The four laning of the Ludhiana-Talwandi Bhai road in Punjab, India was a failure as it was not completed by the scheduled date and only around 53% of the physical work was finished. Key reasons for the failure included a lack of proper control and oversight by the Punjab government, inadequate initial planning and budgeting, issues with project financing, and alleged corruption. The project involved widening the existing two lane road to four lanes but faced challenges with coordination between the multiple organizations involved and meeting construction milestones on time. Lessons from this project highlight the importance of strict government oversight, contingency planning, and preventting corruption to successfully deliver large infrastructure projects.
The document discusses project management as it relates to the Delhi Metro Rail Corporation project, including defining what a project is, the key processes involved in project management, and the various knowledge areas of project management such as integration management, scope management, time management, cost management, quality management, human resource management, communications management, and risk management. It provides an overview of the history and development of project management as a discipline. The document serves to provide context and background information on project management principles and how they can be applied to a large infrastructure project like the Delhi Metro.
The document summarizes an internship report submitted by Naveen Kumar for his summer internship with Larsen & Toubro Construction from June 23rd to July 22nd 2016. It provides details of the Barapullah elevated corridor project being constructed by L&T from Sarai Kale Khan to Mayur Vihar Phase 1, including project parameters, departments involved, construction methodology, safety measures, and equipment used. It also acknowledges the support received from the internship guide and L&T staff during the training period.
Training report(12 btceng040) pdf format of MNNIT BY RITESHMANI TRIPATHI DEAN...Riteshmani Tripathi
The document is a summer internship report submitted by Riteshmani Tripathi for their Bachelor of Technology degree in Civil Engineering at SHIATS-DU, Allahabad. It summarizes their 28 day internship conducting experiments and laboratory work in geotechnical engineering, chemical analysis, transportation engineering, and building materials at Motilal Nehru National Institute of Technology, Allahabad. The report includes an introduction, preface, descriptions of the institute and civil engineering department, acknowledgments, and detailed sections on the laboratory experiments and work conducted in areas like standard penetration testing, direct shear testing, liquid limit and plastic limit testing, and total station handling.
Shubham Bhargava is a civil engineering consultant with over 2 years of experience. He is currently working as a Site Engineer for SYSTRA-CEG-SMCIPL Consortium, providing consultancy services to MMRDA on the Mumbai Metro line 9 and 7A projects. Previously, he worked as a Graduate Civil Engineer for Shree Mangalam Buildcon on the construction of a high-level bridge across Kalisindh River. He holds a Bachelor's degree in Civil Engineering from RGPV University. His responsibilities have included ensuring civil works are executed according to plans and specifications, maintaining quality control, and coordinating with contractors and clients.
Software patents: Breaking Bad in USA & EU - Іларіон ТомаровUBA-komitet
Семінар Комітету АПУ з питань телекомунікацій, інформаційних технологій та Інтернету та Комітету АПУ з інтелектуальної власності.: «Нестандартні способи захисту ІТ продукції» - частина 2, 13.06.2016, м. Київ
El documento presenta el plan de producción de un proyecto audiovisual dividido en 4 fases. Detalla los roles y responsabilidades de cada miembro del equipo, asignando un responsable por fase. La Fase 1 se centra en la organización y termina el 14 de febrero. La Fase 2 es la elaboración del guión y finaliza el 13 de marzo. La Fase 3 es la producción y acaba el 10 de abril. Por último, la Fase 4 es la difusión del proyecto.
Презентація HiiL Justice Accelerator - Дмитро ФоремнийUBA-komitet
Семінар Комітету АПУ з питань телекомунікацій, інформаційних технологій та Інтернету спільно з Гаазьким Інститутом Інновацій в Праві : «LegalTech стартапи. Як отримати поштовх?», 23.06.2016, м. Київ
Три поради аутсорс компаніям - Василь Поп-СтасівUBA-komitet
Засідання Комітету АПУ з питань телекомунікацій, інформаційних технологій та Інтернету і комітету IT-права Lviv IT Cluster «Особливості укладення зовнішньо-економічних договорів у сегменті ІТ», 14 травня 2016 року, м. Львів
The document discusses project management as it relates to the Delhi Metro Rail Corporation project, including defining what a project is, the key processes involved in project management, and the various knowledge areas of project management such as integration management, scope management, time management, cost management, quality management, human resource management, communications management, and risk management. It provides an overview of the history and development of project management as a discipline. The document serves to provide context and background information on project management principles and how they can be applied to a large infrastructure project like the Delhi Metro.
The document summarizes an internship report submitted by Naveen Kumar for his summer internship with Larsen & Toubro Construction from June 23rd to July 22nd 2016. It provides details of the Barapullah elevated corridor project being constructed by L&T from Sarai Kale Khan to Mayur Vihar Phase 1, including project parameters, departments involved, construction methodology, safety measures, and equipment used. It also acknowledges the support received from the internship guide and L&T staff during the training period.
