NUHX - Project Fuqing 1+2 (Internal) Print Date: 5/28/2013
Page: 1 of 5
CLIENT : POWER, FQ 1+2 recovery project
Cut Off: end of each calendar month
Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14
P 15.4 38.5 63.7 85.7 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
A 3.2 16.8 31.6 44.5 58.1 72.3 72.3
P 0.0 0.1 0.3 0.5 0.7 0.9 0.9 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
A 0.0 0.2 0.2 0.4 0.6 0.8
EARLY 1.9 12.3 34.3 55.1 74.9 86.1 93.2 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
LATE 0.8 6.4 18.6 44.6 70.2 85.6 94.1 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
ACTUAL 0.1 3.5 15.9 25.2 38.4 60.4 82.3
FORECAST 0.1 3.5 15.9 25.2 38.4 60.4 82.3 98.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
Engineering
Procurement
OVERALL PROJECT PROGRESS
0
10
20
30
40
50
60
70
80
90
100
Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14
PercentComplete
Time
Early
Finish
Actual
Forecast
Status as of: 30-May-13
NUHX - Project Fuqing 1+2 (Internal) Print Date: 5/28/2013
Page: 2 of 5
CLIENT : POWER, FQ 1+2 recovery project
Cut Off: end of each calendar month
Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14
EARLY 15.4 38.5 63.7 85.7 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
LATE 19.8 41.8 64.8 89.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
ACTUAL 3.2 16.8 31.6 44.5 58.1 72.3 72.3
FORECAST 3.2 16.8 31.6 44.5 58.1 72.3 72.3 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
ENGINEERING PROGRESS
0
10
20
30
40
50
60
70
80
90
100
Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13
PercentComplete
Time
EARLY
LATE
ACTUAL
FORECAST
Status as of 30-May-13
NUHX - Project Fuqing 1+2 (Internal) Print Date: 5/28/2013
Page: 3 of 5
CLIENT : POWER, FQ 1+2 recovery project
Cut Off: end of each calendar month
Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14
EARLY 1.9 16.2 47.6 77.7 98.1 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
LATE 7.0 24.0 61.6 92.8 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
ACTUAL 3.5 18.6 29.7 45.2 66.3 87.0
FORECAST 3.5 18.6 29.7 45.2 66.3 87.0 98.6 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
PROCUREMENT PROGRESS
0
10
20
30
40
50
60
70
80
90
100
Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13
PercentComplete
Time
EARLY
LATE
ACTUAL
FORECAST
Status as of 30-May-13
NUHX - Project Fuqing 1+2 (Internal) Print Date: 5/28/2013
Page: 4 of 5
CLIENT : POWER, FQ 1+2 recovery project
Cut Off: end of each calendar month
Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14
EARLY 19.6 53.3 77.6 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
LATE 15.4 51.4 80.4 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
ACTUAL 2.8 30.8 63.5
FORECAST 2.8 30.8 63.5 95.3 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
MANUFACTURING PROGRESS
0
10
20
30
40
50
60
70
80
90
100
Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13
PercentComplete
Time
EARLY
LATE
ACTUAL
FORECAST
Status as of 30-May-13
NUHX - Project Fuqing 1+2 (Internal) Print Date: 5/28/2013
Page: 5 of 5
CLIENT : POWER, FQ 1+2 recovery project
Cut Off: end of each calendar month
Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14
EARLY 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
LATE 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
ACTUAL
FORECAST 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
TRANSPORT PROGRESS
0
10
20
30
40
50
60
70
80
90
100
Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13
PercentComplete
Time
EARLY
LATE
ACTUAL
FORECAST
Status as of 30-May-13

More Related Content

Viewers also liked

Psychosexualdisorders 131228151731-phpapp01
Psychosexualdisorders 131228151731-phpapp01Psychosexualdisorders 131228151731-phpapp01
Psychosexualdisorders 131228151731-phpapp01Bob Bahaa
 
-Strategy Planning Report
-Strategy Planning Report-Strategy Planning Report
-Strategy Planning Reportyang lu
 
- The preliminary investgation report for the oil gas process equipment co,lt...
- The preliminary investgation report for the oil gas process equipment co,lt...- The preliminary investgation report for the oil gas process equipment co,lt...
- The preliminary investgation report for the oil gas process equipment co,lt...yang lu
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...yang lu
 
-The project control department report summary for 2014
-The project control department report summary for 2014-The project control department report summary for 2014
-The project control department report summary for 2014yang lu
 
Telaah kurikulum
Telaah kurikulumTelaah kurikulum
Telaah kurikulumPa Mulya
 

Viewers also liked (10)

