SlideShare a Scribd company logo
1 of 18
1
PROJECT
ON
“INCREASING PRODUCTIVITY OF L/H & R/H CRANKCASE
COVER”
Under the guidance of:
Mr.J. Sathya,
Manager, Machine cell,
Royal Enfield,Thiruvottiyor, Chennai
From 26/11/2015 to 26/12/2015
By:
Arun Kumar
Sripal Kumar B,
SRM University
Chennai
2
ACKNOWLEDGEMENT
It gives me tremendous pleasure in bringing out this project entitled “ Increasing
Productivity of L/H and R/H crankcase covers” taken up during my final year
B.Tech degree course.
First of all, we would like to thank Mr.J.Sathya, Manager, Machine cell, Royal
Enfield, for guiding us in each and every step of our project right from day 1.
His guidance and supervision were useful to us in many aspects, which led us
successfully complete our project.
Next we would like to thank Mr. Ramalingam, Manager, HR, Royal Enfield for
giving us permission to carry out this project without any interruptions. His kind
gesture and very acceptable nature is to be well appreciated as well.
I am thankful to Mr. Duraivelu, dean and Mr. Karthikeyan Head of Dept of
Mechanical Engineering , SRM University for granting me permission for this
work and the help extended to me during the course of this project.
We would also like to thank the Almighty and our parents without whose
support, successful completion of this project would have been a difficult task.
Last but not the least, we would like to thank each and every staff of Royal
Enfield, Thiruvottiyur for their kind cooperation and helping nature.
3
INDEX
S.NO TOPICS PAGE NO.
1. ACKNOWLEDGEMENT 02
2. INTRODUCTION 04
3. AIM & OBJECTIVES 05
4. MATERIALS AND METHODS 06
5. L/H CRANKCASE COVERS 06
6. R/H CRANKCASE COVERS 09
7. LINE BALANCING 13
8 CONCLUSION 17
4
INTRODUCTION
Royal Enfield was the brand name under which the Enfield Cycle
Company manufactured motorcycles, bicycles,lawnmowers and stationary
engines. The first Royal Enfield motorcycle was built in 1901; the original
British concern was defunct by 1970. The Enfield Cycle Company is
responsible for the design and original production of the Royal Enfield Bullet,
the longest-lived motorcycle design in history.
Like other motorcycle manufacturers such as BSA and IZhMASh, the Enfield
Cycle Company began business as a weapons manufacturer, most famous for
the Enfield rifle. This legacy is reflected in the company logo, a cannon, and
their motto, "Made Like A Gun".
In 1955, Enfield Cycle Company partnered with Madras Motors in India in
forming Enfield of India, based in Chennai, and started assembling the 350cc
Royal Enfield Bullet motorcycle in Madras. The first machines were assembled
from components imported from England. Starting in 1957, Enfield of India
acquired the machines necessary to build components in India, and by 1962 all
components were made in India.
5
AIM & OBJECTIVES
The main aim of our project is to increase the productivity of the manufacturing
cell which manufactures L/H and R/H Crankcase covers. Increase of
productivity requires analysation of various process carried out from raw
material to final product. There are various machining processes which are been
carried out on crank case covers like drilling, boring, counter boring, taping,
reaming, milling, etc. Thus if we require the process to be effective, it is
necessary to monitor each and every aspect of the machining process.
Various objectives which can be carried to accomplish the desired:
1. Reduce cycle time.
2. By line balancing.
3. Reducing interruptions
4. Change the sequence of activities
5. Perform activities in parallel
Here in our project we have studied in detail about the production process of
Crankcase covers and in doing so we have carefully studied about the
implementation of the process of line balancing in order to increase productivity
and eliminates wastage .
6
MATERIALS AND METHODS
In order to increase the productivity of crankcase covers, we have studied the
manufacturing of L/H and R/H crankcase i.e, the no. of cnc machines required
in both the cases, tools required, operations undergone by each cnc machine.
We have also studied the programs fed into each cnc machine using G-codes
and M-codes which does the required operation.
No. of machines required in each case:
1. For L/H crankcase covers, there are 5 cnc machines used, whose
operations in detail would be described later.
2. For R/H crankcase covers, the company uses 2 phases of
manufacturing independently. In phase 1, there are 9 machines used
and the operation time for manufacturing each crankcase is also less.
In phase 2, there are 4 machines used and thus operation time is also
more compared to the previous method.
3. Manufacturing of L/H is less compared to that of R/H because of very
less machining, drill holes, taps and counter bores required. Thus
productivity of L/H is more compared to that of R/H. In order to
equalise the production of both the cases, R/H utilizes 2 phase of
manufacturing.
