Road Maintenance Review 2011 Welcome
Road Maintenance Review 2011 Minister for Housing & Transport Keith Brown MSP Opening Remarks
Road Maintenance Review 2011 Councillor Alison Hay COSLA Regeneration  & Sustainable Development Spokesperson
Road Maintenance Review 2011 Martin McLaughlin Ewan Wallace Context, Scope & Methodology
Context Scope Methodology
 
Change in Traffic Volumes  Change in road maintenance spend Change in  purchasing power Change in roads in acceptable condition Headline Backlog (£) Council Roads + 4%   (since 2004/05)  + 22 % (over last 15 years) + 12% (2004/05 – 2009/10) - 13% (due to road maintenance industry inflation) - 4% (from 2005 to 2010) 1.54 billion (640 million more than  in 2004) Trunk Roads + 3%  (since 2004/05) + 37% (over last 15 years) - 12% (2004/05 – 2009/10) - 32% (due to road maintenance industry inflation) - 6% (from 2006 to 2010) 713 million (480 million more than 2004)
 
 
Audit Scotland Recommendations
Audit Scotland recommendations Strategies and plans for adequate prioritisation  – greatest contribution to economic growth and improved quality of life Collaborative working  (resources & partnerships between councils and with the private sector) Regular reporting of road condition to elected members and the public Benchmarking, improved performance management and reporting
Audit Scotland recommendations Data available to allow effective asset management to take place Consistency in maintenance backlog calculation The SCOTS road asset management project fully deployed  Adoption of performance indicators developed by SCOTS  Benchmark road maintenance activities to drive out cost inefficiencies A costed model for shared services
Context Scope Methodology
Purpose of the Review… National review on how the road network is managed and maintained, with a view to stimulating service redesign and increasing the pace of examining the potential for shared services
… Purpose of the Review How Scottish Government and Local Authorities can work more collaboratively What can be learned from international road management practice
Scope of Review Delivering efficiently managed roads for all within budgets available and identifying opportunities for innovation, collaborative working and the sharing of services Whole of the road asset and all road users Excludes winter service
Context Scope Methodology
 
Methodology BASELINE Full deployment ‘ Accepted/ standard practice’ eg. 80-100% of road authorities employ BEST/GOOD PRACTICE Partial deployment eg. up to 50% of road authorities employ NOVEL/ INNOVATIVE DEPLOYMENT Possibly only  1-10% employ Barriers to wider  adoption/ uptake Cost/ resources/ skills/ risk..? Innovators/ producers Route to market/ trials/ barriers/ risks..?
Phase 1 (March-June)     Evidence gathering & option generation Stakeholder event   (June) Emerging findings & options   Phase 2   (July-Sept) Option analysis & appraisal   Roads Summit   (Oct 2011)
Road Maintenance Review 2011 Donald Bell, Director, Halcrow Emerging Findings
What the public see What’s underneath
Standards Asset Management Prioritisation Funding mechanisms New materials Health & Safety Delivery models
What I will cover Road maintenance Three working groups Asset management and standards Technology & productivity innovation Resourcing Emerging themes
Road maintenance Why?
Road maintenance Who does it benefit?
Road maintenance Who does it involve?
What I will cover Road maintenance Three working groups Asset management and standards Technology & productivity innovation Resourcing Emerging themes
Three Working Groups each looked at…. Baseline Best Practice Innovation
Asset Management & Standards What you have What you need to do When you need to do it How you do it
Asset Management & Standards Local authorities –  “…plan in place no later than the end of 2011…” Transport Scotland –  “...adequate prioritisation [given to routes contributing to] …greatest economic growth”
Asset Management & Standards – State of play Adherence to standards to minimise risk. Developing Codes of Practice - new materials and processes. Older standards may be slowing best practice and innovations. Asset Management Plans deliver value – the sector needs to implement these.  Transport Scotland and 30 of 32 Scottish local authorities have a Road Asset Management Plan in place. Industry KPIs need to be outcome focused. Communication challenges: Increasing competition to retain current share of diminishing budgets Increasing frustration from road users affected by  deterioration of the road.
