OBJECTIVE OF THE DOCUMENT

The modules involved in logistics in SAP are tightly integrated between each other and works seamlessly in an
organization. The module which aligns centrally to all the logistics modules in the planning, execution and
management of capacities, resources and costs is Project System popularly called as PS. In the light of this, it is very
much important for consultants to know various elements of the project and how these elements are related to each
other. Knowing the project structure and its elements along with the database tables will help the consultants to
devise customized reports for various scenarios suiting to individual projects.
This document contains
Database tables for each of the project elements
Connecting link between various database tables
This document does not contain
Detailed information about the elements of project though it is precisely mentioned for the purpose of understanding
Costing related data as my knowledge level is very less in this area
Detailed information about the module as such and the processes involved
Transaction codes for all the project elements. However it is included wherever possible.
This document explains the logic only around the functionalities enabled in PS system, but not in any other modules
like PP or PM. Even in those modules some of these tables may be used, but the logic mentioned here explains the
usage, logic and joins between these tables only in the perspective of PS.

ELEMENTS OF PROJECT AND THEIR TABLES

A project is initiated with the intention of creating a unique purpose; it can be a product a service or combination of
both.
In order to manage the project, the project is subdivided into various small deliverables called WBS elements or Work
Breakdown Structures. Each such deliverables can be used to plan costs and revenues, resources and capacities.
In some cases, the projects are



PROJECT

Project is at the highest level and WBS elements are networks are subordinates of the project. The costs are
revenues at the network or WBS level will finally accrue as the cost and revenue of the project.



The database table which contains the relevant information about the project is PROJ. In this table the field PROJ-
PSPNR represents the project number. There is also another field PROJ-OBJNR is an important field as this field
serves as the foreign key for making any queries at the project level. This is the key field for finding the status of the
project. The method to find out the status of the project is dealt in the later part of the document.



WBS ELEMENTS
A project can have many WBS elements assigned to it. The details pertaining to the WBS elements are available at
the database table PRPS. The table has the field PRPS-PSPNR has the WBS element number. The project related to
the WBS element can be obtained from the field PRPS-PSPHI. Hence using this field all the WBS elements assigned
a project can be easily found in any custom report. The table PRPS also has got another field called PRPS-
OBJNRwhich is the linking field to any other tables containing various information related to the WBS element. This
field is the key field for finding the status of the WBS element. The method to find the status of WBS element using
this field is dealt in the later part of this document.



A project can also contain various networks. Networks contain lot of activities which are linked to each other by
means of different relationship types. The duration which each activity takes and lead time or lag time between two
activities are also available in the network. Some of these activities are also earmarked as Milestones in the project
and based on the Milestone completion; revenue generation can be initiates in Sales and Distribution by means of an
invoice creation for the relevant Milestone using Milestone billing functionality. In a network enabled business
scenario, all the details of the project like Schedule, cost, capacity and reservations will flow from network to the
higher level structures like WBS element and project. Various features of the network and their underlying database
tables are discussed below here.



NETWORK HEADER

The database table AUFK contains the network header related information. Some of the important fields available in
this table are listed one by one as follows.
The field AUFK-AUFNR represents the network number created in the system.



The field AUFK-OBJNR is a field which will be used as a foreign key in case this table needs to be linked with some
other table.
The field AUFK-PSPEL represents the WBS element which is linked to the network at the header level. However if the
business scenario involves activities within the network, this field may not be of much use as each activity can have
different WBS elements of the same project. This field assumes importance if the networks are used without
activities.



In case of assembly processing, where a network is created from a sales order using standard project elements the
fields AUFK-KDAUF and AUFK-KDPOS represents the sales order number and line item respectively which triggered
the network. These fields are seen in the network header in the fields Sales Order Number and Sales Order Item in
the Assignments tab.



There is also another table CAUFV which is similar to AUFK but CAUFV has some other additional information
related to costing etc. The table CAUFV is very important because this table is the central table using which all the
other network related tables are accessed. Some of the important fields in this table are discussed below.



The field CAUFV-AUFNR represents the network number which is same as AUFK-AUFNR.
The field CAUFV-AUFPL represents the connecting link between all the related tables. The field which is read as
“Routing number of Operations in the Order” is the main field to be used for any join using this table.



NETWORK ACTIVITIES

The details pertaining to network activities can be obtained from the table AFVC. When a network number is known it
should be passed as CAUFV-AUFNR and the resultant CAUFV-AUFPL and CAUFV-BEDID should be obtained.



