Improving Focus and Predictability with Critical Chain Project Management
Joe Cooper, Senior Consultant, Allegient LLC

Abstract
Does it seem that projects in your organization require frequent firefighting where due dates are challenged and
heroics are necessary to get things done? Do projects often go from green to red overnight? Is team morale
suffering? Do you believe that your organization could flourish to new heights if this cycle were broken?
Lack of focus and inability to manage uncertainty are two significant causes of project delays, diminished quality,
excessive project durations, and low team spirit. By addressing these root causes, critical chain project management
(CCPM) techniques improve project speed, quality, on-time performance, and team morale.
Reducing nonproductive multitasking enables high-speed execution, high-quality deliverables, a greater sense of
accomplishment, and an increased capacity to think and to innovate for team members. It is significantly more
effective to prioritize and execute tasks sequentially rather than juggling many tasks on multiple projects
simultaneously. The end result is that even the lower priority tasks finish earlier.
Several leading global organizations, such as Eli Lilly (Lechleiter, 2009) and IBM (Ricketts & Dager, 2010), have
adopted CCPM solutions to significantly improve their project management results. Another such organization,
Mazda Motors, credits CCPM with a recent, major company turnaround (Ptak, 2013).

Problems associated with poor project performance
In order to implement effective solutions that improve project performance, it is important to identify the problems
and isolate the root causes. When the numbers of problems are many, it is vital to address the critical few that are
most impactful to achieving the organizational goal(s). One such problem on projects is that of low team morale.
When teams are not operating with passion, energy, enthusiasm, and full engagement, superior project execution is
not sustainable and delivery excellence is difficult to achieve.
Another significant problem worth addressing is on-time performance. When stakeholders expect predictable
delivery of project results, missing a delivery date can be costly in terms of perceived reliability and customer
satisfaction. Improving the frequency of on-time delivery can drastically increase the confidence stakeholders have
in an organization’s ability to deliver and the potential for a steady stream of additional opportunities.
Excessive project durations are another significant problem which impacts projects and oftentimes leads to
decreased return on investment (ROI) and opportunities lost to competitors. This paper explores each of these
project problems in greater detail to identify root causes and to uncover effective solutions.

High stress: Low team morale
When project team members are caught in the frenzy of all tasks being top priority, they quickly find themselves in
the middle of no-win situations. Any passion, excitement, and enthusiasm with which these project teams started is
quickly dissolved into a mindset of simply trying to survive. Project managers begin to fight for team members’
time in an attempt to do what is best for their own projects rather than focusing on what is best for their organization
and customers as a whole. Now, the loudest project manager gets the attention. Micromanaging, having more
meetings, producing more reports, and adding even more project details appear to be the only techniques that can
help. Unfortunately, these tactics deteriorate team morale even further.
When issues strike, project teams begin to focus on what is urgent at the moment and not what is important for the
greater good of the organization. When due dates start to slip, the competition for resource time intensifies to
unhealthy levels. Soon, the organization becomes one that values heroism to get things done. When heroism is
valued, everyone is driven to become the hero. Team members begin to work nights and weekends in an attempt to

© 2013, Joe Cooper
Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana

1
make up lost time and to get ahead. Eventually, everyone is focused on solving crises rather than executing
harmoniously according to plans and organizational goals. This situation is devastating to teamwork and
collaboration which is vital for delivery excellence. What levels of success can an organization achieve in this state?

Missed delivery dates: Late projects
For many product-based companies, being late to the market can cost millions of dollars in lost revenues. This is
especially true when fixed duration patents are involved. Additionally, marketing campaigns that are planning on a
specific launch date can face the high costs of modifying their marketing schedules when projects run past their
delivery dates. An organization that frequently misses their delivery commitments can also suffer negative impacts
to their financial potential and their reputation to customers, shareholders, and other stakeholders.
Conversely, an organization that consistently delivers on time or earlier can create a significant strategic advantage
over their competitors. This strategic advantage can catapult the organization into ever-flourishing status of highgrowth and high-stability. Steve Pryor, Engineering Director of Propulsion Structures and Systems at Spirit
AeroSystems stated in a 2012 PM Network article, "Any missed commitment erodes our credibility with customers.
Even more important is the internal cost for late engineering, which can force high overtime rates, supplier
expediting fees, rework and potential quality issues" (Fretty, 2012, p 52).

Excessive project durations: Reduced return on investment (ROI)
Most project managers are familiar with the situation where a project schedule appears to be significantly longer
than expected based on experience. It is often the case that organizations begin to spend money when projects start,
and they do not begin to make money or save money until projects complete. Therefore, it follows that reducing
project durations directly and significantly improves an organization’s ability to make a return on their investment.
Not only is delivering on-time important, but a company can reap the tremendous rewards of a market bonus, or
substantial additional profits, for each day of early delivery beyond what traditional methods allow (D. Daily,
personal communication, July 1, 2013). Additionally, having a consistent reputation of delivering on shorter lead
times than one’s competitors can play a role in helping to create a decisive competitive edge. This competitive
advantage can contribute to the ability to extend a mafia offer, an offer that customers cannot refuse, and an offer
that competitors cannot or will not match (Lang, 2010).

Causes to the problems associated with poor project performance
Addressing these problems themselves would be like merely treating the symptoms of an illness. Until the root
causes are understood and treated, the core of the problem can never be effectively eliminated. Investigations into
the problems associated with poor project performance begin to uncover root causes such as:







low-trust environments;
nonproductive multitasking which decreases productivity, negatively impacts team morale, and causes
missed due dates;
uncertainty in task estimates that are inadequately addressed;
student syndrome – waiting for the last possible moment to start a task – means that contingency is wasted
and risk is increased;
Parkinson’s Law – allowing work to expand to fill the time allotted – also wastes contingency and
increases risk;
having high amounts of work in progress can cause multitasking and firefighting which leads to low team
morale and extended project durations.

Low-trust environments
One of the causes of poor project performance is low trust environments. Low trust environments are often created
when team members do not feel they have a safe environment to surface issues quickly and transparently without the
fear of being blamed. When team members feel they need to hide issues from management, project performance

© 2013, Joe Cooper
Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana

2
can deteriorate significantly. Issue resolution can take much longer which can jeopardize delivery commitments,
cause project delays, increase stress, and decrease team morale.
In 2009 and early 2010, NASA Dryden Flight Research Center determined workforce morale as one major issue
which was blocking their ability to make significant improvements to their project delivery results. NASA decided
to implement critical chain project management (Horn, 2012). With regard to workforce morale, managers wanted
to address two items. First, they needed to be able to quickly get to the root cause of project issues. Second, they
needed to be able to control work in progress in order to create better project outcomes. However, team members
viewed the investigation of issues as punishment and the controlling of work in progress as micromanagement. It is
safe to say these perceptions, reality or not, were hindering the improvement of trust within the organization.
Management recognized the need to change their approach, and not the mindsets of their teams in order to improve
project performance (Horn, 2012).

Nonproductive multitasking
How much more successful could projects be if nonproductive multitasking could be minimized? A McKinsey
Quarterly article indicates that multitasking damages productivity, slows people down, hampers creativity, makes
employees anxious, and is addictive (Dean & Webb, 2011). Supporting these findings, a recent multitasking study
states, “multitasking makes people less productive, less creative, and more likely to get thrown off by distractions”
(Realization Technologies, Inc., 2013, ¶9). Multitasking can also be seen as a significant cause of extended project
durations as illustrated in Exhibit 1. If a project team member has three project tasks to complete, A, B, and C, it
can be seen that each task takes much longer to
complete when multitasking. Context switching
between tasks increases the completion times even
further and causes the project team members to have to
stop frequently to remember where they were each
Exhibit 1 – Nonproductive multitasking
time they switch to a different task.
Multitasking also causes additional stress on team members as they try to keep all of the plates spinning
simultaneously. The prolonged task durations diminish the sense of accomplishment team members feel when they
drive a task to completion. Once the tasks are eventually completed, any sense of accomplishment is replaced by
feelings of relief that the stressful multitasking of activities is finally over. The result is decreased morale and a
team member who feels more exhausted than excited to have completed their tasks. Additionally, if a problem
arises on one of the juggled tasks, delays can propagate among all of the tasks which can impact the on-time
performance of multiple projects. Therefore, all three project problems – low team morale, missed due dates, and
excessive project durations – can be caused by multitasking.

Uncertainty in task estimates
How much shorter could project schedules be if
team members were not fearful of using most likely
estimates? If team members are asked to provide a
task estimate, are they inclined to provide one that is
50% likely or one that is 95% likely? Most project
team members would provide the 95% likely
estimate (Walker, 2010). Exhibit 2 illustrates two
probability curves. The bell-shaped curve with a
long tail represents the probability density of task
duration. The “s” shaped curve is the cumulative
probability. A project task that is 95% likely is
typically two or more times the duration estimate of
the 50% likely estimate (Exhibit 2).

