REimagining Yonge Street
REIMAGINING YONGE STREET
SHEPPARD AVENUE TO FINCH AVENUE
Source: Bing Maps
ENVIRONMENTAL ASSESSMENT STUDY
PUBLIC OPEN HOUSE 1 - MAY 25, 2016
25/05/2016 1
REimagining Yonge Street
Welcome to the first Public
Open House for the
REimagining Yonge Street
from Sheppard Avenue to
Finch Avenue Environmental
Assessment Study.
The information displayed today is available online at
www.toronto.ca/reimaginingyonge
WELCOME
2
REimagining Yonge Street
IDENTIFY
PROBLEM OR
OPPORTUNITY
RESEARCH
NATURAL,
CULTURAL,
SOCIO-
ECONOMIC
ENVIRONMENT
CONDITIONS
IDENTIFY
ALTERNATIVE
SOLUTION(S)
AND
EVALUATION
CRITERIA
DESIGN
CHARRETTE
EVALUATE
ALTERNATIVE
SOLUTION(S)
SELECT
PREFERRED
SOLUTION(S)
AND DEVELOP
DESIGN
OPTIONS
EVALUATE
DESIGN
OPTIONS
REPORT TO
COUNCIL &
COMPLETE
THE FINAL
REPORT (30
DAY REVIEW
PERIOD)
This study is being carried out as a Schedule C project according to the
Municipal Class Environmental Assessment (EA) process. This is an
approved assessment approach for municipal infrastructure projects under
the provincial Environmental Assessment Act.
There will be opportunities for public input throughout the study, and at the milestones shown in blue.
THE PROJECT & STUDY PROCESS
APRIL 2016 APRIL / MAY 2016 MAY 2016 JUNE 9+11, 2016 JUNE / JULY 2016 JULY 2016 AUGUST-
OCTOBER 2016
DECEMBER 2016-
JANUARY 2017
We are here
3
25/05/2016 2
REimagining Yonge Street
STUDY AREA
In the study focus area, alternatives will focus on
changes to Yonge Street, and mitigating effects to
Beecroft Road, Doris Avenue and east/west streets.
4
Steeles Avenue
Wilson Avenue
York Mills
Road
REimagining Yonge Street
ACCOMMODATING PLANNED GROWTH
The Growth Plan for the Greater Golden Horseshoe promotes accessible public
infrastructure that is essential to the viability of Ontario’s communities and
critical to economic competitiveness, quality of life and the delivery of public
services.
The Growth Plan identifies North York Centre as an urban growth centre.
Accommodating the role as an Urban
Growth Centre requires investment on
Yonge Street, and we must plan for the
ways transportation is changing – ride-
share services like Uber, autonomous and
connected vehicles and declining vehicle
ownership are changing the way we plan
streets and cities.
The City’s vision for North York Centre is that it
should be supported by active transportation
modes. To increase the number of people
moving by transit, walking and cycling, we need
to:
• Make better use of the available street
space to move more people
• Make Yonge
Street a
better public
space, so
people will
want to use it
as a place to
enjoy
The City needs to plan for the future in North York Centre – the
area is continuing to grow:
POPULATION GROWTH
11.2%
Increase from
2006 to 2011
ACTIVE DEVELOPMENT IN
NORTH YORK CENTRE
(April 2016)
• 12 active development proposals
• 3,868 residential units
• 57,134 sq.m. of non-residential
Connected vehicles
5
REimagining Yonge Street
TRANSPORTATION TRENDS AND IMPROVEMENTS
Introduction of VIVA, GO Transit buses, and other transit
improvements resulted in more than a 10% reduction in severe
congestion on Yonge Street south of Steeles Avenue.
Proposed transit improvements include a subway signaling
system upgrade (allowing reduced headways and additional
trains), and the Yonge Subway Extension.
The planned increase in transit capacity is expected to reduce
congestion on Yonge Street.
Proposed improvements to the service road network
will result in reduced traffic demands and improved
operations on Yonge Street.
The City is planning for a connection of Doris Avenue to
Tradewind Avenue to enhance the service road system, under
the North York Centre South Service Road – EA Addendum
Study, a separate process and EA study. That connection is
expected to help accommodate traffic demand.
6
Source: City of Toronto
25/05/2016 3
REimagining Yonge Street
PROBLEM AND OPPORTUNITY
STATEMENT
North York Centre is one of four centres in the City focused on
transit-based employment and residential growth. At its core is
Yonge Street from Sheppard Avenue to north of Finch
Avenue, envisioned as one of the city's primary pedestrian
promenades with a vibrant urban environment that promotes
walking, cycling and safe passage across the street.
Today the area is faced with challenges from inconsistent features
such as sidewalks, pedestrian crossings and medians to lack of
dedicated cycling facilities and concerns over traffic movement.
The City is looking at ways to create an attractive and consistent
streetscape with design appropriate to the civic goals of the North
York Centre that will serve people of all ages as they travel in and
around the area for work, school and leisure.
7
REimagining Yonge Street
EXISTING CONDITIONS
SAFETY
The maps show vehicular collisions and
pedestrian/cyclist injuries from 2012 to 2014
throughout the study corridor.
Key Findings:
• Section between Finch Avenue and Cummer
Avenue accounts for 42% (455 of 1070) of
total vehicle collisions, and 55% (36 of 66) of
total pedestrian/cyclist injuries.
• 66 total pedestrian/cyclist injuries: 63 minor
injuries and 3 KSI (Killed or Seriously Injured)
including 1 pedestrian fatal injury and 2
pedestrian major injuries.
• The Yonge Street/Sheppard Avenue
intersection has the highest number of
vehicle collisions (177) but a relatively small
number of pedestrian/cyclist injuries (6).
• The sections where a median exists have
fewer collisions – particularly for cyclists and
pedestrians.
8
REimagining Yonge Street
EXISTING CONDITIONS
PEDESTRIAN CROSSING AND LANDSCAPED MEDIAN LOCATIONS
• There are significant gaps along Yonge Street between
controlled pedestrian crossing points.
• The raised median acts as a “refuge” in the centre of
the road, allowing pedestrians to cross one direction of
traffic at a time.
• Perceived pedestrian delay to cross Yonge Street at
Kempford Boulevard.
• Where a centre turn lane exists, pedestrians must cross
7 lanes when gaps in traffic coincide in both directions
or wait in the centre turn lane.
• There is the potential for a raised median in sections
where the existing centre turn lane is not required for
left turns into side roads or driveways.
9
REimagining Yonge Street
CURRENT CYCLING
TRIPS
CURRENT TRIPS. This map shows the total number of
cycling trips originating or ending in the study area.
This map also shows existing and planned bike facilities.
Data Source: City of Toronto /
Transportation Tomorrow Survey, 2011
