JohnLopez,presidentof MeridianWaterPumps(asmall waterpumpproducer),washoldingameeting
withhisdepartmentmanagers.Theywere inthe processof planningproductionof medium-sized
pumpsof the next6 months. Mr. Lopeztoleratedsome of the arguingbefore he feltitnecessarytostop
the discussion asitwas goingso thathe coulddirectittoward a solution.A summaryof some of the
argumentsfollows:
Mary Welch,MarketingandSalesManager-“Mysalespeople are verygood,butgetveryfrustratedat
times.Several timeslastyearthe salespeoplespendlotsof theirtime tryingtocalmdownfrustrated
customers.Astheyare supposedtodo,the salespeople soldasmanyof these pumpsastheycould,yet
at timesthe productioncouldnotkeepupwiththe orders.Productionknowsthatwe have some
cyclicalityinthe demand;we have plentyof machine capacity.Theyshouldbe able tohire peopleso
that we can meetthe demandthatwe sell.Why can’ttheygettheirarea to work correctly?“
Frank Jackson,ProductionManager-“Come on,Mary,we know the salesare cyclical, butwe neverknow
exactlywhenthe cycles happen.Even if we did, the HRpeople alwaystake toolongtogetus the people
we need. Bythe time we get the newpeople hiredandtrained,the salesseemtodropagain.Whatam I
supposedtodo?If we keepthemandallow themtokeepproducingpumps,ourinventoryclimbsand
the finance people startyelling. Ican’tjust letthose new peoplesitarounddoingnothing.The only
otheralternative istolaythemoff,butthe HR people getreallyangry.”
ElizabethConrad,HumanResource MANAGER-“Youbetwe getangry.The productionpeople will
occasionallystartpushingustohurry and hire more people,yet getveryimpatient.Ittakestime togo
throughthe interviewprocessandgetpeoplehiredandorientedtoourbusiness.Thenwe nosooner
getthemon site and workingwhen production asksustolaythemoff.That isa real problemfortwo
reasons.First,there are costsinvolved.Ittakesanaverage of $100 to geta personhired,andother$100
to laythemoff.Secondly,those people thatwe hire andthenquicklylayoff tendtonotreturn.I can’t
blame,since fromtheirperspectiveitlookslike we have noideahow torunour business.Inaddition,as
those people complaintootherpeople aboutourtreatmentof them, ourreputationisgettingtolook
bad,and that makes itincreasinglydifficulttofindgoodpeople tohire .”
JosephWestern,Finance manager-“FrankiscorrectthatI getupsetwhenthe inventoryclimbs.Itcosts
us about$5 to keepone of these pumpsinour inventoryforamonth.That cost comesrightout of our
profit.Since myjobisto maximize profitability, Ican’tsitby and letthose inventorydollars shrinkthat
profitability.The same goesforall thathiringandlayoffs.Thatmoneyalsohurtsprofitability. Can’twe
do better?”
At thispointMr. Lopezstoppedthe discussion andsaid“Enoughof tryingto blame eachother.It isour
jobas managersto manage thisprocessmore effectively.Marketinghasjustcompleteda6-month
forecastof anticipateddemandforthisfamilyof pumps,andwe know frompasthistorythattheir
forecastsare prettygood. We shouldbe able tocome upwithan approach that we all can live andfocus
our effortstomeet.Let’sgetto workon it.”
Assignment: Assume you have been given the job to develop an effective approach to the problem. First,
here isthe forecastdevelopedbyMarketing:
Month 1 2 3 4 5 6
Forecasted Demand 600 750 1000 850 750 700
The productionmanagersaid there were currently50 unitesininventory,andtheywouldliketoendthe
6 monthswithonly25 in inventory.He alsoside thatcurrentlyeachworkerproducesanaverage of 25
pumpsinany givenmonth.These are currently20 workersinthe medium-size pumparea.
Question:
Usingthe data,developalevel productionplan.How muchextracost (inventoryandHR costs) are
involvedinthisplan?Whatadditionalcost(bothfinancial and nonfinancial) mightbe involvedwithsuch
a plan?
My answer:
Month 1 2 3 4 5 6
ForecastedDemand 600 750 1000 850 750 700
Productionplan 750 750 750 850 750 725
Planned Inventory(100
in stock)
250 250 0 0 0 25
Addedcost $2250 $1250 0 $400 $400 $225
Workers 30 30 30 34 30 29
1. Jan : hired additional 10workers addedcost $1000 + inventory250pcs*5=$1250 total :$2250
2. Feb: onlyinventorycost250pcs*5=$1250 total:$1250
3. Mar : no any addedcost
4. April:hiredadditional 4workersadded cost$100*4=$400. Total :$400
5. May : laidoff 4 workers=addedcost$400 inventory=0 total :$400
6. June : Laid off 1 worker=addedcost $ 100 inventory=25*5=$125(as required) total :$225
Total addedcost(6months):$4525
That is bestwayto keepproductionsmoothlyandlow cost.

