1
TEMPORARY
STRUCTURES
(SCAFFOLD SAFETY)
2
All employees shall
be protected from
falls of six feet or
more by the use of
an approved fall
protection system
BASIC SAFETY RULE
3
What are approved Fall Protection Systems?
 Fall Arrest Systems
• full body harness/ lanyard/ lifeline
 Ladders
 Scaffold System
• Structural system
• Guardrail system
• Planking
APPROVED FALL PROTECTION SYSTEMS
4
 Must be supervised by a competent person
 Sound footing or anchorage
 Don’t use unstable objects as supports
 Use guardrails
 Use screen
 Use full planking
GENERAL REQMTS FOR SCAFFOLD SAFETY
5
GENERAL REQMTS FOR SCAFFOLD SAFETY
6
 Legs should be plumb
 Eliminate slippery conditions
 Post safety rules
 Scaffold shall be tied and fully braced
 Shall be capable of supporting 4x the design load
 Plan or drawing approved by Structural Engineer
GENERAL REQMTS FOR SCAFFOLD SAFETY
7
 Avoid power lines
 Approval for multiple usage
 Ladders should have landing
 Use outrigger or outboard safety
support
 Provide independent safety lines
GENERAL REQMTS FOR SCAFFOLD SAFETY
8
 Must be supervised
 Provide access ladder or equivalent
 Work during severe weather condition is
prohibited
 Extend and overlap planks
 Do not ride on rolling scaffold
PERSONNEL REQUIREMENTS
9
PERSONNEL REQUIREMENTS
 Secure all materials and
equipment
 Apply brakes at all times
 Should be inspected on a daily
basis
10
 Personnel shall have a secured safety
lanyard
 Provide safe means of ingress/egress
 Area should be fully barricaded
Temporary work platforms/Walkways
(Scaffolds and boards)
INTERSTITIAL WORK
11
MISSING PLANKS
MISSING PLANKS
12
MISSING GUARDRAILS
MISSING GUARDRAILS
13
IMPROPER ACCESS
IMPROPER ACCESS
14
STUPID SET-UPS
STUPID SET-UPS
 The plank is
supported by an
extension
ladder, a closed
step ladder and
a straight
ladder.
 The guardrails
are not
acceptable.
 There is no
stability
 Scaffold are
resting on CHB,
which are
unstable
15
SCAFFOLD REQUIREMENTS
SCAFFOLD REQUIREMENTS
 Be on a firm foundation with base plates
 Be plumb, square and adequately braced
 Have a fully planked work deck
 Have guardrails over 10 feet
 Be tied in over 4 Vert./1 Horiz. high
 Have an adequate means of access
SCAFFOLD CAPACITY
SCAFFOLD CAPACITY
 Must be able support
its own weight and 4
times the maximum
intended load.
 Scaffolds must be
designed by a
qualified person.
 They must and built
and loaded within
design. TIP! Scaffolds can be overloaded by
removing the braces – which cause the
weight to be unevenly supported by fewer
members. Do not remove supports, even
if they’re in the way.
17
COMPETENT PERSONS
COMPETENT PERSONS
 All scaffolds must be
erected, moved,
dismantled or altered
only under the
supervision of a
competent person
18
SCAFFOLD FOUNDATIONS
SCAFFOLD FOUNDATIONS
 Scaffolds must have
base plates, even when
setting on a concrete
floor.
 Also, the lack of a base
plate could damage the
scaffold leg.
19
 Scaffold legs must be
set on base plates and
adequate mudsills.
 There is no base plate
and the scrap plywood
is not adequate.
 The scaffold frame
could penetrate the
plywood.
SCAFFOLD FOUNDATIONS
SCAFFOLD FOUNDATIONS
20
NEVER ON MASONRY!
NEVER ON MASONRY!
 Scaffolds should never
be set on bricks,
masonry blocks, etc.
 These are not structural
elements and could
crush under the scaffold
load.
21
GOOD FOUNDATIONS
GOOD FOUNDATIONS
Mason’s Adjustable
Hydro-mobile
Frames
22
SAFETY & SCAFFOLD CONSTRUCTION
SAFETY & SCAFFOLD CONSTRUCTION
 It all starts in the first bay.
 If it is set plumb and
square, the rest will follow.
Phase 3 – Construct Access
Phase 2 – Construct Structure
Phase 1 – Construct Base
23
Phase 4 – Install Fall Protection Phase 5 – Install Platform Phase 6 – Ensure Stability
SAFETY & SCAFFOLD CONSTRUCTION
SAFETY & SCAFFOLD CONSTRUCTION
24
MOBILE
MOBILE
SCAFFOLDS
SCAFFOLDS
Diagonal
Brace
Full Guardrails
All Frame
Bracing
Fully Planked
Deck
Proper
Access
Stack Pins
Locked
Level
Surface
Total Height Less than 4 times Base
TRAINING REQUIREMENTS
TRAINING REQUIREMENTS
 Workers must be trained in
• Nature of electrical, fall, and falling object hazards
• Correct procedures for protection of above
• Proper use of the scaffold
• Load capacities of scaffolds
• Requirements of OSHS
 Retraining as necessary to restore proficiency
26
PUMP JACK
PUMP JACK
SCAFFOLDS
SCAFFOLDS
 Must have an 18”
platform.