Now the value of CAUFV-AUFPL should be passed as AFVC-AUFPL and AFVC-BEDID respectively. The resultant
list gives the list of all the activities of the network.



Various fields and their importance are provided in detail below.



The field AFVC-VORNR refers to the activity number of the activity in the network. This number can serve as the
foreign key in many of the tables associated with the network activities. However there are also other fields which can
serve as foreign keys in different tables.



The field AFVC-APLZL refers to the counter number of the activity. This is an important field when the network
relationships are to be found out.
There are various fields related to control key of the activity, activity description, plant, work center, calculation type
etc which can be seen using this logic and hence those fields are not discussed in detail here.



The data pertaining to planned cost for primary cost activities can also be found in this table in the fields AFVC-
PRKST for the planned cost and AFVC- SAKTO for the cost element against which the cost is planned.



There is also another table AFVCP where AFVCP-AUFPL = CAUFV-AUFPL using which the WBS element assigned
to each of the activities can be found out.



NETWORK RELATIONSHIP

The details pertaining to the relationship of the network activities can be seen from the table AFAB. In this table
following are the fields which are very important.



The field AFAB-AUFPL_VOR represents the CAUFV-AUFPL of the network where the preceding activity is located.
The field AFAB-APLZL_VOR represents the preceding activity counter number of the network. This value is same as
the value of the field AFVC-APLZL



The field AFAB-AUFPL_NCH represents the network number of the succeeding activity.



The field AFAB-APLZL_NCH represents the counter number of the network which is same as the value of the
fieldAFVC-APLZL.



If the relationship of all the activities are within a single network without involvement of any other sub network like a
task list or maintenance order etc, then the field values will be same for both AFAB-AUFPL_VOR and AFAB-
AUFPL_NCH. In such a scenario the value of the fields AFAB-AUFPL_VOR and AFAB-AUFPL_NCH will be same. In
a case where the activities of one network are related to activities of some other network, then these fields will have
different value. Hence if the relationship of activities in a network needs to be found, then it is necessary to give the
condition that CAUFV-AUFPL should be in either AFAB-AUFPL_VOR or (not and) in the field AFAB-AUFPL_NCH.



NETWORK MILESTONES

Some of the network activities can be maintained as milestones and the list of milestones can be obtained from the
database table MLST. In order to get the information of all the milestones of the network the
table CAUFV and MLSTcan be used.



The field CAUFV-AUFPL can be given as an input in MLST-AUFPL and the resultant list provides the list of
milestones of the network.



The field MLST_ZAEHL is the Milestone number. This field can be used to get information about milestones from
different database tables. For all those purposes, this field can be used as the foreign key.



The field MLST- MLSTN provides the Milestone usage.



If the MS is confirmed then the confirmation number can be obtained from the field MLST- RUECK.



The table also has information related to Trend analysis, Progress analysis, Milestone functions etc which can be
analyzed in detail. As the key fields are already mentioned, it should be easy to get all the other necessary details
used this table.
NETWORK MILESTONE CONFIRMATION DETAILS

The status of the confirmed milestones of a network can be found from the table AFRU. Some of the important fields
in this table are discussed below.



The field AFRU-AUFPL represents the link with all the other tables of the network where this field equals to the
fieldCAUFV-AUFPL or AFVC-AUFPL or MLST-AUFPL. Using this table AFRU can be accessed.



The field AFRU-VORNR represents the activity number whose milestone is confirmed



The field AFRU-APLZL represents the counter number of the activity in the network. This is nothing but the AFVC-
APLZL number.



The field AFRU- RUECK represents the confirmation number. This field is available both in AFRU and also in MLST.
However MLST gives the information that the milestone is confirmed but AFRU also says whether the confirmation is
a final confirmation or not in the field AFRU- AUERU.


Once this information is known, any other confirmation related information can be extracted either from the table
MLST or from AFRU based on requirement.



NETWORK MATERIAL COMPONENTS

The details pertaining to material components and their assigned transactions can be seen in the tables RESB,
AFWD and AFWI.
Some key fields of the table RESB are first explained.



The field RESB- AUFNR represents the network number which triggered the reservation. As this table is the central
table for reservation happening from various other transactions like sales order, planned order etc, different fields will
be updated during different transactions. If the reservation is triggered through the network, then this field will be
filled. For items which do not create reservations from material components, this table is not valid.