Asset Management & Standards - Questions What factors are most important when prioritising spend on assets for the benefit of all road users? How should spend be apportioned between different elements -roads, footways, lighting, traffic lights, etc.  What, if any, reduction in standards or level of service is acceptable within reduced budgets? How can we better communicate issues and benefits? What needs to be done to deliver transformational  change?
Technology & Productivity Innovation Can we do it better?
Technology & Productivity Innovation Transport Scotland and local authorities should   “work together… …achieving more with the resources currently available”
Technology & Productivity Innovation – State of Play Innovation, research and development is predominantly undertaken by the private sector. Examples of public sector organisations working together, and with their supply chains, to develop new materials, tools and techniques. New and innovative techniques are being developed, BUT new materials and techniques have to be trialled across all roads authorities. The use of Lean techniques is limited.  Where they have been used, there has been success in improving the quality and efficiency of services. No apparent strategy within the sector on research and development.  Development and use of new ideas, techniques and  materials can be inconsistent.
Technology & Productivity Innovation - Questions Are there examples from other key sectors that we can learn from, where innovation is supported at the heart of the sector? What types of structures would be required to support greater access to innovation/ access to the market to deliver better outcomes for all road users? How do successful productivity improvements in the road maintenance sector become more widely adopted? What needs to be done to deliver transformational change?
Resourcing How it is set up
Resourcing Transport Scotland and local authorities should explore “…new ways of working, such as service reconfiguration, pooling and flexible use of resources and partnerships between councils and with the private sector ”
Resourcing – State of Play Public sector procurement is governed by European legislation. Management arrangements follow traditional lines  – local or central government fund the work, which is carried out in-house, or put out to tender. Sharing of road maintenance services is not widespread, but is expanding. Given the Audit Scotland recommendations, there is a case for all roads authorities to examine who they can work together with to deliver a better service.
Resourcing - Questions What scope is there for different delivery models to maximise efficiencies whilst maintaining quality maintenance services? How can we utilise procurement or contract mechanisms to drive savings and benefits for all road users? What are the barriers to more shared services and collaboration and how might these be overcome? Are there alternative, or new, funding models to either  deliver access to new streams of funding or  to create better value for money?  What needs to be done to deliver transformational  change?
What I will cover Road maintenance Three working groups Asset management and standards Technology & productivity innovation Resourcing Emerging themes
Findings – Emerging Themes Asset Management & Standards Technology & Productivity Innovation Resourcing Effective Asset Management   Prioritisation   Benchmarking & Monitoring   Delivery Models   Incentivising Innovation    Enabling Faster Change   Communication   
The BIG questions How do we take themes forward? Will they deliver transformational change?  What else needs to be considered?
Road Maintenance Review 2011 Facilitated Working Group Sessions Introduction Professor Malcolm Horner
Scope Evidence base Emerging options Gaps
Scope Resourcing Economic Issues, Impacts, Costs & Benefits  Technology & Productivity Innovation Standards & Prioritisation (Asset Management) National Roads Maintenance Review Evidence Best Practice Innovation Baseline
Full deployment ‘ Accepted/ standard practice’ eg. 80-100% of road authorities employ Partial deployment ‘ Best practice’ eg. up to 50% of road authorities employ Novel/ innovative deployment Possibly only  1-10% employ How do we move more efficiently through the pipeline towards standard/ accepted practice…? Barriers to wider  adoption/ uptake Cost/ resources/ skills/ risk..? Innovators/ producers Route to market/ trials/ barriers/ risks..?