Training report(12 btceng040) pdf format of MNNIT BY RITESHMANI TRIPATHI DEAN...Riteshmani Tripathi
The document is a summer internship report submitted by Riteshmani Tripathi for their Bachelor of Technology degree in Civil Engineering at SHIATS-DU, Allahabad. It summarizes their 28 day internship conducting experiments and laboratory work in geotechnical engineering, chemical analysis, transportation engineering, and building materials at Motilal Nehru National Institute of Technology, Allahabad. The report includes an introduction, preface, descriptions of the institute and civil engineering department, acknowledgments, and detailed sections on the laboratory experiments and work conducted in areas like standard penetration testing, direct shear testing, liquid limit and plastic limit testing, and total station handling.
Shubham Bhargava is a civil engineering consultant with over 2 years of experience. He is currently working as a Site Engineer for SYSTRA-CEG-SMCIPL Consortium, providing consultancy services to MMRDA on the Mumbai Metro line 9 and 7A projects. Previously, he worked as a Graduate Civil Engineer for Shree Mangalam Buildcon on the construction of a high-level bridge across Kalisindh River. He holds a Bachelor's degree in Civil Engineering from RGPV University. His responsibilities have included ensuring civil works are executed according to plans and specifications, maintaining quality control, and coordinating with contractors and clients.
Software patents: Breaking Bad in USA & EU - Іларіон ТомаровUBA-komitet
Семінар Комітету АПУ з питань телекомунікацій, інформаційних технологій та Інтернету та Комітету АПУ з інтелектуальної власності.: «Нестандартні способи захисту ІТ продукції» - частина 2, 13.06.2016, м. Київ
El documento presenta el plan de producción de un proyecto audiovisual dividido en 4 fases. Detalla los roles y responsabilidades de cada miembro del equipo, asignando un responsable por fase. La Fase 1 se centra en la organización y termina el 14 de febrero. La Fase 2 es la elaboración del guión y finaliza el 13 de marzo. La Fase 3 es la producción y acaba el 10 de abril. Por último, la Fase 4 es la difusión del proyecto.
Презентація HiiL Justice Accelerator - Дмитро ФоремнийUBA-komitet
Семінар Комітету АПУ з питань телекомунікацій, інформаційних технологій та Інтернету спільно з Гаазьким Інститутом Інновацій в Праві : «LegalTech стартапи. Як отримати поштовх?», 23.06.2016, м. Київ
Три поради аутсорс компаніям - Василь Поп-СтасівUBA-komitet
Засідання Комітету АПУ з питань телекомунікацій, інформаційних технологій та Інтернету і комітету IT-права Lviv IT Cluster «Особливості укладення зовнішньо-економічних договорів у сегменті ІТ», 14 травня 2016 року, м. Львів
Este documento describe los valores como las normas de conducta y actitudes que guían nuestro comportamiento. Explica que los valores morales surgen principalmente en la familia y conducen al bienestar humano, e incluyen valores como el respeto, la honestidad y la responsabilidad. Además, distingue entre diferentes tipos de valores como los morales, sociales y de ética, y resalta la importancia de los valores para motivar las acciones humanas.
The Department of Defense is undertaking efforts to re-engineer and modernize both rotorcraft and fixed wing aircraft currently in operation. New technologies will be incorporated and airframes will be redesigned to extend the useful life of these assets while improving capabilities. The goal is to develop aircraft that are more efficient, effective, and sustainable for future military operations.
Лабиринты ВРТ в правовом регулировании суррогатного материнства в Украине - А...UBA-komitet
Конференція Асоціації правників України «Особливості правового регулювання репродуктивної медицини та сурогатного материнства. Чи потрібні зміни?», 13.10.2016, м.Київ
Патентування ПЗ та бізнесметодів в США - Катерина ОлійникUBA-komitet
Семінар Комітету АПУ з питань телекомунікацій, інформаційних технологій та Інтернету та Комітету АПУ з інтелектуальної власності: «Патентування програмного забезпечення» - частина 1, 07.06.2016, м. Київ
Complementary Recording for Tradezillla - Daily Market Commentary. For Full Online Mentorship Program visit
http://www.marketcalls.in/workshop/tradezilla-one-month-intensive-mentorship-program.html
O documento descreve um jogo em desenvolvimento onde os jogadores controlam uma batata procurando sua amiga cenoura em uma cozinha. O jogo terá gráficos coloridos, pistas para encontrar a cenoura e obstáculos a evitar.
Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008Anil Kumar Gupta
This document summarizes a paper on management control systems for infrastructure projects executed through Special Purpose Vehicles (SPVs) in India. It provides context on the challenges of infrastructure project management in India. It then discusses different models for executing railway projects in India, including construction units under zonal railways, independent organizations, and SPVs. It analyzes the performance of construction units of Southern Railway and Rail Vikas Nigam Limited, an SPV. It highlights the success of Delhi Metro Rail Corporation in executing projects on time. Finally, it proposes evaluating models based on a new management control framework and developing best practices for SPVs executing infrastructure projects.
The document summarizes the Delhi Metro project, a rail transit system created to address traffic, pollution, and congestion problems in Delhi, India. It discusses the project's phases and goals of expanding the metro network throughout Delhi and surrounding areas by 2021. The Delhi Metro Rail Corporation was established in 1995 to oversee project planning and implementation. Phase I and II were completed on time and within budget, establishing the project as a model for other metro systems. The metro system has provided environmental and economic benefits to Delhi such as reduced traffic and pollution.
electronic city elevated highway project. MILAN JOSEPH
The document summarizes the Bangalore-Hosur Road elevated highway project in India. The 9.985 km long highway was constructed to improve connectivity between Bangalore and Hosur. A consortium consisting of NCC, Soma Enterprises, and Maytas was formed to build the four-lane elevated highway on a BOT basis. The project was inaugurated in January 2010, costing 990 crores ultimately, providing faster travel between Silk Board Junction and Electronics City.
