SlideShare a Scribd company logo
ID WBS Task Name Duration Start Finish Predecessors
0 0 Transportation of
Men's Brazil Football
253 days Mon
15/10/12
Wed
02/10/13
1 1 Managing of the
Entire Project
253 days Mon
15/10/12
Wed
02/10/13
2 2 Project Management 60 days Mon 15/10/12Fri 04/01/13
3 2.1 Stakeholder List 25 days Mon 15/10/12Fri 16/11/12
4 2.1.1 Brainstorm
session with
10 days
5 2.1.2 T-Map Process 10 days
6 2.1.3 Finalized
stakeholder list
5 days
7 2.2 Stakeholder Meetings 30 days Mon 15/10/12Fri 23/11/12
8 2.2.1 Co-ordinate and
Send
5 days
9 2.2.2 Organised
Stakeholder
20 days
10 2.3 Status Reports 5 days
11 3 Mode of Transport 63 days Mon 15/10/12Wed 09/01/13
12 3.1 Meetings With
London Transit
20 days Mon
15/10/12
Fri 09/11/12
13 3.1.1 Disscuss
Stakeholder
5 days
14 3.1.2 Obtain
permission for
5 days
15 3.1.3 Rules and
Regulations
Learned and
10 days
16 3.2 Plan HR Team 25 days Mon 15/10/12Fri 16/11/12
17 3.2.1 Hire Bus Drivers Plan10 days
18 3.2.2 Hire Mechanics Plan5 days
19 3.2.3 Hire Custodians Plan5 days
20 3.2.4 Discover Provided
Venue Servies Plan
5 days Mon
15/10/12
Fri 19/10/12
21 3.3 Meet for Bus Service
Contract
18 days Mon
15/10/12
Wed
07/11/12
22 3.3.1 Plan Negotiation
Meetings
17 days
23 3.3.2 Finalize and Sign
Bus Service
1 day Mon
15/10/12
Mon
15/10/12
24 4 Departure Times 35 days Mon 15/10/12Fri 30/11/12
25 4.1 Information
Gathering from
20 days Mon
15/10/12
Fri 09/11/12
26 4.1.1 Meetings with
Locations Officer
5 days
27 4.1.2 Discuss Plans and
Provided Services
15 days Mon
15/10/12
Fri 02/11/12
28 4.2 Departure
Arrangement
15 days Mon
15/10/12
Fri 02/11/12
29 4.2.1 Plan an ID system 5 days Mon 15/10/12Fri 19/10/12
30 4.2.2 Plan a Meeting
Schedual at
Departure and
10 days Mon
15/10/12
Fri 26/10/12
31 4.3 Bus Pick Up
Coordinated with
Game End
5 days
32 4.4 Luggage
Accomodation
5 days
33 4.5 Finalized Plans 5 days Mon 15/10/12Fri 19/10/12
34 5 Arrival Times 60 days Mon 15/10/12Fri 04/01/13
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
14 Oct '12 21 Oct '12 28 Oct '12 04 Nov '12 11 Nov '12 18 Nov '12 25 Nov '12 02 Dec '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 1
Project: Transportation of Men's B
Date: Thu 14/04/16
ID WBS Task Name Duration Start Finish Predecessors
35 5.1 Information from
Locations officer
20 days Mon
15/10/12
Fri 09/11/12
36 5.1.1 Discuss Planed
Locations of
15 days
37 5.1.2 Discuss Drop off
and Pick up
4 days
38 5.1.3 Sign Agreement 1 day
39 5.2 Information from
Brazil Team Manager
20 days Mon
15/10/12
Fri 09/11/12
40 5.2.1 Discuss Athletes
practice schedule
10 days
41 5.2.2 Plan a Time
schedule that works
5 days
42 5.2.3 Finalize Plan for
Team Needs
5 days
43 5.3 Meeting
Arrangements from
5 days
44 5.4 Game Scheduals
Co-ordinated
5 days
45 5.5 Luggage accomidations5 days
46 5.6 Finalized Plans 5 days
47 6 Bus Routes 35 days Mon 15/10/12Fri 30/11/12
48 6.1 Gather Local Road
System
20 days Mon
15/10/12
Fri 09/11/12
49 6.1.1 Discuss Any
Issues or Risks
with London
Traffice Police
10 days
50 6.1.2 Disscus with
London Transit Past
Bus Routes used for
Locations
10 days
51 6.2 Make Draft Routes 5 days
52 6.3 Finalize Efficient
Schedual
10 days
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
14 Oct '12 21 Oct '12 28 Oct '12 04 Nov '12 11 Nov '12 18 Nov '12 25 Nov '12 02 Dec '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 2
Project: Transportation of Men's B
Date: Thu 14/04/16
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
09 Dec '12 16 Dec '12 23 Dec '12 30 Dec '12 06 Jan '13 13 Jan '13 20 Jan '13 27 Jan '13 03 Feb '13 10 Feb '13 17 Feb '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 3
Project: Transportation of Men's B
Date: Thu 14/04/16
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
09 Dec '12 16 Dec '12 23 Dec '12 30 Dec '12 06 Jan '13 13 Jan '13 20 Jan '13 27 Jan '13 03 Feb '13 10 Feb '13 17 Feb '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 4
Project: Transportation of Men's B
Date: Thu 14/04/16
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
17 Feb '13 24 Feb '13 03 Mar '13 10 Mar '13 17 Mar '13 24 Mar '13 31 Mar '13 07 Apr '13 14 Apr '13 21 Apr '13 28 Apr '13 05 May
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 5
Project: Transportation of Men's B
Date: Thu 14/04/16
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
17 Feb '13 24 Feb '13 03 Mar '13 10 Mar '13 17 Mar '13 24 Mar '13 31 Mar '13 07 Apr '13 14 Apr '13 21 Apr '13 28 Apr '13 05 May
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 6
Project: Transportation of Men's B
Date: Thu 14/04/16
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
05 May '13 12 May '13 19 May '13 26 May '13 02 Jun '13 09 Jun '13 16 Jun '13 23 Jun '13 30 Jun '13 07 Jul '13 14 Jul '13 21
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 7
Project: Transportation of Men's B
Date: Thu 14/04/16
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
05 May '13 12 May '13 19 May '13 26 May '13 02 Jun '13 09 Jun '13 16 Jun '13 23 Jun '13 30 Jun '13 07 Jul '13 14 Jul '13 21
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 8
Project: Transportation of Men's B
Date: Thu 14/04/16
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
21 Jul '13 28 Jul '13 04 Aug '13 11 Aug '13 18 Aug '13 25 Aug '13 01 Sep '13 08 Sep '13 15 Sep '13 22 Sep '13 29 Sep '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 9
Project: Transportation of Men's B
Date: Thu 14/04/16
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
21 Jul '13 28 Jul '13 04 Aug '13 11 Aug '13 18 Aug '13 25 Aug '13 01 Sep '13 08 Sep '13 15 Sep '13 22 Sep '13 29 Sep '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 10
Project: Transportation of Men's B
Date: Thu 14/04/16

