SlideShare a Scribd company logo
1 of 25
The Capacity Programme
    e-Procurement



          Keith Fraser
     Head of Procurement
  Estates Capacity Directorate
The Capacity Problem

• A capacity ceiling was set at 80,000 prisoners after the first Carter
  Report. In late 2006 the media were reporting that this figure had
  been exceeded and prisons were “bursting at the seams”
• Then Home Secretary John Reid authorised the purchase of the
  former secure mental health facility in Ashfield to be converted into
  HMP Kennett providing 500 extra places
• Projections were showing a demand for an additional 4,000 places
  by 2012 with the introduction of Indeterminate Public Protection
  (IPP) sentences and this led to the “Capacity Programme”
• Lord Carter produced a second report to review the estate more
  strategically which will increase capacity by a further 20,000 places
  and replace some of the older estate as new facilities come online
First Tranche Capacity Programme

• 1,500 places delivered through a combination of Rapid Build
  modular technologies as either prison expansions or “drop-in units”
• Procurement was via the “Strategic Alliance” frameworks awarded
  on a cost basis with a variety of supply chains in order to meet the
  capacity demands
• Construction of 2 x 350 place prison expansions and a further 800
  places through single 60 cell units took an average of 32 weeks
  from start on site to completion
• Service life expected to be 60 years
HMP Wayland expansion
Second Tranche Capacity Programme

• 2000 places delivered through a programme of 180 and 240 place
  traditional “Houseblocks” in strategic locations in both the higher
  security Category B and lower security Category C prisons
• Includes an expansion to the east of the HMP Belmarsh site to
  create a second prison named HMP Isis and conversion of RAF
  Coltishall into HMP Bure
• Utilised modular construction using concrete modules from smaller
  supply chain
• Planning applications led to longer lead times that allowed for more
  detailed supplier selection from the Strategic Alliance that focussed
  on design innovations and improved Whole Life Cost
• Service life expected to be 75 years and beyond
Modular Houseblock Construction
Third Tranche Capacity Programme

• Consists of 3 new establishments, 2 PFI sites at Belmarsh West
  and Maghull (Liverpool)
• The third site at Featherstone started as a PFI project but moved
  into the “public sector” for design and build with operation to be
  put to competition
• Maghull will provide 600 places, but has the capacity for 800 if its
  role changes
• Belmarsh will provide 900 places
• Featherstone 2 will provide 1620 places
The “New Prison Programme”

• 7,500 extra places to be delivered through 5 new prisons
• 5,000 places will go from the closure of older, inefficient
  prisons, giving a 2,500 place surplus
• This programme replaces the “Titan” prison concept of
  2,500 place “super prisons”
• The procurement process will involve setting up Framework
  Agreements for PFI providers followed by mini-
  competitions
Public Sector Prisons – Procurement of Construction

• The “Strategic Alliance” is a series of 3 frameworks for
  Consultancy, New Build, and Refurbishment contractors
• 12 major contractors and 20 consultancies operating in 6
  regions
• Delivers all major capital projects valued over £500,000
• £2.25bn spent since 2005
• 32 Capacity Programme projects delivered since 2007
• Over 100 capital projects delivered per year to maintain the
  existing estate
• 135 projects to procure in the FYr 2010-2011
Case Study: HMP Featherstone 2
Featherstone 2: Overview

• Part of the Capacity Programme and initially intended to be a PFI
  project
• Changed direction in Dec 2007 to a publicly built establishment with
  the operation of the prison to go to competition
• Initially to have a capacity of 1140 prisoners, later increased to 1650
  with the decision to build a 3rd Houseblock
• Designated a Category C prison, but built to the higher Category B
  standard so that costs can be reduced if the prison is re-roled at a
  later date
• Construction costs £277m
• Construction programme 27 months, due to be operational April 2012
Featherstone 2: Challenges

•   Procuring the Design & Construction from the Strategic Alliance
    framework, with 3 constructors eventually bidding
•   Devised a procurement strategy that was interested in 3 key areas:
    1. Ability to Deliver – the constructor’s methodology and
       management
    2. Quality of Solution – design and innovation
    3. Cost – build costs and whole life/operating cost
•   Bid was to be based on a Developed Project Proposal (DPP) with
    Agreed Maximum Price (AMP) equivalent to RIBA Stage D design
•   Bid costs to be borne by Constructors
•   Procurement cycle to be complete within 12 months from project
    approval to contract award
Featherstone 2: Procurement Drivers