L/H CRANKCASE MANUFACTURING:
There are 5 operations in manufacturing of a L/H cover which are described as
follows:
1. OPERATION 10
2. OPERATION 20
3. OPERATION 30
4. OPERATION 40
5. OPERATION 50
Here we have studied about the tools required, cycle time, and surface
counters and machining undergone during each operation.
OPERATION 10:
Here, the un machined raw material is machined for 2 purposes.
7
The operations undergone here are:
1.Rough milling
2.7 mm drill hole
3.Chamfering
Cycle time: 1minute 50 seconds
OPERATION 20:
Here the operations are followed in contiguous to that of operation 10.
The operations undergone here are:
1. 5.5mm drill hole
2. 6mm reamer
3. 10 mm end mill
Cycle time: 1 minute 56 seconds
OPERATION 30:
The operations undergone here are:
1. 7 mm mounting drill
2. Combination tool drill
3. 20mm reamer
Cycle time: 30 seconds
OPERATION 40:
The operations undergone here are:
1. Milling for rod insertion
2. Lubrication for smoothening of operations
Cycle time: 40 seconds
OPERATION 50:
The operations undergone here are:
1. Hole for clutch insertion
2. Combination tool drill
Cycle time: 50 seeconds
8
INITIAL PRODUCT:
FINAL MACHINED PRODUCT:
9
PROBLEMS:
1. Imperfection of gauges
2. Improper finish
3. Inaccurate dimensions
4. Breakage of material
RECTIFICATIONS:
1) Regular checking of gauges
2) Use of propertool for machining
3) Replace wearer tool with new one
4) Perform additional machining if required
5) Check the material
R/H CRANKCASE MANUFACTURING:
The operations undergone for machining R/H crankcase are:
1. OPERATION10
2. OPERATON20
3. OPERATION30
4. OPERATION40
10
5. PLUG FIXTURE AND LEAK TEST
OPERATION10:
Operations are performed on un machined R/H cover.
The operations undergone here are:
1 .16 mm end mill
2 .6.75 drill combination with 13.75 mm drill
3 .4.62 mm drill
4 .M5 tap
5 .5.7 double hole drill
6 .23.5 oil seal bore
7 .27 rough bore
8. 35 OD turning
9. milling cutter(joint face)
10. 6mm reamer
11. 14 x 7.2 reamer
12. 24 oil seal reamer
Cycle time: 3 minutes 10 seconds
OPERATION20:
The operations performed here are:
1. 40 mm bore facemill
2. 24.5 bore rough
3. Groove insert
4. 25 mm finish reamer
5. 40mm bore
6. Combination tool of 26.5mm and 19.5mm
7. Combination tool of 27mm and 20mm reamer
8. 5.5 mm drill
9. M6 tap
10.27 Backboard
Cycle time: 3minutes 18 seconds
OPERATION30:
The operations performed here are:
1. 17.5mm drill
2. M20 tap
11
3. 37mm stoppage
4. 10.5mm drill
5. M12 tap
6. 22 stopbore
7. 12.75 mm drill
8. M14 tap
9. 24 stopbore
10.6.5 mm drill
11.6.5 mm whole mill
12.4.5 mm step drill
13.4.5 mm long drill
14.7 mm reamer
15.5.5 mm reamer
Cycle time: 1 minute 54 seconds
OPERATION40:
The operations performed here are:
1. 6.5 mm drill
2. 5 mm oil hole
3. End mill
Cycle time: 55 seconds
PLUG FIXTURE AND LEAK TEST:
The operations performed here are:
1. Insertion of plug and its fixing through proper seal
2. Leak test is performed on R/H crankcase to find out the reason of
leakage and rectification of the same.
INITIAL PRODUCT:
12
FINAL PRODUCT:
PROBLEMS:
1. Wear and tear of tool
2. ATC not functioning properly
3. Pallet Change problem
RECTIFICATIONS:
13
1. Regular checking of tool and replacing the tool
2. Propercodeto be fed in ATC system
3. Replacement of old pallet with new one
IMPLEMENTATION OF LINE BALANCING TO INCREASE THE
PRODUCTIVITY:
Line balancing is an effective tool to improve the throughput of assembly line
while reducing non-value-added activities, cycle time. Line balancing is the
problem of assigning operation to workstation along an assembly line, in such a
way that assignment is optimal in some sense. This project mainly focuses on
improving overall efficiency of single model assembly line by reducing the non-
value added activities, cycle time and distribution of work load at each work
station by line balancing. The methodology adopted includes calculation of
cycle time of process, identifying the non –value-added activities, calculating
total work load on station and distribution of work load on each workstation by
line balancing, in order to improve the efficiency of line and increase overall
productivity.
Assembly line balancing is the problem of assigning various tasks to
workstations, while optimizing one or more objectives without violating any
restrictions imposed on the line. ALBP has been an active field of research over
the past decades due to its relevancy to diversified industries such as garment,
footwear and electronics. The assembly line balancing problem has received
considerable attention in the literature, and many studies have been made on
this subject since 1954. The assembly line balancing problem was first
introduced by Bryton in his graduate thesis. In his study, he accepted the
amount of workstations as constant, the workstation times as equal for all
stations and work tasks as moving among the workstations. The first article was
published in 1955 by Salveson. He developed a 0-1 integer programming model