More Related Content

More from Adam Edwards

Spaces of Age, Snowbirds and the Gerontology
Spaces of Age, Snowbirds and the GerontologySpaces of Age, Snowbirds and the Gerontology
Spaces of Age, Snowbirds and the Gerontology
Adam Edwards
 
Project Closure Report
Project Closure ReportProject Closure Report
Project Closure Report
Adam Edwards
 
Families and Households Research Paper
Families and Households Research PaperFamilies and Households Research Paper
Families and Households Research Paper
Adam Edwards
 
Edwards Moral Philosophy Essay _2
Edwards Moral Philosophy Essay _2Edwards Moral Philosophy Essay _2
Edwards Moral Philosophy Essay _2
Adam Edwards
 
Edwards_Assignment 4_Arbitration
Edwards_Assignment 4_ArbitrationEdwards_Assignment 4_Arbitration
Edwards_Assignment 4_Arbitration
Adam Edwards
 
Classical Sociology Essay #1. (final draft)
Classical Sociology Essay #1. (final draft)Classical Sociology Essay #1. (final draft)
Classical Sociology Essay #1. (final draft)
Adam Edwards
 
Edwards_Adam_2G_Inventory
Edwards_Adam_2G_InventoryEdwards_Adam_2G_Inventory
Edwards_Adam_2G_Inventory
Adam Edwards
 
Edwards_Applied_Project
Edwards_Applied_ProjectEdwards_Applied_Project
Edwards_Applied_Project
Adam Edwards
 
C16-E01-CofELtrhd
C16-E01-CofELtrhdC16-E01-CofELtrhd
C16-E01-CofELtrhd
Adam Edwards
 
C15-E03-CIRevs
C15-E03-CIRevsC15-E03-CIRevs
C15-E03-CIRevs
Adam Edwards
 
C12-E03-Hawaii
C12-E03-HawaiiC12-E03-Hawaii
C12-E03-Hawaii
Adam Edwards
 
Edwards_Adam_3G_Expenses
Edwards_Adam_3G_ExpensesEdwards_Adam_3G_Expenses
Edwards_Adam_3G_Expenses
Adam Edwards
 
Drum Training Presentation
Drum Training PresentationDrum Training Presentation
Drum Training Presentation
Adam Edwards
 
CSR Presentation
CSR PresentationCSR Presentation
CSR Presentation
Adam Edwards
 

More from Adam Edwards (14)