• Improved VFM
• Cost reductions in line with economies of scale
• Drive innovations through design and construction techniques
• Implement “Lean Programming” methodologies
• Introduce performance targets linked to incentives for early
  completion
• Introduce system of liquidated damages for performance failures
• Provide assurances to OGC and Major Projects Review Group (who
  gave us a “green” rating without any conditions to meet – extremely
  rare!)
Featherstone 2: Design Drivers
Featherstone 2: Innovation Drivers

• Building layout taking best practice from the private prisons for efficient
  operation
Featherstone 2: Programme Overview
Featherstone 2: Award

• Complex award criteria with multiple evaluators and 2 moderators:


                                       Project Overall Score
                                              100%




            Ability to Deliver                  Cost                   Quality of Solution
                  Score                        Score                         Score
                   40%                          30%                           30%




      Management             Legal             Cost            Technical              Operational
         Score               Score            Score              Score                  Score
         85%                     15%          100%               40%                     60%
Featherstone 2: Award

• The “Client Representative” (Project Manager) had to co-
  ordinate the evaluation by 7 teams over an 11 week period
• ITT went out before we could get QinetiQ on board, so
  Award had to be built around the structure of the ITT (not
  the other way around as QinetiQ would have preferred)
• Responses had to be uploaded onto Award after the
  submission date for evaluation to begin
• Drawings handled separately as the size was considerably
  bigger than Award’s security accreditation would allow for
  uploads
• Scores had to be uploaded by team leaders and then
  annotated and moderated before being exported into a
  detailed evaluation report and recommendation
Featherstone 2: Procurement Plan
Featherstone 2: Evaluation Methodology Schematic

                             Projects
                             Overall                  Interview
                              Score
                              100%




          Team        Ability to     Quality of         Cost
         working       Deliver       Solution         Compilation
        Scoreshet    Compilation    Compilation         Score
          5 / 40       Score          Score              30%
                        40%            30%




        Manageme        Legal         Operational        Cost
                                       (60%) and
            nt          Score       Technical (40%)      Score
        Score Form      Form         Score Forms         Form
           85%           15%
Featherstone 2: Example Award Report


                                      Moderated count of scores (%)


   45.00%

   40.00%

   35.00%

   30.00%

   25.00%

   20.00%

   15.00%

   10.00%

    5.00%

    0.00%
              Unacceptable    Poor      Fair     Acceptable    Good     Very good   Excellent   Exceptional
   Bidder 1      6.53%       16.45%    32.11%      28.59%      11.10%    3.92%       1.04%        0.26%
   Bidder 2      3.92%       7.70%     18.15%      34.33%      28.20%    6.01%       1.57%        0.13%
   Bidder 3      6.01%       13.84%    22.85%      38.77%      15.01%    3.26%       0.13%        0.13%
Featherstone 2: Example Award Reports
Featherstone 2: Lessons Learned

• Engage Award early to help design tender format to best suit
  evaluation tool and reduce costs
• Consider how you manage large data files and the security
  implications
• Have a good evaluation project plan: treat it as a separate project if it
  helps
• Be realistic in the resources and time in undertaking the evaluation
• Consider what information you will want to report on and extract for
  feedback
• Be clear about what is driving your procurement to get best effect out
  of the exercise
Conclusions

• BAU account for 60% of team activity or an average of 120
  projects a year
• Many of those projects are being awarded via mini-
  competition
• Featherstone 2 has become the benchmark for many of
  those competitions
• Need to have a system like Award in place to facilitate those
  competitions
• Legislation requires a clear audit trail and feedback to be
  given if requested
• Award has assisted in all of these issues and has reduced
  the workload of procurement managers by giving real-time
  reporting
Keith Fraser BSc(Hons)(Lond), MSc(Lond), MIFMA
Head of Procurement
Estates Capacity Directorate

Keith.Fraser@noms.gsi.gov.uk

More Related Content

Similar to Noms Award User Group 2009

Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedEnergy Construction Forum
 
CAST - Next gen sourcing for application services​
CAST - Next gen sourcing for application services​CAST - Next gen sourcing for application services​
CAST - Next gen sourcing for application services​Xavier Escudero Sabadell
 
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Aconex
 
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
Day 1   1620 - 1705 - maple - pranabendu bhattacharyyaDay 1   1620 - 1705 - maple - pranabendu bhattacharyya
Day 1 1620 - 1705 - maple - pranabendu bhattacharyyaPMI2011
 
