SlideShare a Scribd company logo
1 of 4
CHRISTOPHER JOYSON.
17 NEWHAVEN COURT, HARTLEPOOL. TS24 7HR
DOB: 25.08.1958. SINGLE. INDONESIAN MOBILE +62-81372114742.
EMAIL (Preferred Contact Method): C.Joyson@outlook.com
FULL UK PASSPORT VALID TILL 20/01/2021
Page 1 of 3
Versatile Mechanical Engineer with Experience in all levels of Construction,
Completions and Commissioning.
Experienced Mechanical Commissioning/Completions Engineer/manager with 30+ years’
experience; Self-motivated and adaptable individual possessing good team work, management,
communication and interpersonal skills.
Experience in Oil & Gas Construction, Completions & Commissioning in downstream & upstream,
onshore and offshore. Vessels include FPSO, Semi-Sub and Topsides. Systems include Power
generation, Oil & Gas processing, Gas compression, Water injection, Fire water and HVAC
KEY STRENGTHS
 Actively encourage employees to work safely and efficiently.
 Able to communicate at all levels.
 Positions held fromEngineer through commissioninglead and up to Construction Manager.
 Good technical skillsto adaptto new technologies.
 Comprehensive knowledge of Mechanical,Pipingand structural disciples;Gained atboth a supervisory and engineer
level, from construction through to commissioning.
 Highly computer literate: excellent skills in MicrosoftWord,Excel,PowerPoint, Visio & Project. Good knowledge also
of PIMS, WinPCS, GOC systems, MicrosoftProjectand AutoCAD.
 Work to BS, ISO, ABS, DNV, NORSOK, ANSI, ASME and API Standards.
EMPLOYMENTRECORD (Most recent first):
01/14 –Date Lead Mechanical CommissioningEngineer,Mubadala,Manora Topsides,Sattahip, Thailand.
 Management of mechanical completions for the mechanical disciplineof the final construction stages
for the Manora Topsides.
 Deputising for the Commissioningmanager duringhis offshorerotation.
 Set-up and population of PIMS for Mechanical systems & ITR’s
 Writingof Commissioningprocedures for all topsides utility and facilities systems,Power generation,
(3 x Cummins Gas Internal Combustion Engines and 1 Diesel Engine) diesel fuel, HVAC, Platform
Crane, Instrument and Utility Air, FireWater, Seawater, Water treatment & injection and Open &
Closed Drains,
 Offshore Commissioningof the above systems.
05/13 – 12/13 Construction/MCManager, MISC (MalaysiaInternational ShippingCorporation),CendorFPSO,
Malaysia.
 Management of Mechanical Completions up to handover to commissioning.
 Reporting directly to the Projectmanager on Construction issues for the Marineand topsides areas of
the FPSO.
 Providinginformation to the project management team on completion and commissioni ngissues
 Dealingdirectly with the Completions of the Switchgear rooms.
 AdvisingMISC Engineers and MMHE construction on the completions process.
 DirectingMMHE on the completions priorities.
01/13 – 04/13 Lead Mechanical CompletionsEngineer,MMHE(Malaysia Marine & Heavy Engineering) ,
GumusutProject Malaysia.
 Lead completions mechanical engineer ensuringthe timely handover of rotating equipment to
commissioning.
 Engineer in Charge of 3 Flowserve crude oil export pumps, 2x Sultzer water injection Pumps, 2 GE
turbine powered high pressurecompressor trains, Kobelco LP/MP flash gas compressors and TEG
Package.
 Ensuringall ITR’s arecompleted, equipment aligned and installed as per manufacture’s Data.
 Removal & Re-installation of 7 HV motors rangingfrom 700KW to 3000KW for Inspection & overhaul.