Psychosexualdisorders 131228151731-phpapp01
Psychosexualdisorders 131228151731-phpapp01Psychosexualdisorders 131228151731-phpapp01
Psychosexualdisorders 131228151731-phpapp01
 
RacingReflection2014
RacingReflection2014RacingReflection2014
RacingReflection2014
 
-Strategy Planning Report
-Strategy Planning Report-Strategy Planning Report
-Strategy Planning Report
 
- The preliminary investgation report for the oil gas process equipment co,lt...
- The preliminary investgation report for the oil gas process equipment co,lt...- The preliminary investgation report for the oil gas process equipment co,lt...
- The preliminary investgation report for the oil gas process equipment co,lt...
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
 
Laura maroldi management
Laura maroldi managementLaura maroldi management
Laura maroldi management
 
Games and hobbies
Games and hobbiesGames and hobbies
Games and hobbies
 
-The project control department report summary for 2014
-The project control department report summary for 2014-The project control department report summary for 2014
-The project control department report summary for 2014
 
Telaah kurikulum
Telaah kurikulumTelaah kurikulum
Telaah kurikulum
 
Amino acid
Amino acidAmino acid
Amino acid
 

NUHX - FQ1+2_Progress Curves_130524

  • 1. NUHX - Project Fuqing 1+2 (Internal) Print Date: 5/28/2013 Page: 1 of 5 CLIENT : POWER, FQ 1+2 recovery project Cut Off: end of each calendar month Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 P 15.4 38.5 63.7 85.7 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 A 3.2 16.8 31.6 44.5 58.1 72.3 72.3 P 0.0 0.1 0.3 0.5 0.7 0.9 0.9 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 A 0.0 0.2 0.2 0.4 0.6 0.8 EARLY 1.9 12.3 34.3 55.1 74.9 86.1 93.2 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 LATE 0.8 6.4 18.6 44.6 70.2 85.6 94.1 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 ACTUAL 0.1 3.5 15.9 25.2 38.4 60.4 82.3 FORECAST 0.1 3.5 15.9 25.2 38.4 60.4 82.3 98.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 Engineering Procurement OVERALL PROJECT PROGRESS 0 10 20 30 40 50 60 70 80 90 100 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 PercentComplete Time Early Finish Actual Forecast Status as of: 30-May-13
  • 2. NUHX - Project Fuqing 1+2 (Internal) Print Date: 5/28/2013 Page: 2 of 5 CLIENT : POWER, FQ 1+2 recovery project Cut Off: end of each calendar month Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 EARLY 15.4 38.5 63.7 85.7 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 LATE 19.8 41.8 64.8 89.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 ACTUAL 3.2 16.8 31.6 44.5 58.1 72.3 72.3 FORECAST 3.2 16.8 31.6 44.5 58.1 72.3 72.3 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 ENGINEERING PROGRESS 0 10 20 30 40 50 60 70 80 90 100 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 PercentComplete Time EARLY LATE ACTUAL FORECAST Status as of 30-May-13
  • 3. NUHX - Project Fuqing 1+2 (Internal) Print Date: 5/28/2013 Page: 3 of 5 CLIENT : POWER, FQ 1+2 recovery project Cut Off: end of each calendar month Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 EARLY 1.9 16.2 47.6 77.7 98.1 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 LATE 7.0 24.0 61.6 92.8 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 ACTUAL 3.5 18.6 29.7 45.2 66.3 87.0 FORECAST 3.5 18.6 29.7 45.2 66.3 87.0 98.6 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 PROCUREMENT PROGRESS 0 10 20 30 40 50 60 70 80 90 100 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 PercentComplete Time EARLY LATE ACTUAL FORECAST Status as of 30-May-13
  • 4. NUHX - Project Fuqing 1+2 (Internal) Print Date: 5/28/2013 Page: 4 of 5 CLIENT : POWER, FQ 1+2 recovery project Cut Off: end of each calendar month Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 EARLY 19.6 53.3 77.6 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 LATE 15.4 51.4 80.4 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 ACTUAL 2.8 30.8 63.5 FORECAST 2.8 30.8 63.5 95.3 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 MANUFACTURING PROGRESS 0 10 20 30 40 50 60 70 80 90 100 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 PercentComplete Time EARLY LATE ACTUAL FORECAST Status as of 30-May-13
  • 5. NUHX - Project Fuqing 1+2 (Internal) Print Date: 5/28/2013 Page: 5 of 5 CLIENT : POWER, FQ 1+2 recovery project Cut Off: end of each calendar month Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 EARLY 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 LATE 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 ACTUAL FORECAST 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 TRANSPORT PROGRESS 0 10 20 30 40 50 60 70 80 90 100 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 PercentComplete Time EARLY LATE ACTUAL FORECAST Status as of 30-May-13