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02PMI_IREP_TP
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaGlobalSkillup
 
3rd party independant reviews
3rd party independant reviews3rd party independant reviews
3rd party independant reviewsNick Pelham
 
Equipment Guy Brochure Victor Pobihushchy Sept 11, 2015
Equipment Guy Brochure Victor Pobihushchy Sept 11, 2015Equipment Guy Brochure Victor Pobihushchy Sept 11, 2015
Equipment Guy Brochure Victor Pobihushchy Sept 11, 2015Victor Pobihushchy,PMP
 
Week 5: Handout chris piccin lean - 040117 - day 2
Week 5: Handout   chris piccin   lean - 040117 - day 2Week 5: Handout   chris piccin   lean - 040117 - day 2
Week 5: Handout chris piccin lean - 040117 - day 2Talou Diallo
 
SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...
SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...
SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...GoLeanSixSigma.com
 
Pm group project implementation of cargo storage planning system
Pm group project  implementation of cargo storage planning systemPm group project  implementation of cargo storage planning system
Pm group project implementation of cargo storage planning systemMohan Vp
 
Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectArvinThamsir1
 
Capital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptCapital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptArvinThamsir1
 
Citihub Consulting Capabilities Presentation
Citihub Consulting Capabilities PresentationCitihub Consulting Capabilities Presentation
Citihub Consulting Capabilities PresentationChris Allison
 
Brushless dc motor
Brushless dc motorBrushless dc motor
Brushless dc motoraroosa khan
 
Requirements management-plan template
Requirements management-plan templateRequirements management-plan template
Requirements management-plan templateVivek Srivastava
 

Similar to Noms Award User Group 2009 (20)

Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
 
CAST - Next gen sourcing for application services​
CAST - Next gen sourcing for application services​CAST - Next gen sourcing for application services​
CAST - Next gen sourcing for application services​
 
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
 
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
Day 1   1620 - 1705 - maple - pranabendu bhattacharyyaDay 1   1620 - 1705 - maple - pranabendu bhattacharyya
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
 
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
 
3rd party independant reviews
3rd party independant reviews3rd party independant reviews
3rd party independant reviews
 
Equipment Guy Brochure Victor Pobihushchy Sept 11, 2015
Equipment Guy Brochure Victor Pobihushchy Sept 11, 2015Equipment Guy Brochure Victor Pobihushchy Sept 11, 2015
Equipment Guy Brochure Victor Pobihushchy Sept 11, 2015
 
PM Unit - 1.pptx
PM Unit - 1.pptxPM Unit - 1.pptx
PM Unit - 1.pptx
 
ThoughtWorks Approach 2009
ThoughtWorks Approach 2009ThoughtWorks Approach 2009
ThoughtWorks Approach 2009
 
Umar inam karim CV
Umar inam karim  CVUmar inam karim  CV
Umar inam karim CV
 
Week 05_Handout day 2
Week 05_Handout  day 2Week 05_Handout  day 2
Week 05_Handout day 2
 
Week 5: Handout chris piccin lean - 040117 - day 2
Week 5: Handout   chris piccin   lean - 040117 - day 2Week 5: Handout   chris piccin   lean - 040117 - day 2
Week 5: Handout chris piccin lean - 040117 - day 2
 
SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...
SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...
SUCCESS STORY: Improving the Capital Design Review Process at Wastewater Trea...
 
Pm group project implementation of cargo storage planning system
Pm group project  implementation of cargo storage planning systemPm group project  implementation of cargo storage planning system
Pm group project implementation of cargo storage planning system
 
Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of Project
 
Capital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptCapital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .ppt
 
Citihub Consulting Capabilities Presentation
Citihub Consulting Capabilities PresentationCitihub Consulting Capabilities Presentation
Citihub Consulting Capabilities Presentation
 
Brushless dc motor
Brushless dc motorBrushless dc motor
Brushless dc motor
 
Requirements management-plan template
Requirements management-plan templateRequirements management-plan template
Requirements management-plan template
 

More from barnbyvilla

Fm Expo 2013 Presentation
Fm Expo 2013 PresentationFm Expo 2013 Presentation
Fm Expo 2013 Presentationbarnbyvilla
 
Keith Fraser FM World Interview
Keith Fraser FM World InterviewKeith Fraser FM World Interview
Keith Fraser FM World Interviewbarnbyvilla
 