More Related Content

Similar to Production planning with Labor cost

grow Thoughts Issue 2
grow Thoughts Issue 2grow Thoughts Issue 2
grow Thoughts Issue 2
anthony ryman
 
mipb 2 capacityplanning v05_print_sam
mipb 2 capacityplanning v05_print_sammipb 2 capacityplanning v05_print_sam
mipb 2 capacityplanning v05_print_sam
Jason Neale
 
S U C C E S S S T R A T E G I E S by John MautnerTen Princ.docx
S U C C E S S S T R A T E G I E S by John MautnerTen Princ.docxS U C C E S S S T R A T E G I E S by John MautnerTen Princ.docx
S U C C E S S S T R A T E G I E S by John MautnerTen Princ.docx
agnesdcarey33086
 
DF15 Startup Summit: Building a Killer Sales Team
DF15 Startup Summit: Building a Killer Sales TeamDF15 Startup Summit: Building a Killer Sales Team
DF15 Startup Summit: Building a Killer Sales Team
Mike Kreaden
 
How to become an entrepreneur - facing the top 25 challenges
How to become an entrepreneur - facing the top 25 challenges How to become an entrepreneur - facing the top 25 challenges
How to become an entrepreneur - facing the top 25 challenges
Prayukth K V
 
Covid19: are you ready for the change
Covid19: are you ready for the changeCovid19: are you ready for the change
Covid19: are you ready for the change
Mohammed Abdul-Awal
 
Management functions & behavior
Management functions & behaviorManagement functions & behavior
Management functions & behavior
amitymbaassignment
 
Are You In A Foxhole?
Are You In A Foxhole?Are You In A Foxhole?
Are You In A Foxhole?
Owner's Edge, LLC
 
Lean management
Lean managementLean management
Lean management
Agnieszka Bukowska
 
250 FMs Answer The Question…What Is Your Biggest FM Challenge?
250 FMs Answer The Question…What Is Your Biggest FM Challenge?250 FMs Answer The Question…What Is Your Biggest FM Challenge?
250 FMs Answer The Question…What Is Your Biggest FM Challenge?
iOFFICE Inc.
 
7 secrets to tells your career stories
7 secrets to tells your career stories7 secrets to tells your career stories
7 secrets to tells your career stories
jobguide247
 
Radical Management slides Steve Denning
Radical Management slides Steve DenningRadical Management slides Steve Denning
Radical Management slides Steve Denning
Steve Denning
 
Sales Manager Questions
Sales Manager QuestionsSales Manager Questions
Sales Manager Questions
SalesLoft
 
Modelling for decisions
Modelling for decisionsModelling for decisions
Modelling for decisions
coppeliamla
 
Managing difficult customers 2017
Managing difficult customers 2017Managing difficult customers 2017
Managing difficult customers 2017
Dr Yvonne Sum, CSP
 
Agile Methodology: It's Not Just for Software Developers
Agile Methodology: It's Not Just for Software DevelopersAgile Methodology: It's Not Just for Software Developers
Agile Methodology: It's Not Just for Software Developers
Tara Nesbitt
 
How to build startups
How to build startupsHow to build startups
How to build startups
nicolas Sassoli
 
3 BP Solar Shows how Fast 12 Final
3  BP Solar Shows how Fast 12 Final3  BP Solar Shows how Fast 12 Final
3 BP Solar Shows how Fast 12 Final
Paul Monus
 
White Paper Marketing During A Recession
White Paper Marketing During A RecessionWhite Paper Marketing During A Recession
White Paper Marketing During A Recession
Jon Newsome
 
