The document outlines a workplan for a project with activities scheduled monthly from October to September. It details pre-implementation activities like preparation of documents, loan application, bidding and contracting. Implementation activities are listed as purchasing materials, constructing an intake box, reservoir, laying pump lines, building a dosing pump site and connecting pipelines. The final stage is the operation of bulk water supply.