Spaces of Age, Snowbirds and the Gerontology
Spaces of Age, Snowbirds and the GerontologySpaces of Age, Snowbirds and the Gerontology
Spaces of Age, Snowbirds and the Gerontology
 
Project Closure Report
Project Closure ReportProject Closure Report
Project Closure Report
 
Families and Households Research Paper
Families and Households Research PaperFamilies and Households Research Paper
Families and Households Research Paper
 
Edwards Moral Philosophy Essay _2
Edwards Moral Philosophy Essay _2Edwards Moral Philosophy Essay _2
Edwards Moral Philosophy Essay _2
 
Edwards_Assignment 4_Arbitration
Edwards_Assignment 4_ArbitrationEdwards_Assignment 4_Arbitration
Edwards_Assignment 4_Arbitration
 
Classical Sociology Essay #1. (final draft)
Classical Sociology Essay #1. (final draft)Classical Sociology Essay #1. (final draft)
Classical Sociology Essay #1. (final draft)
 
Edwards_Adam_2G_Inventory
Edwards_Adam_2G_InventoryEdwards_Adam_2G_Inventory
Edwards_Adam_2G_Inventory
 
Edwards_Applied_Project
Edwards_Applied_ProjectEdwards_Applied_Project
Edwards_Applied_Project
 
C16-E01-CofELtrhd
C16-E01-CofELtrhdC16-E01-CofELtrhd
C16-E01-CofELtrhd
 
C15-E03-CIRevs
C15-E03-CIRevsC15-E03-CIRevs
C15-E03-CIRevs
 
C12-E03-Hawaii
C12-E03-HawaiiC12-E03-Hawaii
C12-E03-Hawaii
 
Edwards_Adam_3G_Expenses
Edwards_Adam_3G_ExpensesEdwards_Adam_3G_Expenses
Edwards_Adam_3G_Expenses
 
Drum Training Presentation
Drum Training PresentationDrum Training Presentation
Drum Training Presentation
 