Evidence Base Review Working Group input & feedback SCOTS/ Transport Scotland reports & papers Audit Scotland/ Audit Commission reports & data UK case study examples eg. Highways Agency, County Councils, Water Sector,   DfT - Highways Maintenance Efficiency Programme (HMEP) International case studies & benchmarking reports Web resources Topical expert input
Emerging Options Preliminary options developed by Working Groups Examples to support discussion for facilitated sessions  Stakeholder options Post-event shortlist for appraisal
Gaps Feedback on gaps/ additional issues Facilitated sessions Post-event feedback Deadline– 11 th  July
Facilitated Working Group Sessions Technology & Productivity Innovation Scott II Facilitator: Professor Malcolm Horner University of Dundee Standards & Prioritisation  (Asset Management) Scott I Facilitator: Mike Bordiss Independent Consultant Resourcing Burns Suite Facilitator: Emma Langman Progression Partnership Wider Economic Issues, Impacts,  Costs & Benefits Caledonian Facilitator: Professor Iain Docherty University of Glasgow
Lunch Break 12:40-1:15pm Exhibition Viewing In the Lounge
Road Maintenance Review 2011 Coffee Break – 2:15 pm Back in Caledonian Suite - 2:30pm
Road Maintenance Review 2011 High Level Summary Reports Back to Plenary
Road Maintenance Review 2011 Wider Economic Issues, Impacts, Costs & Benefits Professor Iain Docherty
Stakeholder Session Options Wider Economic Issues, Impacts, Costs & Benefits ARE WE HAVING A GOOD CRISIS? No consensus Whose Standards? Prepared to let standards fall? Taxation/hypothecation Democratic Failure? Those who cause damage pay No clear evidence re: outcomes More funding!
Road Maintenance Review 2011 Resourcing Emma Langman
Different Delivery Models :  – revenue funded road maintenance with consistent budget, shared services among smaller local authorities, LLP, PPP and MAC, cross boundary working Procurement or Contract Mechanisms:  – outcome based contracts, standardisation road only procurement, standardised long-term contracts to maximise efficiencies and justify set-up costs. Term maintenance contracts joint TS and LA. Performance-based incentives. Barriers to shared services:  - political and legislative barriers, clear objectives,  Alternative funding models:  - charging utilities for failures and occupation,  re-introduce ring-fencing roads maintenance budgets, flexibility on annualised budgets.  Horizontal integration of services.  Deliver Transformational Change : - political will, positive political buy-in is fundamental,  supported by clear direction and strong management, stable long term budgeting, collaboration Stakeholder Session Options  Resourcing
Road Maintenance Review 2011 Standards & Prioritisation Mike Bordiss
Stakeholder Session Options Standards & Prioritisation (Asset Management) Communication - engaging with all road users on levels of service Communication - politicians on budget scenarios to meet    levels of  service options Commonality of asset management themes and objectives  Long term view of road maintenance v. political cycles Localism (eg potholes) v. asset management prioritisation Standards – difficulty in convincing standard owners to change Climate change adaption and mitigation Redefine backlog to reflect chosen state of roads not perfect Wider issues - street lighting against crime; NHS costs View as community asset not a liability
Road Maintenance Review 2011 Technology & Productivity Innovation Professor Malcolm Horner
Stakeholder Session Options  Technology & Productivity Innovation Key Points Programming and coordination of works Utilities and reinstatements Annualised budgets Standardising protocols Identifying and coordinating a proactive research agenda Accessibility for all / use of voluntary groups to advise Incentivisation for innovation Appropriateness of current standards  Effective communication
Road Maintenance Review 2011 Question & Answer Session For Plenary
Road Maintenance Review 2011 Closing Remarks Ewan Wallace, SCOTS

Roads maintenance review

  • 1.
  • 2.
    Road Maintenance Review2011 Minister for Housing & Transport Keith Brown MSP Opening Remarks
  • 3.
    Road Maintenance Review2011 Councillor Alison Hay COSLA Regeneration & Sustainable Development Spokesperson
  • 4.
    Road Maintenance Review2011 Martin McLaughlin Ewan Wallace Context, Scope & Methodology
  • 5.