Exhibit 2 – Probability of task duration

According to Budd and Cerveny (2010), project task estimates are frequently taken as commitments. When team
members know their estimates will be viewed as time commitments, they will often add excessive hidden padding to

© 2013, Joe Cooper
Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana

3
the task completion date (Realization Technologies, Inc., 2010). Management, receiving pressure to reduce project
durations, will look to decrease task estimates in order to shorten project schedules. Team members, wise to what is
going on, will play the game and add even more padding to counter the actions of management. A missed estimate
equates to a missed commitment which can lead to unfavorable evaluations and sometimes demoralizing
punishment. It follows that this situation can also be a cause of low team morale.

Student syndrome: Waiting until the last possible moment to start a task
Student syndrome causes a significant waste of well-intended contingency. Most people have felt the effects of
student syndrome at some point in their lives. When there is more time to complete a task than is truly necessary, it
is typical that team members will wait until the last possible moment to begin (Blackstone, Cox, & Schleier, 2009).
Exhibit 3 illustrates the amount of effort applied over
time to complete a task. Very little effort is applied in
the early stage of the task even though there are no
factors preventing full focus (Goldratt, 1997).
The addition of excessive hidden padding in task
estimates creates the likelihood of a self-fulfilling
prophecy for task completion (Budd & Cerveny,
2010). If a task has an optimistic duration of two
days, a most-likely duration of five days, and a
pessimistic duration of 12 days (due to the long tail of
most tasks), many team members will provide a task
estimate in the upper end of the spectrum; one that has
Exhibit 3 – Student syndrome
95%+ probability of being achieved. For this
example, it is assumed the estimate provided is 12 days. The team member, knowing that the task will only take two
days if everything goes smoothly and will only take five days in most cases, is likely to wait until day six (or so)
until they become fully engaged. Most of the hidden padding, intended to protect the task from uncertainty, is now
wasted before the task even begins. If something unexpected occurs, there is no longer sufficient contingency to
prevent the task from being late (Exhibit 3). This late task impacts successor tasks which can cause an entire project
to be delayed. When student syndrome is present in an entire sequence of tasks, the damaging effects get multiplied.
A crisis situation is created, increasing stress and damaging team morale even further.

Parkinson’s Law: Work expands to fill the time allotted
When tasks have such significant padding built in, it seems possible that some tasks will finish early. That might be
a reasonable expectation if it were not for Parkinson’s Law. If a team member completes a task early, there is little
chance they will declare the task complete. Sometimes, this can be due to the tendency to improve or polish the
completed deliverable. Other times, it can be a result of a team member wanting to be viewed as a reliable estimator.
Declaring a task complete early can damage this reputation. Moreover, a team member who completes a task early
is likely to have their task durations cut even more the next time they provide an estimate (Newbold, 2013). If this
fear becomes a reality, trust is damaged further, and then let the games begin! The team member will add even more
padding next time to make up for the amount that is likely to be cut.

High work in progress in the project pipeline
Another significant cause to the problems associated with poor project performance is having too many projects in
the delivery pipeline. Are projects frequently started regardless of an organization’s capacity to complete the work?
The statement, “Well, it all has to get done!” might even be heard. Organizations can oftentimes be driven to get
projects started as early as possible, following the ill-fated logic that the earlier a project starts, the earlier it will
finish (Budd & Cerveny, 2010). However, when the capacity of the project delivery pipeline is not taken into
consideration, this well-intended tactic can have devastating effects on the system as a whole. Having too many
projects in the pipeline can slow the entire system down and drastically exacerbate the causes of poor project
performance. What might be a good strategy for activating projects within the project delivery pipeline? Do
projects ever get activated simply to keep everyone busy?
© 2013, Joe Cooper
Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana

4
Critical Chain unlocks a series of new paradigms
Critical chain project management (CCPM) is the project management application of the theory of constraints
(TOC). First introduced by Dr. Eli Goldratt (1997), critical chain has gained significant momentum in the project
community as a solution to the problems associated with poor project performance. CCPM takes resource
constraints into account for more realistic planning and focused execution. The critical chain is the resource-leveled
critical path. CCPM also utilizes pooled contingency to more effectively address the various components of project
uncertainty.
The first solution addressed in this discussion, creating environments of high-trust, is not formally a critical chain
solution. However, having significant trust within teams and across organizations is important when implementing
change (Budd & Cerveny, 2010). The end result of improved morale and quality of work life for team members is
more deliberately emphasized in the literature (Kishira, 2009). Of course, most operational managers, VPs, and
CxOs appreciate the positive effects of high trust in their organizations regardless of the strategies and tactics
utilized.
Additional CCPM solutions are as follows. Pipelining addresses the problems associated with having too much
work in progress. Full kitting addresses the problems associated with starting project tasks without the necessary
predecessor activities completed. To address wasted contingency, 50/50 task estimates are utilized. Executing with
focus, rather than multitasking, addresses elongated task durations, productivity losses due to context switching, and
the stress team members feel as they try to keep many plates spinning simultaneously. Lastly, project buffers
shorten project durations and protect critical project dates from uncertainty; significantly improving the
predictability of project delivery.
In an October 2009 speech, Eli Lilly and Company CEO Dr. John C. Lechleiter, announced the most sweeping
changes in company history, indicating three new competencies that are changing drug development at Lilly. One
of those competencies is critical chain project management. Dr. Lechleiter stated,
The COE is implementing a project management methodology called ‘Critical Chain’, developed by physicist
Eli Goldratt. Critical Chain was actually first applied at Lilly in a completely different context by our IT group.
They, in turn, helped our research labs launch a pilot program that has proved the power of Critical Chain in
drug development. Historically, across our pipeline, we have a 60% success rate in hitting milestones on time.
In other words, we miss almost half of our deadlines. In the Critical Chain pilot program, the success rate so far
is 100%. That’s why we’re now applying Critical Chain in force (Lechleiter, 2009, ¶38).
In a June 2013 keynote address to the Theory of Constraints International Certification Organization (TOCICO)
international conference in Bad Nauheim, Germany, Mr. Mitsuo Hitomi, Executive Officer from the Mazda Motor
Company spoke of a major company turn-around, and he credited critical chain and TOC (Ptak, 2013). Mr. Hitomi
presented remarkable results with an emphasis on employee harmony, improved quality of work life, and positive
financial results in 2013 after four fiscal years of operating in the red. Additionally, Mr. Hitomi indicated that
critical chain momentum grew and resulted in development project durations being cut in half with all projects
delivered with full scope and on time (Ptak, 2013). Echoing the sentiments of Dr. Goldratt himself, Mr. Hitomi
stated after the presentation, “Even the sky is not the limit” (Ptak, 2013, ¶6).

Creating environments of transparency and high-trust
Stephen M. R. Covey, author of The Speed of Trust (Covey & Merrill, 2008), states,
When trust is low, in a company or in a relationship, it places a hidden “tax” on every transaction: every
communication, every interaction, every strategy, every decision is taxed, bringing speed down and sending
costs up. My experience is that significant distrust doubles the cost of doing business and triples the time it
takes to get things done. By contrast, individuals and organizations that have earned and operate with high trust
experience the opposite of a tax -- a "dividend" that is like a performance multiplier, enabling them to succeed
in their communications, interactions, and decisions, and to move with incredible speed. A recent Watson
Wyatt study showed that high trust companies outperform low trust companies by nearly 300%! (p 21)
© 2013, Joe Cooper
Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana

5
Patrick Lencioni, author of The Five Dysfunctions of a Team (2002), indicates that absence of trust is a foundational
cause for team dysfunction. Yuji Kishira, in his book titled WA: Transformation by Harmony (2009; “WA” means
“harmony” in Japanese), emphasizes the superior results observed when organizations are able to optimize high-trust
within their environments and create true harmony within teams. In a PM Network article, Hunsberger (2012)
states, “The critical chain approach can provide much-needed relief for overloaded team members on a tight
deadline” (p 41). Another PM Network article states, “Spirit AeroSystems attributes critical chain project
management to a 50% reduction in employee overtime” (Fretty, 2012, p 55).
Overtime and stress can create tension among teams, which can lead teams down the path toward distrust and
disharmony. When trust is low, productivity can be drastically impacted. The CCPM approach requires a fair level
of trust between teams and management due to the nature of the transparency created. However, once teams begin
to adjust to the new paradigms, CCPM behaviors can become a driving force behind improving trust.

