SlideShare a Scribd company logo
1 of 13
Download to read offline
each
Privatisation of Electricity Networks,
New South Wales, Australia
In June 2014, the State Government in New South Wales (NSW) announced that it intends to
privatise the NSW electricity networks. This briefing note sets out the likely structure of the
privatisation and identifies some key issues.
The NSW electricity networks are currently 100% state-owned and comprise:
• TransGrid, an electricity transmission operator with a regulated asset base of AUD 6.1 billion
that is expected to realise AUD 845 million in annual revenue next financial year. TransGrid
owns roughly 14,000 km of transmission lines in NSW and transmits 71 GWh of electricity per
annum over those lines.
• Networks NSW, which comprises the following three electricity distribution businesses with a
common CEO and common senior management:
o AusGrid, an electricity distributor supplying 1.6 million retail electricity consumers in the
Sydney, Central Coast, Hunter and Newcastle regions of NSW. AusGrid has a regulated
asset base of AUD 14.6 billion across its distribution assets that is expected to realise
some AUD 2.21 billion in revenue in the 2014/15 financial year. AusGrid owns roughly
42,000 km of distribution lines and is capable of meeting peak demand of 5,149 MW;
o Endeavour Energy, an electricity distributor supplying 883,000 retail electricity
consumers in western Sydney and the Illawarra regions of NSW. Endeavour has a
regulated asset base of AUD 5.6 billion across its distribution assets that is expected to
realise some AUD 949 million billion in revenue in the 2014/15 financial year. Endeavour
owns roughly 34,500 km of distribution lines and is capable of meeting peak demand of
3,236 MW; and
o Essential Energy, an electricity distributor supplying 803,000 retail customers in regional
NSW. Essential has a regulated asset base of AUD 6.9 billion across its distribution
assets that is expected to realise some AUD 1.29 billion in revenue in the 2014/15
financial year. Essential owns roughly 191,000 km of distribution lines and is capable of
meeting peak demand of 2,185 MW.
However, the Government has indicated that it does not intend to privatise Essential Energy.
Briefing
July 2014
Privatisation of Electricity Networks, New South Wales, Australia
02 Norton Rose Fulbright
The role of electricity networks in the NEM
Electricity networks transport power from generators to customers. Transmission networks (e.g., TransGrid)
transport power over long distances at high voltages, linking generators to distribution load centres. Distribution
networks (e.g., Networks NSW) then reticulate electricity from the transmission network through urban and
regional areas at lower voltages to provide electricity to customers.
In Australia, the National Electricity Market (NEM) is a wholesale market comprising some 300 generators that
collectively sell some 200 TWh of electricity annually in eastern and southern Australia. The principal customers
of those generators are energy retailers. The energy retailers bundle electricity with network services for sale to
some 9.3 million residential, commercial and industrial energy users. The NEM covers six Australian
jurisdictions — Queensland, NSW, the Australian Capital Territory, Victoria, South Australia and Tasmania.
Electricity is carried within the geographic area of the NEM via five State-based transmission networks,
physically linked by cross-border interconnectors and servicing 13 distribution networks. In geographic span,
the NEM is one of the world’s longest continuous AC systems, covering a distance of some 4,500 kilometres.
Because energy networks are capital intensive and incur declining average costs as output increases, network
services in a particular geographic area can be most efficiently provided by a single supplier, leading to a natural
monopoly industry structure. Within the NEM, each transmission and distribution network has a monopoly in its
particular geographic area. As such, the electricity networks in the NEM are regulated under Australia’s
National Electricity Law to manage the risk of monopoly pricing and to encourage efficient investment in
infrastructure. The National Electricity Law is explained later in this briefing note.
Political context to the privatisation
A number of other States in Australia privatised their electricity assets at an early stage, commencing with
Victoria’s privatisation of the Loy Yang B power station in 1992. However, the privatisation of electricity assets
in NSW was politically controversial for the NSW Labor Party in its role in Government over the 16 year period
from 1995 to 2011. A number of proposals for NSW electricity privatisation did not proceed during that period,
including under Premier Bob Carr in 1997 and Premier Morris Iemma in 2008.
Ultimately, a first phase of privatisation was initiated by Premier Kristina Keneally in NSW in 2008. The first
phase involved the sale of NSW electricity retail businesses, development sites and electricity generation output
contracts (known as the “GenTrader” contracts). The Government realised AUD 5.3 billion in sale proceeds.
With a change in NSW Government to a Liberal/National Coalition in March 2011, Premier Barry O’Farell
initiated a second phase of privatisation. The second phase involved the sale of the electricity generation
businesses. As at June 2014, aspects of this sale are still occurring, including a successful application for
authorisation by AGL Energy to the Australian Competition Tribunal to acquire Macquarie Generation.
In May 2012, the NSW Government announced that as part of its policy to put downward pressure on electricity
prices a common chairman, board and CEO would be appointed to the State’s electricity distribution network
businesses from 1 July 2012. As a result AusGrid, Endeavour Energy and Essential Energy were aggregated to
form Networks NSW in a move viewed as a prelude to privatisation.
On 10 June 2014, Premiere Mike Baird announced the third phase of privatisation, the subject of this briefing
note, as part of a ‘Rebuild NSW’ policy that the Liberal/National Coalition will take to the 2015 State election.
Given political concerns, an outright sale of the electricity networks is not contemplated. Instead, the
privatisation will occur via the sale of 99 year ‘partial leases’. The Government will maintain ownership of 100%
of Essential Energy and will also maintain an average ownership of 51% across all four electricity networks.
Privatisation of Electricity Networks, New South Wales, Australia
03 Norton Rose Fulbright
Timing for the privatisation
Importantly, Premier Mike Baird has announced the privatisation of the electricity networks in the form of a policy
commitment that he will take to the next NSW State election scheduled for 28 March 2015. The formal process
for the privatisation will therefore not commence unless and until the Liberal/National Coalition is returned as the
NSW Government on that date.
As at June 2014, the Labor Party has indicated that it will not proceed with the privatisation if it wins the NSW
State election in March 2015.
Notwithstanding that the privatisation is contingent on the election, the NSW Government is currently
undertaking preparatory work for the privatisation, including the appointment of financial and legal advisors. The
preparatory work will likely involve the completion of a scoping study and an initial vendor due diligence. The
scoping study is likely to make a series of recommendations regarding the structuring of the privatisation and
implementing legislation.
We expect the scoping study to be provided to the NSW Government in late 2014.
Transaction structure – ownership permutations
As at July 2014, the structure for the transaction has not been determined. We have speculated below on some
possible structuring options.
Importantly, the NSW Government has announced that it intends to maintain an overall 51% ownership level
across all four electricity businesses, including maintaining 100% ownership of Essential Energy. The NSW
Government has not yet identified how it will apply the 51% ownership threshold in practice. Some public
statements, for example, refer to the ownership level as “51% of total electricity network assets”.
Given that AusGrid is the most valuable business, the Government may prefer to privatise a full 100% of that
business under a 99 year lease in order to maximise the privatisation proceeds. Similar reasoning may result in
a structure in which different proportions of TransGrid and Endeavour Energy are privatised.
Assuming that this 51% ownership threshold is interpreted as a simple average across the four businesses (or
across three businesses if any two businesses are merged), this could lead to various ownership permutations.
The following table sets out four possible examples:
AusGrid Endeavour TransGrid Essential
Equal
distribution
35% State-owned
65% Private
35% State-owned
65% Private
35% State-owned
65% Private
100% State-owned
Merged
distributors
100% Private
(merger of AusGrid and Endeavour)
53% State-owned
47% Private
100% State-owned
Asymmetric
distribution 1
100% Private 19% State-owned
81% Private
85% State-owned
15% Private
100% State-owned
Asymmetric
distribution 2
100% Private 52% State-owned
48% Private
52% State-owned
48% Private
100% State-owned
Privatisation of Electricity Networks, New South Wales, Australia
04 Norton Rose Fulbright
Other more creative solutions could be adopted. If AusGrid and Endeavour Energy are merged prior to
privatisation, the 49% average can (arguably) be taken over the 3 resulting businesses with the practical
effect of increasing the extent of possible privatisation. This option may maximise sale revenue for the NSW
Government while achieving a more marketable privatisation with investors.
If the 51% level were interpreted as a weighted average across the regulated asset base (RAB) of the
businesses, other permutations would be possible (although weighting by the regulated asset base would
reduce the extent of privatisation). This is illustrated in the following table in which the 51% level has been
weighted by the value of the RAB:
AusGrid Endeavour TransGrid Essential
RAB (AUD
million)
AUD 15,645m AUD 5,616m AUD 6,104m AUD 6,888m
Equal RAB
allocation
23% State-owned
77% Private
60% State-owned
40% Private
55% State-owned
45% Private
100% State-owned
Asymmetric
distribution
100% Private 59% State-owned
41% Private
100% State-owned 100% State-owned
Transaction structure – treatment of a 99 year ‘partial lease’
The NSW Government has indicated that the privatisation of the electricity networks will occur by way of a
99 year ‘partial lease’. A similar 99 year lease structure was used for the recent port privatisations in NSW.
A 200 year lease structure was used for the privatisation of the ETSA Utilities electricity distribution network
in South Australia (SA), creating SA Power Networks.
If a combination of the approaches used in the NSW port privatisations and the ETSA privatisation were
adopted, the following steps may occur:
• First, the NSW Government would enact implementing legislation, potentially modelled in part on the
Electricity Corporations (Restructuring and Disposal) Act 1999 of SA. This legislation would amend
relevant NSW State legislation to facilitate and authorise the privatisation as well as effecting any
changes necessary to implement the desired post-privatisation framework.
• Second, the relevant assets to be privatised would be transferred into a State-owned Ministerial holding
corporation (HoldCo), a State entity established by the implementing legislation to hold the network
assets to be leased to the private sector. In SA, the HoldCo was the “Distribution Lessor Corporation”.
• Third, a Project Company would be created to enter into a 99 year lease with HoldCo. The lease would
provide HoldCo the rights to operate/use the relevant network assets and to retain the economic
benefits of any charges it imposed, but would also impose a range of performance and compliance
obligations. HoldCo would retain no control of the day to day operation of the network assets as its role
as lessor under the 99 year lease.
• Fourth, a separate 99 year lease may also be entered into with HoldCo by the Project Company for the
lease of any associated land, but with HoldCo retaining freehold ownership. HoldCo would retain
step-in rights and the ability to terminate both 99 year leases if the Project Company were to breach key
obligations, but only for the predetermined ‘cure period’.
Privatisation of Electricity Networks, New South Wales, Australia
05 Norton Rose Fulbright
• Fifth, existing key contracts would be assigned by the Project Company. Some employees would also
transfer to the Project Company, supported by various Government commitments intended to preserve
employee entitlements.
The privatisation could subsequently occur by the sale of the shares in the Project Company to an investor
in the desired proportion, such as 100% or 49%. In this manner, investors would be offered a pre-packaged
deal without any involvement in the negotiation of the 99 year lease. Any such sale could involve a trade
sale or an initial public offering (IPO).
In the SA privatisation of ETSA Utilities, bidders were given three different alternatives. Bidders could
acquire shares in the Project Company. Alternatively, bidders could receive a novation of the pre-packaged
200 year leases and acquire the assets and liabilities of the Project Company. Alternatively, bidders could
negotiate their own 200 year leases (to replace the pre-packaged 200 year leases) and acquire the assets
and liabilities of the Project Company. In SA, the successful bidder opted for the third of these options.
The situation becomes more complex if less than 100% of a business is privatised. An investor in a partial
privatisation at less than 100% would, in practical effect, be entering into an incorporated joint venture with
the NSW Government. In Australia, one precedent for such a structure is the TransACT joint venture.
In a joint venture structure, investors may seek a shareholder agreement (or constitutional provisions) that
address key governance issues for the Project Company, including appointment of executives and voting
rights on the Board of Directors. A private investor at less than 50% may wish to secure de facto control.
However, an IPO of a partial interest is also possible as demonstrated by the ‘T1’ privatisation of Telstra.
Sale price
As at June 2014, the sale price for the privatisation is not yet known. The sale price will depend heavily on
the ultimate structure adopted for the privatisation. However, the NSW Government has indicated that it
intends to realise at least AUD 13 billion in aggregate from the lease of NSW’s electricity networks.
All of the sale proceeds are intended to be invested in new roads and other transport infrastructure projects
in NSW. Assuming the Asset Recycling Fund Bill 2014 (Cth) is enacted, the NSW Government should also
receive an amount of some AUD 2 billion as an incentive payment from the Commonwealth Government.
Conditions for the partial lease
In its ‘Rebuilding NSW’ policy for the 2015 State election, the Liberal/National Coalition has laid out strict
conditions for the partial lease of the NSW electricity networks. These conditions are designed to promote
the public interest and address community concerns.
The conditions already announced by the NSW Government include:
• all net proceeds from the privatisation will be invested in new productive infrastructure, through the
Restart NSW Fund;
• electricity network prices will be discounted by 1% off forecast regulated prices until 2019;
• permanent award employees’ jobs will be protected, and treated consistently with previous transactions;
• the transaction will have no adverse impact on electricity reliability; and
• the regional presence of the network businesses will be maintained.
It is possible that further conditions could be announced if the privatisation were to become a major political
issue in the context of the 2015 NSW State election.
Privatisation of Electricity Networks, New South Wales, Australia
06 Norton Rose Fulbright
Preliminary issues
A number of issues raised by the proposed privatisation are briefly summarised below, including:
• the extent to which any regulatory clearances may be required by bidders;
• the manner in which network companies are subject to price regulation;
• the impact of electricity demand on future cash flows; and
• the manner in which requirements for future investment in network infrastructure will be addressed.
We believe one of the most significant issues for bidders will be “regulatory risk”. This is particularly relevant
given the businesses are currently undertaking a regulatory reset for 2014 – 2019, with a draft determination
to be issued by the AER in November 2014 and a final determination to be issued by the AER by 30 April
2015. Any appeal of any determination of the AER to the Australian Competition Tribunal thereafter will take
6 - 12 months to be heard, after any transaction is to be completed. We set out these issues in detail below.
Regulatory clearances for bidders
Key regulatory clearances required by bidders may include foreign investment approvals and competition
clearances. Foreign investment approvals are straightforward and rarely withheld, but are a necessary
formality. Competition clearances may be important if a bidder, or any participants in a bidding consortium,
have existing electricity operations in Australia, whether in generation, transmission, distribution or retail.
The ACCC may be concerned if the acquisition of shares in the Project Company could result in a
substantial lessening of competition in any market in Australia. Concerns could arise, for example, if a
potential investor was an electricity generator or retailer. In such circumstances, the ACCC may be
concerned at the potential for a vertically integrated transmission or distribution network provider to
discriminate in favour of its own operations.
However, the potential for investment of a generator or retailer in vertical integration will not necessarily be
fatal to ACCC clearance of an asset purchase. The ACCC’s reaction would turn on the circumstances of the
case. The investor might be considered to have an immaterial shareholding or a role that gives it no
practical influence. It may in any case be possible to provide a voluntary undertaking to the ACCC that
addresses adequately any competition concerns.
For example, an undertaking could be provided that competitors to the generator/retailer would be able to
connect to the transmission or distribution network on a non-discriminatory basis. Also, requirements that
these aspects of the businesses be ring-fenced may assist. Indeed, the ring fencing restrictions that already
exist under the National Electricity Law may already alleviate these issues.
If competition issues were identified, the strategy and timing for any approach to the ACCC would need to
be carefully considered. Generally, the ACCC is not willing to provide clearance without undertaking public
market inquiries. If confidentiality issues preclude inquiries prior to bid submission, the bid may need to be
made conditional on any ACCC clearance.
Regulation of TransGrid as a transmission network
As a transmission network, TransGrid is subject to price and access regulation under the National Electricity
Rules. The terms on which transmission networks offers transmission services to its customers (largely
distributors) must be fair and reasonable. The Rules provide for commercial arbitration in the event of any
network access dispute.
Privatisation of Electricity Networks, New South Wales, Australia
07 Norton Rose Fulbright
Under the Rules, the services provided by transmission networks are categorised into two baskets:
“prescribed control services” (which comprise most core transmission services) and “negotiated services”.
The charges for prescribed control services are heavily regulated, whereas the charges for negotiated
services are negotiated and need only be based on the costs of providing those services (determined in
accordance with a cost allocation methodology approved by the AER).
In determining the pricing of prescribed control services, the Australian Energy Regulator (AER) must make
a “transmission determination”, typically for a period of 5 years. This period is known as the “regulatory
control period”. The Rules permit the AER to apply a revenue cap to transmission businesses. The AER
has historically applied to TransGrid a revenue cap consistent with the approach adopted for other
transmission networks in the NEM, and will almost certainly continue to do so.
In determining the level of the revenue cap for a transmission network, the AER utilises the building block
model (BBM) and regulated asset base (RAB), as discussed in further detail below. Transmission networks
are required to have an approved pricing methodology that allocates that revenue across the relevant
categories of prescribed control services, thereby determining tariff levels and the tariff structure.
Specifically, transmission networks must seek approval by the AER, via the transmission determination, for
a pricing methodology for an entire regulatory control period. The AER must approve the pricing
methodology if it does not exceed the revenue cap and meets various criteria, including consistency with
pricing principles in the Rules. The pricing principles identify the manner in which costs are to be attributed