 Must have guardrails or
other fall protection
BAD!
GOOD!
27
NOTHING IS SO URGENT THAT IT
CAN NOT BE DONE SAFELY !!!
IF IT CAN’T BE DONE SAFELY,
DON’T DO IT AT ALL
WORKING FROM ELEVATED SURFACES
WORKING FROM ELEVATED SURFACES

Temporary Structures training awareness.

  • 1.
  • 2.
    2 All employees shall beprotected from falls of six feet or more by the use of an approved fall protection system BASIC SAFETY RULE
  • 3.
    3 What are approvedFall Protection Systems?  Fall Arrest Systems • full body harness/ lanyard/ lifeline  Ladders  Scaffold System • Structural system • Guardrail system • Planking APPROVED FALL PROTECTION SYSTEMS
  • 4.
    4  Must besupervised by a competent person  Sound footing or anchorage  Don’t use unstable objects as supports  Use guardrails  Use screen  Use full planking GENERAL REQMTS FOR SCAFFOLD SAFETY
  • 5.
    5 GENERAL REQMTS FORSCAFFOLD SAFETY
  • 6.
    6  Legs shouldbe plumb  Eliminate slippery conditions  Post safety rules  Scaffold shall be tied and fully braced  Shall be capable of supporting 4x the design load  Plan or drawing approved by Structural Engineer GENERAL REQMTS FOR SCAFFOLD SAFETY
  • 7.
    7  Avoid powerlines  Approval for multiple usage  Ladders should have landing  Use outrigger or outboard safety support  Provide independent safety lines GENERAL REQMTS FOR SCAFFOLD SAFETY
  • 8.
    8  Must besupervised  Provide access ladder or equivalent  Work during severe weather condition is prohibited  Extend and overlap planks  Do not ride on rolling scaffold PERSONNEL REQUIREMENTS
  • 9.
    9 PERSONNEL REQUIREMENTS  Secureall materials and equipment  Apply brakes at all times  Should be inspected on a daily basis
  • 10.
    10  Personnel shallhave a secured safety lanyard  Provide safe means of ingress/egress  Area should be fully barricaded Temporary work platforms/Walkways (Scaffolds and boards) INTERSTITIAL WORK
  • 11.
  • 12.
  • 13.
  • 14.
    14 STUPID SET-UPS STUPID SET-UPS The plank is supported by an extension ladder, a closed step ladder and a straight ladder.  The guardrails are not acceptable.  There is no stability  Scaffold are resting on CHB, which are unstable
  • 15.
    15 SCAFFOLD REQUIREMENTS SCAFFOLD REQUIREMENTS Be on a firm foundation with base plates  Be plumb, square and adequately braced  Have a fully planked work deck  Have guardrails over 10 feet  Be tied in over 4 Vert./1 Horiz. high  Have an adequate means of access
  • 16.
    SCAFFOLD CAPACITY SCAFFOLD CAPACITY Must be able support its own weight and 4 times the maximum intended load.  Scaffolds must be designed by a qualified person.  They must and built and loaded within design. TIP! Scaffolds can be overloaded by removing the braces – which cause the weight to be unevenly supported by fewer members. Do not remove supports, even if they’re in the way.
  • 17.
    17 COMPETENT PERSONS COMPETENT PERSONS All scaffolds must be erected, moved, dismantled or altered only under the supervision of a competent person
  • 18.
    18 SCAFFOLD FOUNDATIONS SCAFFOLD FOUNDATIONS Scaffolds must have base plates, even when setting on a concrete floor.  Also, the lack of a base plate could damage the scaffold leg.
  • 19.
    19  Scaffold legsmust be set on base plates and adequate mudsills.  There is no base plate and the scrap plywood is not adequate.  The scaffold frame could penetrate the plywood. SCAFFOLD FOUNDATIONS SCAFFOLD FOUNDATIONS
  • 20.
    20 NEVER ON MASONRY! NEVERON MASONRY!  Scaffolds should never be set on bricks, masonry blocks, etc.  These are not structural elements and could crush under the scaffold load.
  • 21.
    21 GOOD FOUNDATIONS GOOD FOUNDATIONS Mason’sAdjustable Hydro-mobile Frames
  • 22.
    22 SAFETY & SCAFFOLDCONSTRUCTION SAFETY & SCAFFOLD CONSTRUCTION  It all starts in the first bay.  If it is set plumb and square, the rest will follow. Phase 3 – Construct Access Phase 2 – Construct Structure Phase 1 – Construct Base
  • 23.
    23 Phase 4 –Install Fall Protection Phase 5 – Install Platform Phase 6 – Ensure Stability SAFETY & SCAFFOLD CONSTRUCTION SAFETY & SCAFFOLD CONSTRUCTION
  • 24.
    24 MOBILE MOBILE SCAFFOLDS SCAFFOLDS Diagonal Brace Full Guardrails All Frame Bracing FullyPlanked Deck Proper Access Stack Pins Locked Level Surface Total Height Less than 4 times Base
  • 25.