The field RESB- RSNUM represents the reservation number and this can be used to find out all the reservation
related data.
There are other important fields like requirement quantity and requirement date which can be easily found once this
key field is known.



Similarly the tables AFWD and AFWI deals with the material movements associated with the confirmation of
milestones. Because of my limited knowledge on these tables, I am just mentioning these tables and leave the rest
for exploration.



STATUS OF THE PROJECT ELEMENTS

There are two tables related to the status of any transaction provided the transaction is enabled for statuses using a
status profile. They are JCDS and JEST. There are also two other tables TJ02 and TJ30 and these tables are also
discussed here.



Any transaction with the status profiles enabled will get updated in tables which will definitely have a field
calledOBJNR. For example the tables relevant for project, WBS element and network namely PROJ,
PRPS and AUFK have this field OBJNR. This field forms the basis for finding out the correct status.
In other modules transactions include sales order, production order, planned order, maintenance order, task list etc
will also have the object number. In sales order object number will be available for both sales order header and item.
Accordingly the statuses can be seen both at sales order header and at item level. Similarly each transaction has its
own structure and their respective object number.



The table JCDS shows the change history of the status. The relevant object number OBJNR should be given as the
input here and the output should be received.



Here the field JCDS- STAT represents the status. Any status with the prefix E is the user status and the one with the
prefix I is the system status.
In order to get the correct system, the value from this field should be passed on into the field TJ02-ISTAT to get the
system status.



For user status the field TJ30- ESTAT should be filled with the value of the field JCDS-STAT to know the actual user
status. However my knowledge in this table is very limited and there seems to be some more logic involved to find out
the correct status. That part is left for exploration. I will update this logic later if I can find this.



The table JEST shows the current status of the object. The same logic should be used as explained earlier.
The fool proof logic for status identification still needs to be explored.



PROJECT VERSIONS
The database table pertaining to the version of the project elements follows the syntax VS<DATABASE TABLE OF
THE OBJECT>_CN. Using this logic the project versions of all the objects can be found out without any problem.

CONCLUSION

This document still can be evolved by providing information on the logic for getting the information pertaining to actual
costs, actual revenues etc. As of now, I am in the process of trying to standardize the logic for getting these elements
and the same will be updated whenever it is ready. For now, let us all make use of this document and enjoy the world
of PS ing in SAP.

More Related Content

Similar to Ps table

SAP ABAP Latest Interview Questions
SAP ABAP Latest  Interview Questions SAP ABAP Latest  Interview Questions
SAP ABAP Latest Interview Questions
piyushchawala
 
1000 solved questions
1000 solved questions1000 solved questions
1000 solved questions
Kranthi Kumar
 

Similar to Ps table (20)

BAPI - Criação de Ordem de Manutenção
BAPI - Criação de Ordem de ManutençãoBAPI - Criação de Ordem de Manutenção
BAPI - Criação de Ordem de Manutenção
 
ABAP FAQ S On Reports Scripts BDC Dialogs ABAP Reporting SAP TERMINOLOGY
ABAP FAQ S On Reports   Scripts   BDC   Dialogs ABAP Reporting SAP TERMINOLOGYABAP FAQ S On Reports   Scripts   BDC   Dialogs ABAP Reporting SAP TERMINOLOGY
ABAP FAQ S On Reports Scripts BDC Dialogs ABAP Reporting SAP TERMINOLOGY
 
Abap faq
Abap faqAbap faq
Abap faq
 
MD04 Report in BW
MD04 Report in BWMD04 Report in BW
MD04 Report in BW
 
Abap interview questions and answers
Abap interview questions and answersAbap interview questions and answers
Abap interview questions and answers
 
SAP ABAP Latest Interview Questions
SAP ABAP Latest  Interview Questions SAP ABAP Latest  Interview Questions
SAP ABAP Latest Interview Questions
 
SAP ABAP Interview questions
SAP ABAP Interview questionsSAP ABAP Interview questions
SAP ABAP Interview questions
 
1000 solved questions
1000 solved questions1000 solved questions
1000 solved questions
 
1000 sap-interview-qa
1000 sap-interview-qa1000 sap-interview-qa
1000 sap-interview-qa
 
Setup_Steps_ASCP_1.pdf
Setup_Steps_ASCP_1.pdfSetup_Steps_ASCP_1.pdf
Setup_Steps_ASCP_1.pdf
 