Pipelining: Limiting work in progress
Organizations that can successfully focus everyone’s attention on the few, critically important goals, rather than
getting pulled into the tyranny of the urgent, can create a significant strategic advantage over their competitors.
Organizations that are successful with this strategy can be a highly productive, harmonious, collaborative, and
innovative entity that operates within a sustainable, high-trust environment.
The critical need to streamline work in progress is to maximize the flow of projects through the delivery pipeline.
Local measures, such as how quickly a project gets started, are not valuable to the goals of the organization. Rather,
the throughput of the entire organization, global optimization, should be the focus. Most would agree that any
system is made up of bottlenecks and non-bottlenecks or constraints and non-constraints. If an organization
activates projects just to keep the non-constrained team members busy, critically constrained resources quickly
become over-allocated. Critically constrained resources are those who typically have the highest workload and the
fewest resource numbers. What impact might this action have on the flow of projects through the delivery pipeline?
Since CCPM is focused on optimizing globally, the critically constrained resources are identified and projects are
staggered in a way to keep these resources optimally loaded. Of course, if the critically constrained resources are
optimally loaded, the non-constraint resources will be less than optimally loaded; even idle! (Realization
Technologies, Inc., 2010) Granted, this flies in the face of conventional wisdom, but keep in mind, local
optimization does not lead to global optimization. In which of these are most organizations interested? Asked in a
different way, are organizations more concerned with strengthening the weakest link in the chain or the stronger
links in the chain? Now that critically constrained resources are optimally loaded and non-constrained resources
have capacity (i.e., to think, innovate, help others, train, take on unexpected work, etc.), significantly improved
throughput (or flow) within the organization is feasible.
This technique to limit the number of active projects is a key element of critical chain. Concentrating resources
on fewer projects at one time allows teams to focus and reduces multitasking. This not only allows projects to
be executed faster but creates capacity to undertake more initiatives (Fretty, 2012, p 52).

Full kitting
Making sure project team members have all of the necessary predecessor activities completed (full kit) prior to
starting their task ensures they have a greater chance to focus uninterrupted without having to be impacted by
potential upstream delays. Also, they are more likely to be able to drive their project tasks to completion with high
speed and high quality. The need to start, stop, and start again due to missing predecessors can significantly reduce
efficiency and productivity. “[The full kitting] approach requires having all the pieces in place prior to moving a
project work package forward. This step helps significantly reduce the number of second actions to complete a
single stage” (Fretty, 2012, p 52).

© 2013, Joe Cooper
Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana

6
50/50 task estimates, most likely estimates
Critical chain minimizes student syndrome, waiting until the last possible moment to start a task, and Parkinson’s
Law, work expanding to fill the time allotted, by eliminating the need for every team member to hoard safety in their
task estimates. As discussed previously, when team member’s estimates are turned into commitments, project task
estimates and entire project schedules can inflate drastically. Keeping in the spirit of optimizing globally rather than
locally, it is more important to focus on project delivery performance than task completion performance. When
management focus is shifted from on-time task completion to on-time project delivery, team members feel
empowered to get aggressive with their task estimates while still accounting for a reasonable amount of uncertainty.
Instead of using the traditional 95% likely pessimistic task estimates, 50/50 estimates, those that have a 50% chance
of finishing earlier and a 50% chance of finishing later, are provided during planning. The 50/50 estimates are also,
roughly, half of the duration of 95% estimates. Therefore, the project schedule is temporarily cut in half which is a
giant step in the right direction. However, even though the wasting of task contingency has been minimized and
team members have a renewed sense of enthusiasm with this safe, aggressive task goal, there is still a need to protect
the project commitment from unpredictable events.

Focusing on the task at hand rather than multitasking
With the environment of high-trust and transparency created, the project pipeline optimized for throughput, and
project tasks estimated with aggressive and achievable durations, projects are ready for optimized execution. This
requires team members to focus on the task at hand and to drive it to completion with high speed and high quality.
Allowing team members to focus on their tasks sequentially rather than multitasking is, counter intuitively, a very
effective solution to most organization’s need to do more with less. As is illustrated in Exhibit 4, significant
improvements can be made by allowing team members to focus on their tasks until completed. Conventional
wisdom might have team members work more hours
in order to get more work completed faster.
Oftentimes, this option is not sustainable and can take
a devastating toll on team morale and organizational
trust. When organizations begin to realize the
significant productivity improvements that can be
gained by simply reducing multitasking, a new level of
organizational performance can be achieved, creating
a decisive competitive edge over the competition.
Tactically, critical chain enables the concept of focus
by creating a relay race mindset among project team
members rather than utilizing rigid task scheduling
Exhibit 4 – Using focus rather than multitasking
and task deadlines. Once a task begins, the team
members drive the task to completion as quickly as possible with focus on appropriate quality and without fear of
calling out issues that need to be addressed. Some project teams even use relay race batons as a fun way to bring
visibility to the team members who are on the critical chain and who are focused on the task at hand. In a low trust
environment, being on the critical path might be intimidating and uncomfortable, but in a high-trust environment,
being on the critical chain can be a healthy challenge to be conquered.
At a recent conference, Dr. Reddy’s Laboratories shared some striking results. In just 12 weeks after taking focused
measures to sharply reduce its project team’s workload and reduce multitasking, the company's development group
completed 83% more projects than it had in the previous 12 weeks without adding any additional resources (Ziv,
2012).
As team members make progress on project tasks, they provide updates as to how much time they feel is left to
complete their work. This information is used to communicate to the next team member who will take the baton
handoff as soon as it is ready. Also, the remaining time to complete the task is used to determine if any time beyond
the original 50/50 estimate will be needed. If the task is running late, due to unforeseen circumstances, a mechanism

© 2013, Joe Cooper
Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana

7
is needed to prevent an impact to the project delivery. It is not necessary to be concerned with on-time completion
of individual tasks. Rather, it is more important to focus on project on-time performance. The mechanism used to
protect the project delivery commitment is the project buffer.

Buffering for uncertainty
With the project planned using 50/50 task estimates, a decrease of approximately 50% of the overall project duration
is expected. This padding was removed from the
individual tasks (Exhibit 5) in order to prevent it from
being wasted by behaviors associated with student
syndrome and Parkinson’s Law. However, there is still
a need to have some amount of contingency to protect
the project delivery from uncertainty. A portion of the
contingency removed from critical chain tasks,
approximately 50%, is added back to the project
schedule as a pooled contingency, which acts like a
Exhibit 5 – Protecting the project commitment
shock absorber to protect the project delivery
commitment (Exhibit 5). Projects are typically planned
to complete 25% faster while protected by a buffer that absorbs project task variations (Fretty, 2012; Leach, 2011).
This pooled contingency, which is used by everyone on the project team, creates a very interesting, healthy dynamic
for project success. No longer do team members need to feel alone to protect themselves from unpredictable events
(risks). Rather, the entire team is motivated and driven to be successful together. If one team member needs
additional time due to unforeseen circumstances, they
are able to consume a portion of the project buffer. If
another team member completes a task early, they
add their time to help replenish the buffer. The use of
a centralized and transparent project buffer allows for
shorter project durations, improved on-time
performance, and healthier team morale. A word of
caution, testing is not a buffer.
A buffer consumption chart (Exhibit 6) is an
objective, leading indicator of project health and is
kept visible for all to see. The number of days of
work left on the project compared with the number of
days of buffer remaining provides an indication of
how likely a team is to complete their project onExhibit 6 – Buffer consumption chart
time. If the buffer is in the green territory, a team
will continue as planned and managers are not
required to interrupt team members to search for issues. If the project buffer reaches yellow, buffer recovery plans
are made just in case it becomes necessary. If the buffer
penetrates the red area, buffer recovery plans are executed.
Recovery can include any techniques associated with
crashing a project network.
With a buffer consumption chart, all team members,
sponsors, and other stakeholders are informed of the health
of the project at all times. Additionally, reasons for buffer
consumption are documented so that continuous
improvements can be made to the project execution and
delivery system.

Exhibit 7 – Multi-project buffer chart
A similar chart can be used to bring transparency to the health of all projects in a program or portfolio. Exhibit 7
displays a buffer consumption chart that can be used in a multi-project environment to display the duration of work
remaining versus the amount of buffer remaining for each individual project.
© 2013, Joe Cooper
Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana

8
Conclusions
Organizations observe numerous project problems within their environments daily. Some of the most impactful are
team morale, missed project commitments, and excessive project durations. It is important to identify root causes
and not just treat the symptoms of these problems. Root causes include having too much work in progress,
environments of low-trust, multitasking rather than focusing, and wasted contingency at the task level due to student
syndrome and Parkinson’s Law. Critical chain targets these causes by streamlining the number of projects in the
pipeline for maximized throughput and flow, creating an environment of high-trust which allows team members to
get aggressive with task estimates and to call out issues without fear of blame, and by creating an effective
contingency mechanism, a project buffer used by the team, that is an objective and transparent leading indicator of
project health.
The results demonstrated by organizations who have systemically embraced CCPM are impressive. Teams enjoy a
sense of accomplishment as they operate with high focus and with harmony. On-time delivery becomes increasingly
more predictable and on-time performance can improve from 30-60% to 90%+. Project durations can be cut by 25%
or more without sacrificing scope, quality, or team members’ lives outside the workplace.