Ajay Kumar Singh has over 15 years of experience in civil construction project management. He is currently working as a Project Manager for Gawar Infrastructure Ltd. in Udaipur, Rajasthan, where he is responsible for project management, contract administration, budgeting, and manpower management. Prior to his current role, he held positions as Deputy Project Manager for several companies where he managed road, highway and infrastructure projects. He has a Bachelor of Engineering degree in Civil Engineering from Dhule University of Maharashtra.
49,260 kms of roads and highways work and construction in order to boost economic development of the country. USD 71 billion have been awarded to this project NHDP has been implemented in 1998. It has 7 phases and is led by the NHAI
The document is a summer training report submitted by Dhruv Atal to fulfill the requirements for a Bachelor of Technology degree in Civil Engineering. It discusses a summer training project conducted at the Public Works Department in Chaksu, India on road construction and renewal projects. The report includes an introduction, chapters on state highway construction and the highway planning process, and will conclude with a case study and conclusions from the summer training experience.
India’s largest highway project -The Golden Quadrilateral projectSuresh Mandal
India’s largest highway project -The Golden Quadrilateral project
Posted on February 15, 2023
“The Golden Quadrilateral project, India’s largest highway project, was launched in 2001 as part of the National Highways Development Project (NHDP).”
The Golden Quadrilateral is a highway network that connects India’s four major metropolitan cities, namely Delhi, Mumbai, Chennai, and Kolkata, forming a quadrilateral. The Golden Quadrilateral project, India’s largest highway project, was launched in 2001 as part of the National Highways Development Project (NHDP).
The Golden Quadrilateral and the National Highways Development Project (NHDP) are ongoing initiatives aimed at improving India’s road infrastructure. Some future plans for these projects include:
Completion of the remaining stretches: While most sections of the Golden Quadrilateral and the NHDP have been completed, there are still some sections that need to be finished. The government plans to complete these remaining stretches to ensure seamless connectivity across the country.
Upgradation and expansion: To keep up with the increasing traffic and freight movement, the government plans to upgrade and expand the existing highways. This includes widening the existing highways, building new bypasses, and constructing more lanes.
Use of technology: The government plans to use technology to improve road safety and traffic management. This includes the use of intelligent transportation systems, electronic toll collection, and real-time traffic monitoring systems.
Green initiatives: The government plans to incorporate green initiatives in the construction and maintenance of highways. This includes the use of eco-friendly materials and practices, and promoting the use of electric and hybrid vehicles.
New corridors: The government is also considering the development of new corridors to further improve connectivity. One such corridor is the Bharatmala Pariyojana, which aims to build new highways and expressways across the country.
The quadrilateral is 5,846 kilometres long in total, with four and six lane express highways. The project was estimated to cost Rs600 billion ($13.2 billion), but it was completed for roughly half that amount, at Rs308.58 billion. By January 2012, the entire length of the quadrilateral was operational.
For a large country like India to maintain national integration and socioeconomic development, an efficient road network is essential. The National Highway Authority of India maintains a large network of highways in India (NHAI).
These highways account for only 2% of total road infrastructure in the country, but they carry 40% of total national traffic.
The Cities which will get linked by the highway
Phase one of the NHDP is the Golden Quadrilateral highway network project. It connects major Indian cities such as New Delhi, Jaipur (Rajasthan), Gandhinagar (Gujarat), Mumbai and Pune (Maharashtra), Bangalore (Karnataka), Chennai (Tamil Nadu), Visakhapatnam (Andhra Prades
The Delhi Metro project was undertaken to provide a sustainable public transport system for Delhi's growing population. It was implemented in phases and faced challenges including land acquisition, underground construction, and signaling issues. Careful planning and leadership from Dr. E. Sreedharan helped overcome these challenges. Notable aspects included the decision to use standard gauge track, financing support from JICA, and an emphasis on safety, cleanliness, and stakeholder engagement. The metro has been successful in reducing traffic and pollution while symbolizing Delhi's modernization.
The document summarizes infrastructure news from Andhra Pradesh, India between September 19-25, 2015. Key points include:
1) Andhra Pradesh was approved for a new Investment and Manufacturing Zone in Prakasham district, which is expected to create over 20,000 direct jobs and attract $650 million in investment.
2) A Green Highway Policy is expected to be launched by September 2015 to develop eco-friendly national highways, allocating 1% of project costs to maintenance.
3) Odisha received approval for a $240 million highway project under the National Highways Development Program to improve infrastructure and travel.