  • 6.
  • 7.
    Change in TrafficVolumes Change in road maintenance spend Change in purchasing power Change in roads in acceptable condition Headline Backlog (£) Council Roads + 4% (since 2004/05) + 22 % (over last 15 years) + 12% (2004/05 – 2009/10) - 13% (due to road maintenance industry inflation) - 4% (from 2005 to 2010) 1.54 billion (640 million more than in 2004) Trunk Roads + 3% (since 2004/05) + 37% (over last 15 years) - 12% (2004/05 – 2009/10) - 32% (due to road maintenance industry inflation) - 6% (from 2006 to 2010) 713 million (480 million more than 2004)
  • 8.
  • 9.
  • 10.
  • 11.
    Audit Scotland recommendationsStrategies and plans for adequate prioritisation – greatest contribution to economic growth and improved quality of life Collaborative working (resources & partnerships between councils and with the private sector) Regular reporting of road condition to elected members and the public Benchmarking, improved performance management and reporting
  • 12.
    Audit Scotland recommendationsData available to allow effective asset management to take place Consistency in maintenance backlog calculation The SCOTS road asset management project fully deployed Adoption of performance indicators developed by SCOTS Benchmark road maintenance activities to drive out cost inefficiencies A costed model for shared services
  • 13.
  • 14.
    Purpose of theReview… National review on how the road network is managed and maintained, with a view to stimulating service redesign and increasing the pace of examining the potential for shared services
  • 15.
    … Purpose ofthe Review How Scottish Government and Local Authorities can work more collaboratively What can be learned from international road management practice
  • 16.
    Scope of ReviewDelivering efficiently managed roads for all within budgets available and identifying opportunities for innovation, collaborative working and the sharing of services Whole of the road asset and all road users Excludes winter service
  • 17.
  • 18.
  • 19.
    Methodology BASELINE Fulldeployment ‘ Accepted/ standard practice’ eg. 80-100% of road authorities employ BEST/GOOD PRACTICE Partial deployment eg. up to 50% of road authorities employ NOVEL/ INNOVATIVE DEPLOYMENT Possibly only 1-10% employ Barriers to wider adoption/ uptake Cost/ resources/ skills/ risk..? Innovators/ producers Route to market/ trials/ barriers/ risks..?
  • 20.
    Phase 1 (March-June) Evidence gathering & option generation Stakeholder event (June) Emerging findings & options Phase 2 (July-Sept) Option analysis & appraisal Roads Summit (Oct 2011)
  • 21.
    Road Maintenance Review2011 Donald Bell, Director, Halcrow Emerging Findings
  • 22.
    What the publicsee What’s underneath
  • 23.
    Standards Asset ManagementPrioritisation Funding mechanisms New materials Health & Safety Delivery models
  • 24.
    What I willcover Road maintenance Three working groups Asset management and standards Technology & productivity innovation Resourcing Emerging themes
  • 25.
  • 26.
    Road maintenance Whodoes it benefit?
  • 27.
    Road maintenance Whodoes it involve?
  • 28.
    What I willcover Road maintenance Three working groups Asset management and standards Technology & productivity innovation Resourcing Emerging themes
  • 29.
    Three Working Groupseach looked at…. Baseline Best Practice Innovation
  • 30.
    Asset Management &Standards What you have What you need to do When you need to do it How you do it
  • 31.
    Asset Management &Standards Local authorities – “…plan in place no later than the end of 2011…” Transport Scotland – “...adequate prioritisation [given to routes contributing to] …greatest economic growth”
  • 32.
    Asset Management &Standards – State of play Adherence to standards to minimise risk. Developing Codes of Practice - new materials and processes. Older standards may be slowing best practice and innovations. Asset Management Plans deliver value – the sector needs to implement these. Transport Scotland and 30 of 32 Scottish local authorities have a Road Asset Management Plan in place. Industry KPIs need to be outcome focused. Communication challenges: Increasing competition to retain current share of diminishing budgets Increasing frustration from road users affected by deterioration of the road.
