This document summarizes Ihwan Suryadi's projects from 2013-2015 as a project engineer. It includes charts showing the annual value and quantity of equipment and facilities, as well as their regional deployment. Lists of projects are provided for each year, including location, title, timeline, cost, and status. Examples of individual projects are described in more detail with figures. The document concludes with an overview of Ihwan's performance plans for supporting maintenance, engineering, projects, and building relationships.
Herewith I enclosed my resume as a first step in exploring for possibilities of employment with your organization.
Greatly appreciate your time and consideration. I hope to meet with a favorable response.
Herewith I enclosed my resume as a first step in exploring for possibilities of employment with your organization.
Greatly appreciate your time and consideration. I hope to meet with a favorable response.
Over 20 years of Electrical Engineering Experience in Electrical and Instruments installation, QC and commissioning activities in various oil and gas and subsea projects.
Almost 5 years detailed experience working on hazardous area inspection and verification to meet ATEX, AS/NZS & IEC requirements.
Experience includes Construction, Inspection and Commissioning activities.
Dear All,
The Following is my Description.
I have more than 9 years’ experience in Welding Inspection. I have successfully completed my CSWIP 3.1 Welding Inspector training course in December 2011, which was held at The Welding Institute and passed the examination qualification. I Hold UT and RT ASNT level 2.
I graduated from Krisnadwipayana University Jakarta, major in Mechanical Engineering at 2002. I have successfully completed my Welding Inspector training course in 2004, which was held at the Institute for Research and Development of Material and Technical Product Industries (B4T) Bandung, and passed the examination qualification carried out by the Indonesian Welding Society based on the requirements of Indonesian Welding Society “Qualification and Certification on Welding Personnel.”
Regards,
Achmad Soewarso
Over 20 years of Electrical Engineering Experience in Electrical and Instruments installation, QC and commissioning activities in various oil and gas and subsea projects.
Almost 5 years detailed experience working on hazardous area inspection and verification to meet ATEX, AS/NZS & IEC requirements.
Experience includes Construction, Inspection and Commissioning activities.
Dear All,
The Following is my Description.
I have more than 9 years’ experience in Welding Inspection. I have successfully completed my CSWIP 3.1 Welding Inspector training course in December 2011, which was held at The Welding Institute and passed the examination qualification. I Hold UT and RT ASNT level 2.
I graduated from Krisnadwipayana University Jakarta, major in Mechanical Engineering at 2002. I have successfully completed my Welding Inspector training course in 2004, which was held at the Institute for Research and Development of Material and Technical Product Industries (B4T) Bandung, and passed the examination qualification carried out by the Indonesian Welding Society based on the requirements of Indonesian Welding Society “Qualification and Certification on Welding Personnel.”
Regards,
Achmad Soewarso
3. Chart of Annual Tasks
2013 2014 2015
Equipment $368,000.00 $214,800.00 $571,000.00
Facility $175,000.00 $218,000.00 $1,049,700.00
$368,000.00 $214,800.00