across the different categories of prescribed control services. The pricing principles also identify the
permitted fixed and variable tariff structures.
During the regulatory control period, the transmission network must publish annual prices that are
determined in accordance with the approved pricing methodology. To date, transmission charges have
comprised a fixed daily price component and variable demand/consumption component.
Regulation of Networks NSW as distribution networks
While the manner in which the distribution networks of Networks NSW are regulated is similar to
transmission networks, there are some important nuances under the National Electricity Rules.
Under the Rules, the services provided by distribution networks are categorised into three baskets:
• “Direct control services” comprise most core distribution services. Direct control services are subject
to both price and access regulation. The terms of access to direct control services are specified in the
Rules and include connection and system security requirements.
• “Negotiated services” largely comprise site-specific services. Negotiated services are subject to both
price and access regulation. The terms of access to negotiated services must be negotiated by a
distribution network in accordance with a negotiating framework that has been approved by the AER.
• “Unregulated services” largely comprise ancillary services supplied in contestable circumstances or
that do not otherwise need to be regulated. Unregulated services are not subject to access or price
regulation under the National Electricity Rules.
The charges for direct control services are heavily regulated, whereas the charges for negotiated services
are negotiated and need only be based on the costs of providing those services (determined in accordance
with a cost allocation method approved by the AER). Importantly, the level of regulation that may be applied
by the AER to distribution networks for direct control services is greater than the level of regulation that may
be applied by the AER to transmission networks in relation to prescribed control services. This regulation is
referred to in the Rules as “control mechanisms”.
Privatisation of Electricity Networks, New South Wales, Australia
08 Norton Rose Fulbright
A diagram of the pricing baskets applied to electricity distributors is set out below:
In determining the pricing of direct control services, the AER must make a “distribution determination”,
typically for a period of 5 years. Again, this period is known as the “regulatory control period”. The Rules
permit the AER to impose controls over the prices of direct control services, or apply a revenue cap, or both.
The control mechanisms available to the AER are significant, including price caps, price schedules and
revenue caps. The AER has historically applied revenue caps and annual price controls to the distribution
networks in Networks NSW, consistent with the approach adopted for other distribution networks in the
NEM, and will almost certainly continue to do so.
In determining the level of the revenue cap for a distribution network, the AER utilises the building block
model (BBM) and regulated asset base (RAB), as discussed in further detail below.
Unlike transmission networks, distribution networks are required to submit an annual pricing proposal to the
AER that sets out the various tariffs and the tariff structure proposed. The AER must approve the pricing if it
does not exceed the revenue cap and meets various criteria, including consistency with detailed pricing
principles in the Rules. Among other matters, the pricing principles allocate customers into tariff classes and
apply charging parameters to each class. The distribution network is also required to publish on its website
a statement of expected price trends over the full regulatory control period.
To date, customer charges for distribution have comprised three key components:
• a network access charge per day per connection (c/connection/day);
• a electricity usage charge (c/kWh); and
• a capacity charge per kiloWatt or kilovoltAmp, per day (c/kW/day or c/kVA/day) – namely a charge
based on a customer’s maximum demand.
NSW distribution services
Direct control (revenue/price regulated) Negotiated Unregulated
Alternative control
(service specific
charges)
Standard control
(general network
charges)
• Network premises
connections
• Network extensions
• Types 1-4 metering
services
• Metering type 6
installation services
• Metering types 5-6
provision,
maintenance,
reasoning and data
services
• Public lighting
• Ancillary network
services
• Network services
• Augmentation of the
network
• Type 7 metering
services
• Site-specific
services
Privatisation of Electricity Networks, New South Wales, Australia
09 Norton Rose Fulbright
The Building Block Model (BBM) and Regulated Asset Base (RAB)
In order to determine the revenue cap for distribution and transmission networks, the AER makes revenue
determinations that are guided by various statutory criteria. The National Electricity Rules prescribe a cost-
based pricing methodology for those determinations, known as the “building block model” or “BBM”.
The BBM enables an “annual revenue requirement” (or “maximum allowable revenue”) to be determined for
each network business in the form of a revenue cap for each regulatory control period.
The BBM methodology is applied in Australia for the regulation of a wide range of infrastructure. The
objective of the BBM is to deliver an NPV=0 outcome so that an operator only recovers its efficient costs
plus a risk-adjusted return equivalent to its weighted average cost of capital (WACC).
The first step in initial application of the BBM was to historically determine the ‘regulated asset base’ (RAB)
for each business. The initial RAB comprised the value of the sunk network assets. Each year, that ‘locked
in’ RAB has been ‘rolled forward’ via annual adjustments that reflect the net effect of depreciation and asset
disposals (both as a RAB reduction) and capital expenditure and inflation (both as a RAB addition). The
RAB is therefore a snapshot of the regulatory valuation of the assets of an electricity network.
Under the BBM, the Maximum Allowable Revenue (MAR) of the business each year is equal to the sum of
the underlying five “building blocks”, which consist of the return on capital, the return of capital (also known
as depreciation), the forecast operating expenditure (OPEX), corporate income taxes (net of imputation
credits), and adjustments for increments or decrements from an efficiency incentive scheme.
The largest ‘building block’ is the return on capital, which may account for up to two-thirds of the MAR. The
‘building block’ methodology is illustrated by the following diagram:
Unfortunately, the BBM model may arguably create incentives for regulated business to inflate the RAB by
undertaking excessive capital expenditure (CAPEX), a practice known colloquially as ‘gold plating’. The
businesses’ ability to recover CAPEX in the form of higher prices to consumers, has reduced incentive to
minimize CAPEX on ‘gold plating’. Public concerns in Australia have therefore led to revisions to the BBM.
Recent reforms to the National Electricity Rules have introduced disincentives to ‘gold plating’, including by
applying an ‘efficiency’ test to CAPEX. Three mechanisms now achieve this:
• Ex-post reviews: The AER may undertake ex-post reviews of CAPEX to prevent the inclusion of
inefficiently incurred CAPEX in the RAB. In doing so, the AER will consider:
o the efficient costs of achieving the ‘capital expenditure objectives’ (i.e., of meeting and managing
demand, maintaining quality, reliability and security, and complying with regulatory obligations);
o the costs that a prudent operator would require to achieve those objectives; and
o a realistic expectation of the demand forecast and cost inputs to achieve those objectives.
Return on capital (RAB x WACC) +
Return of capital (depreciation of RAB) +
Forecast OPEX +
Efficiency benefit sharing scheme (EBSS) +
Corporate income tax (net of imputation)
Maximum Allowable Revenue
Privatisation of Electricity Networks, New South Wales, Australia
10 Norton Rose Fulbright
• Ex ante incentives: .The AER has developed a CAPEX incentives guideline and efficiency benefit
sharing scheme to encourage efficiencies to be realised and shared with consumers.
• Forecasting guidelines: The AER has developed an Expenditure Forecast Assessment Guideline that
must be complied with by networks for the provision of accurate forecasts of OPEX and CAPEX.
Application of network price regulation in NSW
The amendments to the National Electricity Rules identified above take effect from 1 July 2015. However, in
the case of NSW, the previous 5 year regulatory control period expired on 30 June 2014. Accordingly, an
adjustment process has been adopted in which an interim revenue cap applies for the ‘transitional year’
period from 1 July 2013 to 30 June 2014, known as the ‘placeholder revenue allowance’.
Specifically, a full determination will be made by 30 April 2015 for the whole regulatory control period (1 July
2014 to 30 June 2019). In the full determination, the AER will reconcile any difference between the
placeholder revenue allowance for the transitional year and the final MAR for that transitional year
established by the full determination.
Importantly, each of the network businesses in NSW has already lodged its proposals for the full period to
the AER. The expected timeline is as follows:
Submit Regulatory Proposal to AER Completed
Submissions on Regulatory Proposal close August 2014
AER to publish Draft Determination November 2014
Networks to submit revised Regulatory Proposal to AER January 2015
Submissions on revised Regulatory Proposal and Draft Determination close February 2015
AER to publish final Determination for July 2014 to June 2019 30 April 2015
Accordingly, subject to any appeal of the AER’s decision to the Australian Competition Tribunal (which could
take 6 months), the financial parameters for the various electricity networks in NSW to June 2019 should to
be known before or during the expression of interest period for the privatisation.
As at June 2014, the AER has determined the following outcomes for the relevant NSW networks for the
transitional period:
Current
(2009 to 2014)
Transitional period
(July 2014 - June 2015)
WACC RAB ($m) WACC MAR ($m)
TransGrid 10.05% 6,104 8.1% 845.4
AusGrid 10.02% 12,536 + 2,109 8.1% 1,958 + 252
Endeavour 10.02% 5,616 8.1% 949
Essential 10.02% 6,888 8.1% 1,292
Privatisation of Electricity Networks, New South Wales, Australia
11 Norton Rose Fulbright
The table above illustrates a couple of important issues for the current regulatory control period that will be
relevant for bidders:
• Reduction in WACC: The WACC has significantly reduced in the current regulatory control period
relative to the previous regulatory control period leading to a reduced return on capital and a lower
revenue cap. Recent developments in the capital markets have lowered capital costs. Regulatory
determinations made since 2012 reflect recent reductions in the risk free rate and market and debt risk
premiums that have lowered the cost of capital. The overall cost of capital in determinations made in
2013 was 7–7.5% compared with up to 10.4% in 2010.
• Declining electricity demand: Declining electricity demand has led to surplus generation capacity in
the NEM and has delayed the need to invest in electricity networks, resulting in deferral of CAPEX.
Declining demand also affects electricity prices for network businesses to the extent that tariffs are
variable with volume. All things being equal, a reduction in volume would tend to lead to an increase in
the tariff for the variable component of network charges in order to recover the same revenue. In the
context of the privatisation, the Government has already indicated it will seek commitments on pricing.
We are happy to discuss these and other issues in further detail.
Network extensions and enhancements during a 99 year lease
The adoption of a 99 year lease structure by the NSW Government does create potential complications for
bidders in circumstances where network enhancements and extensions are required. Under the lease
structure, the NSW Government will remain as asset owner and lessor, whereas the successful bidder will be
the lessee and operator. This begs a series of questions:
• who should pay for the CAPEX, particularly network extensions and enhancements;
• if the successful bidder is required to pay for the CAPEX, who will then own the assets;
• if assets are required to be transferred to the NSW Government, will any compensation be paid;
• what taxation consequences flow from such transfers for potential bidders;
• if CAPEX is required in the context of a joint venture with the NSW Government, will the NSW Government
be willing to share in the CAPEX and, if not, what adjustment to relative shareholdings should occur?
Each of these issues is an important point that will need to be worked through carefully in the coming months in
the context of the scoping study.
However, these issues are not unique to the proposed NSW electricity network privatisation. There are many
precedents from Australia and overseas where 99 year leases have been granted in circumstances were
ongoing capital expenditure is required and further substantial asset enhancements have occurred. The
privatisation of ETSA Utilities in South Australia and the rail privatisation in Queensland, for example, both
provide insights into a potential structure that could be adopted in NSW.
In Queensland, the Queensland Government sold a 99-year lease of the central Queensland coal network rail
system to Aurizon. Under the Queensland model, if Aurizon wishes to extend or enhance its rail network it must
meet various criteria and obtain State Government approval. To avoid a charge of stamp duty to Aurizon, the
State Government would directly acquire any necessary land. Aurizon would then build the necessary rail
infrastructure on the land at its cost and then immediately transfer the rail infrastructure to the Queensland
Government. The infrastructure would then be leased back to Aurizon by the Queensland Government as part
of the 99 year lease.
Privatisation of Electricity Networks, New South Wales, Australia
12 Norton Rose Fulbright
In SA, the lessee (SA Power Networks) of the 200 year lease is responsible for all costs, expenses and liabilities
associated with the leased network assets. The lessee is also responsible for all maintenance, upgrading and
replacement of those assets. Again, capital expenditure by the lessee therefore resulted in the creation of assets
that were owned by the lessor (SA Government) and leased back to the lessee.
In the SA example, the 200 year lease of land involves periodic rental payments through the term of the lease,
raising potential tax treatment issues for any bidder. However, the bidder in SA opted to pre-pay all of the rental
payments for the 200 year lease of the network assets in the form of the privatisation price.
Other issues in due diligence
As part of due diligence, any bidder will need to understand the upside and downside risks associated with the
various cash flows generated by each electricity network under the proposed privatisation structure. As
identified above, some of these issues are not necessarily straightforward and will be heavily affected by the
regulatory regime as well as any obligations imposed on bidders relating to electricity pricing.
An important issue in due diligence may also involve the capital structure of the relevant businesses and the
extent to which gearing levels can be changed, particularly in circumstances where the NSW Government still
owns a substantial interest. The capital structure will have a direct impact on valuation.
Other issues for due diligence include the potential impact of new technologies on distribution businesses. For
example, the NEM currently has some 3,500MW of solar power generated by consumers and that rate is
continuing to increase, altering load profiles and resulting in re-injection of power via distributed generation. In
the coming decades, we can also expect the widespread deployment of batteries and electric cars to have a
dramatic on load profiles in distribution networks
Other potential issues for due diligence include, for example:
• property issues, including easement and native title issues;
• insurance and litigation risks, particularly in the context of recent litigation involving damage caused by fires;
• employee and industrial relations issues, including such matters as superannuation entitlements;
• occupational health and safety issues, particularly given the transmission of electricity is an inherently
hazardous operation;
• environmental issues; and
• information technology issues.
Our firm
Norton Rose Fulbright is the third largest global law firm in the world. We have more than 3,800 lawyers working
across some 54 international offices located throughout Europe, the United States, Canada, Latin America, Asia,
Australia, Africa, the Middle East and Central Asia.
We also have one of the largest global energy practices in the world, with lawyers in every major energy market.
Our objective is simple - to deliver seamless, sophisticated and forward thinking advice to our energy clients
wherever they are in the world.
Our team of over 800 energy lawyers offers not only a clear and proven understanding of the law, but also its
unique application within the energy industry. Many of our energy lawyers have worked at major energy
companies. We provide legal capabilities across the full spectrum of energy industry sectors. It is this breadth
Privatisation of Electricity Networks, New South Wales, Australia
13 Norton Rose Fulbright
of experience, combined with our strength in multiple disciplines that enables us to provide our clients with truly
commercial and balanced legal advice.
Our Australian team
Norton Rose Fulbright is one of the largest and leading law firms in the Australian market. As a full service
corporate law firm, our team includes experts in all areas covered by the privatisation. With lawyers in every
major energy market across the world, we are one of the few firms in Australia that can support domestic and
international organisations in the energy sector, including lenders, government and other market participants.
We offer a global energy powerhouse unmatched in scale and experience across the sector, from power,
renewables, oil & gas, and water to sustainability & climate change. In Australia, we advise many of the largest
players in the energy sector with their transactional and operational work by integrating multi-disciplinary teams,
including project and acquisition finance, mergers and acquisitions, construction, disputes, environment and
safety lawyers, to deliver innovative solutions in a challenging market.
Our experience and expertise in the Australian electricity market is very extensive indeed. Our team members
have experience in many of the significant privatisations in the energy sector in Australia including energy sector
privatisations such as the ETSA privatisation mentioned in this briefing note; the AUD 800m ActewAGL
privatisation; the Queensland renewables assets privatisation, and the AUD 2.4 billion Dampier-Bunbury natural
gas pipeline privatisation and sale. We have also advised on major energy and infrastructure sector trade sales
including the recent ElectraNet sale, the AUD 800 million Pulse Energy sale, the AUD 1 billion Basslink bid, the
AUD1.2 billion Southern Hydro sale, the AUD 2 billion Tasmanian water industry corporatisation, and the $2.5
billion Victorian Desalination Plant PPP.
We have listed some 100 of our recent Australian electricity matters in our electricity credentials statement. We
are happy to provide a copy on request.
Contacts
For more information on this briefing note, please contact and of the following partners:
Vincent Dwyer
Partner / Head of Energy (Asia-Pacific)
Norton Rose Fulbright Australia
+61 2 9330 8238
vincent.dwyer@nortonrosefulbright.com
Dr Martyn Taylor
Partner / Author of this note
Norton Rose Fulbright Australia
+61 2 9330 8056
martyn.taylor@nortonrosefulbright.com
Adrian Ahern
Partner / Chairman
Norton Rose Fulbright Australia
+61 2 9330 8216
adrian.ahern@nortonrosefulbright.com
Nigel Deed
Partner
Norton Rose Fulbright Australia
+61 2 9330 8915
nigel.deed@nortonrosefulbright.com
Chris Redden
Partner
Norton Rose Fulbright Australia
+61 2 9330 8435
chris.redden@nortonrosefulbright.com
Simon Currie
Partner / Head of Energy (Global)
Norton Rose Fulbright LLP
+44 20 7444 3402
simon.currie@nortonrosefulbright.com
Norton Rose Fulbright
References to "Norton Rose Fulbright", "the law firm", and "legal practice" are to one or more of the Norton Rose Fulbright members or to one of their respective affiliates
(together "Norton Rose Fulbright entity/entities"). In respect of this bid, advice and services will be provided by Norton Rose Fulbright Australia (the "Contracting Party") in
accordance with its terms of engagement. No other Norton Rose Fulbright entity nor any individual who is a member, partner, shareholder, director, employee or consultant of,
in or to any Norton Rose entity other than the Contracting Party accepts or assumes responsibility, or has any liability, to you or any third party for advice or services provided.
Any reference to a partner or director is to a member, employee or consultant with equivalent standing and qualifications of the relevant Norton Rose Fulbright entity.
www.nortonrosefulbright.com

