SlideShare a Scribd company logo
1 of 5
Download to read offline
2011 FEDCON SUMMIT
                          WILMINGTON, NC



                           LEGAL ISSUES

                           BONDING -
                         THE MILLER ACT




William H. Gammon, Nelson Mullins, LLP
bill.gammon@nelsonmullins.com
GlenLake One, Suite 200
4140 Parklake Avenue
Raleigh, NC 27612


                                          October 19, 2011


~#4811-6182-8871 v.1~
MILLER ACT

Background

       The payment of subcontractors and suppliers on construction projects has always
involved special remedies. For example, all states have provisions allowing unpaid
subcontractors, subsubcontractors and suppliers to file liens on the Owner’s property, if the
subcontractors have not received payment. (Here in North Carolina, see Ch. 44A of the North
Carolina General Statutes.)

       However, on public contracts, public policy has long concluded that an unpaid
subcontractor should not be able to place a lien on public property. The reasoning is that the
property belongs not to a single private person or entity, but to the public at large.

        As a result, Congress enacted the Miller Act (40 U.S.C. 3131, et seq. (formerly 40
U.S.C. § 270, et seq.)) to provide a different type of protection for unpaid subcontractors.
That remedy is the requirement for general contractors to obtain a payment bond from a
surety, thereby providing the subcontractor and suppliers to have an action against the surety
for the nonpayment and thereby not have to rely on the financial strength of the general
contractor.

       Projects of less than $25,000 have no bonding requirements. Projects greater than
$25,000, but less than $100,000, allow for bonds to be supplied by an independent surety or
some alternative. Projects greater than $100,000 require that the bonds be obtained from an
independent surety.

Other Bonds

       The Miller Act not only requires the provision of payment bonds by the contractor on a
federal construction project to guarantee payments to subcontractors and suppliers. It also
requires bidder on public projects to supply bid bonds, and requires the successful bidders to
provide performance bonds.

          Bid Bonds

        Bid bonds are required so that there is security that the winning contractor will proceed
to contract after the solicitation opening and the exposure of proposals or bids. Bid bonds must
be provided with the bid or response to the solicitation in the amount of 20% of the
bid/proposal or $3,000,000, which ever is less.




~#4811-6182-8871 v.1~
Thus, following bid or proposal opening, and thereby the exposure of all bids/proposals
to the fellow competitors, the winning bidder/proposer has a financial incentive to “go to
contract.”

          Performance Bonds

        Performance bonds are required so that there is an outside guarantor who will guarantee
through the issuance of a performance bond, that the awarded contractor will complete the
project. Performance bonds are at 100% of the contract price.

          Payment Bonds

       As noted above, payment bonds secure that payment will be made to subcontractors and
suppliers. When one thinks of the Miller Act, it is this requirement for payment bonds that
most people consider to be the focus of the Act.

       Every person (and that includes laborers) that furnished labor or materials on a federal
construction project, and that has not been paid within 90 days of the last furnishing of such
labor or materials, may bring an action on the bond to secure such payment.

Who Can Bring An Action?

        The Miller Act limits actions against payment bonds to first and second tier
subcontractors.   Stated differently, only subcontractors and those who contract with
subcontractors (or subsubcontractors) and suppliers to the general contractor can bring an
action on the payment bond.

        A third tier subcontractor (or subsubsubcontractor), or anyone below that level has no
such rights to bring an action on the payment bond. In somewhat of a strange quirk, a second
tier supplier (or subsupplier to a supplier) likewise has no rights against the payment bond.
(See the chart at the end of the materials setting forth who can/cannot bring payment bond
actions.)

When Must A Claim Be Brought?

        A subcontractor or supplier can bring a claim against the payment bond at any time
after 90 days has elapsed since the last labor or materials were furnished by the subcontractor/
supplier, but before one year has elapsed.

       The same timing for filing is true of second tier subcontractors or suppliers to
subcontractors, except that the second tier must give written notice to the general contractor
within 90 days of last furnishing labor or materials that the subsubcontractor or subsupplier to
the subcontractor has not been paid. The purpose for the written notice is actually quite simple
-– the general contractor knows who it has paid, but the general contractor often would not
know who its subcontractor has paid – therefore, notice to the general is appropriate.



~#4811-6182-8871 v.1~
~#4811-6182-8871 v.1~
Where Are Miller Act Actions Brought?