Demand for bike parking
can exceed supply: Existing bike parking:
10
REimagining Yonge Street
TRANSPORTATION OPERATIONS
STUDY AREA
Traffic conditions have been assessed
based on current weekday a.m. and p.m.
peak hour volumes.
Key Findings:
• Almost all major north-south roads
operate with adequate capacity
throughout the day.
• Both service roads, Beecroft Road and
Doris Avenue, have unused capacity in
both directions.
• Willowdale Avenue experiences
congestion in both directions in the
vicinity of the TTC commuter parking
lot.
• Traffic growth has been relatively flat
in the last decade on Yonge Street.
Peak period queues
11
Intersections
AM Peak Level
of Service
Good
Fair
Poor
PM Peak Level
of Service
REimagining Yonge Street
TRANSPORTATION OPERATIONS
STUDY FOCUS AREA
Existing traffic conditions have been assessed based on
weekday morning and evening peak hour volumes. we have
assessed Yonge Street, Beecroft Road and Doris Avenue.
Changes to Yonge Street could result in effects on these
parallel streets.
Existing traffic volumes show that all intersections on Beecroft
Road and Doris Avenue, the service roads parallel to Yonge
Street, operate at acceptable levels of service. These
intersections have unused capacity in both directions, and are
able to accommodate additional traffic from Yonge Street.
Intersections
Corridors
AM Peak Level
of Service
Good
Fair
Poor
PM Peak Level
of Service
Transit
AM Peak Queue
PM Peak Queue
Subway Station
34 bus routes use Yonge or the 2 bus
terminals.
During peak periods:
• Most TTC buses operate every 3
to 6 minutes
• GO buses operate every 20 to 30
minutes
• VIVA operates every 15 minutes
• YRT operates every 20 to 30 +
minutes
12
More people are also travelling to North York Centre by transit
and active modes.
REimagining Yonge Street
EXISTING CONDITIONS
PUBLIC AND PRIVATE PARKINGFrom Drewry Avenue / Cummer
Avenue to Tolman Street
From Tolman Street to Park Home
Avenue / Empress Avenue
From Empress Avenue to
Sheppard Avenue
On street parking: 331 spaces
Off-street: 7952 spaces
Total spaces: 8283 spaces
On street parking: 259 spaces
Off-street: 915 spaces
Total spaces: 1174 spaces
Parking is available on most streets in
the study focus area, and in many off-
street lots and garages.
PARKING
SUPPLY
On street parking: 61 spaces
Off-street: 6174 spaces
Total spaces: 6239 spaces
There are high levels of demand for
parking on weekdays in some parts of
the study focus area.
Demand is lower on the weekend.
As part of this study, we will be
conducting a parking utilization study
to understand how the existing
parking is currently being used.
13
Sheppard Avenue East
Finch Avenue West
25/05/2016 4
REimagining Yonge Street
EXISTING CONDITIONS
CULTURAL AND NATURAL ENVIRONMENTS
The study area is highly urbanized and vegetation is limited.
The vegetation is primarily limited to planted trees.
The study area has a rich history, evident by the heritage / historical
plaques, and cultural institutions found along and adjacent to
Yonge Street.
.
Gibson House Museum
Park
St. George Anglican ChurchRose Garden
Sheppard House Historical Plaque
Princess Park – Fire Tower
14
REimagining Yonge Street
EXISTING CROSS SECTIONS
NORTHERN PORTION OF THE STUDY AREA
1. NORTH OF BISHOP AVENUE
Looking North
3. SOUTH OF ELLERSLIE AVENUE
Looking North
2. SOUTH OF FINCH AVENUE
Looking North
Public Right-of-Way = 36.15 metres
Public Right-of-Way = 34.70 metres
Public Right-of-Way = 35.02 metres
The curb lanes provide
parking during off-peak times.
15
REimagining Yonge Street
EXISTING CROSS SECTIONS
SOUTHERN PORTION OF THE STUDY AREA
6. NORTH OF ELMHURST/GREENFIELD AVENUE
Looking North
5. SOUTH OF HOLLYWOOD AVENUE
Looking North
7. NORTH OF SHEPPARD AVENUE
Looking North
Public Right-of-Way = 37.30 metres
Public Right-of-Way = 34.43 metresPublic Right-of-Way = 34.09 metres
4. NORTH OF HILLCREST AVENUE
Looking North
Public Right-of-Way = 36.76 metres
The curb lanes provide parking during off-peak times.
16
REimagining Yonge Street
How would you improve the street ? Please add
your ideas on “post-it” notes to the blank circles.
We have opportunities to …
PUBLIC REALM / STREETSCAPE
HAVE YOUR SAY
Manage
congestion
17
Plant trees
Add cycle
tracks or bike
lanes
Re-align
traffic lanes
Expand sidewalks
and boulevard
widths, and
improve crossings
Enhance the
streetscape
Integrate adjacent
public spaces
REimagining Yonge Street
OPPORTUNITIES TO INTEGRATE
PUBLIC SPACES
One goal is to enhance connections and integration with public spaces.
Potential locations are shown here.
Are there other locations? Please tell
us by adding your post-it note.
Rose Garden
Historic Cemetery
Federal Building
Olive Square
Mel Lastman Square
18
REimagining Yonge Street
STREET DESIGN ELEMENTS
HAVE YOUR SAYWhat do you like or dislike? Do you support this element along
Yonge Street? Why or why not?
Cycle Track
At-grade
planters
Wide sidewalks
Public Art
Street Trees
Street furniture
Landscaped
MedianOn-street
Parking
Separated Bike Lane
19
REimagining Yonge Street
Do you know other streets or
ideas we should consider?
Add a post-it note to tell us
about them.
POTENTIAL VISIONS FOR YONGE STREET
We are researching streets from around the world…
Kitchener
Credit Cory Bluhm
Seattle, WA
Austin, TX
Montreal
Credit: Google Earth
New York, NY
20
REimagining Yonge Street
ALTERNATIVES FOR YONGE STREET
1
Do Nothing
3
Modify
Travel Lanes
Curb
Relocation
Landscaped
Median: Remove,
Narrow, Enhance,
or Extend
4
Transform
2
Enhance
No change No changeProceed with
existing plans
No change
Consider reduction
from 6 lanes to 4 in
sections
Reduce from 6
lanes to 4,
throughout the
corridor
Consider minor
improvement
options
Consider options
in strategic
locations
Consider options
throughout the
corridor
Extensive relocation
No change
Changes in strategic
locations
Proposed Components
Trees &
Planters, Public
Art, Street
Furniture
Wider
Sidewalk
Enhance /
Expand
Pedestrian
Crossings
No changeEnhance as
redevelopment
occurs
Fix existing sidewalk
and enhance as
redevelopment
occurs
Enhance at
strategic locations
Enhance at
strategic locations
Enhance corridor-
wide
Widen throughout
the corridor
Widen in
redevelopment
areas and other
strategic locations
Enhance as
redevelopment
occurs
Add in strategic
locations
Add in strategic
locations
Enhance throughout
the corridor;
consider new
features
Alternative
Business as usual:
continue implementing
the existing plan as
development proceeds
