2. STATUS REPORT OF MY HOME ABHRA Tower-
”A” As On 09.12.13
1.1st To 12th Floor Slabs: Completed
2.13th Floor Slab : Flat No 1 & 2 flats Slab completed, 4&5 flats Slab planning Today,3 rd flats Shuttering work In progress
3. STATUS REPORT OF MY HOME ABHRA Tower1.1st To 12th Floor Slabs : Completed
”B” As On 09.12.13
4. STATUS REPORT OF MY HOME ABHRA Tower-
”C” As On 09.12.13
1.1st To 10th Floor Slabs : Completed
2. Brick Work: 6th Floor External walls in Progress
5. STATUS REPORT OF MY HOME ABHRA Tower-
”D” As On 09.12.13
1.1st To 13th Floor Slabs : Completed
2.14th Floor Slab : Flat No 1 and 2 slabs Complete Today ,4 and 5 flat Slabs Shuttering Work Progress,3 rd Flat Columns work In Progress
3.Brick Work: 8th Floor External walls in Progress
6. STATUS REPORT OF MY HOME ABHRA Tower-
”E” As On 09.12.13
1.1st To 13th Floor Slabs : Completed
2.14th Floor Slab : Flat No 1&2 Slab Completed ,4 & 5 flats Bar bending work Progress, 3 rd Flat Columns work in Progress .
7. STATUS REPORT OF MY HOME ABHRA Tower-
”E” As On 09.12.13
1.1st To 13th Floor Slabs : Completed
2.14th Floor Slab : Flat No 1&2 Slab Completed ,4 & 5 flats Bar bending work Progress, 3 rd Flat Columns work in Progress .