to solve the problem. COMSOAL (Computer
14
Method of Sequencing Operations for Assembly Lines) was first used by Arcus
in 1966 as a solution approach to the assembly line balancing problem.
Helgeson ve Birnie [11] developed the “Ranked Positional Weight Technique”.
In this method, the “Ranked Positional Weight Value” is determined. It is the
sum of a specified operation time and the working times of the other operations
that can’t be assembled without considering the operation finished. While
taking into consideration the cycle time and technological precedence matrix,
the operation having the largest ranged weight is assigned to the first
workstation, and other operations are assigned to workstations in accordance
with their ranked positional weight value. Con figurations of assembly lines for
single and multiple products could be divided by three line types, single-model,
mixed-model and multi-model. Single -model assembles only one product, and
mixed-model assembles multiple products, whereas a multi-model produces a
sequence of batches with intermediate setup operations. A single-model line
balancing problem with real application was solved in this project. ALBP with
various objectives are classified into three types
-I: Minimizes the number of workstations, for a given cycle time.
-II: Minimizes the cycle time, for a given number of workstations.
-III: Maximizes the workload smoothness, for a given number of
workstations.
In type I problems, the ALBP of assigning tasks to workstations is formulated
with the objective of minimizing the number of workstations used to meet a
target cycle time. It can result in low labor costs and reduced space
requirements. Type II problems maximize the production rate of an assembly
line. Since this objective requires a predetermined number of workstations, it
can be seen as the counterpart of the previous one. In general, shop managers
are concerned with the workload equity among all workers. The issue of
workload smoothing in assembly lines allocates tasks among a given number of
workstations, so that the workload is distributed as evenly as possible. This
problem is known as Type III problem. Our project was focused on type-1 line
balancing problem. Relevant data obtained from an apparel industry was used to
formulate the solution. The objective of the project was to balance the cycle
time for various operations and minimization of workstations.
PROBLEM STATEMENTS:
1. Reducing line efficiency.
In flow line production the product moves to one workstation due to time
restriction. Once its get stuck due to accumulation in certain workstation, it
15
exceeds the cycle time in that station. Faster station is limited by slowest
station. Thus, decreasing the rate of productivity.
2. Unbalance workloads
Due to starving, the workers need to wait the products to come.
PROBLEM OBECTIVES
Two objectives are expected in the end of the project:
1. To improve productivity and efficiency of existing layout and new layout
2. To meet unpredictable demand
PROJECT SCOPES
The research will be conducted at manufacturing based company in Kuantan
specifically in electronics company.
1. Software application, WITNESS is used to simulate data.
2. Comparison between existing and new layout.
3. Proposing new layout (3 layout and the best is chosen).
4. Stopwatch is used to take the time
16
FLOW CHART:
Small and Medium Industry
Manually Machining Line
Types of Machining Line
Workstation
Material Handling System
Line Balancing
Simulation
Work Measurement
Efficiency
Productivity
17
CONCLUSION
Thus in this project we have studied about the process of machining of L/H and
R/H crankcase covers. After careful study about the machining process, tools
required and cycle time for each machining process was noted down. The
problems which occurred during the operations were also discussed along with
their rectification methods. Finally, implementation of line balancing was also
proposed which was useful in increasing the productivity by the usage of same
labours and reducing wastage and time required for its completion.
Further improvements in the productivity can be achieved by considering large
amount of order minimum. Proposed layout model has been followed the logic
of modular system (one worker works more than two processeswho is skilled on
all processes and these combination of skilled workers finish their work in piece
flow production) and traditional system (one worker works in one process and
all the workers who may be skilled or not finish their work in bundle flow
production) both together where only modular production system can be
applicable with a series of skilled workers to achieve more productivity. On this
occasion, skilled workers are eligible for the production processes and proper
training and supervision is essential to achieve the optimum improvements on
productivity and efficiency.
18