$571,000.00
$175,000.00
$218,000.00
$1,049,700.00
FACILITY & EQUIPMENT VALUE
2013
2014
2015
7
6
15
4 5 7
FACLITY & EQUIPMENT QTY
Equipment Facility
32%
18%
18%
14%
7% 11%
AREA DEPLOYMENT
East Indonesia Kalimantan
Sumatra Java
HO Mining
4. Project List 2013
NO AREA BRANCH TITLE START END COST CATEGORIES STATUS
1 East Indonesia Soroako Dyno control repair 2/16/2013 6/16/2013 $ 10,000.00 Equipment Done
2 Kalimantan Kariangau Grit blast asset transfer 2/20/2013 7/20/2013 $ 65,000.00 Facility Done
3 Sumatera Pekanbaru Dyno achor base replacement 3/4/2013 5/3/2013 $ 3,000.00 Equipment Done
4 East Indonesia Makassar Overlay Ashpalt 4/10/2013 7/9/2013 $ 45,000.00 Facility Done
5 East Indonesia Makassar Loading & unloading ramp 6/10/2013 9/8/2013 $ 15,000.00 Facility Done
6 Java BSD New Hose Reel 8/20/2013 11/18/2013 $ 90,000.00 Equipment Done
7 Java BSD
Dyno control upgrade include
control valve, penn valve, load cell &
rewiring cable
2/15/2013 7/15/2013 $ 25,000.00 Equipment Done
8 Kalimantan Kariangau
785 Rear Axle Group Remove &
Install Tool
6/20/2013 TBD $ 20,000.00 Equipment Cancelled
9 Kalimantan Kariangau
20 Tones Capacities Rotator
Welding Frame
9/24/2013 12/23/2013 $ 200,000.00 Equipment Cancelled
10 Kalimantan Kariangau Air Compressor Repair 9/29/2013 11/28/2013 $ 20,000.00 Equipment Done
11 East Indonesia Makassar New Concrete Yard 10/18/2013 1/16/2014 $ 50,000.00 Facility Cancelled
TOTAL $ 543,000.0543,000.00
5. NO AREA BRANCH TITLE START END COST CATEGORIES STATUS
1 Kalimantan Samarida Downdraft Table Fabrication 1/6/2014 5/6/2014 $ 3,800.00 Equipment Done
2 Mining Batu Hijau
Trakindo Engineering - Facility
Development
2/20/2014 TBD $ 130,000.00 Facility Cancelled
3 Sumatera Pekanbaru FIP Test Bench Repair 3/6/2014 7/4/2014 $ 6,000.00 Equipment Done
4 East Indonesia Makassar New Hose Room 3/10/2014 TBD $ 21,000.00 Facility Cancelled
5 East Indonesia Luwuk Part Counter Standard 3/15/2014 TBD $ 12,000.00 Facility Cancelled
6 East Indonesia Sorong
New Air Compressor 4.1 m3/hours
@10 bar
3/20/2014 TBD $ 15,000.00 Equipment Cancelled
7 East Indonesia Sorong Office Relayout 3/25/2014 6/23/2014 $ 30,000.00 Facility Done
8 East Indonesia Jayapura New Genset 22 kVA 6/20/2014 8/19/2014 $ 10,000.00 Equipment Done
9 Mining Kuala Kencana Dyno Upgrade to DX3012 9/24/2014 12/23/2014 $ 100,000.00 Equipment Done
10 HO SOS Jakarta Installation Piping for GC Machine 9/29/2014 11/28/2014 $ 10,000.00 Facility Done
11 Sumatera Palembang Dyno Room Upgrade 10/18/2014 1/16/2015 $ 95,000.00 Equipment Done
TOTAL $ 432,800.0
Project List 2014
432,800.00
6. NO AREA BRANCH TITLE START END COST CATEGORIES STATUS
1 Sumatera Palembang
Replacement Power Supply for
Dyno Control on SCC Module
1/5/2015 2/19/2015 $ 2,000.00 Equipment Done
2 Sumatera Palembang Dyno Configuration 1/16/2015 2/5/2015 $ 1,000.00 Equipment Done
3 Java BSD
Dyno Problem (load cell
replacment)
1/19/2015 2/18/2015 $ 1,500.00 Equipment Done
4 East Indonesia Soroako Telecomunication Tower 2/23/2015 TBD $ 15,000.00 Facility Waiting IO
5 Kalimantan
CRC
Samarinda
Downdraft table 1/5/2015 3/6/2015 $ 5,000.00 Equipment Done
6 Sumatera Palembang
Upgraded dyno control include PCI
card 6229, UPS & cable
3/23/2015 6/21/2015 $ 10,000.00 Equipment Done
7 Sumatera Pekanbaru Neoprene ball 3/24/2015 4/23/2015 $ 200.00 Equipment Done
8 East Indonesia Sorong Direction sign 3/31/2015 4/30/2015 $ 2,000.00 Facility Done
9 Mining Kuala Dyno Problem (repair FMU) 4/6/2015 4/16/2015 $ 6,000.00 Equipment Done
10 Java BSD
Dyno Problem (unstable control