Minor Improvements
to the streetscape and
transportation
operations at strategic
locations
Minor reconstruction in
strategic locations, to
improve the
streetscape and
pedestrian facilities,
and bike facilities
Major reconstruction to
create a multi-modal
street and enhanced
streetscape, including
cycle tracks, and
enhanced pedestrian
facilities
Description Bike Facilities
No change
Consider bike
facilities
Consider bike
facilities
No change
21
REimagining Yonge Street
ALTERNATIVE 1: DO NOTHING
ALTERNATIVE 3: MODIFY
ALTERNATIVES FOR YONGE STREET
ALTERNATIVE 2: ENHANCE
New element
New element New element
22
New element
REimagining Yonge Street
ALTERNATIVE 4A: TRANSFORM
ALTERNATIVES FOR YONGE STREET
ALTERNATIVE 4B: TRANSFORM
* *
* Parking lane during off-peak periods
23
ALTERNATIVE 4D: TRANSFORMALTERNATIVE 4C: TRANSFORM
REimagining Yonge Street
ALTERNATIVE 4E: TRANSFORM
ALTERNATIVES FOR YONGE STREET
ALTERNATIVE 4G: TRANSFORM
24
ALTERNATIVE 4H: TRANSFORM
ALTERNATIVE 4F: TRANSFORM
REimagining Yonge Street
EVALUATION CRITERIA
Accessibility, Mobility &
Transportation
Infrastructure
Natural Environment Cycling and Walking Cultural Heritage & Built
Heritage Resources
• Adherence to City design
standards and guidelines for
transportation facilities
• Accessibility (Compliance with
City’s Accessibility Standards and
provincial guidelines)
• Promotes effective movement of
people and goods
• Transportation network capacity
• Parking capacity
• Intersection operations and
Transportation efficiency
• Safety for users
• Minimizes impacts on
vegetation communities and
existing trees
• Wildlife and wildlife habitat
• Maximizes opportunity for
street tree planting in
optimized urban condition
that provides for the long
term health of the trees
• Ability to introduce new
cycling facilities
• Ability to improve pedestrian
facilities
• Supports sustainable
transportation
• Compatibility with City’s
Cycling Network plans
• Connectivity to lands adjacent
to Yonge Street
• Impacts on built heritage
resources
• Impacts on cultural heritage
landscapes
• Potential archaeological
resources
Have we missed anything? Add your comments on a post-it note in the space above.
25
REimagining Yonge Street
EVALUATION CRITERIA
Have we missed anything? Add your comments on a post-it note in the space above.
Costs Constructability &
Utilities
Community Planning Design Excellence
• Construction costs
• Maintenance/operational
costs
• Life cycle costs
• Transit, pedestrian, road, and bike
mobility through the study and
duration of disruption for each
mode
• Number of construction stages and
duration
• Number and scale of existing
utilities affected
• Potential utility conflicts
• Effects on business during
construction
• Supports Yonge Street’s role as a
special public space
• Encourages vibrant, mixed-use
development
• Effects on business (e.g., retail)
• Impacts to Private Property
• Compatibility with existing
planning policy and
environmental assessments
• Noise effects
• Effect on emergency services
• Percentage of the right-of-way
dedicated to public realm uses such as
pedestrian facilities, public art, and
street furniture
• Supports design excellence of
infrastructure and streetscape.
Maximizes impact of corridor on
design of adjacent development
• Enhances the attractiveness of urban
environment and creates place-making
opportunities
• Supports integration with public
spaces
26
25/05/2016 5
REimagining Yonge Street
WHAT YOU’VE TOLD US
SO FAR…
We have been conducting a survey of residents and visitors to help us gather information about how
Yonge Street is used and to identify opportunities and challenges. This survey will inform the study
process, but is not a formal poll.
Interviews were conducted along Yonge Street on Tuesday, May 10, 2016, and the survey is available
on the project website until June 8, 2016. Over 500 surveys have been completed to-date. Key
results are as follows:
0
50
100
150
200
250
300
350
Morning Lunchtime Afternoon Dinnertime Late night Weekends
When are you on Yonge Street?
If you were making one big change to
Yonge Street, it would be:
0
50
100
150
200
250
300
How do you use Yonge Street?
Responses
36%
4%
38%
9%
13%
Most Liked about Yonge Street
Convenient for Walking Convenient for Cycling
Well-served by Transit Convenient for driving
Other
8%
13%
19%
15%
35%
10%
Least liked about Yonge Street
Insufficient Sidewalk Space Lack of Cycling Facilities
Lack of Streetscape Design Poor Conditon of Streetscape
High Traffic Volume Other
Common “Other” responses
include:
• Lack of safe pedestrian
crosswalks
• Lack of parking
• Aesthetics / Streetscape
Design
Common “Other” responses
include:
• The mix and wide variety of
uses, including retail,
services, restaurants, etc.
• Convenience and
accessibility of the area to
transit and highway access
• The level of street activity
and diversity along the
study area
57%
of people surveyed to-date use
Yonge Street for more than one
purpose.
27
25/05/2016 6
REimagining Yonge Street
What is a charrette?
• A charrette is a planning
and design session where
members of the public
work with the Project
Team to collaborate on a
vision for the plan.
• It provides a forum for
ideas and offers the unique
advantage of a
collaborative design
process.
DESIGN CHARRETTE
Your Chance to Participate
INTERESTED IN
PARTICIPATING IN THE
CHARRETTE?
SIGN UP AT THE
FRONT DESK OR
ONLINE
Once available, more information about the charrette
will be posted on the project web page:
www.toronto.ca/reimaginingyonge
What is the purpose?
• The intent is to build on
data gathering and analysis
efforts by the Project Team
to produce alternatives for
a preferred design while
creating a joint vision with
the community.
Thursday June 9 and Saturday June 11, 2016
28
25/05/2016 7
REimagining Yonge Street
After this Public Open
House, the Project
Team will:
• Review and respond to
comments;
• Meet with stakeholders,
external agencies, and a
technical advisory
committee;
• Host Design Charrette
(June 9 and 11, 2016);
• Evaluate the
alternatives; and,
• Prepare for a second
Public Open House (July
25, 2016).
NEXT STEPS
STAY CONNECTED
Kate Nelischer
Senior Public Consultation Coordinator
City of Toronto
Metro Hall, 19th Floor
55 John Street
Toronto, ON M5V 3C6
Tel: 416-392-4360 or Fax: 416-392-2974
Email: knelischer@toronto.ca
THANK YOU
FOR ATTENDING
TODAY’S
PUBLIC OPEN HOUSE
The information presented today is available online at
www.toronto.ca/reimaginingyonge
29