More Related Content

What's hot

Summer training presentation
Summer training presentationSummer training presentation
Summer training presentationMohit Keshav
 
Gorakhpurmechanicalworkshopsummertrainingreport 141115125812-conversion-gate02
Gorakhpurmechanicalworkshopsummertrainingreport 141115125812-conversion-gate02Gorakhpurmechanicalworkshopsummertrainingreport 141115125812-conversion-gate02
Gorakhpurmechanicalworkshopsummertrainingreport 141115125812-conversion-gate02Hemant Rawat
 
Amreli Steel-Internship Report-Yaseen Raza
Amreli Steel-Internship Report-Yaseen RazaAmreli Steel-Internship Report-Yaseen Raza
Amreli Steel-Internship Report-Yaseen RazaYaseen Raza
 
AMRELI STEELS LTD. INTERNSHIP REPORT
AMRELI STEELS LTD. INTERNSHIP REPORTAMRELI STEELS LTD. INTERNSHIP REPORT
AMRELI STEELS LTD. INTERNSHIP REPORTFakhar Essa
 
Turbo-Finish Technical Bulletin
Turbo-Finish Technical BulletinTurbo-Finish Technical Bulletin
Turbo-Finish Technical BulletinDave Davidson
 
Ppt on Gorakhpur railway station
Ppt on Gorakhpur railway stationPpt on Gorakhpur railway station
Ppt on Gorakhpur railway stationdurgesh pathak
 
Sokhi & Group Profile
Sokhi & Group ProfileSokhi & Group Profile
Sokhi & Group ProfileSunil Garg
 
NBC Training Presentation
NBC Training PresentationNBC Training Presentation
NBC Training PresentationHitesh Sharma
 
Basic Training Centre lalgarh Bikaner Training Report
Basic Training Centre lalgarh Bikaner Training ReportBasic Training Centre lalgarh Bikaner Training Report
Basic Training Centre lalgarh Bikaner Training ReportAMIT RAJ
 
HPSF Super-Finishing
HPSF Super-FinishingHPSF Super-Finishing
HPSF Super-FinishingDave Davidson
 
Summer Training Presentation On HMT Machine Tools Ltd
Summer Training Presentation On HMT Machine Tools LtdSummer Training Presentation On HMT Machine Tools Ltd
Summer Training Presentation On HMT Machine Tools LtdPuneet Parihar
 
VOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITED
VOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITEDVOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITED
VOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITEDSurendra Kumar Dewangan
 
Presentation on HMT Ltd
Presentation on HMT LtdPresentation on HMT Ltd
Presentation on HMT LtdSanju Masaun
 
Tractor Division HMT Pinjore Haryana
Tractor Division HMT Pinjore Haryana Tractor Division HMT Pinjore Haryana
Tractor Division HMT Pinjore Haryana Svabhiman Singh
 
Turbo finish dec 2016
Turbo finish dec 2016Turbo finish dec 2016
Turbo finish dec 2016Dave Davidson
 
Centreless lapping machine
Centreless lapping machineCentreless lapping machine
Centreless lapping machineMamesh
 

What's hot (20)

Summer training presentation
Summer training presentationSummer training presentation
Summer training presentation
 
Gorakhpurmechanicalworkshopsummertrainingreport 141115125812-conversion-gate02
Gorakhpurmechanicalworkshopsummertrainingreport 141115125812-conversion-gate02Gorakhpurmechanicalworkshopsummertrainingreport 141115125812-conversion-gate02
Gorakhpurmechanicalworkshopsummertrainingreport 141115125812-conversion-gate02
 
Amreli Steel-Internship Report-Yaseen Raza
Amreli Steel-Internship Report-Yaseen RazaAmreli Steel-Internship Report-Yaseen Raza
Amreli Steel-Internship Report-Yaseen Raza
 
AMRELI STEELS LTD. INTERNSHIP REPORT
AMRELI STEELS LTD. INTERNSHIP REPORTAMRELI STEELS LTD. INTERNSHIP REPORT
AMRELI STEELS LTD. INTERNSHIP REPORT
 
Turbo-Finish Technical Bulletin
Turbo-Finish Technical BulletinTurbo-Finish Technical Bulletin
Turbo-Finish Technical Bulletin
 
Lapping Machine Process and Application
Lapping Machine Process and ApplicationLapping Machine Process and Application
Lapping Machine Process and Application
 
Ppt on Gorakhpur railway station
Ppt on Gorakhpur railway stationPpt on Gorakhpur railway station
Ppt on Gorakhpur railway station
 
merged_document
merged_documentmerged_document
merged_document
 
Sokhi & Group Profile
Sokhi & Group ProfileSokhi & Group Profile
Sokhi & Group Profile
 
NBC Training Presentation
NBC Training PresentationNBC Training Presentation
NBC Training Presentation
 
Centrifugal Iso-Finishing
Centrifugal Iso-FinishingCentrifugal Iso-Finishing
Centrifugal Iso-Finishing
 
Basic Training Centre lalgarh Bikaner Training Report
Basic Training Centre lalgarh Bikaner Training ReportBasic Training Centre lalgarh Bikaner Training Report
Basic Training Centre lalgarh Bikaner Training Report
 
HPSF Super-Finishing
HPSF Super-FinishingHPSF Super-Finishing
HPSF Super-Finishing
 
Summer Training Presentation On HMT Machine Tools Ltd
Summer Training Presentation On HMT Machine Tools LtdSummer Training Presentation On HMT Machine Tools Ltd
Summer Training Presentation On HMT Machine Tools Ltd
 
VOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITED
VOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITEDVOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITED
VOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITED
 
Presentation on HMT Ltd
Presentation on HMT LtdPresentation on HMT Ltd
Presentation on HMT Ltd
 
Tractor Division HMT Pinjore Haryana
Tractor Division HMT Pinjore Haryana Tractor Division HMT Pinjore Haryana
Tractor Division HMT Pinjore Haryana
 
Turbo finish dec 2016
Turbo finish dec 2016Turbo finish dec 2016
Turbo finish dec 2016
 