© 2013, Joe Cooper
Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana

9
References
Blackstone, J. H., Jr., Cox, J. F., III, & Schleier, J. G., Jr. (2009). A tutorial on project management from a theory of
constraints perspective. International Journal of Production Research, 47(24), 7029-7046.
http://dx.doi.org/10.1080/00207540802392551
Budd, C. S., & Cerveny, J. (2010). A critical chain project management primer. In J. Cox III & J. Schleir, Jr. (Eds.),
Theory of Constraints Handbook (pp. 45-77). New York, NY: McGraw Hill.
Covey, S. M. R. & Merrill, R. R. (2008). The speed of trust: The one thing that changes everything. New York, NY:
Free Press.
Dean, D. & Webb, C. (2011, January). Recovering from information overload. McKinsey Quarterly [Electronic
Version] Retrieved on 17 August 2013 from
http://www.mckinsey.com/insights/organization/recovering_from_information_overload
Fretty, P. (2012). Change is in the air. PM Network, 26(2), 50-55.
Goldratt, E. M. (1997). Critical chain. Great Barrington, MA: North River Press.
Horn, T. J. (2012). Changing the project execution culture at NASA Dryden. Ask Magazine [Electronic Version]
Retrieved on 23 March 2013 from
http://www.nasa.gov/offices/oce/appel/ask/issues/48/48i_project_execution_culture.html
Hunsberger, K. (2012). Chain reactions. PM Network, 26(1), 40-43.
Kishira, Y. (2009). WA: transformation management by harmony. Great Barrington, MA: North River Press.
Lang, L. (2010). Mafia offers: Dealing with a market constraint. In J. Cox III & J. Schleir, Jr. (Eds.), Theory of
Constraints Handbook (pp. 603-628). New York, NY: McGraw Hill.
Leach, L. P. (2011). Buffers: Key to project schedule success. PM World Today, XIII(X), 9-11.
Lechleiter, J. C. (2009, October). Reinventing invention: Fixing the engine of biopharmaceutical innovation. Eli
Lilly CEO speech, San Diego, CA, USA. Retrieved on 26 July 2013 from
http://www.lilly.com/news/speeches/Pages/091030.aspx
Lencioni, P. (2002). The five dysfunctions of a team: A leadership fable. San Francisco, CA: Jossy-Bass.
Newbold, R. (2013). The tyranny of deadlines. Retrieved on 24 August 2013 from
http://www.prochain.com/pm/articles/Tyranny_of_Deadlines.pdf

© 2013, Joe Cooper
Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana

10
Ptak, C. (2013). Mazda executive credits theory of constraints for company turnaround. Retrieved on 26 July 2013
from http://www.pr.com/press-release/495307
Realization Technologies, Inc. (2010). Getting durable results with critical chain – A field report. In J. Cox III & J.
Schleir, Jr. (Eds.), Theory of Constraints Handbook (pp. 79-100). New York, NY: McGraw-Hill.
Realization Technologies, Inc. (2013). The effects of multitasking on organizations. Retrieved on 29 August 2013
from http://www.realization.com/the-effects-of-multitasking-on-organizations
Ricketts, J.A., & Dager, J. (2010, September 15). Using the theory of constraints in services [Transcript of audio
podcast]. Retrieved on 12 July 2013 from http://www.docstoc.com/docs/54701354/Using-TOC-in-Services
Walker, E. (2010). The problems with project management. In J. Cox III & J. Schleir, Jr. (Eds.), Theory of
Constraints Handbook (pp. 13-44). New York, NY: McGraw-Hill.
Ziv, Y. (2012). Less is more. TCE: The Chemical Engineer, (851), 40-41.

© 2013, Joe Cooper
Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana

11

More Related Content

What's hot

Managing Dependencies
Managing DependenciesManaging Dependencies
Managing DependenciesJohn Phillips
 
TwoMinute Performance Management- 011916
TwoMinute Performance Management-  011916TwoMinute Performance Management-  011916
TwoMinute Performance Management- 011916Bill Schreiner
 
Why Projects Fail + Four Steps to Succeed
Why Projects Fail + Four Steps to SucceedWhy Projects Fail + Four Steps to Succeed
Why Projects Fail + Four Steps to SucceedKevin Wordon
 
Program Management - Top Down-Bottom Up
Program Management - Top Down-Bottom UpProgram Management - Top Down-Bottom Up
Program Management - Top Down-Bottom UpRNC
 
Project Management case analysis
Project Management case analysisProject Management case analysis
Project Management case analysisWakas Khalid
 
Why Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsWhy Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsMichael Krigsman
 
Collaboration Proposel
Collaboration ProposelCollaboration Proposel
Collaboration ProposelCLse
 
Presentation by prameela kumar
Presentation by prameela kumarPresentation by prameela kumar
Presentation by prameela kumarPMI_IREP_TP
 
Spa - Systemic Project Alignment
Spa - Systemic Project AlignmentSpa - Systemic Project Alignment
Spa - Systemic Project AlignmentDaniel Ofek
 
Mangement assignment 2
Mangement assignment 2Mangement assignment 2
Mangement assignment 2Tomcully18
 
Five Big Ideas For Proj Delivery
Five Big Ideas For Proj DeliveryFive Big Ideas For Proj Delivery
Five Big Ideas For Proj Deliverysundong
 
Presentation by somdatta banerjee
Presentation by somdatta banerjeePresentation by somdatta banerjee
Presentation by somdatta banerjeePMI_IREP_TP
 
Ey prm-predicting-project-risks
Ey prm-predicting-project-risksEy prm-predicting-project-risks
Ey prm-predicting-project-risksdrrb1331
 
Dependency Management In A Large Agile Environment
Dependency Management In A Large Agile EnvironmentDependency Management In A Large Agile Environment
Dependency Management In A Large Agile EnvironmentSteve Greene
 

What's hot (20)

Managing Dependencies
Managing DependenciesManaging Dependencies
Managing Dependencies
 
LPM5
LPM5LPM5
LPM5
 
TwoMinute Performance Management- 011916
TwoMinute Performance Management-  011916TwoMinute Performance Management-  011916
TwoMinute Performance Management- 011916
 
Why Projects Fail + Four Steps to Succeed
Why Projects Fail + Four Steps to SucceedWhy Projects Fail + Four Steps to Succeed
Why Projects Fail + Four Steps to Succeed
 
SecretSocietyofTransformationalLeadership
SecretSocietyofTransformationalLeadershipSecretSocietyofTransformationalLeadership
SecretSocietyofTransformationalLeadership
 
Program Management - Top Down-Bottom Up
Program Management - Top Down-Bottom UpProgram Management - Top Down-Bottom Up
Program Management - Top Down-Bottom Up
 
Project Management case analysis
Project Management case analysisProject Management case analysis
Project Management case analysis
 
Iss 02
Iss 02Iss 02
Iss 02
 
Why Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsWhy Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and Solutions
 
Collaboration Proposel
Collaboration ProposelCollaboration Proposel
Collaboration Proposel
 
PMC4
PMC4PMC4
PMC4
 
Is project failure
Is project failureIs project failure
Is project failure
 
Presentation by prameela kumar
Presentation by prameela kumarPresentation by prameela kumar
Presentation by prameela kumar
 
Spa - Systemic Project Alignment
Spa - Systemic Project AlignmentSpa - Systemic Project Alignment
Spa - Systemic Project Alignment
 
ETCA_1
ETCA_1ETCA_1
ETCA_1
 
Mangement assignment 2
Mangement assignment 2Mangement assignment 2
Mangement assignment 2
 
Five Big Ideas For Proj Delivery
Five Big Ideas For Proj DeliveryFive Big Ideas For Proj Delivery
Five Big Ideas For Proj Delivery
 
Presentation by somdatta banerjee
Presentation by somdatta banerjeePresentation by somdatta banerjee
Presentation by somdatta banerjee
 
Ey prm-predicting-project-risks
Ey prm-predicting-project-risksEy prm-predicting-project-risks
Ey prm-predicting-project-risks
 
Dependency Management In A Large Agile Environment
Dependency Management In A Large Agile EnvironmentDependency Management In A Large Agile Environment
Dependency Management In A Large Agile Environment
 

Similar to Improving Focus, Predictability, and Team Morale on Projects

Dilemmas in Contemporary Project Management - By Karina Rozario Varu
Dilemmas in Contemporary Project Management - By Karina Rozario VaruDilemmas in Contemporary Project Management - By Karina Rozario Varu
Dilemmas in Contemporary Project Management - By Karina Rozario VaruKarina Rozario Varu
 
2 days agoShravani Kasturi DiscussionCOLLAPSETop of Form.docx
2 days agoShravani Kasturi DiscussionCOLLAPSETop of Form.docx2 days agoShravani Kasturi DiscussionCOLLAPSETop of Form.docx
2 days agoShravani Kasturi DiscussionCOLLAPSETop of Form.docxherminaprocter
 