valve)
4/17/2015 4/19/2015 $ 3,000.00 Equipment Done
11 HO HO Asset Dispose ex Jakarta Branch 4/20/2015 5/20/2015 $ 15,000.00 Facility Done
12 Kalimantan Balikpapan Rough Train Crane 60 Ton 6/5/2015 TBD $ 500,000.00 Equipment Waiting IO
13 Java Surabaya New Warehouse 6/10/2015 TBD $ 345,000.00 Facility Waiting IO
14 Sumatera Pekanbaru PM Platform for Multidocker 385 7/5/2015 TBD $ 200,000.00 Equipment Waiting IO
15 Mining Batu Hijau Welding Truck 8/5/2015 TBD $ 115,000.00 Equipment Waiting IO
16 East Indonesia Kendari Genset 13.5 kVA 9/10/2015 11/9/2015 $ 10,000.00 Equipment Waiting IO
17 HO HO Service Truck Standard 9/29/2015 12/28/2015 $ 10,000.00 Equipment Waiting IO
18 Mining Batu Hijau SOS Facility Upgrade 10/8/2015 1/6/2016 $ 90,000.00 Facility On Progres
19 Kalimantan Kariangau TUE Facility Upgrade 10/10/2015 3/8/2016 $ 230,000.00 Facility On Progres
20 East Indonesia Sorong Office Re-layout 11/30/2015 3/9/2016 $ 55,000.00 Facility Waiting PR
21 Java BSD Dyno Problem (repair FMU) 12/1/2015 12/2/2015 $ 1,000.00 Equipment Done
22 East Indonesia Soroako
Dyno Problem (load cell
replacment)
12/15/2015 3/14/2016 $ 4,000.00 Equipment Done
TOTAL $ 1,620,700.
Project List 2015
1,620,700.00
7. SOS LAB Facility Upgrade
Figure
Location : Batu Hijau
Cost : $90,000.-
Time Line : Oct 2015 – Mar 2016
Scope of Work : Lab room expansion, office re-layout, additional Lab equipment, fresh air
conditioning, mechanical & electrical works (piping lines, rack storage & electrical panel).
Obstacle : Different material standard between NNT and Trakindo
Vendor : PT TGTN
Current Condition On progress On progress
Project Description
8. Workshop Facilities Upgrade
Project Description
Figure
Location : Balikpapan
Cost : $230,000.-
Time Line : 6 Month
Scope of Work : Sub Structure, Crane Retrofit, Civil works (bollard, demarcation line,
compressor shelter, security post & fencing), Office Fit Out, Signage, Mechanical & Electrical
Works (piping lines, air compressor, safety equipment & electrical panel).
Vendor : TBD
Current Condition Plan Condition
9. Dyno Problem (Reparation Fuel
Measurement Unit)
Project Description
Figure
Location : Kuala Kencana Timika
Cost : $6,000.-
Time Line : Apr 2015
Scope of Work : Checked software configuration & DAQ hardware condition
Obstacle : While checked default cabling is wrong connected and one of cable is not
installed
Before Troubleshooting After
10. Multidocker 385 PM Platform
Project Description
Figure
Location : Pekanbaru
Cost : $200,000.-
Time Line :TBD
Scope of Work : Design, cost estimate and project control
Obstacle : PM activity should be provide, size of platform & lubrication equipment
Plan
11. Dyno Upgrade DX3010-DX3012
Project Description
Figure
Location : Kuala Kencana
Cost : $100,000.-
Time Line : Sept 2014
Scope of Work : Determine capacity of equipment, bill of material, installation, site
commissioning and testing
12. Dynamometer Systems
Data Acquisition & Control
Thermocouple
Speed sensor
Pressure sensor
Engine Cooling
Throttle
Control
Strain
gage
Engine
Control Valve
Universal
Joint Shaft
Analog Output
Analog Input
Absorbent
Selamat pagi bapak dan ibu
Terimakasih atas undangan interviewnya
Perkenalkan nama ihwan suryadi, umur saya 32 tahun, tinggal di depok, mempunyai 2 anak dan 1 wife
Sekarang saya bekerja di pt trakindo utama sebagai project engineer selama 5 tahun
Tugas saya adalah memage facility & equipment project, facility & equipment maintenace dan desain tool
Skope pekerjaan yang saya lakukan?