How to Break Through No Man's Land - The Stage Where Growing Companies Get Stuck
How to Break Through No Man's Land - The Stage Where Growing Companies Get StuckHow to Break Through No Man's Land - The Stage Where Growing Companies Get Stuck
How to Break Through No Man's Land - The Stage Where Growing Companies Get Stuck
newportboardgroup
 

Similar to Production planning with Labor cost (20)

grow Thoughts Issue 2
grow Thoughts Issue 2grow Thoughts Issue 2
grow Thoughts Issue 2
 
mipb 2 capacityplanning v05_print_sam
mipb 2 capacityplanning v05_print_sammipb 2 capacityplanning v05_print_sam
mipb 2 capacityplanning v05_print_sam
 
S U C C E S S S T R A T E G I E S by John MautnerTen Princ.docx
S U C C E S S S T R A T E G I E S by John MautnerTen Princ.docxS U C C E S S S T R A T E G I E S by John MautnerTen Princ.docx
S U C C E S S S T R A T E G I E S by John MautnerTen Princ.docx
 
DF15 Startup Summit: Building a Killer Sales Team
DF15 Startup Summit: Building a Killer Sales TeamDF15 Startup Summit: Building a Killer Sales Team
DF15 Startup Summit: Building a Killer Sales Team
 
How to become an entrepreneur - facing the top 25 challenges
How to become an entrepreneur - facing the top 25 challenges How to become an entrepreneur - facing the top 25 challenges
How to become an entrepreneur - facing the top 25 challenges
 
Covid19: are you ready for the change
Covid19: are you ready for the changeCovid19: are you ready for the change
Covid19: are you ready for the change
 
Management functions & behavior
Management functions & behaviorManagement functions & behavior
Management functions & behavior
 
Are You In A Foxhole?
Are You In A Foxhole?Are You In A Foxhole?
Are You In A Foxhole?
 
Lean management
Lean managementLean management
Lean management
 
250 FMs Answer The Question…What Is Your Biggest FM Challenge?
250 FMs Answer The Question…What Is Your Biggest FM Challenge?250 FMs Answer The Question…What Is Your Biggest FM Challenge?
250 FMs Answer The Question…What Is Your Biggest FM Challenge?
 
7 secrets to tells your career stories
7 secrets to tells your career stories7 secrets to tells your career stories
7 secrets to tells your career stories
 
Radical Management slides Steve Denning
Radical Management slides Steve DenningRadical Management slides Steve Denning
Radical Management slides Steve Denning
 
Sales Manager Questions
Sales Manager QuestionsSales Manager Questions
Sales Manager Questions
 
Modelling for decisions
Modelling for decisionsModelling for decisions
Modelling for decisions
 
Managing difficult customers 2017
Managing difficult customers 2017Managing difficult customers 2017
Managing difficult customers 2017
 
Agile Methodology: It's Not Just for Software Developers
Agile Methodology: It's Not Just for Software DevelopersAgile Methodology: It's Not Just for Software Developers
Agile Methodology: It's Not Just for Software Developers
 
How to build startups
How to build startupsHow to build startups
How to build startups
 
3 BP Solar Shows how Fast 12 Final
3  BP Solar Shows how Fast 12 Final3  BP Solar Shows how Fast 12 Final
3 BP Solar Shows how Fast 12 Final
 
White Paper Marketing During A Recession
White Paper Marketing During A RecessionWhite Paper Marketing During A Recession
White Paper Marketing During A Recession
 
How to Break Through No Man's Land - The Stage Where Growing Companies Get Stuck
How to Break Through No Man's Land - The Stage Where Growing Companies Get StuckHow to Break Through No Man's Land - The Stage Where Growing Companies Get Stuck
How to Break Through No Man's Land - The Stage Where Growing Companies Get Stuck
 