 Liaisingwith Vendors: General Electric,Voith, Flowserve and Kobelco.
Page 2 of 4
04/12 – 12/12 CommissioningLead,Petrofac,Berantai FPSO Singapore & offshore Malaysia.
 Senior mechanical engineer to supervisethe commissioningof all topsidesequipment including3 x
4.8MW Solar Generators, 2 x Solar Mars 100 Compressors,ClydeUnion Firewater & Seawater pumps.
 Writingof commissioningprocedures for firewater, produced water, seawater & other systems.
 Promoted to commissioning lead for the offshore stage to supervisedisciplineengineers during the
offshore commissioningstage.
 Use of WinPCS to carry out reporting analysison commissioning& completions.
 Reporting on turnover & commissioning packages (TCP’s) & hand over of same to operations.
 Ensuring completion ITR’s in a timely manner.
 Ensuring all work is carried outin a safemanner.
03/12 – 04/12 ConstructionManager, Enermech Secondedto MODEC, Ghana.
 Development of pre-bid construction plan for 1,800toffshore offloading buoy, 21 - 75t Suction Piles,8
pressurevessels and approx.400 Deck Stools for the in-country work of an FPSO.
 Survey of sites for suitability of fabrication work for the project
 vendor/sub-contractor appraisalsfor fabrication work & crane requirements.
 Develop the initial prebid report for Ghana works to MODEC Management.
08/11 –12/11 Mechanical Completions/CommissioningLead–PremierOil,Keppel Benoi,Singapore Then
Offshore Vietnam.
 Commissioningon The LEWEK EMAS 660,000 bbl FPSO (FloatingProduction Storage & Offloading)
Vessel.
 Offshore commissioningof Topsides,Engine room and marineequipment, signingoff on behalf of the
clientall mechanical equipment, witnessingpump runs, flushingoperations and system
commissioning.
 System start-up assistance,performancetesting and hand over to operations of Water Injection,gas
compression,fuel Gas, oil separation and top-sidesystems duringfinal commissioningstages.
 Co-ordination of the final handover to commissioningof all remainingsystems.
04/11 –07/11 Mechanical CompletionsCo-Ordinator–PremierOil,Keppel Benoi,Singapore.
 Co-ordination of the final completions and hand over to commissioningof all remainingsystems prior
to sail-away.
 Short term contractto finalisethe completions work on behalf of the client,Premier Oil.
08/10 –04/11 Mechanical CompletionsCo-Ordinator–Master-Marine,Dry Docks Graha- Batam Island,
Indonesia.
 Completions co-ordination of the ‘NORA’ 118m ‘Service Jack’ barge with dynamic positioning jack up
barge specifically for installation of Wind farms to operate in the North Sea.
 Takingthe project to the final stages of hand-over to commissioning.
02/09 –08/10 Construction/CompletionsEngineer,NorCEOffshore,Bintan Island, Indonesia& Keppel Benoi,
Singapore.
 Preparation of completions documentation and signingover all mechanical systems to commissioning.
 Construction of the NorCE Endeavour 26,000 tonne DLB (Derrick Lay Barge)
 Installation and alignment of SAS pipelaying equipment, 5 W8L20 1780 kVA WartsillaGenerators,8
AmClyde Mooring winches, AmClyde M60 1100 t Ringer crane, 40 plus Allweiller Pumps and automatic
hydraulic Water tightdoors.
01/08 –01/09 Lead Construction Engineer,AMEC,Karachaganak field,KPO, Uralsk,Kazakhstan,
 Lead the Preparation of documentation for Mechanical Completion usingGOC (guidanceon
Certification) for completion and Commissioningof systems.
 Change out of existing sour gas re-injection pipework to 25% chrome.