More Related Content

What's hot

R41960 Fed Energy Contracting Authority
R41960 Fed Energy Contracting AuthorityR41960 Fed Energy Contracting Authority
R41960 Fed Energy Contracting AuthorityAnthony Andrews
 
Reforming the Philippine Electric Power Industry Reform Act (EPIRA)
Reforming the Philippine Electric Power Industry Reform Act (EPIRA)Reforming the Philippine Electric Power Industry Reform Act (EPIRA)
Reforming the Philippine Electric Power Industry Reform Act (EPIRA)Elvin Uy
 
Electricity laws and regulations
Electricity laws and regulationsElectricity laws and regulations
Electricity laws and regulationsAkshat Goel
 
Captive power Policy
Captive power PolicyCaptive power Policy
Captive power PolicyPRIYANK JAIN
 
Indian power market design
Indian power market designIndian power market design
Indian power market designNavajyoti Martha
 
Electricity Act 2003 and its proposed amendments
Electricity Act 2003 and its proposed amendmentsElectricity Act 2003 and its proposed amendments
Electricity Act 2003 and its proposed amendmentsAmitava Nag
 
Wind Force Newsletter Dec, Edition, 2011
Wind Force Newsletter   Dec, Edition, 2011Wind Force Newsletter   Dec, Edition, 2011
Wind Force Newsletter Dec, Edition, 2011rupeshsingh_1
 
Cats overview of_scottish_governments_first_annual_update_of_2020_renewables_...
Cats overview of_scottish_governments_first_annual_update_of_2020_renewables_...Cats overview of_scottish_governments_first_annual_update_of_2020_renewables_...
Cats overview of_scottish_governments_first_annual_update_of_2020_renewables_...preservelenoxmountain
 
Pakistan 2013 - Ministry Power & Water - Roadmap to reform Power & Utility s...
Pakistan 2013 -  Ministry Power & Water - Roadmap to reform Power & Utility s...Pakistan 2013 -  Ministry Power & Water - Roadmap to reform Power & Utility s...
Pakistan 2013 - Ministry Power & Water - Roadmap to reform Power & Utility s...Atif Ahmad
 
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPA
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPAIndian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPA
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPAIPPAI
 
Captive Power Plants
Captive Power PlantsCaptive Power Plants
Captive Power PlantsKoos Smit
 
competition project
competition projectcompetition project
competition projectAnshu Kumar
 