Survey, saya melakukan untuk mendapatkan menggali informasi dari kebutuhan projek
Desain, saya melakukan desain untuk menggambarkan kebutuhan projek. Desain yang dimaksud membuat gambar mekanikal, elektrikal dan juga kontruksi sipil
Estimasi biaya untuk mengetahui berapa besar biaya projek dengan menentukan jenis material, volume yang dibutuhkan, jenis peralatan dan skedule pekerjaan
Projek control, saya melakukan monitoring projek dengan meminta weekly report, site commissioning and testing sampai hand over
Maintenance, saya membuat program perawatan seperti preventive maintenance, SOP dan WIN
What is scope of work I do?
site survey, to dig information of project requirements
Design to describe of project requirements. The design included drawing of mechanical, electrical and also civil construction
Cost estimate to know how much cost of project by determine the type of material, the volume required, the type of equipment and work schedule
Project control, I did project monitoring by asking the weekly reports, site commissioning and testing until hand over
Maintenance, I did maintenance program such as preventive maintenance, SOP and WIN
Grafik pertama adalah menjelaskan jumlah projek dari facility dan equipment
Grafik kedua adalah menjelaskan penyebaran area projek
Grafik ketiga adalah menjelaskan nilai pojek dimulai pada tahun 2013 - 2015
These are Chart of annual tasks?
The first chart describes the number of products from the facility and equipment
-
The second graph is describing the deployment of the project area
Area deployment is divided into 6, east indonesia, kalimantan, sumatra, java, head office and mining
The third chart to explain the value of the project started in the year 2013 - 2015
Berikut list projek 2013
Total 11 projek dengan nilai $ 543,000
The following list of projects in 2013A total of 11 projects by a value of $ 543,000
Dan berikut list projek 2014
Total 11 projek dengan nilai $ 432,000
And the following list of projects in 2014A total of 11 projects with a value of $ 432,000
Kemudian berikut list projek 2015
Total 22 projek dengan nilai $ 1,620,700
Then follows a list of projects in 2015A total of 22 projects with a value of $ 1,620,700
Ada beberapa contoh projek yang telah saya kerjakan yaitu sebagai berikut:
Projek ini di lokasi Newmont, dibutuhkan karena ada penambahan peralatan lab dan safety issue menyenai udara di dalam ruangan terkontaminasi dengan chemical.
There are several examples of projects I have done is as follows:This project at the site of Newmont, is needed because there are additional lab equipment and safety issue menyenai indoor air contaminated with the chemical.
Selanjutnya:
Projek ini di lokasi Balikpapan, dibutuhkan karena ada pekerjaan machine rebuilt untuk off high truck yang dilakukan oleh departement trakindo engineering.
Next:This project at the site of Balikpapan, is needed because there is a job for the rebuilt machine off high truck carried by Trakindo engineering department.
Pekerjaan ini hampir sama dengan pekerjaan sebelumya yaitu melakukan troubleshooting dari cable connection.
Permasalahannya adalah tidak terbaca pada sistem konsumsi bahan bakar.
This work is almost the same as the previous job is to do the troubleshooting of cable connection.The problem is not legible on the system fuel consumption.
Desain platfom ini untuk melakukan pekerjaan PM. Ukuran platform yang tinggi dikarenakan excavator 385 digabung dengan multidocker frame. Tingginya sekitar 12 meter.
Penggunaan platform ini untuk industri kertas.
This ceiling design to do the job PM. Size due to the high platform combined with multidocker 385 excavator frame. Height of about 12 meters.The use of this platform for the paper industry.
Pekerjaan upgrade ini dibutuhkan dikarenakan terjadi keretakan shaft dyno dan kapasitas dyno perlu lebih besar untuk menyesuaikan pengujian engine besar.
This upgrade work is needed because the case rift shaft dyno and capacity needs to be larger to fit a large engine testing.
Dynamometer adalah untuk pengujian performan engine dengan cara mengatur kapasitas aliran air ke dalam housing absorbent.
Absorbent terdiri stator and rotor yang bisa membuat momentum gesekan air.
Gaya momentum tersebut dimanfaatkan untuk dihubungkan ke strain gage.
Data acquisition terdiri dari analog output dan analog output
Contoh analog input adalah seperti pressure sensor, temperature sensor, speed sensor dan strain gage.
Contoh analog output adalah seperti control valve control dan engine throttle control.
Semua parameter akan terbaca di layar desktop untuk mempermudah proses pengujian.