 Planningthe shut downs for the change out of all gas compression and re-injection piping.
03/07-12/07 ConstructionEngineer/ TGT Focal point,Production ServicesNetwork(PSN) Aberdeen
 Focal pointfor all construction, brown-field and shutdown activities atthe ConocoPhillips
Theddlethorpe Gas Terminal (TGT). Also Focal pointfor Lincolnshireand Rivers Terminal,Morecambe
Bay.
 Shutdown co-ordinator for TGT shutdown September 2007.Shutdown completed on time with all
work scopes complete.
Page 3 of 4
10/06-03/07 ConstructionManager, VikingUK GAS, East Knapton GeneratingStation North Yorkshire
 Construction management of two consecutiveprojects: installation of Gas compression unitand
installation of Flow& separation systemfor reclaimed well facility.
06/06-10/06 SeniorConstruction Engineer,Petrofac,WaGEproject for Armada platform
03/06-06/06 PipingImplementationEngineer,AMEC,Maria over Armada Project for BG
02/06-03/06 Shutdown Co-ordinator,AMEC, BP Coryton Crude unit
05/04- 11/05. Mechanical FieldEngineer,TechnipMaritime Offshore Limited.BP Shah Denizproject,
Singapore and Baku, Azerbaijan- 32,000t total, topsides22,000t.
1999- 2004 Mechanical /Piping Supervisor/Superintendentvariousrolesincludingpetrochemical and
nuclear installations.
1978-1999 Mechanical & pipe Fittervarious roles ICI,AMEC & Mitsui Babcock both Nuclearand
Petrochemical Sites
1974-1978 Apprentice Mechanical Fitter- ICI Billingham(as above).
EDUCATION AND QUALIFICATIONS:
1978: Hartlepool College ofFurther Education. City & GuildsOfLondon Full Tech. Cert. (Mech. Eng.).
1982: Blackpool & Fylde College ofFurther Education. Institute ofQuality Assurance Certificate in
Quality Assurance
1984: Hartlepool College ofFurther Education. Higher National Certificate ComputerAided
Production Engineering.
2014: Currentlystudying for Projectmanagement degree withOpenUniversityUK.
ADDITIONAL INFORMATION:
 BOSIET Survival (OPITO approved) currentuntil 20th July 2015
 Open University studies carried outincluding:
Livingwith Technology Foundation course(1992).ModellingWith Mathematics (1993).Systems (1993).
 IOSH ManagingSafety course(2004).
 AMEC Firststeps safety leadership course (2008)
 Main Language English,Good knowledge of Bahasa Indonesia.
HOBBIES/INTERESTS:
Off-roading, own a 1978 Toyota FJ40 4x4 in Indonesia, non-competition use with Indonesian locals.
Motorcycles own 1 Modern (Suzuki 1340 B-King) and the following Classics:
 1981 Honda CBX1000 6 Cylinder
 1974 Kawasaki Z1B900
 1981 Yamaha YZ465 Moto-cross
 1966 Ducati 250 Diana
 1974- 1975 Harley Davidson 250SS (have two of these and two spare bikes)
 1972 Aermacchi (Harley-Davidson) 350SX
 1999 Harley Davidson Sportster 883 (Project Bike with 1260 Engine,Flat track style)
Computer Builds for Home Entertainment, build of NAS (Network Attached Storage) system, using
FREENAS software to provide movies, TV shows and Music around the home to Individual Android
boxes in each room. Built approx. 10 Computers in total.
References:
Alistair Brown CommissioningManager,Premier Oil. alistair_brown@rocketmail.com
Page 4 of 4
Tony Lobb Construction Manager Technip Shah Deniz Project tonylobb1000@yahoo.co.uk
Peter Donnelly Facilities Manager. NorCE Offshore. pdonnel01@aol.com
Andrew Roberts Construction Manager. Valhalla project,BP Lowestoft. robertsandy8@aol.com
Michael Duff Construction Manager, Master Marine. mjduff5154@hotmail.com