Introduction Termination of a project is inevitable, but how it .pdf
Introduction Termination of a project is inevitable, but how it .pdfIntroduction Termination of a project is inevitable, but how it .pdf
Introduction Termination of a project is inevitable, but how it .pdfanuragperipheral
 
Recommendation and Implementation.docx
Recommendation and Implementation.docxRecommendation and Implementation.docx
Recommendation and Implementation.docxwrite4
 
CHAPTER 2 Strategic Management and Project SelectionMore and m.docx
CHAPTER 2 Strategic Management and Project SelectionMore and m.docxCHAPTER 2 Strategic Management and Project SelectionMore and m.docx
CHAPTER 2 Strategic Management and Project SelectionMore and m.docxcravennichole326
 
The Value PMLC Process Capability
The Value PMLC Process CapabilityThe Value PMLC Process Capability
The Value PMLC Process CapabilityBill Monroe
 
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...Mr.Allah Dad Khan
 
1Running Head Leading and Managing HR Project7Leading a.docx
1Running Head Leading and Managing HR Project7Leading a.docx1Running Head Leading and Managing HR Project7Leading a.docx
1Running Head Leading and Managing HR Project7Leading a.docxdrennanmicah
 
Why projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsWhy projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsTa Ngoc
 
FusionPoint: 11 signs your marketing analytic project may be in trouble
FusionPoint: 11 signs your marketing analytic project may be in troubleFusionPoint: 11 signs your marketing analytic project may be in trouble
FusionPoint: 11 signs your marketing analytic project may be in troubleBob Wyman
 
Top 10 project mgt. problems
Top 10 project mgt. problemsTop 10 project mgt. problems
Top 10 project mgt. problemsMaksudul Munna
 
4. the project in the organizational structure
4. the project in the organizational structure4. the project in the organizational structure
4. the project in the organizational structureJeanette C. Patindol
 
Reasons for project failure
Reasons for project failureReasons for project failure
Reasons for project failureDavid Tennant
 
importance of resources allocation in formal method of software engineering ...
 importance of resources allocation in formal method of software engineering ... importance of resources allocation in formal method of software engineering ...
importance of resources allocation in formal method of software engineering ...Abdul Naqashbandi
 
How to Solve Top Project Management Challenges
How to Solve Top Project Management ChallengesHow to Solve Top Project Management Challenges
How to Solve Top Project Management ChallengesOrangescrum
 
MGT323 SEUMid
MGT323 SEUMidMGT323 SEUMid
MGT323 SEUMidJammyDe
 

Similar to Improving Focus, Predictability, and Team Morale on Projects (20)

Dilemmas in Contemporary Project Management - By Karina Rozario Varu
Dilemmas in Contemporary Project Management - By Karina Rozario VaruDilemmas in Contemporary Project Management - By Karina Rozario Varu
Dilemmas in Contemporary Project Management - By Karina Rozario Varu
 
2 days agoShravani Kasturi DiscussionCOLLAPSETop of Form.docx
2 days agoShravani Kasturi DiscussionCOLLAPSETop of Form.docx2 days agoShravani Kasturi DiscussionCOLLAPSETop of Form.docx
2 days agoShravani Kasturi DiscussionCOLLAPSETop of Form.docx
 
Introduction Termination of a project is inevitable, but how it .pdf
Introduction Termination of a project is inevitable, but how it .pdfIntroduction Termination of a project is inevitable, but how it .pdf
Introduction Termination of a project is inevitable, but how it .pdf
 
Recommendation and Implementation.docx
Recommendation and Implementation.docxRecommendation and Implementation.docx
Recommendation and Implementation.docx
 
Success and failure in
Success and failure inSuccess and failure in
Success and failure in
 
CHAPTER 2 Strategic Management and Project SelectionMore and m.docx
CHAPTER 2 Strategic Management and Project SelectionMore and m.docxCHAPTER 2 Strategic Management and Project SelectionMore and m.docx
CHAPTER 2 Strategic Management and Project SelectionMore and m.docx
 
The Value PMLC Process Capability
The Value PMLC Process CapabilityThe Value PMLC Process Capability
The Value PMLC Process Capability
 
Risk managementorrussianroulette -whitepaper_16
Risk managementorrussianroulette -whitepaper_16Risk managementorrussianroulette -whitepaper_16
Risk managementorrussianroulette -whitepaper_16
 
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
 
1Running Head Leading and Managing HR Project7Leading a.docx
1Running Head Leading and Managing HR Project7Leading a.docx1Running Head Leading and Managing HR Project7Leading a.docx
1Running Head Leading and Managing HR Project7Leading a.docx
 
Succes and failures in od
Succes and failures in odSucces and failures in od
Succes and failures in od
 
Why projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsWhy projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfalls
 
FusionPoint: 11 signs your marketing analytic project may be in trouble
FusionPoint: 11 signs your marketing analytic project may be in troubleFusionPoint: 11 signs your marketing analytic project may be in trouble
FusionPoint: 11 signs your marketing analytic project may be in trouble
 
Top 10 project mgt. problems
Top 10 project mgt. problemsTop 10 project mgt. problems
Top 10 project mgt. problems
 
4. the project in the organizational structure
4. the project in the organizational structure4. the project in the organizational structure
4. the project in the organizational structure
 
Reasons for project failure
Reasons for project failureReasons for project failure
Reasons for project failure
 
importance of resources allocation in formal method of software engineering ...
 importance of resources allocation in formal method of software engineering ... importance of resources allocation in formal method of software engineering ...
importance of resources allocation in formal method of software engineering ...
 
How to Solve Top Project Management Challenges
How to Solve Top Project Management ChallengesHow to Solve Top Project Management Challenges
How to Solve Top Project Management Challenges
 
MGT323 SEUMid
MGT323 SEUMidMGT323 SEUMid
MGT323 SEUMid
 
L 63 Article Successful PM
L 63 Article Successful PML 63 Article Successful PM
L 63 Article Successful PM
 

Recently uploaded

0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...lizamodels9
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 

Recently uploaded (20)

