Embed presentation
Download to read offline





The document discusses the concept of crashing, which refers to reducing the duration of an activity by increasing its cost. It provides that the crash cost (Cc) and normal cost (Cn) increase as the crash time (Tc) decreases compared to the normal time (Tn). For example, reducing an activity's normal duration of 8 weeks by 1 week would increase the cost from the normal $9k to the crashed cost of $12k, and reducing it by 2 weeks would increase the cost to $15k.