More Related Content

What's hot

Presentation for public information centres
Presentation for public information centresPresentation for public information centres
Presentation for public information centresknelischer
 
John Street Open House Display Boards
John Street Open House Display BoardsJohn Street Open House Display Boards
John Street Open House Display Boardsknelischer
 
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides Toronto Public Consultation Unit
 
John Street Corridor Improvements - Stakeholder Meeting Presentation
John Street Corridor Improvements - Stakeholder Meeting PresentationJohn Street Corridor Improvements - Stakeholder Meeting Presentation
John Street Corridor Improvements - Stakeholder Meeting Presentationknelischer
 
Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014West Central Association
 
Beacon Street Construction Proposal 10/15/12
Beacon Street Construction Proposal 10/15/12Beacon Street Construction Proposal 10/15/12
Beacon Street Construction Proposal 10/15/12Samantha Coren
 
Central-East Open House - Laird Station to West At-Grade (Sunnybrook - O'Conn...
Central-East Open House - Laird Station to West At-Grade (Sunnybrook - O'Conn...Central-East Open House - Laird Station to West At-Grade (Sunnybrook - O'Conn...
Central-East Open House - Laird Station to West At-Grade (Sunnybrook - O'Conn...Crosstown TO
 
Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14West Central Association
 
Clifton Avenue Streetscape Design - Posters
Clifton Avenue Streetscape Design - PostersClifton Avenue Streetscape Design - Posters
Clifton Avenue Streetscape Design - PostersJake Henderson
 
Urban Design and Street Typology: Do They Matter?
Urban Design and Street Typology: Do They Matter?Urban Design and Street Typology: Do They Matter?
Urban Design and Street Typology: Do They Matter?William Riggs
 
Fulton Market Streetscape - July 15th, 2014 Workshop
Fulton Market Streetscape - July 15th, 2014 WorkshopFulton Market Streetscape - July 15th, 2014 Workshop
Fulton Market Streetscape - July 15th, 2014 WorkshopWest Central Association
 
Manor Park Neighborhood Urban Park
Manor Park Neighborhood Urban ParkManor Park Neighborhood Urban Park
Manor Park Neighborhood Urban ParkJose Carlos Ayala
 
New Street Typologies/New Street Types - Getting more out of the same R.O.W.:...
New Street Typologies/New Street Types - Getting more out of the same R.O.W.:...New Street Typologies/New Street Types - Getting more out of the same R.O.W.:...
New Street Typologies/New Street Types - Getting more out of the same R.O.W.:...Congress for the New Urbanism
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house Crosstown TO
 

What's hot (20)

Steeles Avenue East Bridge Study PIC 1
Steeles Avenue East Bridge Study PIC 1Steeles Avenue East Bridge Study PIC 1
Steeles Avenue East Bridge Study PIC 1
 
Presentation for public information centres
Presentation for public information centresPresentation for public information centres
Presentation for public information centres
 
John Street Open House Display Boards
John Street Open House Display BoardsJohn Street Open House Display Boards
John Street Open House Display Boards
 
Lower Don Valley Trail 2015 Construction
Lower Don Valley Trail 2015 ConstructionLower Don Valley Trail 2015 Construction
Lower Don Valley Trail 2015 Construction
 
Lawrence Park PIC 3 slides
Lawrence Park PIC 3 slidesLawrence Park PIC 3 slides
Lawrence Park PIC 3 slides
 
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
 
John Street Corridor Improvements - Stakeholder Meeting Presentation
John Street Corridor Improvements - Stakeholder Meeting PresentationJohn Street Corridor Improvements - Stakeholder Meeting Presentation
John Street Corridor Improvements - Stakeholder Meeting Presentation
 
Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014
 
Beacon Street Construction Proposal 10/15/12
Beacon Street Construction Proposal 10/15/12Beacon Street Construction Proposal 10/15/12
Beacon Street Construction Proposal 10/15/12
 
2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final
 
Central-East Open House - Laird Station to West At-Grade (Sunnybrook - O'Conn...
Central-East Open House - Laird Station to West At-Grade (Sunnybrook - O'Conn...Central-East Open House - Laird Station to West At-Grade (Sunnybrook - O'Conn...
Central-East Open House - Laird Station to West At-Grade (Sunnybrook - O'Conn...
 
Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14
 
Clifton Avenue Streetscape Design - Posters
Clifton Avenue Streetscape Design - PostersClifton Avenue Streetscape Design - Posters
Clifton Avenue Streetscape Design - Posters
 
Urban Design and Street Typology: Do They Matter?
Urban Design and Street Typology: Do They Matter?Urban Design and Street Typology: Do They Matter?
Urban Design and Street Typology: Do They Matter?
 
Shops at University Town Center
Shops at University Town CenterShops at University Town Center
Shops at University Town Center
 
Fulton Market Streetscape - July 15th, 2014 Workshop
Fulton Market Streetscape - July 15th, 2014 WorkshopFulton Market Streetscape - July 15th, 2014 Workshop
Fulton Market Streetscape - July 15th, 2014 Workshop
 
Manor Park Neighborhood Urban Park
Manor Park Neighborhood Urban ParkManor Park Neighborhood Urban Park
Manor Park Neighborhood Urban Park
 
FG Gardiner New Simcoe Ramp - display boards
FG Gardiner   New Simcoe Ramp - display boardsFG Gardiner   New Simcoe Ramp - display boards
FG Gardiner New Simcoe Ramp - display boards
 
New Street Typologies/New Street Types - Getting more out of the same R.O.W.:...
New Street Typologies/New Street Types - Getting more out of the same R.O.W.:...New Street Typologies/New Street Types - Getting more out of the same R.O.W.:...
New Street Typologies/New Street Types - Getting more out of the same R.O.W.:...
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house
 

Similar to REimagining Yonge Street - Public Open House 1 Display Panels [may 25-16]

Movement for Liveable London Street Talks - Ben Kennedy 22nd January 2014
Movement for Liveable London Street Talks - Ben Kennedy 22nd January 2014Movement for Liveable London Street Talks - Ben Kennedy 22nd January 2014
Movement for Liveable London Street Talks - Ben Kennedy 22nd January 2014Movement for Liveable London
 
Public Forum 3 - Presentation (Feb 6_2014)
Public Forum 3 - Presentation (Feb 6_2014)Public Forum 3 - Presentation (Feb 6_2014)
Public Forum 3 - Presentation (Feb 6_2014)GardinerEast
 
North quarter vision study
North quarter vision studyNorth quarter vision study
North quarter vision studyBrendan O'Connor
 
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...Toronto Public Consultation Unit
 