Legislative Staff Briefing - January 26, 2017
Legislative Staff Briefing - January 26, 2017Legislative Staff Briefing - January 26, 2017
Legislative Staff Briefing - January 26, 2017aectnet
 
Group captive mechanism
Group captive mechanismGroup captive mechanism
Group captive mechanismSusDevIndia
 
Electricity Overview
Electricity OverviewElectricity Overview
Electricity OverviewParthosb
 
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...Anshuman Batra
 
Gridlocked a long term look at south africas electricity sector
Gridlocked   a long term look at south africas electricity sectorGridlocked   a long term look at south africas electricity sector
Gridlocked a long term look at south africas electricity sectorMarketing Durban Chamber
 

What's hot (20)

R41960 Fed Energy Contracting Authority
R41960 Fed Energy Contracting AuthorityR41960 Fed Energy Contracting Authority
R41960 Fed Energy Contracting Authority
 
Reforming the Philippine Electric Power Industry Reform Act (EPIRA)
Reforming the Philippine Electric Power Industry Reform Act (EPIRA)Reforming the Philippine Electric Power Industry Reform Act (EPIRA)
Reforming the Philippine Electric Power Industry Reform Act (EPIRA)
 
Electricity laws and regulations
Electricity laws and regulationsElectricity laws and regulations
Electricity laws and regulations
 
Captive power Policy
Captive power PolicyCaptive power Policy
Captive power Policy
 
Indian power market design
Indian power market designIndian power market design
Indian power market design
 
Electricity Act 2003 and its proposed amendments
Electricity Act 2003 and its proposed amendmentsElectricity Act 2003 and its proposed amendments
Electricity Act 2003 and its proposed amendments
 
Captive gen
Captive genCaptive gen
Captive gen
 
Indian Power Sector
Indian Power SectorIndian Power Sector
Indian Power Sector
 
Wind Force Newsletter Dec, Edition, 2011
Wind Force Newsletter   Dec, Edition, 2011Wind Force Newsletter   Dec, Edition, 2011
Wind Force Newsletter Dec, Edition, 2011
 
Cats overview of_scottish_governments_first_annual_update_of_2020_renewables_...
Cats overview of_scottish_governments_first_annual_update_of_2020_renewables_...Cats overview of_scottish_governments_first_annual_update_of_2020_renewables_...
Cats overview of_scottish_governments_first_annual_update_of_2020_renewables_...
 
Pakistan 2013 - Ministry Power & Water - Roadmap to reform Power & Utility s...
Pakistan 2013 -  Ministry Power & Water - Roadmap to reform Power & Utility s...Pakistan 2013 -  Ministry Power & Water - Roadmap to reform Power & Utility s...
Pakistan 2013 - Ministry Power & Water - Roadmap to reform Power & Utility s...
 
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPA
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPAIndian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPA
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPA
 
Captive Power Plants
Captive Power PlantsCaptive Power Plants
Captive Power Plants
 
competition project
competition projectcompetition project
competition project
 
Electricity policies
Electricity policiesElectricity policies
Electricity policies
 
Legislative Staff Briefing - January 26, 2017
Legislative Staff Briefing - January 26, 2017Legislative Staff Briefing - January 26, 2017
Legislative Staff Briefing - January 26, 2017
 
Group captive mechanism
Group captive mechanismGroup captive mechanism
Group captive mechanism
 
Electricity Overview
Electricity OverviewElectricity Overview
Electricity Overview
 
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
 
Gridlocked a long term look at south africas electricity sector
Gridlocked   a long term look at south africas electricity sectorGridlocked   a long term look at south africas electricity sector
Gridlocked a long term look at south africas electricity sector
 

Viewers also liked

Predatory buying to corner a market: ACCC v Cement Australia
Predatory buying to corner a market: ACCC v Cement AustraliaPredatory buying to corner a market: ACCC v Cement Australia
Predatory buying to corner a market: ACCC v Cement AustraliaMartyn Taylor
 
Australian telecoms licensing - An overview
Australian telecoms licensing - An overviewAustralian telecoms licensing - An overview
Australian telecoms licensing - An overviewMartyn Taylor
 
Unilateral conduct: The historic and international context
Unilateral conduct: The historic and international contextUnilateral conduct: The historic and international context
Unilateral conduct: The historic and international contextMartyn Taylor
 
Australian Convergence Review 2012
Australian Convergence Review 2012Australian Convergence Review 2012
Australian Convergence Review 2012Martyn Taylor
 
Competition Policy in Smaller Economies: Balancing Regulation & Investment
Competition Policy in Smaller Economies: Balancing Regulation & InvestmentCompetition Policy in Smaller Economies: Balancing Regulation & Investment
Competition Policy in Smaller Economies: Balancing Regulation & InvestmentMartyn Taylor
 
EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - M...
EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - M...EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - M...
EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - M...Martyn Taylor
 
Merger review - International insights - April 2016
Merger review - International insights - April 2016Merger review - International insights - April 2016
Merger review - International insights - April 2016Martyn Taylor
 
Competition Law in High Technology Industries - Insights for Australia
Competition Law in High Technology Industries - Insights for AustraliaCompetition Law in High Technology Industries - Insights for Australia
Competition Law in High Technology Industries - Insights for AustraliaMartyn Taylor
 
The greatest Australian competition reforms in 20 years?
The greatest Australian competition reforms in 20 years?The greatest Australian competition reforms in 20 years?
The greatest Australian competition reforms in 20 years?Martyn Taylor
 
Status of Australian Privatisations - October 2016
Status of Australian Privatisations - October 2016Status of Australian Privatisations - October 2016
Status of Australian Privatisations - October 2016Martyn Taylor
 
EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - F...
EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - F...EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - F...
EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - F...Martyn Taylor
 
Fuel industry competition in Australia
Fuel industry competition in AustraliaFuel industry competition in Australia
Fuel industry competition in AustraliaMartyn Taylor
 
Australian Media Ownership Controls: Where To Now?
Australian Media Ownership Controls: Where To Now?Australian Media Ownership Controls: Where To Now?
Australian Media Ownership Controls: Where To Now?Martyn Taylor
 
Physician Strategies - Physician Engagement
Physician Strategies - Physician EngagementPhysician Strategies - Physician Engagement
Physician Strategies - Physician EngagementEndeavor Management
 
Privatisation of Port of Melbourne, Australia
Privatisation of Port of Melbourne, AustraliaPrivatisation of Port of Melbourne, Australia
Privatisation of Port of Melbourne, AustraliaMartyn Taylor
 
Telecoms spectrum licensing - regulation of radiofrequency spectrum
Telecoms spectrum licensing - regulation of radiofrequency spectrumTelecoms spectrum licensing - regulation of radiofrequency spectrum
Telecoms spectrum licensing - regulation of radiofrequency spectrumMartyn Taylor
 
Competition and Consumer Law Update: Every cloud has a silver lining...
Competition and Consumer Law Update: Every cloud has a silver lining...Competition and Consumer Law Update: Every cloud has a silver lining...
Competition and Consumer Law Update: Every cloud has a silver lining...Martyn Taylor
 
Next Generation Broadband In Asia: Strategies to Promote Investment
Next Generation Broadband In Asia: Strategies to Promote InvestmentNext Generation Broadband In Asia: Strategies to Promote Investment
Next Generation Broadband In Asia: Strategies to Promote InvestmentMartyn Taylor
 
Competition Law in High Technology Industries - Insights for Australia (Slides)
Competition Law in High Technology Industries - Insights for Australia (Slides)Competition Law in High Technology Industries - Insights for Australia (Slides)
Competition Law in High Technology Industries - Insights for Australia (Slides)Martyn Taylor
 
MVNOs and mobile resellers - Commercial and regulatory issues
MVNOs and mobile resellers - Commercial and regulatory issuesMVNOs and mobile resellers - Commercial and regulatory issues
MVNOs and mobile resellers - Commercial and regulatory issuesMartyn Taylor
 

Viewers also liked (20)

Predatory buying to corner a market: ACCC v Cement Australia
Predatory buying to corner a market: ACCC v Cement AustraliaPredatory buying to corner a market: ACCC v Cement Australia
Predatory buying to corner a market: ACCC v Cement Australia
 
Australian telecoms licensing - An overview
Australian telecoms licensing - An overviewAustralian telecoms licensing - An overview
Australian telecoms licensing - An overview
 
Unilateral conduct: The historic and international context
Unilateral conduct: The historic and international contextUnilateral conduct: The historic and international context
Unilateral conduct: The historic and international context
 
Australian Convergence Review 2012
Australian Convergence Review 2012Australian Convergence Review 2012
Australian Convergence Review 2012
 
Competition Policy in Smaller Economies: Balancing Regulation & Investment
Competition Policy in Smaller Economies: Balancing Regulation & InvestmentCompetition Policy in Smaller Economies: Balancing Regulation & Investment
Competition Policy in Smaller Economies: Balancing Regulation & Investment
 
EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - M...
EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - M...EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - M...
EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - M...
 
Merger review - International insights - April 2016
Merger review - International insights - April 2016Merger review - International insights - April 2016
Merger review - International insights - April 2016
 
Competition Law in High Technology Industries - Insights for Australia
Competition Law in High Technology Industries - Insights for AustraliaCompetition Law in High Technology Industries - Insights for Australia
Competition Law in High Technology Industries - Insights for Australia
 
The greatest Australian competition reforms in 20 years?
The greatest Australian competition reforms in 20 years?The greatest Australian competition reforms in 20 years?
The greatest Australian competition reforms in 20 years?
 
Status of Australian Privatisations - October 2016
Status of Australian Privatisations - October 2016Status of Australian Privatisations - October 2016
Status of Australian Privatisations - October 2016
 
EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - F...
EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - F...EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - F...
EXPERTS’ REPORT ON NATIONAL ICT POLICY PHASE 2 REFORMS - PAPUA NEW GUINEA - F...
 
Fuel industry competition in Australia
Fuel industry competition in AustraliaFuel industry competition in Australia
Fuel industry competition in Australia
 
Australian Media Ownership Controls: Where To Now?
Australian Media Ownership Controls: Where To Now?Australian Media Ownership Controls: Where To Now?
Australian Media Ownership Controls: Where To Now?
 
Physician Strategies - Physician Engagement
Physician Strategies - Physician EngagementPhysician Strategies - Physician Engagement
Physician Strategies - Physician Engagement
 
Privatisation of Port of Melbourne, Australia
Privatisation of Port of Melbourne, AustraliaPrivatisation of Port of Melbourne, Australia
Privatisation of Port of Melbourne, Australia
 
Telecoms spectrum licensing - regulation of radiofrequency spectrum
Telecoms spectrum licensing - regulation of radiofrequency spectrumTelecoms spectrum licensing - regulation of radiofrequency spectrum
Telecoms spectrum licensing - regulation of radiofrequency spectrum
 
Competition and Consumer Law Update: Every cloud has a silver lining...
Competition and Consumer Law Update: Every cloud has a silver lining...Competition and Consumer Law Update: Every cloud has a silver lining...
Competition and Consumer Law Update: Every cloud has a silver lining...
 