0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 

Improving Focus, Predictability, and Team Morale on Projects

  • 1. Improving Focus and Predictability with Critical Chain Project Management Joe Cooper, Senior Consultant, Allegient LLC Abstract Does it seem that projects in your organization require frequent firefighting where due dates are challenged and heroics are necessary to get things done? Do projects often go from green to red overnight? Is team morale suffering? Do you believe that your organization could flourish to new heights if this cycle were broken? Lack of focus and inability to manage uncertainty are two significant causes of project delays, diminished quality, excessive project durations, and low team spirit. By addressing these root causes, critical chain project management (CCPM) techniques improve project speed, quality, on-time performance, and team morale. Reducing nonproductive multitasking enables high-speed execution, high-quality deliverables, a greater sense of accomplishment, and an increased capacity to think and to innovate for team members. It is significantly more effective to prioritize and execute tasks sequentially rather than juggling many tasks on multiple projects simultaneously. The end result is that even the lower priority tasks finish earlier. Several leading global organizations, such as Eli Lilly (Lechleiter, 2009) and IBM (Ricketts & Dager, 2010), have adopted CCPM solutions to significantly improve their project management results. Another such organization, Mazda Motors, credits CCPM with a recent, major company turnaround (Ptak, 2013). Problems associated with poor project performance In order to implement effective solutions that improve project performance, it is important to identify the problems and isolate the root causes. When the numbers of problems are many, it is vital to address the critical few that are most impactful to achieving the organizational goal(s). One such problem on projects is that of low team morale. When teams are not operating with passion, energy, enthusiasm, and full engagement, superior project execution is not sustainable and delivery excellence is difficult to achieve. Another significant problem worth addressing is on-time performance. When stakeholders expect predictable delivery of project results, missing a delivery date can be costly in terms of perceived reliability and customer satisfaction. Improving the frequency of on-time delivery can drastically increase the confidence stakeholders have in an organization’s ability to deliver and the potential for a steady stream of additional opportunities. Excessive project durations are another significant problem which impacts projects and oftentimes leads to decreased return on investment (ROI) and opportunities lost to competitors. This paper explores each of these project problems in greater detail to identify root causes and to uncover effective solutions. High stress: Low team morale When project team members are caught in the frenzy of all tasks being top priority, they quickly find themselves in the middle of no-win situations. Any passion, excitement, and enthusiasm with which these project teams started is quickly dissolved into a mindset of simply trying to survive. Project managers begin to fight for team members’ time in an attempt to do what is best for their own projects rather than focusing on what is best for their organization and customers as a whole. Now, the loudest project manager gets the attention. Micromanaging, having more meetings, producing more reports, and adding even more project details appear to be the only techniques that can help. Unfortunately, these tactics deteriorate team morale even further. When issues strike, project teams begin to focus on what is urgent at the moment and not what is important for the greater good of the organization. When due dates start to slip, the competition for resource time intensifies to unhealthy levels. Soon, the organization becomes one that values heroism to get things done. When heroism is valued, everyone is driven to become the hero. Team members begin to work nights and weekends in an attempt to © 2013, Joe Cooper Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana 1
  • 2. make up lost time and to get ahead. Eventually, everyone is focused on solving crises rather than executing harmoniously according to plans and organizational goals. This situation is devastating to teamwork and collaboration which is vital for delivery excellence. What levels of success can an organization achieve in this state? Missed delivery dates: Late projects For many product-based companies, being late to the market can cost millions of dollars in lost revenues. This is especially true when fixed duration patents are involved. Additionally, marketing campaigns that are planning on a specific launch date can face the high costs of modifying their marketing schedules when projects run past their delivery dates. An organization that frequently misses their delivery commitments can also suffer negative impacts to their financial potential and their reputation to customers, shareholders, and other stakeholders. Conversely, an organization that consistently delivers on time or earlier can create a significant strategic advantage over their competitors. This strategic advantage can catapult the organization into ever-flourishing status of highgrowth and high-stability. Steve Pryor, Engineering Director of Propulsion Structures and Systems at Spirit AeroSystems stated in a 2012 PM Network article, "Any missed commitment erodes our credibility with customers. Even more important is the internal cost for late engineering, which can force high overtime rates, supplier expediting fees, rework and potential quality issues" (Fretty, 2012, p 52). Excessive project durations: Reduced return on investment (ROI) Most project managers are familiar with the situation where a project schedule appears to be significantly longer than expected based on experience. It is often the case that organizations begin to spend money when projects start, and they do not begin to make money or save money until projects complete. Therefore, it follows that reducing project durations directly and significantly improves an organization’s ability to make a return on their investment. Not only is delivering on-time important, but a company can reap the tremendous rewards of a market bonus, or substantial additional profits, for each day of early delivery beyond what traditional methods allow (D. Daily, personal communication, July 1, 2013). Additionally, having a consistent reputation of delivering on shorter lead times than one’s competitors can play a role in helping to create a decisive competitive edge. This competitive advantage can contribute to the ability to extend a mafia offer, an offer that customers cannot refuse, and an offer that competitors cannot or will not match (Lang, 2010). Causes to the problems associated with poor project performance Addressing these problems themselves would be like merely treating the symptoms of an illness. Until the root causes are understood and treated, the core of the problem can never be effectively eliminated. Investigations into the problems associated with poor project performance begin to uncover root causes such as:       low-trust environments; nonproductive multitasking which decreases productivity, negatively impacts team morale, and causes missed due dates; uncertainty in task estimates that are inadequately addressed; student syndrome – waiting for the last possible moment to start a task – means that contingency is wasted and risk is increased; Parkinson’s Law – allowing work to expand to fill the time allotted – also wastes contingency and increases risk; having high amounts of work in progress can cause multitasking and firefighting which leads to low team morale and extended project durations. Low-trust environments One of the causes of poor project performance is low trust environments. Low trust environments are often created when team members do not feel they have a safe environment to surface issues quickly and transparently without the fear of being blamed. When team members feel they need to hide issues from management, project performance © 2013, Joe Cooper Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana 2
  • 3. can deteriorate significantly. Issue resolution can take much longer which can jeopardize delivery commitments, cause project delays, increase stress, and decrease team morale. In 2009 and early 2010, NASA Dryden Flight Research Center determined workforce morale as one major issue which was blocking their ability to make significant improvements to their project delivery results. NASA decided to implement critical chain project management (Horn, 2012). With regard to workforce morale, managers wanted to address two items. First, they needed to be able to quickly get to the root cause of project issues. Second, they needed to be able to control work in progress in order to create better project outcomes. However, team members viewed the investigation of issues as punishment and the controlling of work in progress as micromanagement. It is safe to say these perceptions, reality or not, were hindering the improvement of trust within the organization. Management recognized the need to change their approach, and not the mindsets of their teams in order to improve project performance (Horn, 2012). Nonproductive multitasking How much more successful could projects be if nonproductive multitasking could be minimized? A McKinsey Quarterly article indicates that multitasking damages productivity, slows people down, hampers creativity, makes employees anxious, and is addictive (Dean & Webb, 2011). Supporting these findings, a recent multitasking study states, “multitasking makes people less productive, less creative, and more likely to get thrown off by distractions” (Realization Technologies, Inc., 2013, ¶9). Multitasking can also be seen as a significant cause of extended project durations as illustrated in Exhibit 1. If a project team member has three project tasks to complete, A, B, and C, it can be seen that each task takes much longer to complete when multitasking. Context switching between tasks increases the completion times even further and causes the project team members to have to stop frequently to remember where they were each Exhibit 1 – Nonproductive multitasking time they switch to a different task. Multitasking also causes additional stress on team members as they try to keep all of the plates spinning simultaneously. The prolonged task durations diminish the sense of accomplishment team members feel when they drive a task to completion. Once the tasks are eventually completed, any sense of accomplishment is replaced by feelings of relief that the stressful multitasking of activities is finally over. The result is decreased morale and a team member who feels more exhausted than excited to have completed their tasks. Additionally, if a problem arises on one of the juggled tasks, delays can propagate among all of the tasks which can impact the on-time performance of multiple projects. Therefore, all three project problems – low team morale, missed due dates, and excessive project durations – can be caused by multitasking. Uncertainty in task estimates How much shorter could project schedules be if team members were not fearful of using most likely estimates? If team members are asked to provide a task estimate, are they inclined to provide one that is 50% likely or one that is 95% likely? Most project team members would provide the 95% likely estimate (Walker, 2010). Exhibit 2 illustrates two probability curves. The bell-shaped curve with a long tail represents the probability density of task duration. The “s” shaped curve is the cumulative probability. A project task that is 95% likely is typically two or more times the duration estimate of the 50% likely estimate (Exhibit 2). Exhibit 2 – Probability of task duration According to Budd and Cerveny (2010), project task estimates are frequently taken as commitments. When team members know their estimates will be viewed as time commitments, they will often add excessive hidden padding to © 2013, Joe Cooper Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana 3
