The document discusses procurement and delivery methods for mega tunnel projects. Several governments have studied how to reduce infrastructure costs. Traditional procurement methods that use adversarial contracting and lowest price bidding were found to increase costs by around 10%. Alternative approaches recommended include early contractor involvement, relationship contracting with shared risk and reward, and selecting contractors based on value for money rather than just lowest price. Proper consultant selection focusing on experience rather than lowest cost is also important to avoid design errors and cost overruns.