Centreless lapping machine
Centreless lapping machineCentreless lapping machine
Centreless lapping machine
 
gorakhpur railway PPT
gorakhpur railway PPTgorakhpur railway PPT
gorakhpur railway PPT
 

Similar to PROJECT

HMT tractor division file
HMT tractor division fileHMT tractor division file
HMT tractor division fileHarpreet Singh
 
BrakesIndia_IntReport_CK_SSN_June2015
BrakesIndia_IntReport_CK_SSN_June2015BrakesIndia_IntReport_CK_SSN_June2015
BrakesIndia_IntReport_CK_SSN_June2015CHANDRA SHEKHAR KUMAR
 
Design and Fabrication of Pneumatic Bar Bending Machine
Design and Fabrication of Pneumatic Bar Bending MachineDesign and Fabrication of Pneumatic Bar Bending Machine
Design and Fabrication of Pneumatic Bar Bending MachineIRJET Journal
 
IRJET- Design and Development of Corn Chaff Peeling Machine
IRJET- Design and Development of Corn Chaff Peeling MachineIRJET- Design and Development of Corn Chaff Peeling Machine
IRJET- Design and Development of Corn Chaff Peeling MachineIRJET Journal
 
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVANIMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVANIRJET Journal
 
Report on Solution for reduction of cycle time in the manufacturing of Al Wheels
Report on Solution for reduction of cycle time in the manufacturing of Al WheelsReport on Solution for reduction of cycle time in the manufacturing of Al Wheels
Report on Solution for reduction of cycle time in the manufacturing of Al WheelsLAVA KUMAR ADDEPALLI
 
Improvement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternImprovement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternIRJET Journal
 
Design and Fabrication of Paper Bailing Machine
Design and Fabrication of Paper Bailing MachineDesign and Fabrication of Paper Bailing Machine
Design and Fabrication of Paper Bailing MachineIRJET Journal
 
Internship report
Internship reportInternship report
Internship reportAsad Ali
 
IRJET- Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...
IRJET-  	  Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...IRJET-  	  Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...
IRJET- Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...IRJET Journal
 
Design & Fabrication of Groundnut Sheller Machine
Design & Fabrication of Groundnut Sheller MachineDesign & Fabrication of Groundnut Sheller Machine
Design & Fabrication of Groundnut Sheller MachineIRJET Journal
 
IRJET- Design and Fabrication of Manual Roller Bending Machine
IRJET-  	  Design and Fabrication of Manual Roller Bending MachineIRJET-  	  Design and Fabrication of Manual Roller Bending Machine
IRJET- Design and Fabrication of Manual Roller Bending MachineIRJET Journal
 
Fabrication of automatic hydraulic bending and bend removing machine
Fabrication of automatic hydraulic bending and bend removing machineFabrication of automatic hydraulic bending and bend removing machine
Fabrication of automatic hydraulic bending and bend removing machineIRJET Journal
 
Abrasive belt grinder capstone report
Abrasive belt grinder   capstone reportAbrasive belt grinder   capstone report
Abrasive belt grinder capstone reportDevenMahajan2
 
Report_Chiller(by Sayan Roy)
Report_Chiller(by Sayan Roy)Report_Chiller(by Sayan Roy)
Report_Chiller(by Sayan Roy)Sayan Roy
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET Journal
 

Similar to PROJECT (20)

HMT tractor division file
HMT tractor division fileHMT tractor division file
HMT tractor division file
 
BrakesIndia_IntReport_CK_SSN_June2015
BrakesIndia_IntReport_CK_SSN_June2015BrakesIndia_IntReport_CK_SSN_June2015
BrakesIndia_IntReport_CK_SSN_June2015
 
Riv2
Riv2Riv2
Riv2
 
Design and Fabrication of Pneumatic Bar Bending Machine
Design and Fabrication of Pneumatic Bar Bending MachineDesign and Fabrication of Pneumatic Bar Bending Machine
Design and Fabrication of Pneumatic Bar Bending Machine
 
IRJET- Design and Development of Corn Chaff Peeling Machine
IRJET- Design and Development of Corn Chaff Peeling MachineIRJET- Design and Development of Corn Chaff Peeling Machine
IRJET- Design and Development of Corn Chaff Peeling Machine
 
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVANIMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
 
Report on Solution for reduction of cycle time in the manufacturing of Al Wheels
Report on Solution for reduction of cycle time in the manufacturing of Al WheelsReport on Solution for reduction of cycle time in the manufacturing of Al Wheels
Report on Solution for reduction of cycle time in the manufacturing of Al Wheels
 
CLUTCH BELL EDITED
CLUTCH BELL EDITEDCLUTCH BELL EDITED
CLUTCH BELL EDITED
 
Improvement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternImprovement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and Pattern
 
Design and Fabrication of Paper Bailing Machine
Design and Fabrication of Paper Bailing MachineDesign and Fabrication of Paper Bailing Machine
Design and Fabrication of Paper Bailing Machine
 
Internship report
Internship reportInternship report
Internship report
 
IRJET- Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...
IRJET-  	  Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...IRJET-  	  Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...
IRJET- Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...
 
