SlideShare a Scribd company logo
1 of 1
__________________________________________________
What’s happening at Hardisty?
The town of Hardisty is a whirlwind of construction activity and a
steady hum of heavy machinery. At the TransCanada Keystone
Hardisty site, workers move purposefully about. Some are
fitting together mammoth oil tanks while others are laying an
infinite ream of colour-coded pipelines that occasionally weave
their way above ground before burrowing back underground
and out of sight.
“There are pipelines running underground and accidentally
damaging one of them could mean a multi-million dollar
lawsuit” says Andrew Foy, WorleyParsonsCord Project
Manager for both the Terminal A brownfield and Terminal B greenfield sites.
It’s not hard to understand Andrew’s caution. Running smack down the middle of the
TransCanada brown field site is a narrow strip of land owned by Husky Energy. Beneath the
surface are Husky pipelines. “We have to take extra precaution to safeguard against hitting one
of the pipelines,” Andrew says.
WorleyParsonsCord is managing the fabrication and field construction portions of the Hardisty
Terminal A brownfield work and Terminal B balance of plant construction at the TransCanada
Keystone Hardisty facility.
Andrew leads a team of 150 workers and subcontractors at both sites. The Greenfield site is
managed by Darcy Pearson and the Brownfield site by Paul Paschinski. The two contracts have
a total value of CAD58 million, and work is scheduled to be completed in June 2013.

More Related Content

More from Darcy Pearson

Hardisty Project Profile
Hardisty Project ProfileHardisty Project Profile
Hardisty Project ProfileDarcy Pearson
 
Safety Milestone Recognition from Suncor
Safety Milestone Recognition from SuncorSafety Milestone Recognition from Suncor
Safety Milestone Recognition from SuncorDarcy Pearson
 
Darcy Pearson - Letter of Recommendation from President & CEO of Tradesmen En...
Darcy Pearson - Letter of Recommendation from President & CEO of Tradesmen En...Darcy Pearson - Letter of Recommendation from President & CEO of Tradesmen En...
Darcy Pearson - Letter of Recommendation from President & CEO of Tradesmen En...Darcy Pearson
 
Dale Carnegie Leadership Training - Certificate of Achievement
Dale Carnegie Leadership Training - Certificate of AchievementDale Carnegie Leadership Training - Certificate of Achievement
Dale Carnegie Leadership Training - Certificate of AchievementDarcy Pearson
 
Mount Royal College - PM Certificate
Mount Royal College - PM CertificateMount Royal College - PM Certificate
Mount Royal College - PM CertificateDarcy Pearson
 
PMP Certificate - Exp 2015
PMP Certificate - Exp 2015PMP Certificate - Exp 2015
PMP Certificate - Exp 2015Darcy Pearson
 

More from Darcy Pearson (6)

Hardisty Project Profile
Hardisty Project ProfileHardisty Project Profile
Hardisty Project Profile
 
Safety Milestone Recognition from Suncor
Safety Milestone Recognition from SuncorSafety Milestone Recognition from Suncor
Safety Milestone Recognition from Suncor
 
Darcy Pearson - Letter of Recommendation from President & CEO of Tradesmen En...
Darcy Pearson - Letter of Recommendation from President & CEO of Tradesmen En...Darcy Pearson - Letter of Recommendation from President & CEO of Tradesmen En...
Darcy Pearson - Letter of Recommendation from President & CEO of Tradesmen En...
 
Dale Carnegie Leadership Training - Certificate of Achievement
Dale Carnegie Leadership Training - Certificate of AchievementDale Carnegie Leadership Training - Certificate of Achievement
Dale Carnegie Leadership Training - Certificate of Achievement
 
Mount Royal College - PM Certificate
Mount Royal College - PM CertificateMount Royal College - PM Certificate
Mount Royal College - PM Certificate
 
PMP Certificate - Exp 2015
PMP Certificate - Exp 2015PMP Certificate - Exp 2015
PMP Certificate - Exp 2015
 

TCPL - Hardisty Newsletter

  • 1. __________________________________________________ What’s happening at Hardisty? The town of Hardisty is a whirlwind of construction activity and a steady hum of heavy machinery. At the TransCanada Keystone Hardisty site, workers move purposefully about. Some are fitting together mammoth oil tanks while others are laying an infinite ream of colour-coded pipelines that occasionally weave their way above ground before burrowing back underground and out of sight. “There are pipelines running underground and accidentally damaging one of them could mean a multi-million dollar lawsuit” says Andrew Foy, WorleyParsonsCord Project Manager for both the Terminal A brownfield and Terminal B greenfield sites. It’s not hard to understand Andrew’s caution. Running smack down the middle of the TransCanada brown field site is a narrow strip of land owned by Husky Energy. Beneath the surface are Husky pipelines. “We have to take extra precaution to safeguard against hitting one of the pipelines,” Andrew says. WorleyParsonsCord is managing the fabrication and field construction portions of the Hardisty Terminal A brownfield work and Terminal B balance of plant construction at the TransCanada Keystone Hardisty facility. Andrew leads a team of 150 workers and subcontractors at both sites. The Greenfield site is managed by Darcy Pearson and the Brownfield site by Paul Paschinski. The two contracts have a total value of CAD58 million, and work is scheduled to be completed in June 2013.