        Any action brought under the Miller Act must be filed in the United States District
Court in the district where the project is located. In other words, if a Miller Act action on a
project at either Camp Lejeune or Ft. Bragg was instituted, it must be filed in the United States
District Court for the Eastern District of North Carolina. On the other hand, a Miller Act
action on a federal project, at say, Charlotte, would have to be brought in the United States
District Court for the Western District of North Carolina.

Subcontractors Entitled To Obtain Copy of Bond?

       The Contracting Officer is required by FAR 32.112-2 to provide a copy of the payment
bond to any subcontractor or supplier, if requested with an Affidavit that the subcontractor
supplied labor and/or materials on the project and was not paid within 90 days.

     There is a similar requirement for contractors to furnish such information, if requested.
FAR 28.106 and FAR 52.228-12, Prospective Subcontractor Requests for Bonds (OCT 1995).




~#4811-6182-8871 v.1~

More Related Content

What's hot

Contract act
Contract actContract act
Contract act
lck005
 
Australian Consumer Law: defects, warranties and unfair contracts basil 120324
Australian Consumer Law: defects, warranties and unfair contracts basil 120324  Australian Consumer Law: defects, warranties and unfair contracts basil 120324
Australian Consumer Law: defects, warranties and unfair contracts basil 120324
Etienne Lawyers
 
Minimizing Risks and Maximizing Success in Government Contracting
Minimizing Risks and Maximizing Success in Government ContractingMinimizing Risks and Maximizing Success in Government Contracting
Minimizing Risks and Maximizing Success in Government Contracting
lruzicka
 
Legality of object-7
Legality of object-7Legality of object-7
Legality of object-7
artipradhan
 

What's hot (19)

Lien Law Update
Lien Law UpdateLien Law Update
Lien Law Update
 
Contract act
Contract actContract act
Contract act
 
Condo Buyer Handbook 2005 158892 7
Condo Buyer Handbook 2005 158892 7Condo Buyer Handbook 2005 158892 7
Condo Buyer Handbook 2005 158892 7
 
SB 179 Policy Analysis
SB 179 Policy AnalysisSB 179 Policy Analysis
SB 179 Policy Analysis
 
Australian Consumer Law
Australian Consumer LawAustralian Consumer Law
Australian Consumer Law
 
Australian Consumer Law: defects, warranties and unfair contracts basil 120324
Australian Consumer Law: defects, warranties and unfair contracts basil 120324  Australian Consumer Law: defects, warranties and unfair contracts basil 120324
Australian Consumer Law: defects, warranties and unfair contracts basil 120324
 
The contract act
The contract actThe contract act
The contract act
 
Minimizing Risks and Maximizing Success in Government Contracting
Minimizing Risks and Maximizing Success in Government ContractingMinimizing Risks and Maximizing Success in Government Contracting
Minimizing Risks and Maximizing Success in Government Contracting
 
Washington State Legislative Updates
Washington State Legislative UpdatesWashington State Legislative Updates
Washington State Legislative Updates
 
Map
MapMap
Map
 
Chapter 9 and PREPA: it’s in the agreement. And the precedent
Chapter 9 and PREPA: it’s in the agreement. And the precedentChapter 9 and PREPA: it’s in the agreement. And the precedent
Chapter 9 and PREPA: it’s in the agreement. And the precedent
 
Chapter 19: Rights of Third Parties
Chapter 19: Rights of Third Parties Chapter 19: Rights of Third Parties
Chapter 19: Rights of Third Parties
 
Using the Miller Acts
Using the Miller ActsUsing the Miller Acts
Using the Miller Acts
 
ACC 2012 - Boilerplate Contract Provisions
ACC 2012 - Boilerplate Contract ProvisionsACC 2012 - Boilerplate Contract Provisions
ACC 2012 - Boilerplate Contract Provisions
 
Dick Hargis Presentation June 2011 Legal Update
Dick Hargis Presentation June 2011 Legal UpdateDick Hargis Presentation June 2011 Legal Update
Dick Hargis Presentation June 2011 Legal Update
 
legal aspects of Material management
legal aspects of Material management legal aspects of Material management
legal aspects of Material management
 
Essentials of Contract
Essentials of ContractEssentials of Contract
Essentials of Contract
 
Legality of object-7
Legality of object-7Legality of object-7
Legality of object-7
 
common_law_on_contracts
common_law_on_contractscommon_law_on_contracts
common_law_on_contracts
 