Finance and Operations in FM 11
Finance and Operations in FM 11Finance and Operations in FM 11
Finance and Operations in FM 11barnbyvilla
 
Contracts and fm 11
Contracts and fm 11Contracts and fm 11
Contracts and fm 11barnbyvilla
 
Contracts And Fm 11
Contracts And Fm 11Contracts And Fm 11
Contracts And Fm 11barnbyvilla
 

More from barnbyvilla (6)

Fm Expo 2013 Presentation
Fm Expo 2013 PresentationFm Expo 2013 Presentation
Fm Expo 2013 Presentation
 
Keith Fraser FM World Interview
Keith Fraser FM World InterviewKeith Fraser FM World Interview
Keith Fraser FM World Interview
 
Career profile
Career profileCareer profile
Career profile
 
Finance and Operations in FM 11
Finance and Operations in FM 11Finance and Operations in FM 11
Finance and Operations in FM 11
 
Contracts and fm 11
Contracts and fm 11Contracts and fm 11
Contracts and fm 11
 
Contracts And Fm 11
Contracts And Fm 11Contracts And Fm 11
Contracts And Fm 11
 

Noms Award User Group 2009

  • 1. The Capacity Programme e-Procurement Keith Fraser Head of Procurement Estates Capacity Directorate
  • 2. The Capacity Problem • A capacity ceiling was set at 80,000 prisoners after the first Carter Report. In late 2006 the media were reporting that this figure had been exceeded and prisons were “bursting at the seams” • Then Home Secretary John Reid authorised the purchase of the former secure mental health facility in Ashfield to be converted into HMP Kennett providing 500 extra places • Projections were showing a demand for an additional 4,000 places by 2012 with the introduction of Indeterminate Public Protection (IPP) sentences and this led to the “Capacity Programme” • Lord Carter produced a second report to review the estate more strategically which will increase capacity by a further 20,000 places and replace some of the older estate as new facilities come online
  • 3. First Tranche Capacity Programme • 1,500 places delivered through a combination of Rapid Build modular technologies as either prison expansions or “drop-in units” • Procurement was via the “Strategic Alliance” frameworks awarded on a cost basis with a variety of supply chains in order to meet the capacity demands • Construction of 2 x 350 place prison expansions and a further 800 places through single 60 cell units took an average of 32 weeks from start on site to completion • Service life expected to be 60 years
  • 5. Second Tranche Capacity Programme • 2000 places delivered through a programme of 180 and 240 place traditional “Houseblocks” in strategic locations in both the higher security Category B and lower security Category C prisons • Includes an expansion to the east of the HMP Belmarsh site to create a second prison named HMP Isis and conversion of RAF Coltishall into HMP Bure • Utilised modular construction using concrete modules from smaller supply chain • Planning applications led to longer lead times that allowed for more detailed supplier selection from the Strategic Alliance that focussed on design innovations and improved Whole Life Cost • Service life expected to be 75 years and beyond
  • 7. Third Tranche Capacity Programme • Consists of 3 new establishments, 2 PFI sites at Belmarsh West and Maghull (Liverpool) • The third site at Featherstone started as a PFI project but moved into the “public sector” for design and build with operation to be put to competition • Maghull will provide 600 places, but has the capacity for 800 if its role changes • Belmarsh will provide 900 places • Featherstone 2 will provide 1620 places
  • 8. The “New Prison Programme” • 7,500 extra places to be delivered through 5 new prisons • 5,000 places will go from the closure of older, inefficient prisons, giving a 2,500 place surplus • This programme replaces the “Titan” prison concept of 2,500 place “super prisons” • The procurement process will involve setting up Framework Agreements for PFI providers followed by mini- competitions
  • 9. Public Sector Prisons – Procurement of Construction • The “Strategic Alliance” is a series of 3 frameworks for Consultancy, New Build, and Refurbishment contractors • 12 major contractors and 20 consultancies operating in 6 regions • Delivers all major capital projects valued over £500,000 • £2.25bn spent since 2005 • 32 Capacity Programme projects delivered since 2007 • Over 100 capital projects delivered per year to maintain the existing estate • 135 projects to procure in the FYr 2010-2011
  • 10. Case Study: HMP Featherstone 2