325546_adding fields in CJI3 & CJI5.pdf
325546_adding fields in CJI3 & CJI5.pdf325546_adding fields in CJI3 & CJI5.pdf
325546_adding fields in CJI3 & CJI5.pdf
 
Kevin Fahy Bi Portfolio
Kevin Fahy   Bi PortfolioKevin Fahy   Bi Portfolio
Kevin Fahy Bi Portfolio
 
How to manage allocations in bpc 7.0
How to manage allocations in bpc 7.0How to manage allocations in bpc 7.0
How to manage allocations in bpc 7.0
 
Oracle_Analytical_function.pdf
Oracle_Analytical_function.pdfOracle_Analytical_function.pdf
Oracle_Analytical_function.pdf
 
How to run v3 job
How to run v3 jobHow to run v3 job
How to run v3 job
 
MAPPING SCDL/BPEL TO ADA FOR FORMAL VERIFICATION OF THE BEHAVIORAL PROPERTIES...
MAPPING SCDL/BPEL TO ADA FOR FORMAL VERIFICATION OF THE BEHAVIORAL PROPERTIES...MAPPING SCDL/BPEL TO ADA FOR FORMAL VERIFICATION OF THE BEHAVIORAL PROPERTIES...
MAPPING SCDL/BPEL TO ADA FOR FORMAL VERIFICATION OF THE BEHAVIORAL PROPERTIES...
 
MAPPING SCDL/BPEL TO ADA FOR FORMAL VERIFICATION OF THE BEHAVIORAL PROPERTIES...
MAPPING SCDL/BPEL TO ADA FOR FORMAL VERIFICATION OF THE BEHAVIORAL PROPERTIES...MAPPING SCDL/BPEL TO ADA FOR FORMAL VERIFICATION OF THE BEHAVIORAL PROPERTIES...
MAPPING SCDL/BPEL TO ADA FOR FORMAL VERIFICATION OF THE BEHAVIORAL PROPERTIES...
 
Sap bw lo extraction
Sap bw lo extractionSap bw lo extraction
Sap bw lo extraction
 
Composite Providers - Nuts and Bolts.pptx
Composite Providers - Nuts and Bolts.pptxComposite Providers - Nuts and Bolts.pptx
Composite Providers - Nuts and Bolts.pptx
 
Paper-STS026-v1.5
Paper-STS026-v1.5Paper-STS026-v1.5
Paper-STS026-v1.5
 

Recently uploaded

CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
giselly40
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
vu2urc
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
Earley Information Science
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
Enterprise Knowledge
 

Recently uploaded (20)

Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 

Ps table

  • 1. OBJECTIVE OF THE DOCUMENT The modules involved in logistics in SAP are tightly integrated between each other and works seamlessly in an organization. The module which aligns centrally to all the logistics modules in the planning, execution and management of capacities, resources and costs is Project System popularly called as PS. In the light of this, it is very much important for consultants to know various elements of the project and how these elements are related to each other. Knowing the project structure and its elements along with the database tables will help the consultants to devise customized reports for various scenarios suiting to individual projects. This document contains Database tables for each of the project elements Connecting link between various database tables This document does not contain Detailed information about the elements of project though it is precisely mentioned for the purpose of understanding Costing related data as my knowledge level is very less in this area Detailed information about the module as such and the processes involved Transaction codes for all the project elements. However it is included wherever possible. This document explains the logic only around the functionalities enabled in PS system, but not in any other modules like PP or PM. Even in those modules some of these tables may be used, but the logic mentioned here explains the usage, logic and joins between these tables only in the perspective of PS. ELEMENTS OF PROJECT AND THEIR TABLES A project is initiated with the intention of creating a unique purpose; it can be a product a service or combination of both. In order to manage the project, the project is subdivided into various small deliverables called WBS elements or Work Breakdown Structures. Each such deliverables can be used to plan costs and revenues, resources and capacities. In some cases, the projects are PROJECT Project is at the highest level and WBS elements are networks are subordinates of the project. The costs are revenues at the network or WBS level will finally accrue as the cost and revenue of the project. The database table which contains the relevant information about the project is PROJ. In this table the field PROJ- PSPNR represents the project number. There is also another field PROJ-OBJNR is an important field as this field serves as the foreign key for making any queries at the project level. This is the key field for finding the status of the project. The method to find out the status of the project is dealt in the later part of the document. WBS ELEMENTS
  • 2. A project can have many WBS elements assigned to it. The details pertaining to the WBS elements are available at the database table PRPS. The table has the field PRPS-PSPNR has the WBS element number. The project related to the WBS element can be obtained from the field PRPS-PSPHI. Hence using this field all the WBS elements assigned a project can be easily found in any custom report. The table PRPS also has got another field called PRPS- OBJNRwhich is the linking field to any other tables containing various information related to the WBS element. This field is the key field for finding the status of the WBS element. The method to find the status of WBS element using this field is dealt in the later part of this document. A project can also contain various networks. Networks contain lot of activities which are linked to each other by means of different relationship types. The duration which each activity takes and lead time or lag time between two activities are also available in the network. Some of these activities are also earmarked as Milestones in the project and based on the Milestone completion; revenue generation can be initiates in Sales and Distribution by means of an invoice creation for the relevant Milestone using Milestone billing functionality. In a network enabled business scenario, all the details of the project like Schedule, cost, capacity and reservations will flow from network to the higher level structures like WBS element and project. Various features of the network and their underlying database tables are discussed below here. NETWORK HEADER The database table AUFK contains the network header related information. Some of the important fields available in this table are listed one by one as follows. The field AUFK-AUFNR represents the network number created in the system. The field AUFK-OBJNR is a field which will be used as a foreign key in case this table needs to be linked with some other table. The field AUFK-PSPEL represents the WBS element which is linked to the network at the header level. However if the business scenario involves activities within the network, this field may not be of much use as each activity can have different WBS elements of the same project. This field assumes importance if the networks are used without activities. In case of assembly processing, where a network is created from a sales order using standard project elements the fields AUFK-KDAUF and AUFK-KDPOS represents the sales order number and line item respectively which triggered the network. These fields are seen in the network header in the fields Sales Order Number and Sales Order Item in the Assignments tab. There is also another table CAUFV which is similar to AUFK but CAUFV has some other additional information related to costing etc. The table CAUFV is very important because this table is the central table using which all the other network related tables are accessed. Some of the important fields in this table are discussed below. The field CAUFV-AUFNR represents the network number which is same as AUFK-AUFNR.
  • 3. The field CAUFV-AUFPL represents the connecting link between all the related tables. The field which is read as “Routing number of Operations in the Order” is the main field to be used for any join using this table. NETWORK ACTIVITIES The details pertaining to network activities can be obtained from the table AFVC. When a network number is known it should be passed as CAUFV-AUFNR and the resultant CAUFV-AUFPL and CAUFV-BEDID should be obtained. Now the value of CAUFV-AUFPL should be passed as AFVC-AUFPL and AFVC-BEDID respectively. The resultant list gives the list of all the activities of the network. Various fields and their importance are provided in detail below. The field AFVC-VORNR refers to the activity number of the activity in the network. This number can serve as the foreign key in many of the tables associated with the network activities. However there are also other fields which can serve as foreign keys in different tables. The field AFVC-APLZL refers to the counter number of the activity. This is an important field when the network relationships are to be found out. There are various fields related to control key of the activity, activity description, plant, work center, calculation type etc which can be seen using this logic and hence those fields are not discussed in detail here. The data pertaining to planned cost for primary cost activities can also be found in this table in the fields AFVC- PRKST for the planned cost and AFVC- SAKTO for the cost element against which the cost is planned. There is also another table AFVCP where AFVCP-AUFPL = CAUFV-AUFPL using which the WBS element assigned to each of the activities can be found out. NETWORK RELATIONSHIP The details pertaining to the relationship of the network activities can be seen from the table AFAB. In this table following are the fields which are very important. The field AFAB-AUFPL_VOR represents the CAUFV-AUFPL of the network where the preceding activity is located.