More Related Content

Viewers also liked

Viewers also liked (17)

Jose's cv
Jose's cvJose's cv
Jose's cv
 
Isaac Williams CV
Isaac Williams CVIsaac Williams CV
Isaac Williams CV
 
CV
CVCV
CV
 
CV Mr Michael Marley-Savage
CV Mr Michael Marley-SavageCV Mr Michael Marley-Savage
CV Mr Michael Marley-Savage
 
Aaron Sem curriculum vitea
Aaron Sem curriculum viteaAaron Sem curriculum vitea
Aaron Sem curriculum vitea
 
CVPeterDevers 2015
CVPeterDevers 2015CVPeterDevers 2015
CVPeterDevers 2015
 
1 S. Munisamy Latest CV
1 S. Munisamy Latest CV1 S. Munisamy Latest CV
1 S. Munisamy Latest CV
 
BRIDGE ELECTRICAL ENGINEERING WORK1
BRIDGE ELECTRICAL ENGINEERING WORK1BRIDGE ELECTRICAL ENGINEERING WORK1
BRIDGE ELECTRICAL ENGINEERING WORK1
 
Arnold CV
Arnold CVArnold CV
Arnold CV
 
Cv RM Final
Cv RM FinalCv RM Final
Cv RM Final
 
ERNESTO DOMNGOS JOSE CAMILO CV
ERNESTO DOMNGOS JOSE CAMILO CVERNESTO DOMNGOS JOSE CAMILO CV
ERNESTO DOMNGOS JOSE CAMILO CV
 
Paul Hickey CV.
Paul Hickey CV.Paul Hickey CV.
Paul Hickey CV.
 
Anibal_Carias_CV(1)
Anibal_Carias_CV(1)Anibal_Carias_CV(1)
Anibal_Carias_CV(1)
 
Cv
CvCv
Cv
 
Long-Eric CV (2014)modified 241114 Page1
Long-Eric CV (2014)modified 241114 Page1Long-Eric CV (2014)modified 241114 Page1
Long-Eric CV (2014)modified 241114 Page1
 
ori PAUSON CV ING ed.
ori PAUSON CV ING ed.ori PAUSON CV ING ed.
ori PAUSON CV ING ed.
 