  • 33.
    Asset Management &Standards - Questions What factors are most important when prioritising spend on assets for the benefit of all road users? How should spend be apportioned between different elements -roads, footways, lighting, traffic lights, etc. What, if any, reduction in standards or level of service is acceptable within reduced budgets? How can we better communicate issues and benefits? What needs to be done to deliver transformational change?
  • 34.
    Technology & ProductivityInnovation Can we do it better?
  • 35.
    Technology & ProductivityInnovation Transport Scotland and local authorities should “work together… …achieving more with the resources currently available”
  • 36.
    Technology & ProductivityInnovation – State of Play Innovation, research and development is predominantly undertaken by the private sector. Examples of public sector organisations working together, and with their supply chains, to develop new materials, tools and techniques. New and innovative techniques are being developed, BUT new materials and techniques have to be trialled across all roads authorities. The use of Lean techniques is limited. Where they have been used, there has been success in improving the quality and efficiency of services. No apparent strategy within the sector on research and development. Development and use of new ideas, techniques and materials can be inconsistent.
  • 37.
    Technology & ProductivityInnovation - Questions Are there examples from other key sectors that we can learn from, where innovation is supported at the heart of the sector? What types of structures would be required to support greater access to innovation/ access to the market to deliver better outcomes for all road users? How do successful productivity improvements in the road maintenance sector become more widely adopted? What needs to be done to deliver transformational change?
  • 38.
  • 39.
    Resourcing Transport Scotlandand local authorities should explore “…new ways of working, such as service reconfiguration, pooling and flexible use of resources and partnerships between councils and with the private sector ”
  • 40.
    Resourcing – Stateof Play Public sector procurement is governed by European legislation. Management arrangements follow traditional lines – local or central government fund the work, which is carried out in-house, or put out to tender. Sharing of road maintenance services is not widespread, but is expanding. Given the Audit Scotland recommendations, there is a case for all roads authorities to examine who they can work together with to deliver a better service.
  • 41.
    Resourcing - QuestionsWhat scope is there for different delivery models to maximise efficiencies whilst maintaining quality maintenance services? How can we utilise procurement or contract mechanisms to drive savings and benefits for all road users? What are the barriers to more shared services and collaboration and how might these be overcome? Are there alternative, or new, funding models to either deliver access to new streams of funding or to create better value for money? What needs to be done to deliver transformational change?
  • 42.
    What I willcover Road maintenance Three working groups Asset management and standards Technology & productivity innovation Resourcing Emerging themes
  • 43.
    Findings – EmergingThemes Asset Management & Standards Technology & Productivity Innovation Resourcing Effective Asset Management   Prioritisation   Benchmarking & Monitoring   Delivery Models   Incentivising Innovation    Enabling Faster Change   Communication   
  • 44.
    The BIG questionsHow do we take themes forward? Will they deliver transformational change? What else needs to be considered?
  • 45.
    Road Maintenance Review2011 Facilitated Working Group Sessions Introduction Professor Malcolm Horner
  • 46.
    Scope Evidence baseEmerging options Gaps
  • 47.
    Scope Resourcing EconomicIssues, Impacts, Costs & Benefits Technology & Productivity Innovation Standards & Prioritisation (Asset Management) National Roads Maintenance Review Evidence Best Practice Innovation Baseline
  • 48.
    Full deployment ‘Accepted/ standard practice’ eg. 80-100% of road authorities employ Partial deployment ‘ Best practice’ eg. up to 50% of road authorities employ Novel/ innovative deployment Possibly only 1-10% employ How do we move more efficiently through the pipeline towards standard/ accepted practice…? Barriers to wider adoption/ uptake Cost/ resources/ skills/ risk..? Innovators/ producers Route to market/ trials/ barriers/ risks..?
  • 49.