Oxford City Centre Movement and Public Realm Strategy
Oxford City Centre Movement and Public Realm StrategyOxford City Centre Movement and Public Realm Strategy
Oxford City Centre Movement and Public Realm StrategyOxfordshireCC
 
Sustainable Transport: Making Hong Kong a walkable city
Sustainable Transport: Making Hong Kong a walkable citySustainable Transport: Making Hong Kong a walkable city
Sustainable Transport: Making Hong Kong a walkable cityDesigningHongKong
 
Group_3_Assignment-2 Seccondary plan.pdf
Group_3_Assignment-2 Seccondary plan.pdfGroup_3_Assignment-2 Seccondary plan.pdf
Group_3_Assignment-2 Seccondary plan.pdfAarthiR54
 
Greville and King Engegement Analysis Report August 2015
Greville and King Engegement Analysis Report August 2015 Greville and King Engegement Analysis Report August 2015
Greville and King Engegement Analysis Report August 2015 Stonnington
 
Four Mile Run Watershed and Mobility Public Meeting May 22
Four Mile Run Watershed and Mobility Public Meeting May 22Four Mile Run Watershed and Mobility Public Meeting May 22
Four Mile Run Watershed and Mobility Public Meeting May 22Sara Blumenstein
 
Gardiner short briefing package
Gardiner   short briefing packageGardiner   short briefing package
Gardiner short briefing packageWaterfrontTO
 
02 cta yellow line station evanston cc 04.16.12
02   cta yellow line station evanston cc 04.16.1202   cta yellow line station evanston cc 04.16.12
02 cta yellow line station evanston cc 04.16.12cityofevanston
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2Crosstown TO
 
Maumee Valley Planning Organization Regional Transportation Planning Overview
Maumee Valley Planning Organization Regional Transportation Planning OverviewMaumee Valley Planning Organization Regional Transportation Planning Overview
Maumee Valley Planning Organization Regional Transportation Planning OverviewRPO America
 

Similar to REimagining Yonge Street - Public Open House 1 Display Panels [may 25-16] (20)

Highland Creek Village Transportation Master Plan
Highland Creek Village Transportation Master PlanHighland Creek Village Transportation Master Plan
Highland Creek Village Transportation Master Plan
 
Movement for Liveable London Street Talks - Ben Kennedy 22nd January 2014
Movement for Liveable London Street Talks - Ben Kennedy 22nd January 2014Movement for Liveable London Street Talks - Ben Kennedy 22nd January 2014
Movement for Liveable London Street Talks - Ben Kennedy 22nd January 2014
 
Bike East Bay
Bike East BayBike East Bay
Bike East Bay
 
Public Forum 3 - Presentation (Feb 6_2014)
Public Forum 3 - Presentation (Feb 6_2014)Public Forum 3 - Presentation (Feb 6_2014)
Public Forum 3 - Presentation (Feb 6_2014)
 
North quarter vision study
North quarter vision studyNorth quarter vision study
North quarter vision study
 
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
 
Oxford City Centre Movement and Public Realm Strategy
Oxford City Centre Movement and Public Realm StrategyOxford City Centre Movement and Public Realm Strategy
Oxford City Centre Movement and Public Realm Strategy
 
King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck
 
Pedestrian Friendly Shopping Plaza at M.G. Road, Kochi
Pedestrian Friendly Shopping Plaza at M.G. Road, KochiPedestrian Friendly Shopping Plaza at M.G. Road, Kochi
Pedestrian Friendly Shopping Plaza at M.G. Road, Kochi
 
Sustainable Transport: Making Hong Kong a walkable city
Sustainable Transport: Making Hong Kong a walkable citySustainable Transport: Making Hong Kong a walkable city
Sustainable Transport: Making Hong Kong a walkable city
 
Group_3_Assignment-2 Seccondary plan.pdf
Group_3_Assignment-2 Seccondary plan.pdfGroup_3_Assignment-2 Seccondary plan.pdf
Group_3_Assignment-2 Seccondary plan.pdf
 
Greville and King Engegement Analysis Report August 2015
Greville and King Engegement Analysis Report August 2015 Greville and King Engegement Analysis Report August 2015
Greville and King Engegement Analysis Report August 2015
 
Four Mile Run Watershed and Mobility Public Meeting May 22
Four Mile Run Watershed and Mobility Public Meeting May 22Four Mile Run Watershed and Mobility Public Meeting May 22
Four Mile Run Watershed and Mobility Public Meeting May 22
 
Gardiner short briefing package
Gardiner   short briefing packageGardiner   short briefing package
Gardiner short briefing package
 
02 cta yellow line station evanston cc 04.16.12
02   cta yellow line station evanston cc 04.16.1202   cta yellow line station evanston cc 04.16.12
02 cta yellow line station evanston cc 04.16.12
 
2 cip infuse-ottawa-bennett
2 cip infuse-ottawa-bennett2 cip infuse-ottawa-bennett
2 cip infuse-ottawa-bennett
 
Pic 2 panels june 23 2015
Pic 2 panels june 23 2015Pic 2 panels june 23 2015
Pic 2 panels june 23 2015
 
Public Meeting #2 Information Materials
Public Meeting #2 Information MaterialsPublic Meeting #2 Information Materials
Public Meeting #2 Information Materials
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
Maumee Valley Planning Organization Regional Transportation Planning Overview
Maumee Valley Planning Organization Regional Transportation Planning OverviewMaumee Valley Planning Organization Regional Transportation Planning Overview
Maumee Valley Planning Organization Regional Transportation Planning Overview
 

More from knelischer

Rosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting PresentationRosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting Presentationknelischer
 
318 Queens Quay Public Event Activity1 Collage Images
318 Queens Quay Public Event Activity1 Collage Images318 Queens Quay Public Event Activity1 Collage Images
318 Queens Quay Public Event Activity1 Collage Imagesknelischer
 
318 Queens Quay Public Event 1 Display Panels
318 Queens Quay Public Event 1 Display Panels318 Queens Quay Public Event 1 Display Panels
318 Queens Quay Public Event 1 Display Panelsknelischer
 
Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_knelischer
 
Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_knelischer
 
Proposed peak hour_extensions_public_meeting_presentation
Proposed peak hour_extensions_public_meeting_presentationProposed peak hour_extensions_public_meeting_presentation
Proposed peak hour_extensions_public_meeting_presentationknelischer
 
Design Review Panel Presentation - December 2014
Design Review Panel Presentation - December 2014Design Review Panel Presentation - December 2014
Design Review Panel Presentation - December 2014knelischer
 

More from knelischer (7)

Rosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting PresentationRosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting Presentation
 
318 Queens Quay Public Event Activity1 Collage Images
318 Queens Quay Public Event Activity1 Collage Images318 Queens Quay Public Event Activity1 Collage Images
318 Queens Quay Public Event Activity1 Collage Images
 