Icha Peter_cv
Icha Peter_cvIcha Peter_cv
Icha Peter_cv
 

Chris joyson CV 03-2015

  • 1. CHRISTOPHER JOYSON. 17 NEWHAVEN COURT, HARTLEPOOL. TS24 7HR DOB: 25.08.1958. SINGLE. INDONESIAN MOBILE +62-81372114742. EMAIL (Preferred Contact Method): C.Joyson@outlook.com FULL UK PASSPORT VALID TILL 20/01/2021 Page 1 of 3 Versatile Mechanical Engineer with Experience in all levels of Construction, Completions and Commissioning. Experienced Mechanical Commissioning/Completions Engineer/manager with 30+ years’ experience; Self-motivated and adaptable individual possessing good team work, management, communication and interpersonal skills. Experience in Oil & Gas Construction, Completions & Commissioning in downstream & upstream, onshore and offshore. Vessels include FPSO, Semi-Sub and Topsides. Systems include Power generation, Oil & Gas processing, Gas compression, Water injection, Fire water and HVAC KEY STRENGTHS  Actively encourage employees to work safely and efficiently.  Able to communicate at all levels.  Positions held fromEngineer through commissioninglead and up to Construction Manager.  Good technical skillsto adaptto new technologies.  Comprehensive knowledge of Mechanical,Pipingand structural disciples;Gained atboth a supervisory and engineer level, from construction through to commissioning.  Highly computer literate: excellent skills in MicrosoftWord,Excel,PowerPoint, Visio & Project. Good knowledge also of PIMS, WinPCS, GOC systems, MicrosoftProjectand AutoCAD.  Work to BS, ISO, ABS, DNV, NORSOK, ANSI, ASME and API Standards. EMPLOYMENTRECORD (Most recent first): 01/14 –Date Lead Mechanical CommissioningEngineer,Mubadala,Manora Topsides,Sattahip, Thailand.  Management of mechanical completions for the mechanical disciplineof the final construction stages for the Manora Topsides.  Deputising for the Commissioningmanager duringhis offshorerotation.  Set-up and population of PIMS for Mechanical systems & ITR’s  Writingof Commissioningprocedures for all topsides utility and facilities systems,Power generation, (3 x Cummins Gas Internal Combustion Engines and 1 Diesel Engine) diesel fuel, HVAC, Platform Crane, Instrument and Utility Air, FireWater, Seawater, Water treatment & injection and Open & Closed Drains,  Offshore Commissioningof the above systems. 05/13 – 12/13 Construction/MCManager, MISC (MalaysiaInternational ShippingCorporation),CendorFPSO, Malaysia.  Management of Mechanical Completions up to handover to commissioning.  Reporting directly to the Projectmanager on Construction issues for the Marineand topsides areas of the FPSO.  Providinginformation to the project management team on completion and commissioni ngissues  Dealingdirectly with the Completions of the Switchgear rooms.  AdvisingMISC Engineers and MMHE construction on the completions process.  DirectingMMHE on the completions priorities. 01/13 – 04/13 Lead Mechanical CompletionsEngineer,MMHE(Malaysia Marine & Heavy Engineering) , GumusutProject Malaysia.  Lead completions mechanical engineer ensuringthe timely handover of rotating equipment to commissioning.  Engineer in Charge of 3 Flowserve crude oil export pumps, 2x Sultzer water injection Pumps, 2 GE turbine powered high pressurecompressor trains, Kobelco LP/MP flash gas compressors and TEG Package.  Ensuringall ITR’s arecompleted, equipment aligned and installed as per manufacture’s Data.  Removal & Re-installation of 7 HV motors rangingfrom 700KW to 3000KW for Inspection & overhaul.  Liaisingwith Vendors: General Electric,Voith, Flowserve and Kobelco.
  • 2. Page 2 of 4 04/12 – 12/12 CommissioningLead,Petrofac,Berantai FPSO Singapore & offshore Malaysia.  Senior mechanical engineer to supervisethe commissioningof all topsidesequipment including3 x 4.8MW Solar Generators, 2 x Solar Mars 100 Compressors,ClydeUnion Firewater & Seawater pumps.  Writingof commissioningprocedures for firewater, produced water, seawater & other systems.  Promoted to commissioning lead for the offshore stage to supervisedisciplineengineers during the offshore commissioningstage.  Use of WinPCS to carry out reporting analysison commissioning& completions.  Reporting on turnover & commissioning packages (TCP’s) & hand over of same to operations.  Ensuring completion ITR’s in a timely manner.  Ensuring all work is carried outin a safemanner. 03/12 – 04/12 ConstructionManager, Enermech Secondedto MODEC, Ghana.  Development of pre-bid construction plan for 1,800toffshore offloading buoy, 21 - 75t Suction Piles,8 pressurevessels and approx.400 Deck Stools for the in-country work of an FPSO.  Survey of sites for suitability of fabrication work for the project  vendor/sub-contractor appraisalsfor fabrication work & crane requirements.  Develop the initial prebid report for Ghana works to MODEC Management. 08/11 –12/11 Mechanical Completions/CommissioningLead–PremierOil,Keppel Benoi,Singapore Then Offshore Vietnam.  Commissioningon The LEWEK EMAS 660,000 bbl FPSO (FloatingProduction Storage & Offloading) Vessel.  Offshore commissioningof Topsides,Engine room and marineequipment, signingoff on behalf of the clientall mechanical equipment, witnessingpump runs, flushingoperations and system commissioning.  