  • 4. the task completion date (Realization Technologies, Inc., 2010). Management, receiving pressure to reduce project durations, will look to decrease task estimates in order to shorten project schedules. Team members, wise to what is going on, will play the game and add even more padding to counter the actions of management. A missed estimate equates to a missed commitment which can lead to unfavorable evaluations and sometimes demoralizing punishment. It follows that this situation can also be a cause of low team morale. Student syndrome: Waiting until the last possible moment to start a task Student syndrome causes a significant waste of well-intended contingency. Most people have felt the effects of student syndrome at some point in their lives. When there is more time to complete a task than is truly necessary, it is typical that team members will wait until the last possible moment to begin (Blackstone, Cox, & Schleier, 2009). Exhibit 3 illustrates the amount of effort applied over time to complete a task. Very little effort is applied in the early stage of the task even though there are no factors preventing full focus (Goldratt, 1997). The addition of excessive hidden padding in task estimates creates the likelihood of a self-fulfilling prophecy for task completion (Budd & Cerveny, 2010). If a task has an optimistic duration of two days, a most-likely duration of five days, and a pessimistic duration of 12 days (due to the long tail of most tasks), many team members will provide a task estimate in the upper end of the spectrum; one that has Exhibit 3 – Student syndrome 95%+ probability of being achieved. For this example, it is assumed the estimate provided is 12 days. The team member, knowing that the task will only take two days if everything goes smoothly and will only take five days in most cases, is likely to wait until day six (or so) until they become fully engaged. Most of the hidden padding, intended to protect the task from uncertainty, is now wasted before the task even begins. If something unexpected occurs, there is no longer sufficient contingency to prevent the task from being late (Exhibit 3). This late task impacts successor tasks which can cause an entire project to be delayed. When student syndrome is present in an entire sequence of tasks, the damaging effects get multiplied. A crisis situation is created, increasing stress and damaging team morale even further. Parkinson’s Law: Work expands to fill the time allotted When tasks have such significant padding built in, it seems possible that some tasks will finish early. That might be a reasonable expectation if it were not for Parkinson’s Law. If a team member completes a task early, there is little chance they will declare the task complete. Sometimes, this can be due to the tendency to improve or polish the completed deliverable. Other times, it can be a result of a team member wanting to be viewed as a reliable estimator. Declaring a task complete early can damage this reputation. Moreover, a team member who completes a task early is likely to have their task durations cut even more the next time they provide an estimate (Newbold, 2013). If this fear becomes a reality, trust is damaged further, and then let the games begin! The team member will add even more padding next time to make up for the amount that is likely to be cut. High work in progress in the project pipeline Another significant cause to the problems associated with poor project performance is having too many projects in the delivery pipeline. Are projects frequently started regardless of an organization’s capacity to complete the work? The statement, “Well, it all has to get done!” might even be heard. Organizations can oftentimes be driven to get projects started as early as possible, following the ill-fated logic that the earlier a project starts, the earlier it will finish (Budd & Cerveny, 2010). However, when the capacity of the project delivery pipeline is not taken into consideration, this well-intended tactic can have devastating effects on the system as a whole. Having too many projects in the pipeline can slow the entire system down and drastically exacerbate the causes of poor project performance. What might be a good strategy for activating projects within the project delivery pipeline? Do projects ever get activated simply to keep everyone busy? © 2013, Joe Cooper Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana 4
  • 5. Critical Chain unlocks a series of new paradigms Critical chain project management (CCPM) is the project management application of the theory of constraints (TOC). First introduced by Dr. Eli Goldratt (1997), critical chain has gained significant momentum in the project community as a solution to the problems associated with poor project performance. CCPM takes resource constraints into account for more realistic planning and focused execution. The critical chain is the resource-leveled critical path. CCPM also utilizes pooled contingency to more effectively address the various components of project uncertainty. The first solution addressed in this discussion, creating environments of high-trust, is not formally a critical chain solution. However, having significant trust within teams and across organizations is important when implementing change (Budd & Cerveny, 2010). The end result of improved morale and quality of work life for team members is more deliberately emphasized in the literature (Kishira, 2009). Of course, most operational managers, VPs, and CxOs appreciate the positive effects of high trust in their organizations regardless of the strategies and tactics utilized. Additional CCPM solutions are as follows. Pipelining addresses the problems associated with having too much work in progress. Full kitting addresses the problems associated with starting project tasks without the necessary predecessor activities completed. To address wasted contingency, 50/50 task estimates are utilized. Executing with focus, rather than multitasking, addresses elongated task durations, productivity losses due to context switching, and the stress team members feel as they try to keep many plates spinning simultaneously. Lastly, project buffers shorten project durations and protect critical project dates from uncertainty; significantly improving the predictability of project delivery. In an October 2009 speech, Eli Lilly and Company CEO Dr. John C. Lechleiter, announced the most sweeping changes in company history, indicating three new competencies that are changing drug development at Lilly. One of those competencies is critical chain project management. Dr. Lechleiter stated, The COE is implementing a project management methodology called ‘Critical Chain’, developed by physicist Eli Goldratt. Critical Chain was actually first applied at Lilly in a completely different context by our IT group. They, in turn, helped our research labs launch a pilot program that has proved the power of Critical Chain in drug development. Historically, across our pipeline, we have a 60% success rate in hitting milestones on time. In other words, we miss almost half of our deadlines. In the Critical Chain pilot program, the success rate so far is 100%. That’s why we’re now applying Critical Chain in force (Lechleiter, 2009, ¶38). In a June 2013 keynote address to the Theory of Constraints International Certification Organization (TOCICO) international conference in Bad Nauheim, Germany, Mr. Mitsuo Hitomi, Executive Officer from the Mazda Motor Company spoke of a major company turn-around, and he credited critical chain and TOC (Ptak, 2013). Mr. Hitomi presented remarkable results with an emphasis on employee harmony, improved quality of work life, and positive financial results in 2013 after four fiscal years of operating in the red. Additionally, Mr. Hitomi indicated that critical chain momentum grew and resulted in development project durations being cut in half with all projects delivered with full scope and on time (Ptak, 2013). Echoing the sentiments of Dr. Goldratt himself, Mr. Hitomi stated after the presentation, “Even the sky is not the limit” (Ptak, 2013, ¶6). Creating environments of transparency and high-trust Stephen M. R. Covey, author of The Speed of Trust (Covey & Merrill, 2008), states, When trust is low, in a company or in a relationship, it places a hidden “tax” on every transaction: every communication, every interaction, every strategy, every decision is taxed, bringing speed down and sending costs up. My experience is that significant distrust doubles the cost of doing business and triples the time it takes to get things done. By contrast, individuals and organizations that have earned and operate with high trust experience the opposite of a tax -- a "dividend" that is like a performance multiplier, enabling them to succeed in their communications, interactions, and decisions, and to move with incredible speed. A recent Watson Wyatt study showed that high trust companies outperform low trust companies by nearly 300%! (p 21) © 2013, Joe Cooper Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana 5
  • 6. Patrick Lencioni, author of The Five Dysfunctions of a Team (2002), indicates that absence of trust is a foundational cause for team dysfunction. Yuji Kishira, in his book titled WA: Transformation by Harmony (2009; “WA” means “harmony” in Japanese), emphasizes the superior results observed when organizations are able to optimize high-trust within their environments and create true harmony within teams. In a PM Network article, Hunsberger (2012) states, “The critical chain approach can provide much-needed relief for overloaded team members on a tight deadline” (p 41). Another PM Network article states, “Spirit AeroSystems attributes critical chain project management to a 50% reduction in employee overtime” (Fretty, 2012, p 55). Overtime and stress can create tension among teams, which can lead teams down the path toward distrust and disharmony. When trust is low, productivity can be drastically impacted. The CCPM approach requires a fair level of trust between teams and management due to the nature of the transparency created. However, once teams begin to adjust to the new paradigms, CCPM behaviors can become a driving force behind improving trust. Pipelining: Limiting work in progress Organizations that can successfully focus everyone’s attention on the few, critically important goals, rather than getting pulled into the tyranny of the urgent, can create a significant strategic advantage over their competitors. Organizations that are successful with this strategy can be a highly productive, harmonious, collaborative, and innovative entity that operates within a sustainable, high-trust environment. The critical need to streamline work in progress is to maximize the flow of projects through the delivery pipeline. Local measures, such as how quickly a project gets started, are not valuable to the goals of the organization. Rather, the throughput of the entire organization, global optimization, should be the focus. Most would agree that any system is made up of bottlenecks and non-bottlenecks or constraints and non-constraints. If an organization activates projects just to keep the non-constrained team members busy, critically constrained resources quickly become over-allocated. Critically constrained resources are those who typically have the highest workload and the fewest resource numbers. What impact might this action have on the flow of projects through the delivery pipeline? Since CCPM is focused on optimizing globally, the critically constrained resources are identified and projects are staggered in a way to keep these resources optimally loaded. Of course, if the critically constrained resources are optimally loaded, the non-constraint resources will be less than optimally loaded; even idle! (Realization Technologies, Inc., 2010) Granted, this flies in the face of conventional wisdom, but keep in mind, local optimization does not lead to global optimization. In which of these are most organizations interested? Asked in a different way, are organizations more concerned with strengthening the weakest link in the chain or the stronger links in the chain? Now that critically constrained resources are optimally loaded and non-constrained resources have capacity (i.e., to think, innovate, help others, train, take on unexpected work, etc.), significantly improved throughput (or flow) within the organization is feasible. This technique to limit the number of active projects is a key element of critical chain. Concentrating resources on fewer projects at one time allows teams to focus and reduces multitasking. This not only allows projects to be executed faster but creates capacity to undertake more initiatives (Fretty, 2012, p 52). Full kitting Making sure project team members have all of the necessary predecessor activities completed (full kit) prior to starting their task ensures they have a greater chance to focus uninterrupted without having to be impacted by potential upstream delays. Also, they are more likely to be able to drive their project tasks to completion with high speed and high quality. The need to start, stop, and start again due to missing predecessors can significantly reduce efficiency and productivity. “[The full kitting] approach requires having all the pieces in place prior to moving a project work package forward. This step helps significantly reduce the number of second actions to complete a single stage” (Fretty, 2012, p 52). © 2013, Joe Cooper Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana 6