Next Generation Broadband In Asia: Strategies to Promote Investment
Next Generation Broadband In Asia: Strategies to Promote InvestmentNext Generation Broadband In Asia: Strategies to Promote Investment
Next Generation Broadband In Asia: Strategies to Promote Investment
 
Competition Law in High Technology Industries - Insights for Australia (Slides)
Competition Law in High Technology Industries - Insights for Australia (Slides)Competition Law in High Technology Industries - Insights for Australia (Slides)
Competition Law in High Technology Industries - Insights for Australia (Slides)
 
MVNOs and mobile resellers - Commercial and regulatory issues
MVNOs and mobile resellers - Commercial and regulatory issuesMVNOs and mobile resellers - Commercial and regulatory issues
MVNOs and mobile resellers - Commercial and regulatory issues
 

Similar to NSW Government to Partially Privatise Electricity Networks

Energy Malaysia Volume 6 (1)
Energy Malaysia Volume 6 (1)Energy Malaysia Volume 6 (1)
Energy Malaysia Volume 6 (1)Nieza Noordin
 
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...TransGrid AU
 
Independent Review of the Australian National Electricity Market
Independent Review of the Australian National Electricity MarketIndependent Review of the Australian National Electricity Market
Independent Review of the Australian National Electricity MarketTurlough Guerin GAICD FGIA
 
Investment in solar and wind generation in australia lessons learned
Investment in solar and wind generation in australia   lessons learnedInvestment in solar and wind generation in australia   lessons learned
Investment in solar and wind generation in australia lessons learnedachanana
 
Construction Regulatory Issues for Large Scale Solar (PWC 2016)
Construction Regulatory Issues for Large Scale Solar (PWC 2016)Construction Regulatory Issues for Large Scale Solar (PWC 2016)
Construction Regulatory Issues for Large Scale Solar (PWC 2016)Turlough Guerin GAICD FGIA
 
Energy policy aus
Energy policy ausEnergy policy aus
Energy policy ausRohil Kumar
 
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Energy Network marcus evans
 
Group2 current scenario of deregulation in developed and developing countries
Group2 current scenario of deregulation in developed and developing countriesGroup2 current scenario of deregulation in developed and developing countries
Group2 current scenario of deregulation in developed and developing countriesPulakesh k kalita
 
Sunpowerd - Distributed Solar in Ghana
Sunpowerd - Distributed Solar in GhanaSunpowerd - Distributed Solar in Ghana
Sunpowerd - Distributed Solar in GhanaAlex Pischalnikov
 
Canada’s electricity sector reform
Canada’s electricity sector reform Canada’s electricity sector reform
Canada’s electricity sector reform PRIYANK JAIN
 
POWER GENERATION SCENERIO IN INDIA
POWER GENERATION SCENERIO IN INDIAPOWER GENERATION SCENERIO IN INDIA
POWER GENERATION SCENERIO IN INDIASAURAV DAYAL SING
 
20 20 Vision Cleantech
20 20 Vision Cleantech20 20 Vision Cleantech
20 20 Vision Cleantechmnewson
 
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022 Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022 collinsR1
 
Offshore Wind Energy Market Trends and Forecast 2014 - 2022
Offshore Wind Energy Market Trends and Forecast 2014 - 2022Offshore Wind Energy Market Trends and Forecast 2014 - 2022
Offshore Wind Energy Market Trends and Forecast 2014 - 2022collinsR1
 

Similar to NSW Government to Partially Privatise Electricity Networks (20)

Opportunities for wind energy in NSW
Opportunities for wind energy in NSWOpportunities for wind energy in NSW
Opportunities for wind energy in NSW
 
Energy Malaysia Volume 6 (1)
Energy Malaysia Volume 6 (1)Energy Malaysia Volume 6 (1)
Energy Malaysia Volume 6 (1)
 
9-Energy
9-Energy9-Energy
9-Energy
 
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
 
Independent Review of the Australian National Electricity Market
Independent Review of the Australian National Electricity MarketIndependent Review of the Australian National Electricity Market
Independent Review of the Australian National Electricity Market
 
Investment in solar and wind generation in australia lessons learned
Investment in solar and wind generation in australia   lessons learnedInvestment in solar and wind generation in australia   lessons learned
Investment in solar and wind generation in australia lessons learned
 
Construction Regulatory Issues for Large Scale Solar (PWC 2016)
Construction Regulatory Issues for Large Scale Solar (PWC 2016)Construction Regulatory Issues for Large Scale Solar (PWC 2016)
Construction Regulatory Issues for Large Scale Solar (PWC 2016)
 
Energy policy aus
Energy policy ausEnergy policy aus
Energy policy aus
 
Power scenerio in india
Power scenerio in indiaPower scenerio in india
Power scenerio in india
 
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
 
Group2 current scenario of deregulation in developed and developing countries
Group2 current scenario of deregulation in developed and developing countriesGroup2 current scenario of deregulation in developed and developing countries
Group2 current scenario of deregulation in developed and developing countries
 
Case Study and Recommendations
Case Study and RecommendationsCase Study and Recommendations
Case Study and Recommendations
 
Sunpowerd - Distributed Solar in Ghana
Sunpowerd - Distributed Solar in GhanaSunpowerd - Distributed Solar in Ghana
Sunpowerd - Distributed Solar in Ghana
 
G0371051055
G0371051055G0371051055
G0371051055
 
Canada’s electricity sector reform
Canada’s electricity sector reform Canada’s electricity sector reform
Canada’s electricity sector reform
 
POWER GENERATION SCENERIO IN INDIA
POWER GENERATION SCENERIO IN INDIAPOWER GENERATION SCENERIO IN INDIA
POWER GENERATION SCENERIO IN INDIA
 
20 20 Vision Cleantech
20 20 Vision Cleantech20 20 Vision Cleantech
20 20 Vision Cleantech
 
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022 Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
Offshore Wind Energy Installed Capacity to Reach 52,120.9 MW by 2022
 
Offshore Wind Energy Market Trends and Forecast 2014 - 2022
Offshore Wind Energy Market Trends and Forecast 2014 - 2022Offshore Wind Energy Market Trends and Forecast 2014 - 2022
Offshore Wind Energy Market Trends and Forecast 2014 - 2022
 
F0513644
F0513644F0513644
F0513644
 

More from Martyn Taylor

Developments in the TMT Sector - Current trends & emerging legal issues
Developments in the TMT Sector - Current trends & emerging legal issuesDevelopments in the TMT Sector - Current trends & emerging legal issues
Developments in the TMT Sector - Current trends & emerging legal issuesMartyn Taylor
 
Telecoms in a convergent world - Emerging issues
Telecoms in a convergent world - Emerging issuesTelecoms in a convergent world - Emerging issues
Telecoms in a convergent world - Emerging issuesMartyn Taylor
 
Infrastructure regulation - exploring the key models (Australia)
Infrastructure regulation - exploring the key models (Australia)Infrastructure regulation - exploring the key models (Australia)
Infrastructure regulation - exploring the key models (Australia)Martyn Taylor
 
MVNOs & M2M (Machine to Machine) - Mobile telecommunications in 2015
MVNOs & M2M (Machine to Machine) - Mobile telecommunications in 2015MVNOs & M2M (Machine to Machine) - Mobile telecommunications in 2015
MVNOs & M2M (Machine to Machine) - Mobile telecommunications in 2015Martyn Taylor
 
M&A law in the Asia-Pacific
M&A law in the Asia-PacificM&A law in the Asia-Pacific
M&A law in the Asia-PacificMartyn Taylor
 
M2M (Machine to Machine) & MVNOs - Mobile telecommunications in 2014
M2M (Machine to Machine) & MVNOs - Mobile telecommunications in 2014M2M (Machine to Machine) & MVNOs - Mobile telecommunications in 2014
M2M (Machine to Machine) & MVNOs - Mobile telecommunications in 2014Martyn Taylor
 
Privatisation of Port of Newcastle, Australia
Privatisation of Port of Newcastle, AustraliaPrivatisation of Port of Newcastle, Australia
Privatisation of Port of Newcastle, AustraliaMartyn Taylor
 
Analysis of the Australian National Access Regime
Analysis of the Australian National Access RegimeAnalysis of the Australian National Access Regime
Analysis of the Australian National Access RegimeMartyn Taylor
 
A Practical Approach to Australian Competition Issues
A Practical Approach to Australian Competition IssuesA Practical Approach to Australian Competition Issues
A Practical Approach to Australian Competition IssuesMartyn Taylor
 
Obtaining Australian merger and acquisition clearances in 2012
Obtaining Australian merger and acquisition clearances in 2012Obtaining Australian merger and acquisition clearances in 2012
Obtaining Australian merger and acquisition clearances in 2012Martyn Taylor
 
Competition and Access Issues in Mining And Resources
Competition and Access Issues in Mining And ResourcesCompetition and Access Issues in Mining And Resources
Competition and Access Issues in Mining And ResourcesMartyn Taylor
 
International Competition Law
International Competition LawInternational Competition Law
International Competition LawMartyn Taylor
 
Privatisation of Port Botany and Port Kembla, Australia
Privatisation of Port Botany and Port Kembla, AustraliaPrivatisation of Port Botany and Port Kembla, Australia
Privatisation of Port Botany and Port Kembla, AustraliaMartyn Taylor
 

More from Martyn Taylor (13)

Developments in the TMT Sector - Current trends & emerging legal issues
Developments in the TMT Sector - Current trends & emerging legal issuesDevelopments in the TMT Sector - Current trends & emerging legal issues
Developments in the TMT Sector - Current trends & emerging legal issues
 
Telecoms in a convergent world - Emerging issues
Telecoms in a convergent world - Emerging issuesTelecoms in a convergent world - Emerging issues
Telecoms in a convergent world - Emerging issues
 
Infrastructure regulation - exploring the key models (Australia)
Infrastructure regulation - exploring the key models (Australia)Infrastructure regulation - exploring the key models (Australia)
Infrastructure regulation - exploring the key models (Australia)
 
MVNOs & M2M (Machine to Machine) - Mobile telecommunications in 2015
MVNOs & M2M (Machine to Machine) - Mobile telecommunications in 2015MVNOs & M2M (Machine to Machine) - Mobile telecommunications in 2015
MVNOs & M2M (Machine to Machine) - Mobile telecommunications in 2015
 
M&A law in the Asia-Pacific
M&A law in the Asia-PacificM&A law in the Asia-Pacific
M&A law in the Asia-Pacific
 
M2M (Machine to Machine) & MVNOs - Mobile telecommunications in 2014
M2M (Machine to Machine) & MVNOs - Mobile telecommunications in 2014M2M (Machine to Machine) & MVNOs - Mobile telecommunications in 2014
M2M (Machine to Machine) & MVNOs - Mobile telecommunications in 2014
 
Privatisation of Port of Newcastle, Australia
Privatisation of Port of Newcastle, AustraliaPrivatisation of Port of Newcastle, Australia
Privatisation of Port of Newcastle, Australia
 
Analysis of the Australian National Access Regime
Analysis of the Australian National Access RegimeAnalysis of the Australian National Access Regime
Analysis of the Australian National Access Regime
 
A Practical Approach to Australian Competition Issues
A Practical Approach to Australian Competition IssuesA Practical Approach to Australian Competition Issues
A Practical Approach to Australian Competition Issues
 
Obtaining Australian merger and acquisition clearances in 2012
Obtaining Australian merger and acquisition clearances in 2012Obtaining Australian merger and acquisition clearances in 2012
Obtaining Australian merger and acquisition clearances in 2012
 
Competition and Access Issues in Mining And Resources
Competition and Access Issues in Mining And ResourcesCompetition and Access Issues in Mining And Resources
Competition and Access Issues in Mining And Resources
 
International Competition Law
International Competition LawInternational Competition Law
International Competition Law
 
Privatisation of Port Botany and Port Kembla, Australia
Privatisation of Port Botany and Port Kembla, AustraliaPrivatisation of Port Botany and Port Kembla, Australia
Privatisation of Port Botany and Port Kembla, Australia
 

Recently uploaded

Key Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax RatesKey Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax RatesHome Tax Saver
 
如何办理威斯康星大学密尔沃基分校毕业证学位证书
 如何办理威斯康星大学密尔沃基分校毕业证学位证书 如何办理威斯康星大学密尔沃基分校毕业证学位证书
如何办理威斯康星大学密尔沃基分校毕业证学位证书Fir sss
 
Difference between LLP, Partnership, and Company
Difference between LLP, Partnership, and CompanyDifference between LLP, Partnership, and Company
Difference between LLP, Partnership, and Companyaneesashraf6
 
如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书SD DS
 
Trial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 seditionTrial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 seditionNilamPadekar1
 
Succession (Articles 774-1116 Civil Code
Succession (Articles 774-1116 Civil CodeSuccession (Articles 774-1116 Civil Code
Succession (Articles 774-1116 Civil CodeMelvinPernez2
 
Alexis O'Connell Arrest Records Houston Texas lexileeyogi
Alexis O'Connell Arrest Records Houston Texas lexileeyogiAlexis O'Connell Arrest Records Houston Texas lexileeyogi
Alexis O'Connell Arrest Records Houston Texas lexileeyogiBlayneRush1
 
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Dr. Oliver Massmann
 
Alexis O'Connell Lexileeyogi 512-840-8791
Alexis O'Connell Lexileeyogi 512-840-8791Alexis O'Connell Lexileeyogi 512-840-8791
Alexis O'Connell Lexileeyogi 512-840-8791BlayneRush1
 
Vanderburgh County Sheriff says he will Not Raid Delta 8 Shops
Vanderburgh County Sheriff says he will Not Raid Delta 8 ShopsVanderburgh County Sheriff says he will Not Raid Delta 8 Shops
Vanderburgh County Sheriff says he will Not Raid Delta 8 ShopsAbdul-Hakim Shabazz
 