318 Queens Quay Public Event 1 Display Panels
318 Queens Quay Public Event 1 Display Panels318 Queens Quay Public Event 1 Display Panels
318 Queens Quay Public Event 1 Display Panels
 
Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_
 
Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_
 
Proposed peak hour_extensions_public_meeting_presentation
Proposed peak hour_extensions_public_meeting_presentationProposed peak hour_extensions_public_meeting_presentation
Proposed peak hour_extensions_public_meeting_presentation
 
Design Review Panel Presentation - December 2014
Design Review Panel Presentation - December 2014Design Review Panel Presentation - December 2014
Design Review Panel Presentation - December 2014
 

Recently uploaded

WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.Christina Parmionova
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28JSchaus & Associates
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...tanu pandey
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxtsionhagos36
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Call Girls in Nagpur High Profile
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...aartirawatdelhi
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxPeter Miles
 
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceHigh Profile Call Girls
 
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.Christina Parmionova
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Dipal Arora
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxaaryamanorathofficia
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...ranjana rawat
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29JSchaus & Associates
 

Recently uploaded (20)

WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
 
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptx
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29
 

REimagining Yonge Street - Public Open House 1 Display Panels [may 25-16]

  • 1. REimagining Yonge Street REIMAGINING YONGE STREET SHEPPARD AVENUE TO FINCH AVENUE Source: Bing Maps ENVIRONMENTAL ASSESSMENT STUDY PUBLIC OPEN HOUSE 1 - MAY 25, 2016
  • 2. 25/05/2016 1 REimagining Yonge Street Welcome to the first Public Open House for the REimagining Yonge Street from Sheppard Avenue to Finch Avenue Environmental Assessment Study. The information displayed today is available online at www.toronto.ca/reimaginingyonge WELCOME 2
  • 3. REimagining Yonge Street IDENTIFY PROBLEM OR OPPORTUNITY RESEARCH NATURAL, CULTURAL, SOCIO- ECONOMIC ENVIRONMENT CONDITIONS IDENTIFY ALTERNATIVE SOLUTION(S) AND EVALUATION CRITERIA DESIGN CHARRETTE EVALUATE ALTERNATIVE SOLUTION(S) SELECT PREFERRED SOLUTION(S) AND DEVELOP DESIGN OPTIONS EVALUATE DESIGN OPTIONS REPORT TO COUNCIL & COMPLETE THE FINAL REPORT (30 DAY REVIEW PERIOD) This study is being carried out as a Schedule C project according to the Municipal Class Environmental Assessment (EA) process. This is an approved assessment approach for municipal infrastructure projects under the provincial Environmental Assessment Act. There will be opportunities for public input throughout the study, and at the milestones shown in blue. THE PROJECT & STUDY PROCESS APRIL 2016 APRIL / MAY 2016 MAY 2016 JUNE 9+11, 2016 JUNE / JULY 2016 JULY 2016 AUGUST- OCTOBER 2016 DECEMBER 2016- JANUARY 2017 We are here 3
  • 4. 25/05/2016 2 REimagining Yonge Street STUDY AREA In the study focus area, alternatives will focus on changes to Yonge Street, and mitigating effects to Beecroft Road, Doris Avenue and east/west streets. 4 Steeles Avenue Wilson Avenue York Mills Road
  • 5. REimagining Yonge Street ACCOMMODATING PLANNED GROWTH The Growth Plan for the Greater Golden Horseshoe promotes accessible public infrastructure that is essential to the viability of Ontario’s communities and critical to economic competitiveness, quality of life and the delivery of public services. The Growth Plan identifies North York Centre as an urban growth centre. Accommodating the role as an Urban Growth Centre requires investment on Yonge Street, and we must plan for the ways transportation is changing – ride- share services like Uber, autonomous and connected vehicles and declining vehicle ownership are changing the way we plan streets and cities. The City’s vision for North York Centre is that it should be supported by active transportation modes. To increase the number of people moving by transit, walking and cycling, we need to: • Make better use of the available street space to move more people • Make Yonge Street a better public space, so people will want to use it as a place to enjoy The City needs to plan for the future in North York Centre – the area is continuing to grow: POPULATION GROWTH 11.2% Increase from 2006 to 2011 ACTIVE DEVELOPMENT IN NORTH YORK CENTRE (April 2016) • 12 active development proposals • 3,868 residential units • 57,134 sq.m. of non-residential Connected vehicles 5
  • 6. REimagining Yonge Street TRANSPORTATION TRENDS AND IMPROVEMENTS Introduction of VIVA, GO Transit buses, and other transit improvements resulted in more than a 10% reduction in severe congestion on Yonge Street south of Steeles Avenue. Proposed transit improvements include a subway signaling system upgrade (allowing reduced headways and additional trains), and the Yonge Subway Extension. The planned increase in transit capacity is expected to reduce congestion on Yonge Street. Proposed improvements to the service road network will result in reduced traffic demands and improved operations on Yonge Street. The City is planning for a connection of Doris Avenue to Tradewind Avenue to enhance the service road system, under the North York Centre South Service Road – EA Addendum Study, a separate process and EA study. That connection is expected to help accommodate traffic demand. 6 Source: City of Toronto
  • 7. 25/05/2016 3 REimagining Yonge Street PROBLEM AND OPPORTUNITY STATEMENT North York Centre is one of four centres in the City focused on transit-based employment and residential growth. At its core is Yonge Street from Sheppard Avenue to north of Finch Avenue, envisioned as one of the city's primary pedestrian promenades with a vibrant urban environment that promotes walking, cycling and safe passage across the street. Today the area is faced with challenges from inconsistent features such as sidewalks, pedestrian crossings and medians to lack of dedicated cycling facilities and concerns over traffic movement. The City is looking at ways to create an attractive and consistent streetscape with design appropriate to the civic goals of the North York Centre that will serve people of all ages as they travel in and around the area for work, school and leisure. 7
  • 8. REimagining Yonge Street EXISTING CONDITIONS SAFETY The maps show vehicular collisions and pedestrian/cyclist injuries from 2012 to 2014 throughout the study corridor. Key Findings: • Section between Finch Avenue and Cummer Avenue accounts for 42% (455 of 1070) of total vehicle collisions, and 55% (36 of 66) of total pedestrian/cyclist injuries. • 66 total pedestrian/cyclist injuries: 63 minor injuries and 3 KSI (Killed or Seriously Injured) including 1 pedestrian fatal injury and 2 pedestrian major injuries. • The Yonge Street/Sheppard Avenue intersection has the highest number of vehicle collisions (177) but a relatively small number of pedestrian/cyclist injuries (6). • The sections where a median exists have fewer collisions – particularly for cyclists and pedestrians. 8