Similar to Miller act and rights of subcontractors

Rapid Rescore Compliance Infractions
Rapid Rescore Compliance InfractionsRapid Rescore Compliance Infractions
Rapid Rescore Compliance Infractions
NAMBLive
 
Federal Procurement Updates June 2010
Federal Procurement Updates June 2010Federal Procurement Updates June 2010
Federal Procurement Updates June 2010
fkenniasty
 
Chicago Daily Law Bulletin - Legal-malpractice suit can advance in case of m
Chicago Daily Law Bulletin - Legal-malpractice suit can advance in case of mChicago Daily Law Bulletin - Legal-malpractice suit can advance in case of m
Chicago Daily Law Bulletin - Legal-malpractice suit can advance in case of m
Paul Porvaznik
 
Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA
Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA
Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA
Law Office of Ann N. Nguyen
 
Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA
Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA
Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA
Law Office of Ann N. Nguyen
 

Similar to Miller act and rights of subcontractors (20)

Arizona Lien Law
Arizona Lien LawArizona Lien Law
Arizona Lien Law
 
Rapid Rescore Compliance Infractions
Rapid Rescore Compliance InfractionsRapid Rescore Compliance Infractions
Rapid Rescore Compliance Infractions
 
Hurricane Recovery Compilation for Community Association
Hurricane Recovery Compilation for Community AssociationHurricane Recovery Compilation for Community Association
Hurricane Recovery Compilation for Community Association
 
How To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsHow To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal Interests
 
Loan transfer
Loan transferLoan transfer
Loan transfer
 
Federal Procurement Updates June 2010
Federal Procurement Updates June 2010Federal Procurement Updates June 2010
Federal Procurement Updates June 2010
 
Bonds
BondsBonds
Bonds
 
Messy.mechanics.lien
Messy.mechanics.lienMessy.mechanics.lien
Messy.mechanics.lien
 
Messy.mechanics.lien
Messy.mechanics.lienMessy.mechanics.lien
Messy.mechanics.lien
 
Chicago Daily Law Bulletin - Legal-malpractice suit can advance in case of m
Chicago Daily Law Bulletin - Legal-malpractice suit can advance in case of mChicago Daily Law Bulletin - Legal-malpractice suit can advance in case of m
Chicago Daily Law Bulletin - Legal-malpractice suit can advance in case of m
 
2011 Utah Real Estate Caravan
2011 Utah Real Estate Caravan2011 Utah Real Estate Caravan
2011 Utah Real Estate Caravan
 
Construction Meets Texas Law: Selected Statutory Overrides
Construction Meets Texas Law: Selected Statutory OverridesConstruction Meets Texas Law: Selected Statutory Overrides
Construction Meets Texas Law: Selected Statutory Overrides
 
Understanding A Mechanic’s, Contractor’s, Or Materialman’s Lien-What Every Pr...
Understanding A Mechanic’s, Contractor’s, Or Materialman’s Lien-What Every Pr...Understanding A Mechanic’s, Contractor’s, Or Materialman’s Lien-What Every Pr...
Understanding A Mechanic’s, Contractor’s, Or Materialman’s Lien-What Every Pr...
 
lien waivers
lien waiverslien waivers
lien waivers
 
Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA
Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA
Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA
 
Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA
Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA
Loan Modification and Bankruptcy Basics Powerpoint Slideshow 2009 NCVAA
 
What To Do When Customers Won't Pay
What To Do When Customers Won't PayWhat To Do When Customers Won't Pay
What To Do When Customers Won't Pay
 
Adam Leitman Bailey, P.C. Fall 2019 Newsletter
Adam Leitman Bailey, P.C. Fall 2019 NewsletterAdam Leitman Bailey, P.C. Fall 2019 Newsletter
Adam Leitman Bailey, P.C. Fall 2019 Newsletter
 
Truth In Lending
Truth In LendingTruth In Lending
Truth In Lending
 
Mechanics Lien Coverage
Mechanics Lien CoverageMechanics Lien Coverage
Mechanics Lien Coverage
 

More from NC Military Business Center

Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14
NC Military Business Center
 
FEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction ProjectsFEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction Projects
NC Military Business Center
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/Delays
NC Military Business Center
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/Delays
NC Military Business Center
 
FEDCON Summit: Department of Transportation Construction Opportunities
FEDCON Summit:  Department of Transportation Construction OpportunitiesFEDCON Summit:  Department of Transportation Construction Opportunities
FEDCON Summit: Department of Transportation Construction Opportunities
NC Military Business Center
 