    Evidence Base ReviewWorking Group input & feedback SCOTS/ Transport Scotland reports & papers Audit Scotland/ Audit Commission reports & data UK case study examples eg. Highways Agency, County Councils, Water Sector, DfT - Highways Maintenance Efficiency Programme (HMEP) International case studies & benchmarking reports Web resources Topical expert input
  • 50.
    Emerging Options Preliminaryoptions developed by Working Groups Examples to support discussion for facilitated sessions Stakeholder options Post-event shortlist for appraisal
  • 51.
    Gaps Feedback ongaps/ additional issues Facilitated sessions Post-event feedback Deadline– 11 th July
  • 52.
    Facilitated Working GroupSessions Technology & Productivity Innovation Scott II Facilitator: Professor Malcolm Horner University of Dundee Standards & Prioritisation (Asset Management) Scott I Facilitator: Mike Bordiss Independent Consultant Resourcing Burns Suite Facilitator: Emma Langman Progression Partnership Wider Economic Issues, Impacts, Costs & Benefits Caledonian Facilitator: Professor Iain Docherty University of Glasgow
  • 53.
    Lunch Break 12:40-1:15pmExhibition Viewing In the Lounge
  • 54.
    Road Maintenance Review2011 Coffee Break – 2:15 pm Back in Caledonian Suite - 2:30pm
  • 55.
    Road Maintenance Review2011 High Level Summary Reports Back to Plenary
  • 56.
    Road Maintenance Review2011 Wider Economic Issues, Impacts, Costs & Benefits Professor Iain Docherty
  • 57.
    Stakeholder Session OptionsWider Economic Issues, Impacts, Costs & Benefits ARE WE HAVING A GOOD CRISIS? No consensus Whose Standards? Prepared to let standards fall? Taxation/hypothecation Democratic Failure? Those who cause damage pay No clear evidence re: outcomes More funding!
  • 58.
    Road Maintenance Review2011 Resourcing Emma Langman
  • 59.
    Different Delivery Models: – revenue funded road maintenance with consistent budget, shared services among smaller local authorities, LLP, PPP and MAC, cross boundary working Procurement or Contract Mechanisms: – outcome based contracts, standardisation road only procurement, standardised long-term contracts to maximise efficiencies and justify set-up costs. Term maintenance contracts joint TS and LA. Performance-based incentives. Barriers to shared services: - political and legislative barriers, clear objectives, Alternative funding models: - charging utilities for failures and occupation, re-introduce ring-fencing roads maintenance budgets, flexibility on annualised budgets. Horizontal integration of services. Deliver Transformational Change : - political will, positive political buy-in is fundamental, supported by clear direction and strong management, stable long term budgeting, collaboration Stakeholder Session Options Resourcing
  • 60.
    Road Maintenance Review2011 Standards & Prioritisation Mike Bordiss
  • 61.
    Stakeholder Session OptionsStandards & Prioritisation (Asset Management) Communication - engaging with all road users on levels of service Communication - politicians on budget scenarios to meet levels of service options Commonality of asset management themes and objectives Long term view of road maintenance v. political cycles Localism (eg potholes) v. asset management prioritisation Standards – difficulty in convincing standard owners to change Climate change adaption and mitigation Redefine backlog to reflect chosen state of roads not perfect Wider issues - street lighting against crime; NHS costs View as community asset not a liability
  • 62.
    Road Maintenance Review2011 Technology & Productivity Innovation Professor Malcolm Horner
  • 63.
    Stakeholder Session Options Technology & Productivity Innovation Key Points Programming and coordination of works Utilities and reinstatements Annualised budgets Standardising protocols Identifying and coordinating a proactive research agenda Accessibility for all / use of voluntary groups to advise Incentivisation for innovation Appropriateness of current standards Effective communication
  • 64.
    Road Maintenance Review2011 Question & Answer Session For Plenary
  • 65.
    Road Maintenance Review2011 Closing Remarks Ewan Wallace, SCOTS