Design & Fabrication of Groundnut Sheller Machine
Design & Fabrication of Groundnut Sheller MachineDesign & Fabrication of Groundnut Sheller Machine
Design & Fabrication of Groundnut Sheller Machine
 
IRJET- Design and Fabrication of Manual Roller Bending Machine
IRJET-  	  Design and Fabrication of Manual Roller Bending MachineIRJET-  	  Design and Fabrication of Manual Roller Bending Machine
IRJET- Design and Fabrication of Manual Roller Bending Machine
 
contents
contentscontents
contents
 
Fabrication of automatic hydraulic bending and bend removing machine
Fabrication of automatic hydraulic bending and bend removing machineFabrication of automatic hydraulic bending and bend removing machine
Fabrication of automatic hydraulic bending and bend removing machine
 
Abrasive belt grinder capstone report
Abrasive belt grinder   capstone reportAbrasive belt grinder   capstone report
Abrasive belt grinder capstone report
 
Report_Chiller(by Sayan Roy)
Report_Chiller(by Sayan Roy)Report_Chiller(by Sayan Roy)
Report_Chiller(by Sayan Roy)
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
 
Ijmet 10 02_042
Ijmet 10 02_042Ijmet 10 02_042
Ijmet 10 02_042
 

PROJECT

  • 1. 1 PROJECT ON “INCREASING PRODUCTIVITY OF L/H & R/H CRANKCASE COVER” Under the guidance of: Mr.J. Sathya, Manager, Machine cell, Royal Enfield,Thiruvottiyor, Chennai From 26/11/2015 to 26/12/2015 By: Arun Kumar Sripal Kumar B, SRM University Chennai
  • 2. 2 ACKNOWLEDGEMENT It gives me tremendous pleasure in bringing out this project entitled “ Increasing Productivity of L/H and R/H crankcase covers” taken up during my final year B.Tech degree course. First of all, we would like to thank Mr.J.Sathya, Manager, Machine cell, Royal Enfield, for guiding us in each and every step of our project right from day 1. His guidance and supervision were useful to us in many aspects, which led us successfully complete our project. Next we would like to thank Mr. Ramalingam, Manager, HR, Royal Enfield for giving us permission to carry out this project without any interruptions. His kind gesture and very acceptable nature is to be well appreciated as well. I am thankful to Mr. Duraivelu, dean and Mr. Karthikeyan Head of Dept of Mechanical Engineering , SRM University for granting me permission for this work and the help extended to me during the course of this project. We would also like to thank the Almighty and our parents without whose support, successful completion of this project would have been a difficult task. Last but not the least, we would like to thank each and every staff of Royal Enfield, Thiruvottiyur for their kind cooperation and helping nature.
  • 3. 3 INDEX S.NO TOPICS PAGE NO. 1. ACKNOWLEDGEMENT 02 2. INTRODUCTION 04 3. AIM & OBJECTIVES 05 4. MATERIALS AND METHODS 06 5. L/H CRANKCASE COVERS 06 6. R/H CRANKCASE COVERS 09 7. LINE BALANCING 13 8 CONCLUSION 17
  • 4. 4 INTRODUCTION Royal Enfield was the brand name under which the Enfield Cycle Company manufactured motorcycles, bicycles,lawnmowers and stationary engines. The first Royal Enfield motorcycle was built in 1901; the original British concern was defunct by 1970. The Enfield Cycle Company is responsible for the design and original production of the Royal Enfield Bullet, the longest-lived motorcycle design in history. Like other motorcycle manufacturers such as BSA and IZhMASh, the Enfield Cycle Company began business as a weapons manufacturer, most famous for the Enfield rifle. This legacy is reflected in the company logo, a cannon, and their motto, "Made Like A Gun". In 1955, Enfield Cycle Company partnered with Madras Motors in India in forming Enfield of India, based in Chennai, and started assembling the 350cc Royal Enfield Bullet motorcycle in Madras. The first machines were assembled from components imported from England. Starting in 1957, Enfield of India acquired the machines necessary to build components in India, and by 1962 all components were made in India.
  • 5. 5 AIM & OBJECTIVES The main aim of our project is to increase the productivity of the manufacturing cell which manufactures L/H and R/H Crankcase covers. Increase of productivity requires analysation of various process carried out from raw material to final product. There are various machining processes which are been carried out on crank case covers like drilling, boring, counter boring, taping, reaming, milling, etc. Thus if we require the process to be effective, it is necessary to monitor each and every aspect of the machining process. Various objectives which can be carried to accomplish the desired: 1. Reduce cycle time. 2. By line balancing. 3. Reducing interruptions 4. Change the sequence of activities 5. Perform activities in parallel Here in our project we have studied in detail about the production process of Crankcase covers and in doing so we have carefully studied about the implementation of the process of line balancing in order to increase productivity and eliminates wastage .
