Enhancing forest data transparency for climate action
ASFPM 2016: Phase and Forget?
1. June 23, 2016
Phase and Forget?
How to Move Phased HMGP Projects to Construction
Jordan Williams, CFM
2. Hazard Mitigation
2
Sustained action to reduce or eliminate
long-term risk to human life and
property from hazards.
The only phase of emergency
management specifically dedicated to
breaking the cycle of damage,
reconstruction, and repeated damage.
3. Hazard Mitigation Assistance
HMA programs reduce community vulnerability to disasters and
their effects, promote individual and community safety and
resilience, and promote community vitality after an incident
Pre-Disaster Mitigation (PDM)
Provides funds for hazard mitigation planning and projects on an annual
basis.
Available annually and nationally competitive
Flood Mitigation Assistance (FMA)
Provides funds for flood hazard mitigation projects as well as plan
development on an annual basis.
Priority to Repetitive Flood Claims, Severe Repetitive Loss, and NFIP
properties Available annually and nationally competitive
Hazard Mitigation Grant Program (HMGP)
Assists in implementing long-term hazard mitigation measures following a
major disaster.
4. Hazard Mitigation Assistance
HMA programs reduce community vulnerability to disasters and
their effects, promote individual and community safety and
resilience, and promote community vitality after an incident
Pre-Disaster Mitigation (PDM)
Provides funds for hazard mitigation planning and projects on an annual
basis.
Available annually and nationally competitive
Flood Mitigation Assistance (FMA)
Provides funds for flood hazard mitigation projects as well as plan
development on an annual basis.
Priority to Repetitive Flood Claims, Severe Repetitive Loss, and NFIP
properties Available annually and nationally competitive
Hazard Mitigation Grant Program (HMGP)
Assists in implementing long-term hazard mitigation measures following a
major disaster.
5. What is a phased project?
Projects that receive funding in phases to complete complex
activities and to allow the Applicant to develop a full work
scope/data package to support the full project description.
Phase 1: Design and Application Development
Phase 2: Construction
HMGP phasing does NOT equal partial solution/phased
construction
Some application components will be based on assumptions
and engineering judgement
Can be a great tool to allow communities to implement more
complex projects
5
6. The Number$
For Hurricane Sandy in New York
HMGP Ceiling is approximately $1.4 Billion
Approximately 50% is going to phased projects
33% is awaiting obligation pending Phase 2 approval
For Hurricane Katrina in Louisiana
Approximately $450 Million allocated to phased projects
in January 2015
Approximately $375 Million yet to be obligated
6
7. Why do projects get phased?
Communities don’t have a lot of technical staff on
Cost of design plans
Need for more detailed engineering analysis such as H&H
Complicated EHP
7
FEMA/Jennings
8. Examples
Larger complex community drainage
projects
Large critical facility building retrofits
Bridge upgrades
HMGP phasing does NOT equal partial solution/phased construction
8
FEMA/Booher
9. What should be in the initial application?
Scope of work
Available engineering analysis
Cost estimate
Benefit cost analysis
EHP requirements
Clearly stated assumptions
9
10. How do we move these forward?
Clear guidance on Phase 1 deliverables
Maintain accountability
Frequent and honest communication
10
FEMA News Photo
11. What are our recommendations?
Set clear deliverables and milestones in award letters
Consider time it will take State/Subapplicant to procure a designer
Consider the time it will take for FEMA and the State to review
Award letter should include:
Engineering analysis required
H&H
Geotechnical reports
Required design milestones
30%, 60%, 90%
Detailed cost-estimate
Benefit-cost analysis
EHP Requirements
TIMELINES!
Projects should be evaluated/
confirmed along the way
11
12. What are our recommendations?
Require Progress Reports and Status meetings
Avoid phase and forget
Review along the way
If deliverables show that a project will not meet HMA requirements
then adjust or deny
Don’t keep investing in projects that will not get approved
12
FEMA/Booher
13. What are our recommendations?
Joint review of materials versus submitting and
corresponding through an RFI
Use RFI’s to document the process and to ensure accountability
But work together to break the cycle of endless back and forth
13
14. What are our recommendations?
States should consider using Advance Assistance
versus phasing a project
Advance Assistance can be used to develop
mitigation strategies and obtain data to prioritize,
select, and develop complete HMGP applications
Under HMGP: 25% of ceiling or $10 Million
(whichever is less)
14
15. What are our recommendations?
Not every complex and/or incomplete project needs to be
phased, some can be ‘approvable’ through an RFI
FEMA/State should not use phasing as an extended way to
avoid saying “No”
Phased projects are not meant to be a band aid
Wastes resources
Organized file managment
15
16. Recommendations and Conclusions
Need to avoid “Phase and forget”
This process can be more work than traditional applications
Communication is key to success
These projects can work and provide better comprehensive
mitigation solutions
16
FEMA/Caliendo