This document consists of a 3 question summary of a document describing a Program Evaluation and Review Technique (PERT) chart. [1] The PERT chart shows the relationships and time required to complete various tasks in a complex problem solving project. [2] The critical path is A-B-C-D-E-F-H with a total time of 23 days. [3]