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal ContractsFEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
NC Military Business Center
 
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
NC Military Business Center
 
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry ExperienceFEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
NC Military Business Center
 
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
NC Military Business Center
 
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry PanelFEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
NC Military Business Center
 
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced AnalyticsHuman/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
NC Military Business Center
 

More from NC Military Business Center (20)

Camp Lejeune Small Business Outreach Event
Camp Lejeune Small Business Outreach EventCamp Lejeune Small Business Outreach Event
Camp Lejeune Small Business Outreach Event
 
MCAS Cherry Point Small Business Outreach Event
MCAS Cherry Point Small Business Outreach EventMCAS Cherry Point Small Business Outreach Event
MCAS Cherry Point Small Business Outreach Event
 
Spawar slides
Spawar slidesSpawar slides
Spawar slides
 
Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14
 
FEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction ProjectsFEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction Projects
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/Delays
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/Delays
 
FEDCON Summit: Department of Transportation Construction Opportunities
FEDCON Summit:  Department of Transportation Construction OpportunitiesFEDCON Summit:  Department of Transportation Construction Opportunities
FEDCON Summit: Department of Transportation Construction Opportunities
 
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal ContractsFEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
 
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
 
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry ExperienceFEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
 
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
 
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry PanelFEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
 
FEDCON Summit: Marine Corps Installations East
FEDCON Summit: Marine Corps Installations EastFEDCON Summit: Marine Corps Installations East
FEDCON Summit: Marine Corps Installations East
 
FEDCON Summit: NCMBC Tools for Contractors
FEDCON Summit: NCMBC Tools for ContractorsFEDCON Summit: NCMBC Tools for Contractors
FEDCON Summit: NCMBC Tools for Contractors
 
FEDCON Summit: Public Private Ventures
FEDCON Summit: Public Private VenturesFEDCON Summit: Public Private Ventures
FEDCON Summit: Public Private Ventures
 
FEDCON Summit: Teaming Arrangements
FEDCON Summit: Teaming ArrangementsFEDCON Summit: Teaming Arrangements
FEDCON Summit: Teaming Arrangements
 
FEDCON Summit: Veterans Affairs
FEDCON Summit: Veterans AffairsFEDCON Summit: Veterans Affairs
FEDCON Summit: Veterans Affairs
 
Medical Technologies
Medical TechnologiesMedical Technologies
Medical Technologies
 
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced AnalyticsHuman/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
 

Recently uploaded

Recently uploaded (20)

2999,Vashi Fantastic Ellete Call Girls📞📞9833754194 CBD Belapur Genuine Call G...
2999,Vashi Fantastic Ellete Call Girls📞📞9833754194 CBD Belapur Genuine Call G...2999,Vashi Fantastic Ellete Call Girls📞📞9833754194 CBD Belapur Genuine Call G...
2999,Vashi Fantastic Ellete Call Girls📞📞9833754194 CBD Belapur Genuine Call G...
 
Seeman_Fiintouch_LLP_Newsletter_May-2024.pdf
Seeman_Fiintouch_LLP_Newsletter_May-2024.pdfSeeman_Fiintouch_LLP_Newsletter_May-2024.pdf
Seeman_Fiintouch_LLP_Newsletter_May-2024.pdf
 
GIFT City Overview India's Gateway to Global Finance
GIFT City Overview  India's Gateway to Global FinanceGIFT City Overview  India's Gateway to Global Finance
GIFT City Overview India's Gateway to Global Finance
 
cost-volume-profit analysis.ppt(managerial accounting).pptx
cost-volume-profit analysis.ppt(managerial accounting).pptxcost-volume-profit analysis.ppt(managerial accounting).pptx
cost-volume-profit analysis.ppt(managerial accounting).pptx
 
Bhubaneswar🌹Kalpana Mesuem ❤CALL GIRLS 9777949614 💟 CALL GIRLS IN bhubaneswa...
Bhubaneswar🌹Kalpana Mesuem  ❤CALL GIRLS 9777949614 💟 CALL GIRLS IN bhubaneswa...Bhubaneswar🌹Kalpana Mesuem  ❤CALL GIRLS 9777949614 💟 CALL GIRLS IN bhubaneswa...
Bhubaneswar🌹Kalpana Mesuem ❤CALL GIRLS 9777949614 💟 CALL GIRLS IN bhubaneswa...
 
Mahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Mahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot GirlsMahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Mahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
 
Call Girls in Benson Town / 8250092165 Genuine Call girls with real Photos an...
Call Girls in Benson Town / 8250092165 Genuine Call girls with real Photos an...Call Girls in Benson Town / 8250092165 Genuine Call girls with real Photos an...
Call Girls in Benson Town / 8250092165 Genuine Call girls with real Photos an...
 
Vip Call Girls Rasulgada😉 Bhubaneswar 9777949614 Housewife Call Girls Servic...
Vip Call Girls Rasulgada😉  Bhubaneswar 9777949614 Housewife Call Girls Servic...Vip Call Girls Rasulgada😉  Bhubaneswar 9777949614 Housewife Call Girls Servic...
Vip Call Girls Rasulgada😉 Bhubaneswar 9777949614 Housewife Call Girls Servic...
 
In Sharjah ௵(+971)558539980 *_௵abortion pills now available.
In Sharjah ௵(+971)558539980 *_௵abortion pills now available.In Sharjah ௵(+971)558539980 *_௵abortion pills now available.
In Sharjah ௵(+971)558539980 *_௵abortion pills now available.
 
Dubai Call Girls Deira O525547819 Dubai Call Girls Bur Dubai Multiple
Dubai Call Girls Deira O525547819 Dubai Call Girls Bur Dubai MultipleDubai Call Girls Deira O525547819 Dubai Call Girls Bur Dubai Multiple
Dubai Call Girls Deira O525547819 Dubai Call Girls Bur Dubai Multiple
 
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & RequirementsExplore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
 
Toronto dominion bank investor presentation.pdf
Toronto dominion bank investor presentation.pdfToronto dominion bank investor presentation.pdf
Toronto dominion bank investor presentation.pdf
 
Female Escorts Service in Hyderabad Starting with 5000/- for Savita Escorts S...
Female Escorts Service in Hyderabad Starting with 5000/- for Savita Escorts S...Female Escorts Service in Hyderabad Starting with 5000/- for Savita Escorts S...
Female Escorts Service in Hyderabad Starting with 5000/- for Savita Escorts S...
 
20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...
20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...
20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...
 
Virar Best Sex Call Girls Number-📞📞9833754194-Poorbi Nalasopara Housewife Cal...
Virar Best Sex Call Girls Number-📞📞9833754194-Poorbi Nalasopara Housewife Cal...Virar Best Sex Call Girls Number-📞📞9833754194-Poorbi Nalasopara Housewife Cal...
Virar Best Sex Call Girls Number-📞📞9833754194-Poorbi Nalasopara Housewife Cal...
 
7 steps to achieve financial freedom.pdf
7 steps to achieve financial freedom.pdf7 steps to achieve financial freedom.pdf
7 steps to achieve financial freedom.pdf
 
Kurla Capable Call Girls ,07506202331, Sion Affordable Call Girls
Kurla Capable Call Girls ,07506202331, Sion Affordable Call GirlsKurla Capable Call Girls ,07506202331, Sion Affordable Call Girls
Kurla Capable Call Girls ,07506202331, Sion Affordable Call Girls
 
Significant AI Trends for the Financial Industry in 2024 and How to Utilize Them
Significant AI Trends for the Financial Industry in 2024 and How to Utilize ThemSignificant AI Trends for the Financial Industry in 2024 and How to Utilize Them
Significant AI Trends for the Financial Industry in 2024 and How to Utilize Them
 
Fixed exchange rate and flexible exchange rate.pptx
Fixed exchange rate and flexible exchange rate.pptxFixed exchange rate and flexible exchange rate.pptx
Fixed exchange rate and flexible exchange rate.pptx
 
Webinar on E-Invoicing for Fintech Belgium
Webinar on E-Invoicing for Fintech BelgiumWebinar on E-Invoicing for Fintech Belgium
Webinar on E-Invoicing for Fintech Belgium
 