PM Modi Reviews 9 Infrastructure Projects Worth Over Rs 41,500 Cr to Boost In...Suresh Mandal
PM Modi Reviews 9 Infrastructure Projects Worth Over Rs 41,500 Cr to Boost India’s Economy and Connectivity
merabharatmahanby merabharatmahanFebruary 23, 2023
In a significant move to boost the infrastructure sector in India, Prime Minister Narendra Modi recently reviewed nine major projects worth over Rs 41,500 crore. These projects are expected to create employment opportunities, enhance connectivity, and improve the overall quality of life for the people of the country. The Prime Minister’s review comes at a time when the Indian economy is slowly but steadily recovering from the impact of the COVID-19 pandemic.
Overview of the Projects
The nine projects that were reviewed by PM Modi include the Mumbai-Ahmedabad High-Speed Rail (MAHSR) corridor, the Eastern Dedicated Freight Corridor (EDFC), the Delhi-Mumbai Expressway, the Delhi-Dehradun Economic Corridor, the Bengaluru Suburban Rail Project, the Chennai Peripheral Ring Road, the Semi-High Speed Rail Corridor between Delhi and Chandigarh, the Char Dham All-Weather Road Project, and the Ahmedabad-Dholera Expressway.
Key Highlights of the 9 Infrastructure Projects Review
During the review, PM Modi emphasized the need to complete these projects within the set timelines while maintaining quality standards. He also stressed the importance of adopting modern technologies and innovative solutions to ensure that these projects are completed within the budgeted cost.
The Prime Minister highlighted that these projects are not just infrastructure projects but are crucial for the development of the country. They will help to reduce transportation costs, increase the speed of freight movement, and provide better connectivity to different parts of the country.
PM Modi also emphasized the need to ensure that these projects are environment-friendly and sustainable. He directed the concerned authorities to take adequate measures to mitigate the environmental impact of these projects and ensure that they are aligned with India’s commitment to reduce carbon emissions.
Expected Benefits
The nine projects reviewed by PM Modi are expected to have far-reaching benefits for the Indian economy and society. They will create employment opportunities for the youth and help to boost economic growth by improving connectivity and reducing transportation costs. These projects will also enhance the quality of life of the people by providing them with better access to healthcare, education, and other essential services.
Conclusion
The review of these nine infrastructure projects by PM Modi is a significant step towards strengthening India’s infrastructure sector. The Prime Minister’s emphasis on completing these projects within the set timelines and maintaining quality standards is a welcome move. The completion of these projects will provide a much-needed boost to the Indian economy and help to create a better future for the people of the country.
Nhdp get the fact - itp India - HighwaysArnaud Renard
National Highways Development Project: Get The Fact is the 3th edition of India Transport Portal.
How the highway construction pace has changed over last few years? Where do we stand?
This document summarizes a research paper analyzing challenges facing public-private partnerships (PPP) for road infrastructure projects in India. It identifies issues that have plagued PPP projects and affected their implementation. These include private sector companies bidding aggressively without considering risks, regulatory delays increasing costs, and banks tightening funding as projects faced delays meeting financial obligations. Suggestions are made to address these, such as establishing a single window for project clearances, creating a market to trade projects, revising toll pricing policies, and having backup parties involved in projects from the start.
Este documento describe los valores como las normas de conducta y actitudes que guían nuestro comportamiento. Explica que los valores morales surgen principalmente en la familia y conducen al bienestar humano, e incluyen valores como el respeto, la honestidad y la responsabilidad. Además, distingue entre diferentes tipos de valores como los morales, sociales y de ética, y resalta la importancia de los valores para motivar las acciones humanas.
The Department of Defense is undertaking efforts to re-engineer and modernize both rotorcraft and fixed wing aircraft currently in operation. New technologies will be incorporated and airframes will be redesigned to extend the useful life of these assets while improving capabilities. The goal is to develop aircraft that are more efficient, effective, and sustainable for future military operations.
Лабиринты ВРТ в правовом регулировании суррогатного материнства в Украине - А...UBA-komitet
Конференція Асоціації правників України «Особливості правового регулювання репродуктивної медицини та сурогатного материнства. Чи потрібні зміни?», 13.10.2016, м.Київ
Патентування ПЗ та бізнесметодів в США - Катерина ОлійникUBA-komitet
Семінар Комітету АПУ з питань телекомунікацій, інформаційних технологій та Інтернету та Комітету АПУ з інтелектуальної власності: «Патентування програмного забезпечення» - частина 1, 07.06.2016, м. Київ
Complementary Recording for Tradezillla - Daily Market Commentary. For Full Online Mentorship Program visit
http://www.marketcalls.in/workshop/tradezilla-one-month-intensive-mentorship-program.html
O documento descreve um jogo em desenvolvimento onde os jogadores controlam uma batata procurando sua amiga cenoura em uma cozinha. O jogo terá gráficos coloridos, pistas para encontrar a cenoura e obstáculos a evitar.
Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008Anil Kumar Gupta
This document summarizes a paper on management control systems for infrastructure projects executed through Special Purpose Vehicles (SPVs) in India. It provides context on the challenges of infrastructure project management in India. It then discusses different models for executing railway projects in India, including construction units under zonal railways, independent organizations, and SPVs. It analyzes the performance of construction units of Southern Railway and Rail Vikas Nigam Limited, an SPV. It highlights the success of Delhi Metro Rail Corporation in executing projects on time. Finally, it proposes evaluating models based on a new management control framework and developing best practices for SPVs executing infrastructure projects.