    TRAINING REQUIREMENTS TRAINING REQUIREMENTS Workers must be trained in • Nature of electrical, fall, and falling object hazards • Correct procedures for protection of above • Proper use of the scaffold • Load capacities of scaffolds • Requirements of OSHS  Retraining as necessary to restore proficiency
  • 26.
    26 PUMP JACK PUMP JACK SCAFFOLDS SCAFFOLDS Must have an 18” platform.  Must have guardrails or other fall protection BAD! GOOD!
  • 27.
    27 NOTHING IS SOURGENT THAT IT CAN NOT BE DONE SAFELY !!! IF IT CAN’T BE DONE SAFELY, DON’T DO IT AT ALL WORKING FROM ELEVATED SURFACES WORKING FROM ELEVATED SURFACES

Editor's Notes

  • #2 State that all employees shall be protected from falls of 6 ft. or more by the use of an approved fall protection system
  • #3 State that all employees shall be protected from falls of 6 ft. or more by the use of an approved fall protection system
  • #4 States that; No scaffold shall be erected, moved dismantled or altered except under the supervision of a competent person The footing or anchorage for scaffolds shall be rigid, level, sound and capable of carrying the maximum intended load without settling or displacement Unstable objects such as drums, boxes, loose CHB or concrete blocks are not to be used to support scaffolds or planks Guardrails, mid-rails , and toeboards shall be installed on all open sides and ends of platforms more than 6 ft. above the working surface. It shall be 2” nominal diameter or its equivalent, between 36-42 inches high, supports shall be at intervals not to exceed 8 ft. Toeboards shall be at least 4 inches in height. Where persons are required to work or pass under the scaffold, it shall be provided with a screen between the toeboard and guardrail The entire work platform of a scaffold must be fully covered. If a ladder obstruct full planking, an equivalent fall protection shall be put in place.
  • #5 States that; No scaffold shall be erected, moved dismantled or altered except under the supervision of a competent person The footing or anchorage for scaffolds shall be rigid, level, sound and capable of carrying the maximum intended load without settling or displacement Unstable objects such as drums, boxes, loose CHB or concrete blocks are not to be used to support scaffolds or planks Guardrails, mid-rails , and toeboards shall be installed on all open sides and ends of platforms more than 6 ft. above the working surface. It shall be 2” nominal diameter or its equivalent, between 36-42 inches high, supports shall be at intervals not to exceed 8 ft. Toeboards shall be at least 4 inches in height. Where persons are required to work or pass under the scaffold, it shall be provided with a screen between the toeboard and guardrail The entire work platform of a scaffold must be fully covered. If a ladder obstruct full planking, an equivalent fall protection shall be put in place.
  • #6  Poles, legs of scaffolds shall be plumb and securely braced to prevent swaying and displacement. Slippery conditions on scaffold must be eliminated as soon as they occur. Scaffolding safety rules shall be posted in a conspicuous place and make sure people follow them. Barricade at least 1 meter around the scaffold or the entire floor area where interstitial work is going on The entire scaffold shall be tied to and securely braced against the building at intervals not to exceed 30 ft horizontally and 26 ft. vertically Shall be constructed to support 4x the max load expected Any scaffold that exceed 20 ft. in length and 10 ft. in height requires a scaffold plan or drawing approved/signed by a Civil or Structural Engineer prior to erection.
  • #7  Never erect a scaffold within 10 ft. of power lines Use of scaffold by multiple contractor must be approved by a competent person. Each contractor must be responsible to inspect and ensure the scaffolding is in safe condition prior to any employee working on scaffold Straight access ladders attached to scaffolding shall not exceed 20 ft. without a break or offset (landing) that would limit the potential fall exposure Outrigger should be used/installed when scaffold is more than 4x higher than the narrowest base dimension All suspended scaffolds require independent safety line for each employee. Employee must use full body harness when working from any suspended scaffold.
  • #8 Requirements for personnel working on scaffolds or other work platforms; All scaffolds and other work platforms must be installed under the supervision of a competent person Access ladder or equivalent means of safe access must be provided on all scaffolds External work on scaffold during severe weather condition is prohibited Planks used on scaffolding work platforms must extend between 6-18 inches from the end support; overlap at least 12 inches; and be secured to prevent movement Do not ride on rolling scaffold.
  • #9 Requirements for personnel working on scaffolds or other work platforms; All scaffolds and other work platforms must be installed under the supervision of a competent person Access ladder or equivalent means of safe access must be provided on all scaffolds External work on scaffold during severe weather condition is prohibited Planks used on scaffolding work platforms must extend between 6-18 inches from the end support; overlap at least 12 inches; and be secured to prevent movement Do not ride on rolling scaffold.
  • #10  Personnel working from temporary platforms or travelling on temporary catwalks shall have their safety lanyard secured at all times to a lifeline or structure capable of supporting a min of 5400 lbs. Every temporary work platform or walkway must be provided with a safe means of access/egress which allows personnel to remain tied off all times. Retractable lifelines can be used to achieve fall protection for ascending/descending When working overhead or interstitial, the entire floor area below the interstitial work being done must be fully barricaded.