  • 6. 6 MATERIALS AND METHODS In order to increase the productivity of crankcase covers, we have studied the manufacturing of L/H and R/H crankcase i.e, the no. of cnc machines required in both the cases, tools required, operations undergone by each cnc machine. We have also studied the programs fed into each cnc machine using G-codes and M-codes which does the required operation. No. of machines required in each case: 1. For L/H crankcase covers, there are 5 cnc machines used, whose operations in detail would be described later. 2. For R/H crankcase covers, the company uses 2 phases of manufacturing independently. In phase 1, there are 9 machines used and the operation time for manufacturing each crankcase is also less. In phase 2, there are 4 machines used and thus operation time is also more compared to the previous method. 3. Manufacturing of L/H is less compared to that of R/H because of very less machining, drill holes, taps and counter bores required. Thus productivity of L/H is more compared to that of R/H. In order to equalise the production of both the cases, R/H utilizes 2 phase of manufacturing. L/H CRANKCASE MANUFACTURING: There are 5 operations in manufacturing of a L/H cover which are described as follows: 1. OPERATION 10 2. OPERATION 20 3. OPERATION 30 4. OPERATION 40 5. OPERATION 50 Here we have studied about the tools required, cycle time, and surface counters and machining undergone during each operation. OPERATION 10: Here, the un machined raw material is machined for 2 purposes.
  • 7. 7 The operations undergone here are: 1.Rough milling 2.7 mm drill hole 3.Chamfering Cycle time: 1minute 50 seconds OPERATION 20: Here the operations are followed in contiguous to that of operation 10. The operations undergone here are: 1. 5.5mm drill hole 2. 6mm reamer 3. 10 mm end mill Cycle time: 1 minute 56 seconds OPERATION 30: The operations undergone here are: 1. 7 mm mounting drill 2. Combination tool drill 3. 20mm reamer Cycle time: 30 seconds OPERATION 40: The operations undergone here are: 1. Milling for rod insertion 2. Lubrication for smoothening of operations Cycle time: 40 seconds OPERATION 50: The operations undergone here are: 1. Hole for clutch insertion 2. Combination tool drill Cycle time: 50 seeconds
  • 9. 9 PROBLEMS: 1. Imperfection of gauges 2. Improper finish 3. Inaccurate dimensions 4. Breakage of material RECTIFICATIONS: 1) Regular checking of gauges 2) Use of propertool for machining 3) Replace wearer tool with new one 4) Perform additional machining if required 5) Check the material R/H CRANKCASE MANUFACTURING: The operations undergone for machining R/H crankcase are: 1. OPERATION10 2. OPERATON20 3. OPERATION30 4. OPERATION40
  • 10. 10 5. PLUG FIXTURE AND LEAK TEST OPERATION10: Operations are performed on un machined R/H cover. The operations undergone here are: 1 .16 mm end mill 2 .6.75 drill combination with 13.75 mm drill 3 .4.62 mm drill 4 .M5 tap 5 .5.7 double hole drill 6 .23.5 oil seal bore 7 .27 rough bore 8. 35 OD turning 9. milling cutter(joint face) 10. 6mm reamer 11. 14 x 7.2 reamer 12. 24 oil seal reamer Cycle time: 3 minutes 10 seconds OPERATION20: The operations performed here are: 1. 40 mm bore facemill 2. 24.5 bore rough 3. Groove insert 4. 25 mm finish reamer 5. 40mm bore 6. Combination tool of 26.5mm and 19.5mm 7. Combination tool of 27mm and 20mm reamer 8. 5.5 mm drill 9. M6 tap 10.27 Backboard Cycle time: 3minutes 18 seconds OPERATION30: The operations performed here are: 1. 17.5mm drill 2. M20 tap
  • 11. 11 3. 37mm stoppage 4. 10.5mm drill 5. M12 tap 6. 22 stopbore 7. 12.75 mm drill 8. M14 tap 9. 24 stopbore 10.6.5 mm drill 11.6.5 mm whole mill 12.4.5 mm step drill 13.4.5 mm long drill 14.7 mm reamer 15.5.5 mm reamer Cycle time: 1 minute 54 seconds OPERATION40: The operations performed here are: 1. 6.5 mm drill 2. 5 mm oil hole 3. End mill Cycle time: 55 seconds PLUG FIXTURE AND LEAK TEST: The operations performed here are: 1. Insertion of plug and its fixing through proper seal 2. Leak test is performed on R/H crankcase to find out the reason of leakage and rectification of the same. INITIAL PRODUCT:
  • 12. 12 FINAL PRODUCT: PROBLEMS: 1. Wear and tear of tool 2. ATC not functioning properly 3. Pallet Change problem RECTIFICATIONS:
  • 13. 13 1. Regular checking of tool and replacing the tool 2. Propercodeto be fed in ATC system 3. Replacement of old pallet with new one IMPLEMENTATION OF LINE BALANCING TO INCREASE THE PRODUCTIVITY: Line balancing is an effective tool to improve the throughput of assembly line while reducing non-value-added activities, cycle time. Line balancing is the problem of assigning operation to workstation along an assembly line, in such a way that assignment is optimal in some sense. This project mainly focuses on improving overall efficiency of single model assembly line by reducing the non- value added activities, cycle time and distribution of work load at each work station by line balancing. The methodology adopted includes calculation of cycle time of process, identifying the non –value-added activities, calculating total work load on station and distribution of work load on each workstation by line balancing, in order to improve the efficiency of line and increase overall productivity. Assembly line balancing is the problem of assigning various tasks to workstations, while optimizing one or more objectives without violating any restrictions imposed on the line. ALBP has been an active field of research over the past decades due to its relevancy to diversified industries such as garment, footwear and electronics. The assembly line balancing problem has received considerable attention in the literature, and many studies have been made on this subject since 1954. The assembly line balancing problem was first introduced by Bryton in his graduate thesis. In his study, he accepted the amount of workstations as constant, the workstation times as equal for all stations and work tasks as moving among the workstations. The first article was published in 1955 by Salveson. He developed a 0-1 integer programming model to solve the problem. COMSOAL (Computer
