support theo list release đến bãi sơn.  Bàn giao các spools hoặc pipe support này cho bộ phận sơn. ..LinkBDS.doc  Theo dõi tình trạng sơn.  Mang những spools hoặc pipe support đã sơn xong về tập kết tại khu vực chuẩn bị lắp đặt.  Ngoài ra một số thiết bị hoặc Valves mà Vendor chưa sơn hoặc sơn chưa đúng code thì cũng bàn giao cho bộ phận sơn để sơn lại.  Cập nhật tình trạng sơn vào “Piping Control Sheet” để theo dõi.
  • 21. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 9. LẮP ĐẶT  Trước tiên chuẩn bị đầy đủ các bảng đã nêu ở trên.  Lập kế hoạch lắp đặt cho thiết bị và các đường ống.  Thiết bị phải lắp trước để có cơ sở lắp & đấu nối các đường ống vào các Nozzles.  Qui hoạch các thiết bị chính và hệ thống ống chính phải ưu tiên lắp trước.  Lập lệnh sản xuất cho từng gói lắp đặt.  Lập và đánh giá JSA cho các gói lắp đặt có nguy cơ nguy hiểm cao.  Order các thiết bị và dụng cụ cần thiết để phục vụ lắp đặt.  Đưa các thiết bị, spools và valves cần lắp vào vị trí.  Cân chỉnh & Fit cố định thiết bị trước sau đó đấu nối các line ống vào các nozzles.
  • 22. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY  Hàn cố định những chân hoặc support cho các thiết bị.  Dùng bulông tạm để lắp tạm những mối nối bằng mặt bích.  Dùng spools tạm để gá, lắp cho những vị trí valve hoặc thiết bị trên đường ống mà chưa về hoặc không yêu cầu lắp trước hydrotest.  Fit-up và request yêu cầu kiểm tra fit-up những mối FW.  Hàn, và request yêu cầu kiểm tra visual và làm NDT những mối FW.  Cập nhật tình trạng fit-up, weld, NDT và số lượng spools lắp được vào Piping Control Sheet để theo dõi.  Lắp những Stud-bolt, Gasket và Valves cần lắp trước hydrotest.  Siết bulông cho những mối nối mặt bích cần thiết trước khi hydrotest. ..LinkX.BL.doc
  • 23. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 10. HYDROTEST (HT)  Chuẩn bị và update các gói thử trước khi test.  Tiến hành cùng với QC đi line checking và lập “Punch List”.  Clear những item thuộc “category A” trong Punch list trước khi HT.  Tiến hành cùng QC và QC chủ đầu tư kiểm tra lại những item A đã được clear.  Làm request đề nghị QC chủ đầu tư kiểm tra dự liệu trong test package, ký Chart Page và tiến hành làm chứng (witness) trong quá trình thử HT.  Rửa sạch (Flushing) hệ thống ống cần test trước khi HT.  Thử hydrotest. (Tuỳ theo yêu cầu của thiết kế một số gói thử có thể test bằng khí N2 hoặc service test mà thôi). ..LinkHT.doc  Làm sạch lại và thổi khô hệ thống ống bằng khí nén.  Ký nghiệm thu “check sheet” cho quá trình Flushing và thử HT.  Cập nhật tình trạng hydrotest vào “Hydotest Register” để theo dõi. ..LinkH.R.xls
  • 24. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 11. REINSTATEMENT ..LinkRT.doc  Lắp hoàn thiện lại hệ thống sau khi hoàn thiện hydrotest xong.(tất cả dùng vật tư chính thức).  Phối hợp với bộ phận E & I để nhận và lắp các thiết bị điện mà bộ phận piping phải lắp.  Tiến hành siết bulông những mặt bích chưa siết trong quá trình HT theo đúng qui trình.  Tiến hành clear toàn bộ những item thuộc “category B” trong punch list.  Ký nghiệm thu những check sheet còn lại thuộc phần reinstatement cùng với QC và QC chủ đầu tư (kể cả những gói thiết bị).  Bàn giao tất cả Test Package và công việc còn lại thuộc phần chạy thử (commissioning) cho bộ phận Re-com.  Hổ trợ bộ phận re-com. thực hiện những công việc trong quá trình chạy thử mà theo yêu cầu từ bộ phận re-com.
  • 25. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY 12. CÔNG VIỆC HOÀN THIỆN CUỐI CÙNG  Hoàn thiện những công việc còn tồn đọng lại sau khi các hệ thống đã chạy thử xong.  Hoàn thiện những item còn tồn đọng cuối cùng thuộc “category C” trong punch list.  Hoàn thiện những công việc “page work” còn tồn đọng cuối cùng.  Phối hợp giữa các bộ phận re-com. và QC để bàn giao dự án cho chủ đầu tư.  Kết thúc dự án.
  • 26. HƯỚNG DẪN CÁC BƯỚC THỰC HIỆN THI CÔNG & QUẢN LÝ DỰ ÁN BỘ PHẬN: XƯỞNG CƠ KHÍ & LẮP MÁY “KẾT THÚC PHẦN I”