I am reporting to you the progress that my group and I have made over the past three weeks.
We tried to start modeling the watershed with WinTR 55
Looked for other modeling programs and found SWMM
Will use SWMM to model watershed
Learning how to work with GIS to generate map
Used WebSoils to determine soil type in the area
We have finally received all of the information from Tony Puttnam. We will be using this information to
model using a program called SWMM. We were not able to use WinTR 55 because it only allowed ten subareas,
whereas the information that was given to us used 19 subareas. We are staying intouch with Alex about the program
GIS.
We have collected rainwater samples to run COD and TSS test on. During his presentation Scott
Banks stated that turbidity has been an issue. So in order to address this issue in our design we need to run a
COD and TSS test.
Please let me know if there are any other test that we need to run. I will continue to keep you updated on our
progress.