  • 11. Featherstone 2: Overview • Part of the Capacity Programme and initially intended to be a PFI project • Changed direction in Dec 2007 to a publicly built establishment with the operation of the prison to go to competition • Initially to have a capacity of 1140 prisoners, later increased to 1650 with the decision to build a 3rd Houseblock • Designated a Category C prison, but built to the higher Category B standard so that costs can be reduced if the prison is re-roled at a later date • Construction costs £277m • Construction programme 27 months, due to be operational April 2012
  • 12. Featherstone 2: Challenges • Procuring the Design & Construction from the Strategic Alliance framework, with 3 constructors eventually bidding • Devised a procurement strategy that was interested in 3 key areas: 1. Ability to Deliver – the constructor’s methodology and management 2. Quality of Solution – design and innovation 3. Cost – build costs and whole life/operating cost • Bid was to be based on a Developed Project Proposal (DPP) with Agreed Maximum Price (AMP) equivalent to RIBA Stage D design • Bid costs to be borne by Constructors • Procurement cycle to be complete within 12 months from project approval to contract award
  • 13. Featherstone 2: Procurement Drivers • Improved VFM • Cost reductions in line with economies of scale • Drive innovations through design and construction techniques • Implement “Lean Programming” methodologies • Introduce performance targets linked to incentives for early completion • Introduce system of liquidated damages for performance failures • Provide assurances to OGC and Major Projects Review Group (who gave us a “green” rating without any conditions to meet – extremely rare!)
  • 15. Featherstone 2: Innovation Drivers • Building layout taking best practice from the private prisons for efficient operation
  • 17. Featherstone 2: Award • Complex award criteria with multiple evaluators and 2 moderators: Project Overall Score 100% Ability to Deliver Cost Quality of Solution Score Score Score 40% 30% 30% Management Legal Cost Technical Operational Score Score Score Score Score 85% 15% 100% 40% 60%
  • 18. Featherstone 2: Award • The “Client Representative” (Project Manager) had to co- ordinate the evaluation by 7 teams over an 11 week period • ITT went out before we could get QinetiQ on board, so Award had to be built around the structure of the ITT (not the other way around as QinetiQ would have preferred) • Responses had to be uploaded onto Award after the submission date for evaluation to begin • Drawings handled separately as the size was considerably bigger than Award’s security accreditation would allow for uploads • Scores had to be uploaded by team leaders and then annotated and moderated before being exported into a detailed evaluation report and recommendation
  • 20. Featherstone 2: Evaluation Methodology Schematic Projects Overall Interview Score 100% Team Ability to Quality of Cost working Deliver Solution Compilation Scoreshet Compilation Compilation Score 5 / 40 Score Score 30% 40% 30% Manageme Legal Operational Cost (60%) and nt Score Technical (40%) Score Score Form Form Score Forms Form 85% 15%
  • 21. Featherstone 2: Example Award Report Moderated count of scores (%) 45.00% 40.00% 35.00% 30.00% 25.00% 20.00% 15.00% 10.00% 5.00% 0.00% Unacceptable Poor Fair Acceptable Good Very good Excellent Exceptional Bidder 1 6.53% 16.45% 32.11% 28.59% 11.10% 3.92% 1.04% 0.26% Bidder 2 3.92% 7.70% 18.15% 34.33% 28.20% 6.01% 1.57% 0.13% Bidder 3 6.01% 13.84% 22.85% 38.77% 15.01% 3.26% 0.13% 0.13%
  • 22. Featherstone 2: Example Award Reports
  • 23. Featherstone 2: Lessons Learned • Engage Award early to help design tender format to best suit evaluation tool and reduce costs • Consider how you manage large data files and the security implications • Have a good evaluation project plan: treat it as a separate project if it helps • Be realistic in the resources and time in undertaking the evaluation • Consider what information you will want to report on and extract for feedback • Be clear about what is driving your procurement to get best effect out of the exercise
  • 24. Conclusions • BAU account for 60% of team activity or an average of 120 projects a year • Many of those projects are being awarded via mini- competition • Featherstone 2 has become the benchmark for many of those competitions • Need to have a system like Award in place to facilitate those competitions • Legislation requires a clear audit trail and feedback to be given if requested • Award has assisted in all of these issues and has reduced the workload of procurement managers by giving real-time reporting
  • 25. Keith Fraser BSc(Hons)(Lond), MSc(Lond), MIFMA Head of Procurement Estates Capacity Directorate Keith.Fraser@noms.gsi.gov.uk