System start-up assistance,performancetesting and hand over to operations of Water Injection,gas compression,fuel Gas, oil separation and top-sidesystems duringfinal commissioningstages.  Co-ordination of the final handover to commissioningof all remainingsystems. 04/11 –07/11 Mechanical CompletionsCo-Ordinator–PremierOil,Keppel Benoi,Singapore.  Co-ordination of the final completions and hand over to commissioningof all remainingsystems prior to sail-away.  Short term contractto finalisethe completions work on behalf of the client,Premier Oil. 08/10 –04/11 Mechanical CompletionsCo-Ordinator–Master-Marine,Dry Docks Graha- Batam Island, Indonesia.  Completions co-ordination of the ‘NORA’ 118m ‘Service Jack’ barge with dynamic positioning jack up barge specifically for installation of Wind farms to operate in the North Sea.  Takingthe project to the final stages of hand-over to commissioning. 02/09 –08/10 Construction/CompletionsEngineer,NorCEOffshore,Bintan Island, Indonesia& Keppel Benoi, Singapore.  Preparation of completions documentation and signingover all mechanical systems to commissioning.  Construction of the NorCE Endeavour 26,000 tonne DLB (Derrick Lay Barge)  Installation and alignment of SAS pipelaying equipment, 5 W8L20 1780 kVA WartsillaGenerators,8 AmClyde Mooring winches, AmClyde M60 1100 t Ringer crane, 40 plus Allweiller Pumps and automatic hydraulic Water tightdoors. 01/08 –01/09 Lead Construction Engineer,AMEC,Karachaganak field,KPO, Uralsk,Kazakhstan,  Lead the Preparation of documentation for Mechanical Completion usingGOC (guidanceon Certification) for completion and Commissioningof systems.  Change out of existing sour gas re-injection pipework to 25% chrome.  Planningthe shut downs for the change out of all gas compression and re-injection piping. 03/07-12/07 ConstructionEngineer/ TGT Focal point,Production ServicesNetwork(PSN) Aberdeen  Focal pointfor all construction, brown-field and shutdown activities atthe ConocoPhillips Theddlethorpe Gas Terminal (TGT). Also Focal pointfor Lincolnshireand Rivers Terminal,Morecambe Bay.  Shutdown co-ordinator for TGT shutdown September 2007.Shutdown completed on time with all work scopes complete.
  • 3. Page 3 of 4 10/06-03/07 ConstructionManager, VikingUK GAS, East Knapton GeneratingStation North Yorkshire  Construction management of two consecutiveprojects: installation of Gas compression unitand installation of Flow& separation systemfor reclaimed well facility. 06/06-10/06 SeniorConstruction Engineer,Petrofac,WaGEproject for Armada platform 03/06-06/06 PipingImplementationEngineer,AMEC,Maria over Armada Project for BG 02/06-03/06 Shutdown Co-ordinator,AMEC, BP Coryton Crude unit 05/04- 11/05. Mechanical FieldEngineer,TechnipMaritime Offshore Limited.BP Shah Denizproject, Singapore and Baku, Azerbaijan- 32,000t total, topsides22,000t. 1999- 2004 Mechanical /Piping Supervisor/Superintendentvariousrolesincludingpetrochemical and nuclear installations. 1978-1999 Mechanical & pipe Fittervarious roles ICI,AMEC & Mitsui Babcock both Nuclearand Petrochemical Sites 1974-1978 Apprentice Mechanical Fitter- ICI Billingham(as above). EDUCATION AND QUALIFICATIONS: 1978: Hartlepool College ofFurther Education. City & GuildsOfLondon Full Tech. Cert. (Mech. Eng.). 1982: Blackpool & Fylde College ofFurther Education. Institute ofQuality Assurance Certificate in Quality Assurance 1984: Hartlepool College ofFurther Education. Higher National Certificate ComputerAided Production Engineering. 2014: Currentlystudying for Projectmanagement degree withOpenUniversityUK. ADDITIONAL INFORMATION:  BOSIET Survival (OPITO approved) currentuntil 20th July 2015  Open University studies carried outincluding: Livingwith Technology Foundation course(1992).ModellingWith Mathematics (1993).Systems (1993).  IOSH ManagingSafety course(2004).  AMEC Firststeps safety leadership course (2008)  Main Language English,Good knowledge of Bahasa Indonesia. HOBBIES/INTERESTS: Off-roading, own a 1978 Toyota FJ40 4x4 in Indonesia, non-competition use with Indonesian locals. Motorcycles own 1 Modern (Suzuki 1340 B-King) and the following Classics:  1981 Honda CBX1000 6 Cylinder  1974 Kawasaki Z1B900  1981 Yamaha YZ465 Moto-cross  1966 Ducati 250 Diana  1974- 1975 Harley Davidson 250SS (have two of these and two spare bikes)  1972 Aermacchi (Harley-Davidson) 350SX  1999 Harley Davidson Sportster 883 (Project Bike with 1260 Engine,Flat track style) Computer Builds for Home Entertainment, build of NAS (Network Attached Storage) system, using FREENAS software to provide movies, TV shows and Music around the home to Individual Android boxes in each room. Built approx. 10 Computers in total. References: Alistair Brown CommissioningManager,Premier Oil. alistair_brown@rocketmail.com
  • 4. Page 4 of 4 Tony Lobb Construction Manager Technip Shah Deniz Project tonylobb1000@yahoo.co.uk Peter Donnelly Facilities Manager. NorCE Offshore. pdonnel01@aol.com Andrew Roberts Construction Manager. Valhalla project,BP Lowestoft. robertsandy8@aol.com Michael Duff Construction Manager, Master Marine. mjduff5154@hotmail.com