Miller act and rights of subcontractors

  • 1. 2011 FEDCON SUMMIT WILMINGTON, NC LEGAL ISSUES BONDING - THE MILLER ACT William H. Gammon, Nelson Mullins, LLP bill.gammon@nelsonmullins.com GlenLake One, Suite 200 4140 Parklake Avenue Raleigh, NC 27612 October 19, 2011 ~#4811-6182-8871 v.1~
  • 2. MILLER ACT Background The payment of subcontractors and suppliers on construction projects has always involved special remedies. For example, all states have provisions allowing unpaid subcontractors, subsubcontractors and suppliers to file liens on the Owner’s property, if the subcontractors have not received payment. (Here in North Carolina, see Ch. 44A of the North Carolina General Statutes.) However, on public contracts, public policy has long concluded that an unpaid subcontractor should not be able to place a lien on public property. The reasoning is that the property belongs not to a single private person or entity, but to the public at large. As a result, Congress enacted the Miller Act (40 U.S.C. 3131, et seq. (formerly 40 U.S.C. § 270, et seq.)) to provide a different type of protection for unpaid subcontractors. That remedy is the requirement for general contractors to obtain a payment bond from a surety, thereby providing the subcontractor and suppliers to have an action against the surety for the nonpayment and thereby not have to rely on the financial strength of the general contractor. Projects of less than $25,000 have no bonding requirements. Projects greater than $25,000, but less than $100,000, allow for bonds to be supplied by an independent surety or some alternative. Projects greater than $100,000 require that the bonds be obtained from an independent surety. Other Bonds The Miller Act not only requires the provision of payment bonds by the contractor on a federal construction project to guarantee payments to subcontractors and suppliers. It also requires bidder on public projects to supply bid bonds, and requires the successful bidders to provide performance bonds. Bid Bonds Bid bonds are required so that there is security that the winning contractor will proceed to contract after the solicitation opening and the exposure of proposals or bids. Bid bonds must be provided with the bid or response to the solicitation in the amount of 20% of the bid/proposal or $3,000,000, which ever is less. ~#4811-6182-8871 v.1~
  • 3. Thus, following bid or proposal opening, and thereby the exposure of all bids/proposals to the fellow competitors, the winning bidder/proposer has a financial incentive to “go to contract.” Performance Bonds Performance bonds are required so that there is an outside guarantor who will guarantee through the issuance of a performance bond, that the awarded contractor will complete the project. Performance bonds are at 100% of the contract price. Payment Bonds As noted above, payment bonds secure that payment will be made to subcontractors and suppliers. When one thinks of the Miller Act, it is this requirement for payment bonds that most people consider to be the focus of the Act. Every person (and that includes laborers) that furnished labor or materials on a federal construction project, and that has not been paid within 90 days of the last furnishing of such labor or materials, may bring an action on the bond to secure such payment. Who Can Bring An Action? The Miller Act limits actions against payment bonds to first and second tier subcontractors. Stated differently, only subcontractors and those who contract with subcontractors (or subsubcontractors) and suppliers to the general contractor can bring an action on the payment bond. A third tier subcontractor (or subsubsubcontractor), or anyone below that level has no such rights to bring an action on the payment bond. In somewhat of a strange quirk, a second tier supplier (or subsupplier to a supplier) likewise has no rights against the payment bond. (See the chart at the end of the materials setting forth who can/cannot bring payment bond actions.) When Must A Claim Be Brought? A subcontractor or supplier can bring a claim against the payment bond at any time after 90 days has elapsed since the last labor or materials were furnished by the subcontractor/ supplier, but before one year has elapsed. The same timing for filing is true of second tier subcontractors or suppliers to subcontractors, except that the second tier must give written notice to the general contractor within 90 days of last furnishing labor or materials that the subsubcontractor or subsupplier to the subcontractor has not been paid. The purpose for the written notice is actually quite simple -– the general contractor knows who it has paid, but the general contractor often would not know who its subcontractor has paid – therefore, notice to the general is appropriate. ~#4811-6182-8871 v.1~
  • 5. Where Are Miller Act Actions Brought? Any action brought under the Miller Act must be filed in the United States District Court in the district where the project is located. In other words, if a Miller Act action on a project at either Camp Lejeune or Ft. Bragg was instituted, it must be filed in the United States District Court for the Eastern District of North Carolina. On the other hand, a Miller Act action on a federal project, at say, Charlotte, would have to be brought in the United States District Court for the Western District of North Carolina. Subcontractors Entitled To Obtain Copy of Bond? The Contracting Officer is required by FAR 32.112-2 to provide a copy of the payment bond to any subcontractor or supplier, if requested with an Affidavit that the subcontractor supplied labor and/or materials on the project and was not paid within 90 days. There is a similar requirement for contractors to furnish such information, if requested. FAR 28.106 and FAR 52.228-12, Prospective Subcontractor Requests for Bonds (OCT 1995). ~#4811-6182-8871 v.1~