Dynamometer is for testing engine performance by regulating the capacity of water flow into the absorbent housing .
Absorbent consists of a stator and rotor that can be water friction momentum.The momentum force used to be connected to the strain gage.
Data acquisition consists of analog output and analog outputExamples of analog inputs such as pressure sensors, temperature sensors, speed sensors and strain gage.Examples of analog output such is the control valve control and engine throttle control.All parameters will be read on the desktop screen to simplify the testing process.
Sebelum saya bekerja di PT Trakindo, saya pernah bekerja sebagai design engineer di PT Ostenco.
Salah satu projek yang saya lakukan membuat gambar conveyor ingot.
Conveyor ingot terdiri dari motor, helical gear dan worm gear sebagai penggerak.
Furnace mengalirkan cairan aluminum ke rool distributor kemudian membagikan ke casting.
Casting membawa cairan aluminum ke ground water tank sampai ke ingot hammer.
Ingot hammer berfungsi untuk mempermudah melepaskan solid aluminum.
Ingot hammer bekerja dengan pergerakan mekanikal cam
Before I worked at PT Trakindo, I've worked as a design engineer at PT Ostenco.
One project that I did make the image ingot conveyor.
Conveyor ingot consists of a motor, helical gear and worm gear as the driving force.
Furnace drain the liquid aluminum to rool distributors then distribute to casting.
Casting aluminum carrying liquids into ground water tank up to the ingot hammer.
Ingot hammer serves to easy the release of solid aluminum.
Ingot hammer works with the mechanical movement of the cam
Relationship
Carry out interactive communicate with 2 way direction
Sharing product knowledge
Give professional services
Engineering
- Designing drive package of motor and gear box
Make engineering solution to handle costume design
Project
Create cost estimate to know project cost and for submitting quotation rate
Project control by handling installation, commissioning and testing
Maintenance
Create maintenance program such as PM, SOP and WIN
Conduct repair and troubleshooting
Support
Encourage sales to better profit include new unit purchase, installation serve and maintenance serve
Fast response service in 1day/24hour to reply inquires
Interview contains are:
Self introduction
Selling point
over 40 project was handled by me, and I’m agile operating design software and I believe can be professional engineer and sales product together with Voith
Weakness point
I’m not smart people so before I doing, I was preparing information and literature regarding problems solve.
I’m often annoyed if work yet has been done
Knowing what has become the company service
Voith is mechanical company and the product are hydropower, power transmission and paper machine
Solving problem
Knowing root cause of problem
Identified cause of problem
Find the way out to clear the problems
Why you suitable with our company
I have some experience which relevant of your requirement
I’m ready for handle multiple tasks and achieve your target / goal
How much salary do you want
Around 12 million rupiah, it is fair to me cause I have plan for education fund my children
Why you interesting joint
I exciting with Voith technology, since 18 century has began research & development and I think Vioth one of biggest mechanical company so I hope can joint
How long you will works
I’m typically loyal with company
As long the company pin fait to me
Reason moving other company
I look better income and advancing my engineering skill
Ambitions to achieve?
Within 3-4 years, I’m going to generate Voith product market share will increase. As project engineer I support technical and product sales.
Idea or strategies to this company?
- My idea to make good relationship between voith and costumer by sharing product knowledge, training class or even free inspection services
Conflict to superior
Iya saya pernah, ketika saya ada perbedaan pendapat dalam menyelesaikan masalah tapi dengan kesabaran dan waktu maka akan didapatkan solusi yang terbaik.
When you ready if you be accepted at Voith?
1 month after agreement by voith
Whether your colleague is not like you?
I believe in teamwork, but if anyone not like me then I would avoid it
How you work if under pressure?
Keep relaxed and I think patience and focus will help me to accomplish the task
Question to voith?
Who are the competitor of Voith?
How Voith do, can be survive at this moment that economic is still crisis?
When I begin joint at voith?
What kind facility project?
Facility project is a project that improvement, development and addition of office facilities and workshop facilities
What kind equipment project?
Equipment project is a project that maintenance, replacement and new purchases of workshop equipment and test bench equipment
Benefit & question
Transportation
Medical
Business trip allowance
Employment status
Education funds
Basic salary