The document summarizes the Delhi Metro project, a rail transit system created to address traffic, pollution, and congestion problems in Delhi, India. It discusses the project's phases and goals of expanding the metro network throughout Delhi and surrounding areas by 2021. The Delhi Metro Rail Corporation was established in 1995 to oversee project planning and implementation. Phase I and II were completed on time and within budget, establishing the project as a model for other metro systems. The metro system has provided environmental and economic benefits to Delhi such as reduced traffic and pollution.
electronic city elevated highway project. MILAN JOSEPH
The document summarizes the Bangalore-Hosur Road elevated highway project in India. The 9.985 km long highway was constructed to improve connectivity between Bangalore and Hosur. A consortium consisting of NCC, Soma Enterprises, and Maytas was formed to build the four-lane elevated highway on a BOT basis. The project was inaugurated in January 2010, costing 990 crores ultimately, providing faster travel between Silk Board Junction and Electronics City.
Ajay Kumar Singh has over 15 years of experience in civil construction project management. He is currently working as a Project Manager for Gawar Infrastructure Ltd. in Udaipur, Rajasthan, where he is responsible for project management, contract administration, budgeting, and manpower management. Prior to his current role, he held positions as Deputy Project Manager for several companies where he managed road, highway and infrastructure projects. He has a Bachelor of Engineering degree in Civil Engineering from Dhule University of Maharashtra.
49,260 kms of roads and highways work and construction in order to boost economic development of the country. USD 71 billion have been awarded to this project NHDP has been implemented in 1998. It has 7 phases and is led by the NHAI
The document is a summer training report submitted by Dhruv Atal to fulfill the requirements for a Bachelor of Technology degree in Civil Engineering. It discusses a summer training project conducted at the Public Works Department in Chaksu, India on road construction and renewal projects. The report includes an introduction, chapters on state highway construction and the highway planning process, and will conclude with a case study and conclusions from the summer training experience.
India’s largest highway project -The Golden Quadrilateral projectSuresh Mandal
India’s largest highway project -The Golden Quadrilateral project
Posted on February 15, 2023
“The Golden Quadrilateral project, India’s largest highway project, was launched in 2001 as part of the National Highways Development Project (NHDP).”
The Golden Quadrilateral is a highway network that connects India’s four major metropolitan cities, namely Delhi, Mumbai, Chennai, and Kolkata, forming a quadrilateral. The Golden Quadrilateral project, India’s largest highway project, was launched in 2001 as part of the National Highways Development Project (NHDP).
The Golden Quadrilateral and the National Highways Development Project (NHDP) are ongoing initiatives aimed at improving India’s road infrastructure. Some future plans for these projects include:
Completion of the remaining stretches: While most sections of the Golden Quadrilateral and the NHDP have been completed, there are still some sections that need to be finished. The government plans to complete these remaining stretches to ensure seamless connectivity across the country.
Upgradation and expansion: To keep up with the increasing traffic and freight movement, the government plans to upgrade and expand the existing highways. This includes widening the existing highways, building new bypasses, and constructing more lanes.
Use of technology: The government plans to use technology to improve road safety and traffic management. This includes the use of intelligent transportation systems, electronic toll collection, and real-time traffic monitoring systems.
Green initiatives: The government plans to incorporate green initiatives in the construction and maintenance of highways. This includes the use of eco-friendly materials and practices, and promoting the use of electric and hybrid vehicles.
New corridors: The government is also considering the development of new corridors to further improve connectivity. One such corridor is the Bharatmala Pariyojana, which aims to build new highways and expressways across the country.
The quadrilateral is 5,846 kilometres long in total, with four and six lane express highways. The project was estimated to cost Rs600 billion ($13.2 billion), but it was completed for roughly half that amount, at Rs308.58 billion. By January 2012, the entire length of the quadrilateral was operational.
For a large country like India to maintain national integration and socioeconomic development, an efficient road network is essential. The National Highway Authority of India maintains a large network of highways in India (NHAI).
These highways account for only 2% of total road infrastructure in the country, but they carry 40% of total national traffic.
The Cities which will get linked by the highway
Phase one of the NHDP is the Golden Quadrilateral highway network project. It connects major Indian cities such as New Delhi, Jaipur (Rajasthan), Gandhinagar (Gujarat), Mumbai and Pune (Maharashtra), Bangalore (Karnataka), Chennai (Tamil Nadu), Visakhapatnam (Andhra Prades
The Delhi Metro project was undertaken to provide a sustainable public transport system for Delhi's growing population. It was implemented in phases and faced challenges including land acquisition, underground construction, and signaling issues. Careful planning and leadership from Dr. E. Sreedharan helped overcome these challenges. Notable aspects included the decision to use standard gauge track, financing support from JICA, and an emphasis on safety, cleanliness, and stakeholder engagement. The metro has been successful in reducing traffic and pollution while symbolizing Delhi's modernization.
The document summarizes infrastructure news from Andhra Pradesh, India between September 19-25, 2015. Key points include:
1) Andhra Pradesh was approved for a new Investment and Manufacturing Zone in Prakasham district, which is expected to create over 20,000 direct jobs and attract $650 million in investment.