  • 4. The field AFAB-APLZL_VOR represents the preceding activity counter number of the network. This value is same as the value of the field AFVC-APLZL The field AFAB-AUFPL_NCH represents the network number of the succeeding activity. The field AFAB-APLZL_NCH represents the counter number of the network which is same as the value of the fieldAFVC-APLZL. If the relationship of all the activities are within a single network without involvement of any other sub network like a task list or maintenance order etc, then the field values will be same for both AFAB-AUFPL_VOR and AFAB- AUFPL_NCH. In such a scenario the value of the fields AFAB-AUFPL_VOR and AFAB-AUFPL_NCH will be same. In a case where the activities of one network are related to activities of some other network, then these fields will have different value. Hence if the relationship of activities in a network needs to be found, then it is necessary to give the condition that CAUFV-AUFPL should be in either AFAB-AUFPL_VOR or (not and) in the field AFAB-AUFPL_NCH. NETWORK MILESTONES Some of the network activities can be maintained as milestones and the list of milestones can be obtained from the database table MLST. In order to get the information of all the milestones of the network the table CAUFV and MLSTcan be used. The field CAUFV-AUFPL can be given as an input in MLST-AUFPL and the resultant list provides the list of milestones of the network. The field MLST_ZAEHL is the Milestone number. This field can be used to get information about milestones from different database tables. For all those purposes, this field can be used as the foreign key. The field MLST- MLSTN provides the Milestone usage. If the MS is confirmed then the confirmation number can be obtained from the field MLST- RUECK. The table also has information related to Trend analysis, Progress analysis, Milestone functions etc which can be analyzed in detail. As the key fields are already mentioned, it should be easy to get all the other necessary details used this table.
  • 5. NETWORK MILESTONE CONFIRMATION DETAILS The status of the confirmed milestones of a network can be found from the table AFRU. Some of the important fields in this table are discussed below. The field AFRU-AUFPL represents the link with all the other tables of the network where this field equals to the fieldCAUFV-AUFPL or AFVC-AUFPL or MLST-AUFPL. Using this table AFRU can be accessed. The field AFRU-VORNR represents the activity number whose milestone is confirmed The field AFRU-APLZL represents the counter number of the activity in the network. This is nothing but the AFVC- APLZL number. The field AFRU- RUECK represents the confirmation number. This field is available both in AFRU and also in MLST. However MLST gives the information that the milestone is confirmed but AFRU also says whether the confirmation is a final confirmation or not in the field AFRU- AUERU. Once this information is known, any other confirmation related information can be extracted either from the table MLST or from AFRU based on requirement. NETWORK MATERIAL COMPONENTS The details pertaining to material components and their assigned transactions can be seen in the tables RESB, AFWD and AFWI. Some key fields of the table RESB are first explained. The field RESB- AUFNR represents the network number which triggered the reservation. As this table is the central table for reservation happening from various other transactions like sales order, planned order etc, different fields will be updated during different transactions. If the reservation is triggered through the network, then this field will be filled. For items which do not create reservations from material components, this table is not valid. The field RESB- RSNUM represents the reservation number and this can be used to find out all the reservation related data.
  • 6. There are other important fields like requirement quantity and requirement date which can be easily found once this key field is known. Similarly the tables AFWD and AFWI deals with the material movements associated with the confirmation of milestones. Because of my limited knowledge on these tables, I am just mentioning these tables and leave the rest for exploration. STATUS OF THE PROJECT ELEMENTS There are two tables related to the status of any transaction provided the transaction is enabled for statuses using a status profile. They are JCDS and JEST. There are also two other tables TJ02 and TJ30 and these tables are also discussed here. Any transaction with the status profiles enabled will get updated in tables which will definitely have a field calledOBJNR. For example the tables relevant for project, WBS element and network namely PROJ, PRPS and AUFK have this field OBJNR. This field forms the basis for finding out the correct status. In other modules transactions include sales order, production order, planned order, maintenance order, task list etc will also have the object number. In sales order object number will be available for both sales order header and item. Accordingly the statuses can be seen both at sales order header and at item level. Similarly each transaction has its own structure and their respective object number. The table JCDS shows the change history of the status. The relevant object number OBJNR should be given as the input here and the output should be received. Here the field JCDS- STAT represents the status. Any status with the prefix E is the user status and the one with the prefix I is the system status. In order to get the correct system, the value from this field should be passed on into the field TJ02-ISTAT to get the system status. For user status the field TJ30- ESTAT should be filled with the value of the field JCDS-STAT to know the actual user status. However my knowledge in this table is very limited and there seems to be some more logic involved to find out the correct status. That part is left for exploration. I will update this logic later if I can find this. The table JEST shows the current status of the object. The same logic should be used as explained earlier. The fool proof logic for status identification still needs to be explored. PROJECT VERSIONS
  • 7. The database table pertaining to the version of the project elements follows the syntax VS<DATABASE TABLE OF THE OBJECT>_CN. Using this logic the project versions of all the objects can be found out without any problem. CONCLUSION This document still can be evolved by providing information on the logic for getting the information pertaining to actual costs, actual revenues etc. As of now, I am in the process of trying to standardize the logic for getting these elements and the same will be updated whenever it is ready. For now, let us all make use of this document and enjoy the world of PS ing in SAP.