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书SD DS
 
Test Identification Parade & Dying Declaration.pptx
Test Identification Parade & Dying Declaration.pptxTest Identification Parade & Dying Declaration.pptx
Test Identification Parade & Dying Declaration.pptxsrikarna235
 
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书Fir L
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书FS LS
 
Law360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics GuidanceLaw360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics GuidanceMichael Cicero
 
如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书
如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书
如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书SD DS
 
Indian Contract Act-1872-presentation.pptx
Indian Contract Act-1872-presentation.pptxIndian Contract Act-1872-presentation.pptx
Indian Contract Act-1872-presentation.pptxSauravAnand68
 
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书srst S
 
POLICE ACT, 1861 the details about police system.pptx
POLICE ACT, 1861 the details about police system.pptxPOLICE ACT, 1861 the details about police system.pptx
POLICE ACT, 1861 the details about police system.pptxAbhishekchatterjee248859
 
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书FS LS
 

Recently uploaded (20)

Key Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax RatesKey Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax Rates
 
如何办理威斯康星大学密尔沃基分校毕业证学位证书
 如何办理威斯康星大学密尔沃基分校毕业证学位证书 如何办理威斯康星大学密尔沃基分校毕业证学位证书
如何办理威斯康星大学密尔沃基分校毕业证学位证书
 
Difference between LLP, Partnership, and Company
Difference between LLP, Partnership, and CompanyDifference between LLP, Partnership, and Company
Difference between LLP, Partnership, and Company
 
如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书
 
Trial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 seditionTrial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 sedition
 
Succession (Articles 774-1116 Civil Code
Succession (Articles 774-1116 Civil CodeSuccession (Articles 774-1116 Civil Code
Succession (Articles 774-1116 Civil Code
 
Alexis O'Connell Arrest Records Houston Texas lexileeyogi
Alexis O'Connell Arrest Records Houston Texas lexileeyogiAlexis O'Connell Arrest Records Houston Texas lexileeyogi
Alexis O'Connell Arrest Records Houston Texas lexileeyogi
 
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
 
Alexis O'Connell Lexileeyogi 512-840-8791
Alexis O'Connell Lexileeyogi 512-840-8791Alexis O'Connell Lexileeyogi 512-840-8791
Alexis O'Connell Lexileeyogi 512-840-8791
 
Vanderburgh County Sheriff says he will Not Raid Delta 8 Shops
Vanderburgh County Sheriff says he will Not Raid Delta 8 ShopsVanderburgh County Sheriff says he will Not Raid Delta 8 Shops
Vanderburgh County Sheriff says he will Not Raid Delta 8 Shops
 
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
 
Test Identification Parade & Dying Declaration.pptx
Test Identification Parade & Dying Declaration.pptxTest Identification Parade & Dying Declaration.pptx
Test Identification Parade & Dying Declaration.pptx
 
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
 
Law360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics GuidanceLaw360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
 
如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书
如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书
如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书
 
Indian Contract Act-1872-presentation.pptx
Indian Contract Act-1872-presentation.pptxIndian Contract Act-1872-presentation.pptx
Indian Contract Act-1872-presentation.pptx
 
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
 
POLICE ACT, 1861 the details about police system.pptx
POLICE ACT, 1861 the details about police system.pptxPOLICE ACT, 1861 the details about police system.pptx
POLICE ACT, 1861 the details about police system.pptx
 