2) A Green Highway Policy is expected to be launched by September 2015 to develop eco-friendly national highways, allocating 1% of project costs to maintenance.
3) Odisha received approval for a $240 million highway project under the National Highways Development Program to improve infrastructure and travel.
PM Modi Reviews 9 Infrastructure Projects Worth Over Rs 41,500 Cr to Boost In...Suresh Mandal
PM Modi Reviews 9 Infrastructure Projects Worth Over Rs 41,500 Cr to Boost India’s Economy and Connectivity
merabharatmahanby merabharatmahanFebruary 23, 2023
In a significant move to boost the infrastructure sector in India, Prime Minister Narendra Modi recently reviewed nine major projects worth over Rs 41,500 crore. These projects are expected to create employment opportunities, enhance connectivity, and improve the overall quality of life for the people of the country. The Prime Minister’s review comes at a time when the Indian economy is slowly but steadily recovering from the impact of the COVID-19 pandemic.
Overview of the Projects
The nine projects that were reviewed by PM Modi include the Mumbai-Ahmedabad High-Speed Rail (MAHSR) corridor, the Eastern Dedicated Freight Corridor (EDFC), the Delhi-Mumbai Expressway, the Delhi-Dehradun Economic Corridor, the Bengaluru Suburban Rail Project, the Chennai Peripheral Ring Road, the Semi-High Speed Rail Corridor between Delhi and Chandigarh, the Char Dham All-Weather Road Project, and the Ahmedabad-Dholera Expressway.
Key Highlights of the 9 Infrastructure Projects Review
During the review, PM Modi emphasized the need to complete these projects within the set timelines while maintaining quality standards. He also stressed the importance of adopting modern technologies and innovative solutions to ensure that these projects are completed within the budgeted cost.
The Prime Minister highlighted that these projects are not just infrastructure projects but are crucial for the development of the country. They will help to reduce transportation costs, increase the speed of freight movement, and provide better connectivity to different parts of the country.
PM Modi also emphasized the need to ensure that these projects are environment-friendly and sustainable. He directed the concerned authorities to take adequate measures to mitigate the environmental impact of these projects and ensure that they are aligned with India’s commitment to reduce carbon emissions.
Expected Benefits
The nine projects reviewed by PM Modi are expected to have far-reaching benefits for the Indian economy and society. They will create employment opportunities for the youth and help to boost economic growth by improving connectivity and reducing transportation costs. These projects will also enhance the quality of life of the people by providing them with better access to healthcare, education, and other essential services.
Conclusion
The review of these nine infrastructure projects by PM Modi is a significant step towards strengthening India’s infrastructure sector. The Prime Minister’s emphasis on completing these projects within the set timelines and maintaining quality standards is a welcome move. The completion of these projects will provide a much-needed boost to the Indian economy and help to create a better future for the people of the country.
Nhdp get the fact - itp India - HighwaysArnaud Renard
National Highways Development Project: Get The Fact is the 3th edition of India Transport Portal.
How the highway construction pace has changed over last few years? Where do we stand?
This document summarizes a research paper analyzing challenges facing public-private partnerships (PPP) for road infrastructure projects in India. It identifies issues that have plagued PPP projects and affected their implementation. These include private sector companies bidding aggressively without considering risks, regulatory delays increasing costs, and banks tightening funding as projects faced delays meeting financial obligations. Suggestions are made to address these, such as establishing a single window for project clearances, creating a market to trade projects, revising toll pricing policies, and having backup parties involved in projects from the start.
CASE STUDY POLICY OF NITI AYOG SALIENT FEATURES,RECOMMENDATION HIGHWAY PROJECTSmit Patel
The document provides information about the Bharatmala Pariyojana highway project in India. It discusses that the project aims to develop 24,800 km of roads in Phase I at a cost of Rs. 3.85 lakh crore. This includes 9,000 km of economic corridors, 6,000 km of inter-corridor and feeder routes, 5,000 km for improving national corridor efficiency, 2,000 km of border and international connectivity roads, 2,000 km of coastal and port connectivity roads, and 800 km of greenfield expressways. The document further describes the components and selection criteria for each category under Phase I of the Bharatmala Pariyojana project
This document provides a technical report on village road construction in India. It discusses the historical development of rural roads, including policies and funding through various Five Year Plans. A key focus is the Pradhan Mantri Gram Sadak Yojana (PMGSY) program and Bharat Nirman initiative to provide connectivity to rural villages. The report analyzes achievements to date and makes recommendations to continue expanding rural road infrastructure in the 11th Five Year Plan and beyond, including the need for increased funding, maintenance, capacity building, and addressing environmental and social issues.
Impact of road extension project on the residents of ktmNabin Bhattarai
This report is the study of the impacts of road extension project on the residents of Kathmandu valley. The project was initiated by former prime minister Dr. Baburam Bhattarai. the project tremendously affected the living condition of people.
Industrial Summer Training Report at Construction Site of CPWD Alok Mishra
Construction of Police Station Khajuri Khas, Near Sonia Vihar, Delhi (SH: C/o Police Station Building, Electric sub Station & External Development Work i.e. Internal Electrical Installations)
Essential of Project Managemnet project metrobusAhmad Zeeshan
The 25.6-kilometer Peshawar Mor to New Islamabad Airport Metro Bus project has faced delays due to lack of funding. Only 25% of the required Rs. 4.57 billion was allocated in 2019-2020, leaving 60% of the project unfinished. Completion is now estimated for 2022 if annual funding increases. The project will reduce traffic and provide public transport to the new airport when finished.