  • 9. REimagining Yonge Street EXISTING CONDITIONS PEDESTRIAN CROSSING AND LANDSCAPED MEDIAN LOCATIONS • There are significant gaps along Yonge Street between controlled pedestrian crossing points. • The raised median acts as a “refuge” in the centre of the road, allowing pedestrians to cross one direction of traffic at a time. • Perceived pedestrian delay to cross Yonge Street at Kempford Boulevard. • Where a centre turn lane exists, pedestrians must cross 7 lanes when gaps in traffic coincide in both directions or wait in the centre turn lane. • There is the potential for a raised median in sections where the existing centre turn lane is not required for left turns into side roads or driveways. 9
  • 10. REimagining Yonge Street CURRENT CYCLING TRIPS CURRENT TRIPS. This map shows the total number of cycling trips originating or ending in the study area. This map also shows existing and planned bike facilities. Data Source: City of Toronto / Transportation Tomorrow Survey, 2011 Demand for bike parking can exceed supply: Existing bike parking: 10
  • 11. REimagining Yonge Street TRANSPORTATION OPERATIONS STUDY AREA Traffic conditions have been assessed based on current weekday a.m. and p.m. peak hour volumes. Key Findings: • Almost all major north-south roads operate with adequate capacity throughout the day. • Both service roads, Beecroft Road and Doris Avenue, have unused capacity in both directions. • Willowdale Avenue experiences congestion in both directions in the vicinity of the TTC commuter parking lot. • Traffic growth has been relatively flat in the last decade on Yonge Street. Peak period queues 11 Intersections AM Peak Level of Service Good Fair Poor PM Peak Level of Service
  • 12. REimagining Yonge Street TRANSPORTATION OPERATIONS STUDY FOCUS AREA Existing traffic conditions have been assessed based on weekday morning and evening peak hour volumes. we have assessed Yonge Street, Beecroft Road and Doris Avenue. Changes to Yonge Street could result in effects on these parallel streets. Existing traffic volumes show that all intersections on Beecroft Road and Doris Avenue, the service roads parallel to Yonge Street, operate at acceptable levels of service. These intersections have unused capacity in both directions, and are able to accommodate additional traffic from Yonge Street. Intersections Corridors AM Peak Level of Service Good Fair Poor PM Peak Level of Service Transit AM Peak Queue PM Peak Queue Subway Station 34 bus routes use Yonge or the 2 bus terminals. During peak periods: • Most TTC buses operate every 3 to 6 minutes • GO buses operate every 20 to 30 minutes • VIVA operates every 15 minutes • YRT operates every 20 to 30 + minutes 12 More people are also travelling to North York Centre by transit and active modes.
  • 13. REimagining Yonge Street EXISTING CONDITIONS PUBLIC AND PRIVATE PARKINGFrom Drewry Avenue / Cummer Avenue to Tolman Street From Tolman Street to Park Home Avenue / Empress Avenue From Empress Avenue to Sheppard Avenue On street parking: 331 spaces Off-street: 7952 spaces Total spaces: 8283 spaces On street parking: 259 spaces Off-street: 915 spaces Total spaces: 1174 spaces Parking is available on most streets in the study focus area, and in many off- street lots and garages. PARKING SUPPLY On street parking: 61 spaces Off-street: 6174 spaces Total spaces: 6239 spaces There are high levels of demand for parking on weekdays in some parts of the study focus area. Demand is lower on the weekend. As part of this study, we will be conducting a parking utilization study to understand how the existing parking is currently being used. 13 Sheppard Avenue East Finch Avenue West
  • 14. 25/05/2016 4 REimagining Yonge Street EXISTING CONDITIONS CULTURAL AND NATURAL ENVIRONMENTS The study area is highly urbanized and vegetation is limited. The vegetation is primarily limited to planted trees. The study area has a rich history, evident by the heritage / historical plaques, and cultural institutions found along and adjacent to Yonge Street. . Gibson House Museum Park St. George Anglican ChurchRose Garden Sheppard House Historical Plaque Princess Park – Fire Tower 14
  • 15. REimagining Yonge Street EXISTING CROSS SECTIONS NORTHERN PORTION OF THE STUDY AREA 1. NORTH OF BISHOP AVENUE Looking North 3. SOUTH OF ELLERSLIE AVENUE Looking North 2. SOUTH OF FINCH AVENUE Looking North Public Right-of-Way = 36.15 metres Public Right-of-Way = 34.70 metres Public Right-of-Way = 35.02 metres The curb lanes provide parking during off-peak times. 15
  • 16. REimagining Yonge Street EXISTING CROSS SECTIONS SOUTHERN PORTION OF THE STUDY AREA 6. NORTH OF ELMHURST/GREENFIELD AVENUE Looking North 5. SOUTH OF HOLLYWOOD AVENUE Looking North 7. NORTH OF SHEPPARD AVENUE Looking North Public Right-of-Way = 37.30 metres Public Right-of-Way = 34.43 metresPublic Right-of-Way = 34.09 metres 4. NORTH OF HILLCREST AVENUE Looking North Public Right-of-Way = 36.76 metres The curb lanes provide parking during off-peak times. 16
  • 17. REimagining Yonge Street How would you improve the street ? Please add your ideas on “post-it” notes to the blank circles. We have opportunities to … PUBLIC REALM / STREETSCAPE HAVE YOUR SAY Manage congestion 17 Plant trees Add cycle tracks or bike lanes Re-align traffic lanes Expand sidewalks and boulevard widths, and improve crossings Enhance the streetscape Integrate adjacent public spaces
  • 18. REimagining Yonge Street OPPORTUNITIES TO INTEGRATE PUBLIC SPACES One goal is to enhance connections and integration with public spaces. Potential locations are shown here. Are there other locations? Please tell us by adding your post-it note. Rose Garden Historic Cemetery Federal Building Olive Square Mel Lastman Square 18
  • 19. REimagining Yonge Street STREET DESIGN ELEMENTS HAVE YOUR SAYWhat do you like or dislike? Do you support this element along Yonge Street? Why or why not? Cycle Track At-grade planters Wide sidewalks Public Art Street Trees Street furniture Landscaped MedianOn-street Parking Separated Bike Lane 19
  • 20. REimagining Yonge Street Do you know other streets or ideas we should consider? Add a post-it note to tell us about them. POTENTIAL VISIONS FOR YONGE STREET We are researching streets from around the world… Kitchener Credit Cory Bluhm Seattle, WA Austin, TX Montreal Credit: Google Earth New York, NY 20