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
 

NSW Government to Partially Privatise Electricity Networks

  • 1. each Privatisation of Electricity Networks, New South Wales, Australia In June 2014, the State Government in New South Wales (NSW) announced that it intends to privatise the NSW electricity networks. This briefing note sets out the likely structure of the privatisation and identifies some key issues. The NSW electricity networks are currently 100% state-owned and comprise: • TransGrid, an electricity transmission operator with a regulated asset base of AUD 6.1 billion that is expected to realise AUD 845 million in annual revenue next financial year. TransGrid owns roughly 14,000 km of transmission lines in NSW and transmits 71 GWh of electricity per annum over those lines. • Networks NSW, which comprises the following three electricity distribution businesses with a common CEO and common senior management: o AusGrid, an electricity distributor supplying 1.6 million retail electricity consumers in the Sydney, Central Coast, Hunter and Newcastle regions of NSW. AusGrid has a regulated asset base of AUD 14.6 billion across its distribution assets that is expected to realise some AUD 2.21 billion in revenue in the 2014/15 financial year. AusGrid owns roughly 42,000 km of distribution lines and is capable of meeting peak demand of 5,149 MW; o Endeavour Energy, an electricity distributor supplying 883,000 retail electricity consumers in western Sydney and the Illawarra regions of NSW. Endeavour has a regulated asset base of AUD 5.6 billion across its distribution assets that is expected to realise some AUD 949 million billion in revenue in the 2014/15 financial year. Endeavour owns roughly 34,500 km of distribution lines and is capable of meeting peak demand of 3,236 MW; and o Essential Energy, an electricity distributor supplying 803,000 retail customers in regional NSW. Essential has a regulated asset base of AUD 6.9 billion across its distribution assets that is expected to realise some AUD 1.29 billion in revenue in the 2014/15 financial year. Essential owns roughly 191,000 km of distribution lines and is capable of meeting peak demand of 2,185 MW. However, the Government has indicated that it does not intend to privatise Essential Energy. Briefing July 2014
  • 2. Privatisation of Electricity Networks, New South Wales, Australia 02 Norton Rose Fulbright The role of electricity networks in the NEM Electricity networks transport power from generators to customers. Transmission networks (e.g., TransGrid) transport power over long distances at high voltages, linking generators to distribution load centres. Distribution networks (e.g., Networks NSW) then reticulate electricity from the transmission network through urban and regional areas at lower voltages to provide electricity to customers. In Australia, the National Electricity Market (NEM) is a wholesale market comprising some 300 generators that collectively sell some 200 TWh of electricity annually in eastern and southern Australia. The principal customers of those generators are energy retailers. The energy retailers bundle electricity with network services for sale to some 9.3 million residential, commercial and industrial energy users. The NEM covers six Australian jurisdictions — Queensland, NSW, the Australian Capital Territory, Victoria, South Australia and Tasmania. Electricity is carried within the geographic area of the NEM via five State-based transmission networks, physically linked by cross-border interconnectors and servicing 13 distribution networks. In geographic span, the NEM is one of the world’s longest continuous AC systems, covering a distance of some 4,500 kilometres. Because energy networks are capital intensive and incur declining average costs as output increases, network services in a particular geographic area can be most efficiently provided by a single supplier, leading to a natural monopoly industry structure. Within the NEM, each transmission and distribution network has a monopoly in its particular geographic area. As such, the electricity networks in the NEM are regulated under Australia’s National Electricity Law to manage the risk of monopoly pricing and to encourage efficient investment in infrastructure. The National Electricity Law is explained later in this briefing note. Political context to the privatisation A number of other States in Australia privatised their electricity assets at an early stage, commencing with Victoria’s privatisation of the Loy Yang B power station in 1992. However, the privatisation of electricity assets in NSW was politically controversial for the NSW Labor Party in its role in Government over the 16 year period from 1995 to 2011. A number of proposals for NSW electricity privatisation did not proceed during that period, including under Premier Bob Carr in 1997 and Premier Morris Iemma in 2008. Ultimately, a first phase of privatisation was initiated by Premier Kristina Keneally in NSW in 2008. The first phase involved the sale of NSW electricity retail businesses, development sites and electricity generation output contracts (known as the “GenTrader” contracts). The Government realised AUD 5.3 billion in sale proceeds. With a change in NSW Government to a Liberal/National Coalition in March 2011, Premier Barry O’Farell initiated a second phase of privatisation. The second phase involved the sale of the electricity generation businesses. As at June 2014, aspects of this sale are still occurring, including a successful application for authorisation by AGL Energy to the Australian Competition Tribunal to acquire Macquarie Generation. In May 2012, the NSW Government announced that as part of its policy to put downward pressure on electricity prices a common chairman, board and CEO would be appointed to the State’s electricity distribution network businesses from 1 July 2012. As a result AusGrid, Endeavour Energy and Essential Energy were aggregated to form Networks NSW in a move viewed as a prelude to privatisation. On 10 June 2014, Premiere Mike Baird announced the third phase of privatisation, the subject of this briefing note, as part of a ‘Rebuild NSW’ policy that the Liberal/National Coalition will take to the 2015 State election. Given political concerns, an outright sale of the electricity networks is not contemplated. Instead, the privatisation will occur via the sale of 99 year ‘partial leases’. The Government will maintain ownership of 100% of Essential Energy and will also maintain an average ownership of 51% across all four electricity networks.
  • 3. Privatisation of Electricity Networks, New South Wales, Australia 03 Norton Rose Fulbright Timing for the privatisation Importantly, Premier Mike Baird has announced the privatisation of the electricity networks in the form of a policy commitment that he will take to the next NSW State election scheduled for 28 March 2015. The formal process for the privatisation will therefore not commence unless and until the Liberal/National Coalition is returned as the NSW Government on that date. As at June 2014, the Labor Party has indicated that it will not proceed with the privatisation if it wins the NSW State election in March 2015. Notwithstanding that the privatisation is contingent on the election, the NSW Government is currently undertaking preparatory work for the privatisation, including the appointment of financial and legal advisors. The preparatory work will likely involve the completion of a scoping study and an initial vendor due diligence. The scoping study is likely to make a series of recommendations regarding the structuring of the privatisation and implementing legislation. We expect the scoping study to be provided to the NSW Government in late 2014. Transaction structure – ownership permutations As at July 2014, the structure for the transaction has not been determined. We have speculated below on some possible structuring options. Importantly, the NSW Government has announced that it intends to maintain an overall 51% ownership level across all four electricity businesses, including maintaining 100% ownership of Essential Energy. The NSW Government has not yet identified how it will apply the 51% ownership threshold in practice. Some public statements, for example, refer to the ownership level as “51% of total electricity network assets”. Given that AusGrid is the most valuable business, the Government may prefer to privatise a full 100% of that business under a 99 year lease in order to maximise the privatisation proceeds. Similar reasoning may result in a structure in which different proportions of TransGrid and Endeavour Energy are privatised. Assuming that this 51% ownership threshold is interpreted as a simple average across the four businesses (or across three businesses if any two businesses are merged), this could lead to various ownership permutations. The following table sets out four possible examples: AusGrid Endeavour TransGrid Essential Equal distribution 35% State-owned 65% Private 35% State-owned 65% Private 35% State-owned 65% Private 100% State-owned Merged distributors 100% Private (merger of AusGrid and Endeavour) 53% State-owned 47% Private 100% State-owned Asymmetric distribution 1 100% Private 19% State-owned 81% Private 85% State-owned 15% Private 100% State-owned Asymmetric distribution 2 100% Private 52% State-owned 48% Private 52% State-owned 48% Private 100% State-owned
  • 4. Privatisation of Electricity Networks, New South Wales, Australia 04 Norton Rose Fulbright Other more creative solutions could be adopted. If AusGrid and Endeavour Energy are merged prior to privatisation, the 49% average can (arguably) be taken over the 3 resulting businesses with the practical effect of increasing the extent of possible privatisation. This option may maximise sale revenue for the NSW Government while achieving a more marketable privatisation with investors. If the 51% level were interpreted as a weighted average across the regulated asset base (RAB) of the businesses, other permutations would be possible (although weighting by the regulated asset base would reduce the extent of privatisation). This is illustrated in the following table in which the 51% level has been weighted by the value of the RAB: AusGrid Endeavour TransGrid Essential RAB (AUD million) AUD 15,645m AUD 5,616m AUD 6,104m AUD 6,888m Equal RAB allocation 23% State-owned 77% Private 60% State-owned 40% Private 55% State-owned 45% Private 100% State-owned Asymmetric distribution 100% Private 59% State-owned 41% Private 100% State-owned 100% State-owned Transaction structure – treatment of a 99 year ‘partial lease’ The NSW Government has indicated that the privatisation of the electricity networks will occur by way of a 99 year ‘partial lease’. A similar 99 year lease structure was used for the recent port privatisations in NSW. A 200 year lease structure was used for the privatisation of the ETSA Utilities electricity distribution network in South Australia (SA), creating SA Power Networks. If a combination of the approaches used in the NSW port privatisations and the ETSA privatisation were adopted, the following steps may occur: • First, the NSW Government would enact implementing legislation, potentially modelled in part on the Electricity Corporations (Restructuring and Disposal) Act 1999 of SA. This legislation would amend relevant NSW State legislation to facilitate and authorise the privatisation as well as effecting any changes necessary to implement the desired post-privatisation framework. • Second, the relevant assets to be privatised would be transferred into a State-owned Ministerial holding corporation (HoldCo), a State entity established by the implementing legislation to hold the network assets to be leased to the private sector. In SA, the HoldCo was the “Distribution Lessor Corporation”. • Third, a Project Company would be created to enter into a 99 year lease with HoldCo. The lease would provide HoldCo the rights to operate/use the relevant network assets and to retain the economic benefits of any charges it imposed, but would also impose a range of performance and compliance obligations. HoldCo would retain no control of the day to day operation of the network assets as its role as lessor under the 99 year lease. • Fourth, a separate 99 year lease may also be entered into with HoldCo by the Project Company for the lease of any associated land, but with HoldCo retaining freehold ownership. HoldCo would retain step-in rights and the ability to terminate both 99 year leases if the Project Company were to breach key obligations, but only for the predetermined ‘cure period’.
  • 5. Privatisation of Electricity Networks, New South Wales, Australia 05 Norton Rose Fulbright • Fifth, existing key contracts would be assigned by the Project Company. Some employees would also transfer to the Project Company, supported by various Government commitments intended to preserve employee entitlements. The privatisation could subsequently occur by the sale of the shares in the Project Company to an investor in the desired proportion, such as 100% or 49%. In this manner, investors would be offered a pre-packaged deal without any involvement in the negotiation of the 99 year lease. Any such sale could involve a trade sale or an initial public offering (IPO). In the SA privatisation of ETSA Utilities, bidders were given three different alternatives. Bidders could acquire shares in the Project Company. Alternatively, bidders could receive a novation of the pre-packaged 200 year leases and acquire the assets and liabilities of the Project Company. Alternatively, bidders could negotiate their own 200 year leases (to replace the pre-packaged 200 year leases) and acquire the assets and liabilities of the Project Company. In SA, the successful bidder opted for the third of these options. The situation becomes more complex if less than 100% of a business is privatised. An investor in a partial privatisation at less than 100% would, in practical effect, be entering into an incorporated joint venture with the NSW Government. In Australia, one precedent for such a structure is the TransACT joint venture. In a joint venture structure, investors may seek a shareholder agreement (or constitutional provisions) that address key governance issues for the Project Company, including appointment of executives and voting rights on the Board of Directors. A private investor at less than 50% may wish to secure de facto control. However, an IPO of a partial interest is also possible as demonstrated by the ‘T1’ privatisation of Telstra. Sale price As at June 2014, the sale price for the privatisation is not yet known. The sale price will depend heavily on the ultimate structure adopted for the privatisation. However, the NSW Government has indicated that it intends to realise at least AUD 13 billion in aggregate from the lease of NSW’s electricity networks. All of the sale proceeds are intended to be invested in new roads and other transport infrastructure projects in NSW. Assuming the Asset Recycling Fund Bill 2014 (Cth) is enacted, the NSW Government should also receive an amount of some AUD 2 billion as an incentive payment from the Commonwealth Government. Conditions for the partial lease In its ‘Rebuilding NSW’ policy for the 2015 State election, the Liberal/National Coalition has laid out strict conditions for the partial lease of the NSW electricity networks. These conditions are designed to promote the public interest and address community concerns. The conditions already announced by the NSW Government include: • all net proceeds from the privatisation will be invested in new productive infrastructure, through the Restart NSW Fund; • electricity network prices will be discounted by 1% off forecast regulated prices until 2019; • permanent award employees’ jobs will be protected, and treated consistently with previous transactions; • the transaction will have no adverse impact on electricity reliability; and • the regional presence of the network businesses will be maintained. It is possible that further conditions could be announced if the privatisation were to become a major political issue in the context of the 2015 NSW State election.
  • 6. Privatisation of Electricity Networks, New South Wales, Australia 06 Norton Rose Fulbright Preliminary issues A number of issues raised by the proposed privatisation are briefly summarised below, including: • the extent to which any regulatory clearances may be required by bidders; • the manner in which network companies are subject to price regulation; • the impact of electricity demand on future cash flows; and • the manner in which requirements for future investment in network infrastructure will be addressed. We believe one of the most significant issues for bidders will be “regulatory risk”. This is particularly relevant given the businesses are currently undertaking a regulatory reset for 2014 – 2019, with a draft determination to be issued by the AER in November 2014 and a final determination to be issued by the AER by 30 April 2015. Any appeal of any determination of the AER to the Australian Competition Tribunal thereafter will take 6 - 12 months to be heard, after any transaction is to be completed. We set out these issues in detail below. Regulatory clearances for bidders Key regulatory clearances required by bidders may include foreign investment approvals and competition clearances. Foreign investment approvals are straightforward and rarely withheld, but are a necessary formality. Competition clearances may be important if a bidder, or any participants in a bidding consortium, have existing electricity operations in Australia, whether in generation, transmission, distribution or retail. The ACCC may be concerned if the acquisition of shares in the Project Company could result in a substantial lessening of competition in any market in Australia. Concerns could arise, for example, if a potential investor was an electricity generator or retailer. In such circumstances, the ACCC may be concerned at the potential for a vertically integrated transmission or distribution network provider to discriminate in favour of its own operations. However, the potential for investment of a generator or retailer in vertical integration will not necessarily be fatal to ACCC clearance of an asset purchase. The ACCC’s reaction would turn on the circumstances of the case. The investor might be considered to have an immaterial shareholding or a role that gives it no practical influence. It may in any case be possible to provide a voluntary undertaking to the ACCC that addresses adequately any competition concerns. For example, an undertaking could be provided that competitors to the generator/retailer would be able to connect to the transmission or distribution network on a non-discriminatory basis. Also, requirements that these aspects of the businesses be ring-fenced may assist. Indeed, the ring fencing restrictions that already exist under the National Electricity Law may already alleviate these issues. If competition issues were identified, the strategy and timing for any approach to the ACCC would need to be carefully considered. Generally, the ACCC is not willing to provide clearance without undertaking public market inquiries. If confidentiality issues preclude inquiries prior to bid submission, the bid may need to be made conditional on any ACCC clearance. Regulation of TransGrid as a transmission network As a transmission network, TransGrid is subject to price and access regulation under the National Electricity Rules. The terms on which transmission networks offers transmission services to its customers (largely distributors) must be fair and reasonable. The Rules provide for commercial arbitration in the event of any network access dispute.