The document is a curriculum vitae for an applicant applying for a Resident Engineer position focusing on roads. It summarizes the applicant's 18 years of experience in civil engineering and road construction project management. Key details include experience supervising road projects in India and Qatar valued between $600 million to $1.1 billion, managing teams of highway engineers, and ensuring compliance with construction standards and specifications. The applicant's qualifications include a bachelor's degree in civil engineering and experience overseeing the construction of highways, bridges, and other road infrastructure using techniques like rigid pavement construction.
1. Running head: FOUR LANING LUDHIANA-TALWANDI BHAI ROAD PROJECT 1
Research Paper
on
Four laning Ludhiana-Talwandi Bhai Road Project
Gurpartap Singh Toor
(N01193805)
Humber College
2. FOUR LANING LUDHIANA-TALWANDI BHAI ROAD PROJECT 2
Success and failure are two sides of a coin and there are number of factors which lead a
project to success or failure. This research paper discusses various socio-cultural and technical
factors that contributed to the failure Ludhiana-Talwandi Bhai four laning road project in the
state of Punjab, India.
Four laning of Ludhiana-Talwandi Bhai road was a government project with the main
purpose of widening the road from two lanes to four lanes and providing more efficient
transportation services. National Highways Authority of India (NHAI) was assigned with the
responsibility of completing the project.
There are various technical and sociocultural dimensions that play very important role in
success or failure of any project. The four laning project failed drastically because due
importance was not given to socio-technical dimensions and this research paper will discuss the
various sociocultural and technical dimensions of the project in detail.
Overview of Project
Four laning the National Highway-95 section from Ludhiana to Talwandi Bhai
commenced on March 26, 2012 and the scheduled date for completion was September 21, 2014.
Punjab government handed over the project to National Highways Authority of India (NHAI)
and rights of stretch were given to Essel Ludhiana Talwandi Toll Road Private Limited with
concession period of 29 years. Louis Berger Group Inc. USA in association with Louis Berger
Consulting Pvt. Ltd. India was hired as independent engineer and PAN India infrastructure Pvt.
Ltd. was assigned with responsibility of Engineering, Procurement, and Construction. The main
purpose of the four laning project was to widen the two lane section of Ludhiana-Talwandi Bhai
section of NH 95 to four lane divided carriageway and widening/constructing new bridges,
thirteen Box culverts and fifty-one Hume pipe culverts, ROBs, strengthening of exiting
3. FOUR LANING LUDHIANA-TALWANDI BHAI ROAD PROJECT 3
pavements, roadside drainage (Louis Berger Group Inc., 2014). The project also involved
compensation for acquisition of land for improvement of junctions and construction of Toll
Plaza.
The four laning project was initially awarded for Rs. 479 crores to National Highways
Authority of India (NHAI) but the total cost of the project was Rs. 735 crores from which Rs.
594 was spent on Engineering, Procurement, and Construction. Scheduled date to start
construction was September 21, 2012 and target dates for start of construction of bridges and
facilities were March 25 and September 26, 2013. The biggest risk associated with the project
was safety of the people and worker and disruption of traffic due to construction works.
The execution of the project was on tract as the first milestone to finish the construction
of highways on September 21, 2012 was achieved and the second milestone to finish
construction of bridges was also achieved on time but the third milestone to Finish construction
of facilities was not met. Last milestone was to complete the project on September 21, 2014, this
goal was also not achieved as only 53% of physical work was done.
The four laning project is still in the execution stage as the construction of facilities has
not been finished and roads and bridges are incomplete. New schedules have been prepared and
responsibilities are assigned to complete the project.
4. FOUR LANING LUDHIANA-TALWANDI BHAI ROAD PROJECT 4
Technical and Sociocultural Dimensions
Sociocultural Dimensions
National Highways Authority of India (NHAI) had to face many Sociocultural challenges
as the firm had to work with three other organizations, Essel Ludhiana Talwandi Toll Road
Private Limited, Louis Berger Group Inc. USA in association with Louis Berger Consulting Pvt.
Ltd. India and PAN India infrastructure Pvt. Ltd., and NHAI also had to report to the Punjab
government. Each of these organizations have different structures and cultures and these
differences pose great challenge in communication and problem solving. The leadership and
communication style between these organizations is shown in figure 1.
Figure 1
Any changes in budget had to be approved by the government of Punjab. Initial estimated
cost was Rs. 479 crores, but when the concessionaire (Essel Ludhiana Talwandi Toll Road
Private Limited) estimated the total project cost (735 crores), additional funds were provided by
National Highways Authority of India
Essel Ludhiana Talwandi
Toll Roads Pvt. Ltd.
Louis Berger Group, Inc in
Asso. With LBC Pvt. Ltd.-
USA
Pan Indian Networks Pvt.
Ltd.
EsselLudhiana Talwandi Toll Roads Pvt.
Ltd.