  • 21. REimagining Yonge Street ALTERNATIVES FOR YONGE STREET 1 Do Nothing 3 Modify Travel Lanes Curb Relocation Landscaped Median: Remove, Narrow, Enhance, or Extend 4 Transform 2 Enhance No change No changeProceed with existing plans No change Consider reduction from 6 lanes to 4 in sections Reduce from 6 lanes to 4, throughout the corridor Consider minor improvement options Consider options in strategic locations Consider options throughout the corridor Extensive relocation No change Changes in strategic locations Proposed Components Trees & Planters, Public Art, Street Furniture Wider Sidewalk Enhance / Expand Pedestrian Crossings No changeEnhance as redevelopment occurs Fix existing sidewalk and enhance as redevelopment occurs Enhance at strategic locations Enhance at strategic locations Enhance corridor- wide Widen throughout the corridor Widen in redevelopment areas and other strategic locations Enhance as redevelopment occurs Add in strategic locations Add in strategic locations Enhance throughout the corridor; consider new features Alternative Business as usual: continue implementing the existing plan as development proceeds Minor Improvements to the streetscape and transportation operations at strategic locations Minor reconstruction in strategic locations, to improve the streetscape and pedestrian facilities, and bike facilities Major reconstruction to create a multi-modal street and enhanced streetscape, including cycle tracks, and enhanced pedestrian facilities Description Bike Facilities No change Consider bike facilities Consider bike facilities No change 21
  • 22. REimagining Yonge Street ALTERNATIVE 1: DO NOTHING ALTERNATIVE 3: MODIFY ALTERNATIVES FOR YONGE STREET ALTERNATIVE 2: ENHANCE New element New element New element 22 New element
  • 23. REimagining Yonge Street ALTERNATIVE 4A: TRANSFORM ALTERNATIVES FOR YONGE STREET ALTERNATIVE 4B: TRANSFORM * * * Parking lane during off-peak periods 23 ALTERNATIVE 4D: TRANSFORMALTERNATIVE 4C: TRANSFORM
  • 24. REimagining Yonge Street ALTERNATIVE 4E: TRANSFORM ALTERNATIVES FOR YONGE STREET ALTERNATIVE 4G: TRANSFORM 24 ALTERNATIVE 4H: TRANSFORM ALTERNATIVE 4F: TRANSFORM
  • 25. REimagining Yonge Street EVALUATION CRITERIA Accessibility, Mobility & Transportation Infrastructure Natural Environment Cycling and Walking Cultural Heritage & Built Heritage Resources • Adherence to City design standards and guidelines for transportation facilities • Accessibility (Compliance with City’s Accessibility Standards and provincial guidelines) • Promotes effective movement of people and goods • Transportation network capacity • Parking capacity • Intersection operations and Transportation efficiency • Safety for users • Minimizes impacts on vegetation communities and existing trees • Wildlife and wildlife habitat • Maximizes opportunity for street tree planting in optimized urban condition that provides for the long term health of the trees • Ability to introduce new cycling facilities • Ability to improve pedestrian facilities • Supports sustainable transportation • Compatibility with City’s Cycling Network plans • Connectivity to lands adjacent to Yonge Street • Impacts on built heritage resources • Impacts on cultural heritage landscapes • Potential archaeological resources Have we missed anything? Add your comments on a post-it note in the space above. 25
  • 26. REimagining Yonge Street EVALUATION CRITERIA Have we missed anything? Add your comments on a post-it note in the space above. Costs Constructability & Utilities Community Planning Design Excellence • Construction costs • Maintenance/operational costs • Life cycle costs • Transit, pedestrian, road, and bike mobility through the study and duration of disruption for each mode • Number of construction stages and duration • Number and scale of existing utilities affected • Potential utility conflicts • Effects on business during construction • Supports Yonge Street’s role as a special public space • Encourages vibrant, mixed-use development • Effects on business (e.g., retail) • Impacts to Private Property • Compatibility with existing planning policy and environmental assessments • Noise effects • Effect on emergency services • Percentage of the right-of-way dedicated to public realm uses such as pedestrian facilities, public art, and street furniture • Supports design excellence of infrastructure and streetscape. Maximizes impact of corridor on design of adjacent development • Enhances the attractiveness of urban environment and creates place-making opportunities • Supports integration with public spaces 26
  • 27. 25/05/2016 5 REimagining Yonge Street WHAT YOU’VE TOLD US SO FAR… We have been conducting a survey of residents and visitors to help us gather information about how Yonge Street is used and to identify opportunities and challenges. This survey will inform the study process, but is not a formal poll. Interviews were conducted along Yonge Street on Tuesday, May 10, 2016, and the survey is available on the project website until June 8, 2016. Over 500 surveys have been completed to-date. Key results are as follows: 0 50 100 150 200 250 300 350 Morning Lunchtime Afternoon Dinnertime Late night Weekends When are you on Yonge Street? If you were making one big change to Yonge Street, it would be: 0 50 100 150 200 250 300 How do you use Yonge Street? Responses 36% 4% 38% 9% 13% Most Liked about Yonge Street Convenient for Walking Convenient for Cycling Well-served by Transit Convenient for driving Other 8% 13% 19% 15% 35% 10% Least liked about Yonge Street Insufficient Sidewalk Space Lack of Cycling Facilities Lack of Streetscape Design Poor Conditon of Streetscape High Traffic Volume Other Common “Other” responses include: • Lack of safe pedestrian crosswalks • Lack of parking • Aesthetics / Streetscape Design Common “Other” responses include: • The mix and wide variety of uses, including retail, services, restaurants, etc. • Convenience and accessibility of the area to transit and highway access • The level of street activity and diversity along the study area 57% of people surveyed to-date use Yonge Street for more than one purpose. 27
  • 28. 25/05/2016 6 REimagining Yonge Street What is a charrette? • A charrette is a planning and design session where members of the public work with the Project Team to collaborate on a vision for the plan. • It provides a forum for ideas and offers the unique advantage of a collaborative design process. DESIGN CHARRETTE Your Chance to Participate INTERESTED IN PARTICIPATING IN THE CHARRETTE? SIGN UP AT THE FRONT DESK OR ONLINE Once available, more information about the charrette will be posted on the project web page: www.toronto.ca/reimaginingyonge What is the purpose? • The intent is to build on data gathering and analysis efforts by the Project Team to produce alternatives for a preferred design while creating a joint vision with the community. Thursday June 9 and Saturday June 11, 2016 28
  • 29. 25/05/2016 7 REimagining Yonge Street After this Public Open House, the Project Team will: • Review and respond to comments; • Meet with stakeholders, external agencies, and a technical advisory committee; • Host Design Charrette (June 9 and 11, 2016); • Evaluate the alternatives; and, • Prepare for a second Public Open House (July 25, 2016). NEXT STEPS STAY CONNECTED Kate Nelischer Senior Public Consultation Coordinator City of Toronto Metro Hall, 19th Floor 55 John Street Toronto, ON M5V 3C6 Tel: 416-392-4360 or Fax: 416-392-2974 Email: knelischer@toronto.ca THANK YOU FOR ATTENDING TODAY’S PUBLIC OPEN HOUSE The information presented today is available online at www.toronto.ca/reimaginingyonge 29