  • 7. 50/50 task estimates, most likely estimates Critical chain minimizes student syndrome, waiting until the last possible moment to start a task, and Parkinson’s Law, work expanding to fill the time allotted, by eliminating the need for every team member to hoard safety in their task estimates. As discussed previously, when team member’s estimates are turned into commitments, project task estimates and entire project schedules can inflate drastically. Keeping in the spirit of optimizing globally rather than locally, it is more important to focus on project delivery performance than task completion performance. When management focus is shifted from on-time task completion to on-time project delivery, team members feel empowered to get aggressive with their task estimates while still accounting for a reasonable amount of uncertainty. Instead of using the traditional 95% likely pessimistic task estimates, 50/50 estimates, those that have a 50% chance of finishing earlier and a 50% chance of finishing later, are provided during planning. The 50/50 estimates are also, roughly, half of the duration of 95% estimates. Therefore, the project schedule is temporarily cut in half which is a giant step in the right direction. However, even though the wasting of task contingency has been minimized and team members have a renewed sense of enthusiasm with this safe, aggressive task goal, there is still a need to protect the project commitment from unpredictable events. Focusing on the task at hand rather than multitasking With the environment of high-trust and transparency created, the project pipeline optimized for throughput, and project tasks estimated with aggressive and achievable durations, projects are ready for optimized execution. This requires team members to focus on the task at hand and to drive it to completion with high speed and high quality. Allowing team members to focus on their tasks sequentially rather than multitasking is, counter intuitively, a very effective solution to most organization’s need to do more with less. As is illustrated in Exhibit 4, significant improvements can be made by allowing team members to focus on their tasks until completed. Conventional wisdom might have team members work more hours in order to get more work completed faster. Oftentimes, this option is not sustainable and can take a devastating toll on team morale and organizational trust. When organizations begin to realize the significant productivity improvements that can be gained by simply reducing multitasking, a new level of organizational performance can be achieved, creating a decisive competitive edge over the competition. Tactically, critical chain enables the concept of focus by creating a relay race mindset among project team members rather than utilizing rigid task scheduling Exhibit 4 – Using focus rather than multitasking and task deadlines. Once a task begins, the team members drive the task to completion as quickly as possible with focus on appropriate quality and without fear of calling out issues that need to be addressed. Some project teams even use relay race batons as a fun way to bring visibility to the team members who are on the critical chain and who are focused on the task at hand. In a low trust environment, being on the critical path might be intimidating and uncomfortable, but in a high-trust environment, being on the critical chain can be a healthy challenge to be conquered. At a recent conference, Dr. Reddy’s Laboratories shared some striking results. In just 12 weeks after taking focused measures to sharply reduce its project team’s workload and reduce multitasking, the company's development group completed 83% more projects than it had in the previous 12 weeks without adding any additional resources (Ziv, 2012). As team members make progress on project tasks, they provide updates as to how much time they feel is left to complete their work. This information is used to communicate to the next team member who will take the baton handoff as soon as it is ready. Also, the remaining time to complete the task is used to determine if any time beyond the original 50/50 estimate will be needed. If the task is running late, due to unforeseen circumstances, a mechanism © 2013, Joe Cooper Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana 7
  • 8. is needed to prevent an impact to the project delivery. It is not necessary to be concerned with on-time completion of individual tasks. Rather, it is more important to focus on project on-time performance. The mechanism used to protect the project delivery commitment is the project buffer. Buffering for uncertainty With the project planned using 50/50 task estimates, a decrease of approximately 50% of the overall project duration is expected. This padding was removed from the individual tasks (Exhibit 5) in order to prevent it from being wasted by behaviors associated with student syndrome and Parkinson’s Law. However, there is still a need to have some amount of contingency to protect the project delivery from uncertainty. A portion of the contingency removed from critical chain tasks, approximately 50%, is added back to the project schedule as a pooled contingency, which acts like a Exhibit 5 – Protecting the project commitment shock absorber to protect the project delivery commitment (Exhibit 5). Projects are typically planned to complete 25% faster while protected by a buffer that absorbs project task variations (Fretty, 2012; Leach, 2011). This pooled contingency, which is used by everyone on the project team, creates a very interesting, healthy dynamic for project success. No longer do team members need to feel alone to protect themselves from unpredictable events (risks). Rather, the entire team is motivated and driven to be successful together. If one team member needs additional time due to unforeseen circumstances, they are able to consume a portion of the project buffer. If another team member completes a task early, they add their time to help replenish the buffer. The use of a centralized and transparent project buffer allows for shorter project durations, improved on-time performance, and healthier team morale. A word of caution, testing is not a buffer. A buffer consumption chart (Exhibit 6) is an objective, leading indicator of project health and is kept visible for all to see. The number of days of work left on the project compared with the number of days of buffer remaining provides an indication of how likely a team is to complete their project onExhibit 6 – Buffer consumption chart time. If the buffer is in the green territory, a team will continue as planned and managers are not required to interrupt team members to search for issues. If the project buffer reaches yellow, buffer recovery plans are made just in case it becomes necessary. If the buffer penetrates the red area, buffer recovery plans are executed. Recovery can include any techniques associated with crashing a project network. With a buffer consumption chart, all team members, sponsors, and other stakeholders are informed of the health of the project at all times. Additionally, reasons for buffer consumption are documented so that continuous improvements can be made to the project execution and delivery system. Exhibit 7 – Multi-project buffer chart A similar chart can be used to bring transparency to the health of all projects in a program or portfolio. Exhibit 7 displays a buffer consumption chart that can be used in a multi-project environment to display the duration of work remaining versus the amount of buffer remaining for each individual project. © 2013, Joe Cooper Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana 8
  • 9. Conclusions Organizations observe numerous project problems within their environments daily. Some of the most impactful are team morale, missed project commitments, and excessive project durations. It is important to identify root causes and not just treat the symptoms of these problems. Root causes include having too much work in progress, environments of low-trust, multitasking rather than focusing, and wasted contingency at the task level due to student syndrome and Parkinson’s Law. Critical chain targets these causes by streamlining the number of projects in the pipeline for maximized throughput and flow, creating an environment of high-trust which allows team members to get aggressive with task estimates and to call out issues without fear of blame, and by creating an effective contingency mechanism, a project buffer used by the team, that is an objective and transparent leading indicator of project health. The results demonstrated by organizations who have systemically embraced CCPM are impressive. Teams enjoy a sense of accomplishment as they operate with high focus and with harmony. On-time delivery becomes increasingly more predictable and on-time performance can improve from 30-60% to 90%+. Project durations can be cut by 25% or more without sacrificing scope, quality, or team members’ lives outside the workplace. © 2013, Joe Cooper Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana 9
  • 10. References Blackstone, J. H., Jr., Cox, J. F., III, & Schleier, J. G., Jr. (2009). A tutorial on project management from a theory of constraints perspective. International Journal of Production Research, 47(24), 7029-7046. http://dx.doi.org/10.1080/00207540802392551 Budd, C. S., & Cerveny, J. (2010). A critical chain project management primer. In J. Cox III & J. Schleir, Jr. (Eds.), Theory of Constraints Handbook (pp. 45-77). New York, NY: McGraw Hill. Covey, S. M. R. & Merrill, R. R. (2008). The speed of trust: The one thing that changes everything. New York, NY: Free Press. Dean, D. & Webb, C. (2011, January). Recovering from information overload. McKinsey Quarterly [Electronic Version] Retrieved on 17 August 2013 from http://www.mckinsey.com/insights/organization/recovering_from_information_overload Fretty, P. (2012). Change is in the air. PM Network, 26(2), 50-55. Goldratt, E. M. (1997). Critical chain. Great Barrington, MA: North River Press. Horn, T. J. (2012). Changing the project execution culture at NASA Dryden. Ask Magazine [Electronic Version] Retrieved on 23 March 2013 from http://www.nasa.gov/offices/oce/appel/ask/issues/48/48i_project_execution_culture.html Hunsberger, K. (2012). Chain reactions. PM Network, 26(1), 40-43. Kishira, Y. (2009). WA: transformation management by harmony. Great Barrington, MA: North River Press. Lang, L. (2010). Mafia offers: Dealing with a market constraint. In J. Cox III & J. Schleir, Jr. (Eds.), Theory of Constraints Handbook (pp. 603-628). New York, NY: McGraw Hill. Leach, L. P. (2011). Buffers: Key to project schedule success. PM World Today, XIII(X), 9-11. Lechleiter, J. C. (2009, October). Reinventing invention: Fixing the engine of biopharmaceutical innovation. Eli Lilly CEO speech, San Diego, CA, USA. Retrieved on 26 July 2013 from http://www.lilly.com/news/speeches/Pages/091030.aspx Lencioni, P. (2002). The five dysfunctions of a team: A leadership fable. San Francisco, CA: Jossy-Bass. Newbold, R. (2013). The tyranny of deadlines. Retrieved on 24 August 2013 from http://www.prochain.com/pm/articles/Tyranny_of_Deadlines.pdf © 2013, Joe Cooper Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana 10
  • 11. Ptak, C. (2013). Mazda executive credits theory of constraints for company turnaround. Retrieved on 26 July 2013 from http://www.pr.com/press-release/495307 Realization Technologies, Inc. (2010). Getting durable results with critical chain – A field report. In J. Cox III & J. Schleir, Jr. (Eds.), Theory of Constraints Handbook (pp. 79-100). New York, NY: McGraw-Hill. Realization Technologies, Inc. (2013). The effects of multitasking on organizations. Retrieved on 29 August 2013 from http://www.realization.com/the-effects-of-multitasking-on-organizations Ricketts, J.A., & Dager, J. (2010, September 15). Using the theory of constraints in services [Transcript of audio podcast]. Retrieved on 12 July 2013 from http://www.docstoc.com/docs/54701354/Using-TOC-in-Services Walker, E. (2010). The problems with project management. In J. Cox III & J. Schleir, Jr. (Eds.), Theory of Constraints Handbook (pp. 13-44). New York, NY: McGraw-Hill. Ziv, Y. (2012). Less is more. TCE: The Chemical Engineer, (851), 40-41. © 2013, Joe Cooper Originally published as part of 2013 PMI Global Congress Proceedings – New Orleans, Louisiana 11