Hickory Company manufactures two products -14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: (The total estimated overhead cost may not agree with the sum of allocated overhead costs to each product.) A. What is the company\'s plantwide overhead rate (round your answer to 2 Decimal Places) B. Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places and final answers to the nearest dollar amount.) Solution a) 206000+145600+307200 = 658800 / 12000 = 54.9 .