Production planning with Labor cost

  • 1. JohnLopez,presidentof MeridianWaterPumps(asmall waterpumpproducer),washoldingameeting withhisdepartmentmanagers.Theywere inthe processof planningproductionof medium-sized pumpsof the next6 months. Mr. Lopeztoleratedsome of the arguingbefore he feltitnecessarytostop the discussion asitwas goingso thathe coulddirectittoward a solution.A summaryof some of the argumentsfollows: Mary Welch,MarketingandSalesManager-“Mysalespeople are verygood,butgetveryfrustratedat times.Several timeslastyearthe salespeoplespendlotsof theirtime tryingtocalmdownfrustrated customers.Astheyare supposedtodo,the salespeople soldasmanyof these pumpsastheycould,yet at timesthe productioncouldnotkeepupwiththe orders.Productionknowsthatwe have some cyclicalityinthe demand;we have plentyof machine capacity.Theyshouldbe able tohire peopleso that we can meetthe demandthatwe sell.Why can’ttheygettheirarea to work correctly?“ Frank Jackson,ProductionManager-“Come on,Mary,we know the salesare cyclical, butwe neverknow exactlywhenthe cycles happen.Even if we did, the HRpeople alwaystake toolongtogetus the people we need. Bythe time we get the newpeople hiredandtrained,the salesseemtodropagain.Whatam I supposedtodo?If we keepthemandallow themtokeepproducingpumps,ourinventoryclimbsand the finance people startyelling. Ican’tjust letthose new peoplesitarounddoingnothing.The only otheralternative istolaythemoff,butthe HR people getreallyangry.” ElizabethConrad,HumanResource MANAGER-“Youbetwe getangry.The productionpeople will occasionallystartpushingustohurry and hire more people,yet getveryimpatient.Ittakestime togo throughthe interviewprocessandgetpeoplehiredandorientedtoourbusiness.Thenwe nosooner getthemon site and workingwhen production asksustolaythemoff.That isa real problemfortwo reasons.First,there are costsinvolved.Ittakesanaverage of $100 to geta personhired,andother$100 to laythemoff.Secondly,those people thatwe hire andthenquicklylayoff tendtonotreturn.I can’t blame,since fromtheirperspectiveitlookslike we have noideahow torunour business.Inaddition,as those people complaintootherpeople aboutourtreatmentof them, ourreputationisgettingtolook bad,and that makes itincreasinglydifficulttofindgoodpeople tohire .” JosephWestern,Finance manager-“FrankiscorrectthatI getupsetwhenthe inventoryclimbs.Itcosts us about$5 to keepone of these pumpsinour inventoryforamonth.That cost comesrightout of our profit.Since myjobisto maximize profitability, Ican’tsitby and letthose inventorydollars shrinkthat profitability.The same goesforall thathiringandlayoffs.Thatmoneyalsohurtsprofitability. Can’twe do better?” At thispointMr. Lopezstoppedthe discussion andsaid“Enoughof tryingto blame eachother.It isour jobas managersto manage thisprocessmore effectively.Marketinghasjustcompleteda6-month forecastof anticipateddemandforthisfamilyof pumps,andwe know frompasthistorythattheir forecastsare prettygood. We shouldbe able tocome upwithan approach that we all can live andfocus our effortstomeet.Let’sgetto workon it.” Assignment: Assume you have been given the job to develop an effective approach to the problem. First, here isthe forecastdevelopedbyMarketing:
  • 2. Month 1 2 3 4 5 6 Forecasted Demand 600 750 1000 850 750 700 The productionmanagersaid there were currently50 unitesininventory,andtheywouldliketoendthe 6 monthswithonly25 in inventory.He alsoside thatcurrentlyeachworkerproducesanaverage of 25 pumpsinany givenmonth.These are currently20 workersinthe medium-size pumparea. Question: Usingthe data,developalevel productionplan.How muchextracost (inventoryandHR costs) are involvedinthisplan?Whatadditionalcost(bothfinancial and nonfinancial) mightbe involvedwithsuch a plan? My answer: Month 1 2 3 4 5 6 ForecastedDemand 600 750 1000 850 750 700 Productionplan 750 750 750 850 750 725 Planned Inventory(100 in stock) 250 250 0 0 0 25 Addedcost $2250 $1250 0 $400 $400 $225 Workers 30 30 30 34 30 29 1. Jan : hired additional 10workers addedcost $1000 + inventory250pcs*5=$1250 total :$2250 2. Feb: onlyinventorycost250pcs*5=$1250 total:$1250 3. Mar : no any addedcost 4. April:hiredadditional 4workersadded cost$100*4=$400. Total :$400 5. May : laidoff 4 workers=addedcost$400 inventory=0 total :$400 6. June : Laid off 1 worker=addedcost $ 100 inventory=25*5=$125(as required) total :$225 Total addedcost(6months):$4525 That is bestwayto keepproductionsmoothlyandlow cost.