5. FOUR LANING LUDHIANA-TALWANDI BHAI ROAD PROJECT 5
the government of Punjab. Involvement of three other organizations made it really difficult to
implement solid means of problem solving, which led to incompletion of the project.
The deliverables of the projects were four lane road, bridges, facilities and flyovers and
the main purpose of the project was to provide effective and efficient transportation services
especially to commuters. Customer’s expectations were timely completion of bridges and
highways without any disturbance of traffic. Safety of the people and workers were also an
important part of the project.
Technical Dimensions
Technical dimensions of lane laning of NH-95 project are shown in table no.1.
Table No. 1
Technical Dimensions
Project
Objectives
o To widen the existing two-lane road to four-lane road.
o Strengthening/Constructing new twelve bridges, thirteen Box culverts and
fifty-one Hume pipe culverts.
o Building other facilities like Bus bays, Trucks lay byes vehicular
underpass, Toll plazas and Pedestrian underpass.
o Safety of people and construction workers during construction.
Project Cost Rs. 735 crores
Length of Project 910 days (March 26, 2012 to September 21, 2014)
Work Breakdown
Structure
Construction of Highways 10% of capital cost September 21, 2012
(180th day)
Construction of bridges and culverts 35% of capital cost March 25, 2013
(365th day)
Construction of the Facilities 70% of capital cost September 26, 2013
(550th day)
Scheduled date of completion 100% of capital
cost
September 21, 2014
(910th day)
6. Running head: FOUR LANING LUDHIANA-TALWANDI BHAI ROAD PROJECT 6
Analysis of Project Success or Failure
The Four laning Ludhiana-Talwandi Bhai project was a failure because all deliverables
were not delivered on the scheduled completion date of the project, September 21, 2014. There
were various factors led this project to failure and these factors are:
Inefficient Control: Punjab government did not exercise any control over the working of the
project and did not take any action when the third milestone (construction of facilities) was
not achieved. Top management control over the activities and support are very essential
sociocultural dimensions in any project. The government of Punjab did not take any strict
action when yearly progress was not schedule and this ignorance on the part of government
led to incompletion of the project.
Improper Planning and Finance management: Initial project cost estimate was Rs. 479
crores, but the concessionaire estimated the total cost to be Rs. 735 crores. National
Highways Authority of India (NHAI) did not plan any problem solving measure as it did not
take any immediate actions when varaha Infrastructure terminated their contract with PAN
India infrastructure Pvt. Ltd. because Rs. 50 crores were not paid and work was stopped from
October, 2013 to July, 2015 (Narula, 2016).
Corruption: Corruption was another responsible for failure of the project. According to the
letter wrote by authorities to chairman of Essel group highlighted that the concessionaire had
withdrawn Rs. 653 crores from the escrow account of project whereas only Rs. 278 crores
worth physical work was done (Seth, 2014). Corruption on the part of Essel group was
responsible for improper management of finance and proper allocation of funds is another
important technical dimension of any project.
7. FOUR LANING LUDHIANA-TALWANDI BHAI ROAD PROJECT 7
Failure to provide safety: Providing safety to the peoples during construction was also a
main objective of the project and it failed to achieve this objective as 88 accidents and 50
deaths were caused on the highway that passes through Moga district during construction.
(Seth, 2014).
Suggestions for improvement
First and foremost, Punjab government should exercise strict control over the government
projects and should closely overview the execution of the projects. Secondly, proper planning
and budget estimation are two key elements to the success of any project, so National Highways
Authority of India (NHAI) should spend more time on these factors. Thirdly, there are always
some risk associated with every project and therefore, National Highways Authority of India
(NHAI) should make contingency plans to avoid unnecessary stoppage of work, in case anything
goes wrong. Finally, corruption is a very serious issue and to ensure that the government funds
are utilized properly, government of Punjab should take stringent actions against those who are
accused of corruption.
Conclusion
Four laning Ludhiana-Talwandi Bhai project was a disaster because only half of estimated
physical work was done on the scheduled date of completion and ignorance on the part of
government, inadequate planning and budgeting and corruption played key roles in the failure of
the project. Understanding the various socio-technical dimension of the project and their impact
on success or failure of the project is very important in order to manage any project successfully.
Making contingency plans in case anything goes wrong, is essential to ensure uninterrupted
execution of the project.
8. FOUR LANING LUDHIANA-TALWANDI BHAI ROAD PROJECT 8
References
Louis Berger Group Inc. (2014, Sep 10). Monthly progress report for month of September 2014.
Retrived from
http://nhai.org.in/spw/IEReport/MPR%20for%20the%20month%20of%20September-
2014.pdf
Narula, P.S. (2016, Apr 18). Ludhiana-Talwandi Bhai four-laning project in limbo. Retrived from
http://www.hindustantimes.com/punjab/ludhiana-talwandi-bhai-four-laning-stuck-in-the-
middle/story-QBMJ7zMPTnDp7ZayMyxfQI.html
Seth, A. (2014, Dec 23). Ludhiana-Talwandi Bhai four-laning: Stuck in the middle. Retrived
from http://www.hindustantimes.com/punjab/ludhiana-talwandi-bhai-four-laning-stuck-
in-the-middle/story-QBMJ7zMPTnDp7ZayMyxfQI.html