CSR Presentation
CSR PresentationCSR Presentation
CSR Presentation
 

WBS Olympic Simulation

  • 1. ID WBS Task Name Duration Start Finish Predecessors 0 0 Transportation of Men's Brazil Football 253 days Mon 15/10/12 Wed 02/10/13 1 1 Managing of the Entire Project 253 days Mon 15/10/12 Wed 02/10/13 2 2 Project Management 60 days Mon 15/10/12Fri 04/01/13 3 2.1 Stakeholder List 25 days Mon 15/10/12Fri 16/11/12 4 2.1.1 Brainstorm session with 10 days 5 2.1.2 T-Map Process 10 days 6 2.1.3 Finalized stakeholder list 5 days 7 2.2 Stakeholder Meetings 30 days Mon 15/10/12Fri 23/11/12 8 2.2.1 Co-ordinate and Send 5 days 9 2.2.2 Organised Stakeholder 20 days 10 2.3 Status Reports 5 days 11 3 Mode of Transport 63 days Mon 15/10/12Wed 09/01/13 12 3.1 Meetings With London Transit 20 days Mon 15/10/12 Fri 09/11/12 13 3.1.1 Disscuss Stakeholder 5 days 14 3.1.2 Obtain permission for 5 days 15 3.1.3 Rules and Regulations Learned and 10 days 16 3.2 Plan HR Team 25 days Mon 15/10/12Fri 16/11/12 17 3.2.1 Hire Bus Drivers Plan10 days 18 3.2.2 Hire Mechanics Plan5 days 19 3.2.3 Hire Custodians Plan5 days 20 3.2.4 Discover Provided Venue Servies Plan 5 days Mon 15/10/12 Fri 19/10/12 21 3.3 Meet for Bus Service Contract 18 days Mon 15/10/12 Wed 07/11/12 22 3.3.1 Plan Negotiation Meetings 17 days 23 3.3.2 Finalize and Sign Bus Service 1 day Mon 15/10/12 Mon 15/10/12 24 4 Departure Times 35 days Mon 15/10/12Fri 30/11/12 25 4.1 Information Gathering from 20 days Mon 15/10/12 Fri 09/11/12 26 4.1.1 Meetings with Locations Officer 5 days 27 4.1.2 Discuss Plans and Provided Services 15 days Mon 15/10/12 Fri 02/11/12 28 4.2 Departure Arrangement 15 days Mon 15/10/12 Fri 02/11/12 29 4.2.1 Plan an ID system 5 days Mon 15/10/12Fri 19/10/12 30 4.2.2 Plan a Meeting Schedual at Departure and 10 days Mon 15/10/12 Fri 26/10/12 31 4.3 Bus Pick Up Coordinated with Game End 5 days 32 4.4 Luggage Accomodation 5 days 33 4.5 Finalized Plans 5 days Mon 15/10/12Fri 19/10/12 34 5 Arrival Times 60 days Mon 15/10/12Fri 04/01/13 S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W 14 Oct '12 21 Oct '12 28 Oct '12 04 Nov '12 11 Nov '12 18 Nov '12 25 Nov '12 02 Dec '12 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Manual Progress Page 1 Project: Transportation of Men's B Date: Thu 14/04/16
  • 2. ID WBS Task Name Duration Start Finish Predecessors 35 5.1 Information from Locations officer 20 days Mon 15/10/12 Fri 09/11/12 36 5.1.1 Discuss Planed Locations of 15 days 37 5.1.2 Discuss Drop off and Pick up 4 days 38 5.1.3 Sign Agreement 1 day 39 5.2 Information from Brazil Team Manager 20 days Mon 15/10/12 Fri 09/11/12 40 5.2.1 Discuss Athletes practice schedule 10 days 41 5.2.2 Plan a Time schedule that works 5 days 42 5.2.3 Finalize Plan for Team Needs 5 days 43 5.3 Meeting Arrangements from 5 days 44 5.4 Game Scheduals Co-ordinated 5 days 45 5.5 Luggage accomidations5 days 46 5.6 Finalized Plans 5 days 47 6 Bus Routes 35 days Mon 15/10/12Fri 30/11/12 48 6.1 Gather Local Road System 20 days Mon 15/10/12 Fri 09/11/12 49 6.1.1 Discuss Any Issues or Risks with London Traffice Police 10 days 50 6.1.2 Disscus with London Transit Past Bus Routes used for Locations 10 days 51 6.2 Make Draft Routes 5 days 52 6.3 Finalize Efficient Schedual 10 days S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W 14 Oct '12 21 Oct '12 28 Oct '12 04 Nov '12 11 Nov '12 18 Nov '12 25 Nov '12 02 Dec '12 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Manual Progress Page 2 Project: Transportation of Men's B Date: Thu 14/04/16
  • 3. W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T 09 Dec '12 16 Dec '12 23 Dec '12 30 Dec '12 06 Jan '13 13 Jan '13 20 Jan '13 27 Jan '13 03 Feb '13 10 Feb '13 17 Feb '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Manual Progress Page 3 Project: Transportation of Men's B Date: Thu 14/04/16
  • 4. W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T 09 Dec '12 16 Dec '12 23 Dec '12 30 Dec '12 06 Jan '13 13 Jan '13 20 Jan '13 27 Jan '13 03 Feb '13 10 Feb '13 17 Feb '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Manual Progress Page 4 Project: Transportation of Men's B Date: Thu 14/04/16
  • 5. T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M 17 Feb '13 24 Feb '13 03 Mar '13 10 Mar '13 17 Mar '13 24 Mar '13 31 Mar '13 07 Apr '13 14 Apr '13 21 Apr '13 28 Apr '13 05 May Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Manual Progress Page 5 Project: Transportation of Men's B Date: Thu 14/04/16
  • 6. T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M 17 Feb '13 24 Feb '13 03 Mar '13 10 Mar '13 17 Mar '13 24 Mar '13 31 Mar '13 07 Apr '13 14 Apr '13 21 Apr '13 28 Apr '13 05 May Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Manual Progress Page 6 Project: Transportation of Men's B Date: Thu 14/04/16
  • 7. M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S 05 May '13 12 May '13 19 May '13 26 May '13 02 Jun '13 09 Jun '13 16 Jun '13 23 Jun '13 30 Jun '13 07 Jul '13 14 Jul '13 21 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Manual Progress Page 7 Project: Transportation of Men's B Date: Thu 14/04/16
  • 8. M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S 05 May '13 12 May '13 19 May '13 26 May '13 02 Jun '13 09 Jun '13 16 Jun '13 23 Jun '13 30 Jun '13 07 Jul '13 14 Jul '13 21 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Manual Progress Page 8 Project: Transportation of Men's B Date: Thu 14/04/16
  • 9. S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S 21 Jul '13 28 Jul '13 04 Aug '13 11 Aug '13 18 Aug '13 25 Aug '13 01 Sep '13 08 Sep '13 15 Sep '13 22 Sep '13 29 Sep '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Manual Progress Page 9 Project: Transportation of Men's B Date: Thu 14/04/16
  • 10. S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S 21 Jul '13 28 Jul '13 04 Aug '13 11 Aug '13 18 Aug '13 25 Aug '13 01 Sep '13 08 Sep '13 15 Sep '13 22 Sep '13 29 Sep '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Manual Progress Page 10 Project: Transportation of Men's B Date: Thu 14/04/16