  • 7. Privatisation of Electricity Networks, New South Wales, Australia 07 Norton Rose Fulbright Under the Rules, the services provided by transmission networks are categorised into two baskets: “prescribed control services” (which comprise most core transmission services) and “negotiated services”. The charges for prescribed control services are heavily regulated, whereas the charges for negotiated services are negotiated and need only be based on the costs of providing those services (determined in accordance with a cost allocation methodology approved by the AER). In determining the pricing of prescribed control services, the Australian Energy Regulator (AER) must make a “transmission determination”, typically for a period of 5 years. This period is known as the “regulatory control period”. The Rules permit the AER to apply a revenue cap to transmission businesses. The AER has historically applied to TransGrid a revenue cap consistent with the approach adopted for other transmission networks in the NEM, and will almost certainly continue to do so. In determining the level of the revenue cap for a transmission network, the AER utilises the building block model (BBM) and regulated asset base (RAB), as discussed in further detail below. Transmission networks are required to have an approved pricing methodology that allocates that revenue across the relevant categories of prescribed control services, thereby determining tariff levels and the tariff structure. Specifically, transmission networks must seek approval by the AER, via the transmission determination, for a pricing methodology for an entire regulatory control period. The AER must approve the pricing methodology if it does not exceed the revenue cap and meets various criteria, including consistency with pricing principles in the Rules. The pricing principles identify the manner in which costs are to be attributed across the different categories of prescribed control services. The pricing principles also identify the permitted fixed and variable tariff structures. During the regulatory control period, the transmission network must publish annual prices that are determined in accordance with the approved pricing methodology. To date, transmission charges have comprised a fixed daily price component and variable demand/consumption component. Regulation of Networks NSW as distribution networks While the manner in which the distribution networks of Networks NSW are regulated is similar to transmission networks, there are some important nuances under the National Electricity Rules. Under the Rules, the services provided by distribution networks are categorised into three baskets: • “Direct control services” comprise most core distribution services. Direct control services are subject to both price and access regulation. The terms of access to direct control services are specified in the Rules and include connection and system security requirements. • “Negotiated services” largely comprise site-specific services. Negotiated services are subject to both price and access regulation. The terms of access to negotiated services must be negotiated by a distribution network in accordance with a negotiating framework that has been approved by the AER. • “Unregulated services” largely comprise ancillary services supplied in contestable circumstances or that do not otherwise need to be regulated. Unregulated services are not subject to access or price regulation under the National Electricity Rules. The charges for direct control services are heavily regulated, whereas the charges for negotiated services are negotiated and need only be based on the costs of providing those services (determined in accordance with a cost allocation method approved by the AER). Importantly, the level of regulation that may be applied by the AER to distribution networks for direct control services is greater than the level of regulation that may be applied by the AER to transmission networks in relation to prescribed control services. This regulation is referred to in the Rules as “control mechanisms”.
  • 8. Privatisation of Electricity Networks, New South Wales, Australia 08 Norton Rose Fulbright A diagram of the pricing baskets applied to electricity distributors is set out below: In determining the pricing of direct control services, the AER must make a “distribution determination”, typically for a period of 5 years. Again, this period is known as the “regulatory control period”. The Rules permit the AER to impose controls over the prices of direct control services, or apply a revenue cap, or both. The control mechanisms available to the AER are significant, including price caps, price schedules and revenue caps. The AER has historically applied revenue caps and annual price controls to the distribution networks in Networks NSW, consistent with the approach adopted for other distribution networks in the NEM, and will almost certainly continue to do so. In determining the level of the revenue cap for a distribution network, the AER utilises the building block model (BBM) and regulated asset base (RAB), as discussed in further detail below. Unlike transmission networks, distribution networks are required to submit an annual pricing proposal to the AER that sets out the various tariffs and the tariff structure proposed. The AER must approve the pricing if it does not exceed the revenue cap and meets various criteria, including consistency with detailed pricing principles in the Rules. Among other matters, the pricing principles allocate customers into tariff classes and apply charging parameters to each class. The distribution network is also required to publish on its website a statement of expected price trends over the full regulatory control period. To date, customer charges for distribution have comprised three key components: • a network access charge per day per connection (c/connection/day); • a electricity usage charge (c/kWh); and • a capacity charge per kiloWatt or kilovoltAmp, per day (c/kW/day or c/kVA/day) – namely a charge based on a customer’s maximum demand. NSW distribution services Direct control (revenue/price regulated) Negotiated Unregulated Alternative control (service specific charges) Standard control (general network charges) • Network premises connections • Network extensions • Types 1-4 metering services • Metering type 6 installation services • Metering types 5-6 provision, maintenance, reasoning and data services • Public lighting • Ancillary network services • Network services • Augmentation of the network • Type 7 metering services • Site-specific services
  • 9. Privatisation of Electricity Networks, New South Wales, Australia 09 Norton Rose Fulbright The Building Block Model (BBM) and Regulated Asset Base (RAB) In order to determine the revenue cap for distribution and transmission networks, the AER makes revenue determinations that are guided by various statutory criteria. The National Electricity Rules prescribe a cost- based pricing methodology for those determinations, known as the “building block model” or “BBM”. The BBM enables an “annual revenue requirement” (or “maximum allowable revenue”) to be determined for each network business in the form of a revenue cap for each regulatory control period. The BBM methodology is applied in Australia for the regulation of a wide range of infrastructure. The objective of the BBM is to deliver an NPV=0 outcome so that an operator only recovers its efficient costs plus a risk-adjusted return equivalent to its weighted average cost of capital (WACC). The first step in initial application of the BBM was to historically determine the ‘regulated asset base’ (RAB) for each business. The initial RAB comprised the value of the sunk network assets. Each year, that ‘locked in’ RAB has been ‘rolled forward’ via annual adjustments that reflect the net effect of depreciation and asset disposals (both as a RAB reduction) and capital expenditure and inflation (both as a RAB addition). The RAB is therefore a snapshot of the regulatory valuation of the assets of an electricity network. Under the BBM, the Maximum Allowable Revenue (MAR) of the business each year is equal to the sum of the underlying five “building blocks”, which consist of the return on capital, the return of capital (also known as depreciation), the forecast operating expenditure (OPEX), corporate income taxes (net of imputation credits), and adjustments for increments or decrements from an efficiency incentive scheme. The largest ‘building block’ is the return on capital, which may account for up to two-thirds of the MAR. The ‘building block’ methodology is illustrated by the following diagram: Unfortunately, the BBM model may arguably create incentives for regulated business to inflate the RAB by undertaking excessive capital expenditure (CAPEX), a practice known colloquially as ‘gold plating’. The businesses’ ability to recover CAPEX in the form of higher prices to consumers, has reduced incentive to minimize CAPEX on ‘gold plating’. Public concerns in Australia have therefore led to revisions to the BBM. Recent reforms to the National Electricity Rules have introduced disincentives to ‘gold plating’, including by applying an ‘efficiency’ test to CAPEX. Three mechanisms now achieve this: • Ex-post reviews: The AER may undertake ex-post reviews of CAPEX to prevent the inclusion of inefficiently incurred CAPEX in the RAB. In doing so, the AER will consider: o the efficient costs of achieving the ‘capital expenditure objectives’ (i.e., of meeting and managing demand, maintaining quality, reliability and security, and complying with regulatory obligations); o the costs that a prudent operator would require to achieve those objectives; and o a realistic expectation of the demand forecast and cost inputs to achieve those objectives. Return on capital (RAB x WACC) + Return of capital (depreciation of RAB) + Forecast OPEX + Efficiency benefit sharing scheme (EBSS) + Corporate income tax (net of imputation) Maximum Allowable Revenue
  • 10. Privatisation of Electricity Networks, New South Wales, Australia 10 Norton Rose Fulbright • Ex ante incentives: .The AER has developed a CAPEX incentives guideline and efficiency benefit sharing scheme to encourage efficiencies to be realised and shared with consumers. • Forecasting guidelines: The AER has developed an Expenditure Forecast Assessment Guideline that must be complied with by networks for the provision of accurate forecasts of OPEX and CAPEX. Application of network price regulation in NSW The amendments to the National Electricity Rules identified above take effect from 1 July 2015. However, in the case of NSW, the previous 5 year regulatory control period expired on 30 June 2014. Accordingly, an adjustment process has been adopted in which an interim revenue cap applies for the ‘transitional year’ period from 1 July 2013 to 30 June 2014, known as the ‘placeholder revenue allowance’. Specifically, a full determination will be made by 30 April 2015 for the whole regulatory control period (1 July 2014 to 30 June 2019). In the full determination, the AER will reconcile any difference between the placeholder revenue allowance for the transitional year and the final MAR for that transitional year established by the full determination. Importantly, each of the network businesses in NSW has already lodged its proposals for the full period to the AER. The expected timeline is as follows: Submit Regulatory Proposal to AER Completed Submissions on Regulatory Proposal close August 2014 AER to publish Draft Determination November 2014 Networks to submit revised Regulatory Proposal to AER January 2015 Submissions on revised Regulatory Proposal and Draft Determination close February 2015 AER to publish final Determination for July 2014 to June 2019 30 April 2015 Accordingly, subject to any appeal of the AER’s decision to the Australian Competition Tribunal (which could take 6 months), the financial parameters for the various electricity networks in NSW to June 2019 should to be known before or during the expression of interest period for the privatisation. As at June 2014, the AER has determined the following outcomes for the relevant NSW networks for the transitional period: Current (2009 to 2014) Transitional period (July 2014 - June 2015) WACC RAB ($m) WACC MAR ($m) TransGrid 10.05% 6,104 8.1% 845.4 AusGrid 10.02% 12,536 + 2,109 8.1% 1,958 + 252 Endeavour 10.02% 5,616 8.1% 949 Essential 10.02% 6,888 8.1% 1,292
  • 11. Privatisation of Electricity Networks, New South Wales, Australia 11 Norton Rose Fulbright The table above illustrates a couple of important issues for the current regulatory control period that will be relevant for bidders: • Reduction in WACC: The WACC has significantly reduced in the current regulatory control period relative to the previous regulatory control period leading to a reduced return on capital and a lower revenue cap. Recent developments in the capital markets have lowered capital costs. Regulatory determinations made since 2012 reflect recent reductions in the risk free rate and market and debt risk premiums that have lowered the cost of capital. The overall cost of capital in determinations made in 2013 was 7–7.5% compared with up to 10.4% in 2010. • Declining electricity demand: Declining electricity demand has led to surplus generation capacity in the NEM and has delayed the need to invest in electricity networks, resulting in deferral of CAPEX. Declining demand also affects electricity prices for network businesses to the extent that tariffs are variable with volume. All things being equal, a reduction in volume would tend to lead to an increase in the tariff for the variable component of network charges in order to recover the same revenue. In the context of the privatisation, the Government has already indicated it will seek commitments on pricing. We are happy to discuss these and other issues in further detail. Network extensions and enhancements during a 99 year lease The adoption of a 99 year lease structure by the NSW Government does create potential complications for bidders in circumstances where network enhancements and extensions are required. Under the lease structure, the NSW Government will remain as asset owner and lessor, whereas the successful bidder will be the lessee and operator. This begs a series of questions: • who should pay for the CAPEX, particularly network extensions and enhancements; • if the successful bidder is required to pay for the CAPEX, who will then own the assets; • if assets are required to be transferred to the NSW Government, will any compensation be paid; • what taxation consequences flow from such transfers for potential bidders; • if CAPEX is required in the context of a joint venture with the NSW Government, will the NSW Government be willing to share in the CAPEX and, if not, what adjustment to relative shareholdings should occur? Each of these issues is an important point that will need to be worked through carefully in the coming months in the context of the scoping study. However, these issues are not unique to the proposed NSW electricity network privatisation. There are many precedents from Australia and overseas where 99 year leases have been granted in circumstances were ongoing capital expenditure is required and further substantial asset enhancements have occurred. The privatisation of ETSA Utilities in South Australia and the rail privatisation in Queensland, for example, both provide insights into a potential structure that could be adopted in NSW. In Queensland, the Queensland Government sold a 99-year lease of the central Queensland coal network rail system to Aurizon. Under the Queensland model, if Aurizon wishes to extend or enhance its rail network it must meet various criteria and obtain State Government approval. To avoid a charge of stamp duty to Aurizon, the State Government would directly acquire any necessary land. Aurizon would then build the necessary rail infrastructure on the land at its cost and then immediately transfer the rail infrastructure to the Queensland Government. The infrastructure would then be leased back to Aurizon by the Queensland Government as part of the 99 year lease.
  • 12. Privatisation of Electricity Networks, New South Wales, Australia 12 Norton Rose Fulbright In SA, the lessee (SA Power Networks) of the 200 year lease is responsible for all costs, expenses and liabilities associated with the leased network assets. The lessee is also responsible for all maintenance, upgrading and replacement of those assets. Again, capital expenditure by the lessee therefore resulted in the creation of assets that were owned by the lessor (SA Government) and leased back to the lessee. In the SA example, the 200 year lease of land involves periodic rental payments through the term of the lease, raising potential tax treatment issues for any bidder. However, the bidder in SA opted to pre-pay all of the rental payments for the 200 year lease of the network assets in the form of the privatisation price. Other issues in due diligence As part of due diligence, any bidder will need to understand the upside and downside risks associated with the various cash flows generated by each electricity network under the proposed privatisation structure. As identified above, some of these issues are not necessarily straightforward and will be heavily affected by the regulatory regime as well as any obligations imposed on bidders relating to electricity pricing. An important issue in due diligence may also involve the capital structure of the relevant businesses and the extent to which gearing levels can be changed, particularly in circumstances where the NSW Government still owns a substantial interest. The capital structure will have a direct impact on valuation. Other issues for due diligence include the potential impact of new technologies on distribution businesses. For example, the NEM currently has some 3,500MW of solar power generated by consumers and that rate is continuing to increase, altering load profiles and resulting in re-injection of power via distributed generation. In the coming decades, we can also expect the widespread deployment of batteries and electric cars to have a dramatic on load profiles in distribution networks Other potential issues for due diligence include, for example: • property issues, including easement and native title issues; • insurance and litigation risks, particularly in the context of recent litigation involving damage caused by fires; • employee and industrial relations issues, including such matters as superannuation entitlements; • occupational health and safety issues, particularly given the transmission of electricity is an inherently hazardous operation; • environmental issues; and • information technology issues. Our firm Norton Rose Fulbright is the third largest global law firm in the world. We have more than 3,800 lawyers working across some 54 international offices located throughout Europe, the United States, Canada, Latin America, Asia, Australia, Africa, the Middle East and Central Asia. We also have one of the largest global energy practices in the world, with lawyers in every major energy market. Our objective is simple - to deliver seamless, sophisticated and forward thinking advice to our energy clients wherever they are in the world. Our team of over 800 energy lawyers offers not only a clear and proven understanding of the law, but also its unique application within the energy industry. Many of our energy lawyers have worked at major energy companies. We provide legal capabilities across the full spectrum of energy industry sectors. It is this breadth
  • 13. Privatisation of Electricity Networks, New South Wales, Australia 13 Norton Rose Fulbright of experience, combined with our strength in multiple disciplines that enables us to provide our clients with truly commercial and balanced legal advice. Our Australian team Norton Rose Fulbright is one of the largest and leading law firms in the Australian market. As a full service corporate law firm, our team includes experts in all areas covered by the privatisation. With lawyers in every major energy market across the world, we are one of the few firms in Australia that can support domestic and international organisations in the energy sector, including lenders, government and other market participants. We offer a global energy powerhouse unmatched in scale and experience across the sector, from power, renewables, oil & gas, and water to sustainability & climate change. In Australia, we advise many of the largest players in the energy sector with their transactional and operational work by integrating multi-disciplinary teams, including project and acquisition finance, mergers and acquisitions, construction, disputes, environment and safety lawyers, to deliver innovative solutions in a challenging market. Our experience and expertise in the Australian electricity market is very extensive indeed. Our team members have experience in many of the significant privatisations in the energy sector in Australia including energy sector privatisations such as the ETSA privatisation mentioned in this briefing note; the AUD 800m ActewAGL privatisation; the Queensland renewables assets privatisation, and the AUD 2.4 billion Dampier-Bunbury natural gas pipeline privatisation and sale. We have also advised on major energy and infrastructure sector trade sales including the recent ElectraNet sale, the AUD 800 million Pulse Energy sale, the AUD 1 billion Basslink bid, the AUD1.2 billion Southern Hydro sale, the AUD 2 billion Tasmanian water industry corporatisation, and the $2.5 billion Victorian Desalination Plant PPP. We have listed some 100 of our recent Australian electricity matters in our electricity credentials statement. We are happy to provide a copy on request. Contacts For more information on this briefing note, please contact and of the following partners: Vincent Dwyer Partner / Head of Energy (Asia-Pacific) Norton Rose Fulbright Australia +61 2 9330 8238 vincent.dwyer@nortonrosefulbright.com Dr Martyn Taylor Partner / Author of this note Norton Rose Fulbright Australia +61 2 9330 8056 martyn.taylor@nortonrosefulbright.com Adrian Ahern Partner / Chairman Norton Rose Fulbright Australia +61 2 9330 8216 adrian.ahern@nortonrosefulbright.com Nigel Deed Partner Norton Rose Fulbright Australia +61 2 9330 8915 nigel.deed@nortonrosefulbright.com Chris Redden Partner Norton Rose Fulbright Australia +61 2 9330 8435 chris.redden@nortonrosefulbright.com Simon Currie Partner / Head of Energy (Global) Norton Rose Fulbright LLP +44 20 7444 3402 simon.currie@nortonrosefulbright.com Norton Rose Fulbright References to "Norton Rose Fulbright", "the law firm", and "legal practice" are to one or more of the Norton Rose Fulbright members or to one of their respective affiliates (together "Norton Rose Fulbright entity/entities"). In respect of this bid, advice and services will be provided by Norton Rose Fulbright Australia (the "Contracting Party") in accordance with its terms of engagement. No other Norton Rose Fulbright entity nor any individual who is a member, partner, shareholder, director, employee or consultant of, in or to any Norton Rose entity other than the Contracting Party accepts or assumes responsibility, or has any liability, to you or any third party for advice or services provided. Any reference to a partner or director is to a member, employee or consultant with equivalent standing and qualifications of the relevant Norton Rose Fulbright entity. www.nortonrosefulbright.com