  • 14. 14 Method of Sequencing Operations for Assembly Lines) was first used by Arcus in 1966 as a solution approach to the assembly line balancing problem. Helgeson ve Birnie [11] developed the “Ranked Positional Weight Technique”. In this method, the “Ranked Positional Weight Value” is determined. It is the sum of a specified operation time and the working times of the other operations that can’t be assembled without considering the operation finished. While taking into consideration the cycle time and technological precedence matrix, the operation having the largest ranged weight is assigned to the first workstation, and other operations are assigned to workstations in accordance with their ranked positional weight value. Con figurations of assembly lines for single and multiple products could be divided by three line types, single-model, mixed-model and multi-model. Single -model assembles only one product, and mixed-model assembles multiple products, whereas a multi-model produces a sequence of batches with intermediate setup operations. A single-model line balancing problem with real application was solved in this project. ALBP with various objectives are classified into three types -I: Minimizes the number of workstations, for a given cycle time. -II: Minimizes the cycle time, for a given number of workstations. -III: Maximizes the workload smoothness, for a given number of workstations. In type I problems, the ALBP of assigning tasks to workstations is formulated with the objective of minimizing the number of workstations used to meet a target cycle time. It can result in low labor costs and reduced space requirements. Type II problems maximize the production rate of an assembly line. Since this objective requires a predetermined number of workstations, it can be seen as the counterpart of the previous one. In general, shop managers are concerned with the workload equity among all workers. The issue of workload smoothing in assembly lines allocates tasks among a given number of workstations, so that the workload is distributed as evenly as possible. This problem is known as Type III problem. Our project was focused on type-1 line balancing problem. Relevant data obtained from an apparel industry was used to formulate the solution. The objective of the project was to balance the cycle time for various operations and minimization of workstations. PROBLEM STATEMENTS: 1. Reducing line efficiency. In flow line production the product moves to one workstation due to time restriction. Once its get stuck due to accumulation in certain workstation, it
  • 15. 15 exceeds the cycle time in that station. Faster station is limited by slowest station. Thus, decreasing the rate of productivity. 2. Unbalance workloads Due to starving, the workers need to wait the products to come. PROBLEM OBECTIVES Two objectives are expected in the end of the project: 1. To improve productivity and efficiency of existing layout and new layout 2. To meet unpredictable demand PROJECT SCOPES The research will be conducted at manufacturing based company in Kuantan specifically in electronics company. 1. Software application, WITNESS is used to simulate data. 2. Comparison between existing and new layout. 3. Proposing new layout (3 layout and the best is chosen). 4. Stopwatch is used to take the time
  • 16. 16 FLOW CHART: Small and Medium Industry Manually Machining Line Types of Machining Line Workstation Material Handling System Line Balancing Simulation Work Measurement Efficiency Productivity
  • 17. 17 CONCLUSION Thus in this project we have studied about the process of machining of L/H and R/H crankcase covers. After careful study about the machining process, tools required and cycle time for each machining process was noted down. The problems which occurred during the operations were also discussed along with their rectification methods. Finally, implementation of line balancing was also proposed which was useful in increasing the productivity by the usage of same labours and reducing wastage and time required for its completion. Further improvements in the productivity can be achieved by considering large amount of order minimum. Proposed layout model has been followed the logic of modular system (one worker works more than two processeswho is skilled on all processes and these combination of skilled workers finish their work in piece flow production) and traditional system (one worker works in one process and all the workers who may be skilled or not finish their work in bundle flow production) both together where only modular production system can be applicable with a series of skilled workers to achieve more productivity. On this occasion, skilled workers are eligible for the production processes and proper training and supervision is essential to achieve the optimum improvements on productivity and efficiency.
  • 18. 18