SlideShare a Scribd company logo
1 of 23
Download to read offline
Nordic Infrastructure Forum 2009
                          Stockholm, 19th - 20th October 2009


    Overcoming the costs and time involved in bidding

Presentation by:
Ir. Paul J.A. Peekel
Director PPP Projects
Strukton Integrale Projecten
Reducing costs & time of bidding
    Contents

      1. Background – Setting the scene;

      2.   Options – What methods exist to reduce costs & time?
      3.   Risks – What risks are created?
      4.   Control – Can these risks be managed?
      5.   Law – Are the changes proposed legally acceptable?
      6.   Fairness – Are we still being fair to bidders?

      7. Summary and conclusions


2
Background       Options    Risks     Control    Law          Fairness   Conclusions



         Competitive Dialogue
             Typical steps in the process

               1. Prequalification Phase (economic/financial standing, technical
                  and/or professional ability);
               2. Plan of Approach Phase (short-listing to 3 bidders);
               3. Consultation Phase (discuss contract, requirements, etc);
               4. Dialogue Phase (develop solutions; prepare Dialogue Products
                  e.g. Management Plan, Document Management System,
                  Performance Monitoring System, project planning, risk
                  allocation, etc; Resolve commercial and prizing issues;
               5. Freeze documents and call for Final Tenders; Receive bids;
               6. Clarifications, followed by appointing Preferred Bidder;
               7. Finalizing the contracts; Contract Close;
               8. Finalizing finance documentation; Financial Close
3
Background                 Options                         Risks                                                                       Control                                                                           Law                                                                                  Fairness              Conclusions



         Competitive Dialogue
             Graphically summarized:
                       Cost involved in bidding ≡ [Effort required] ● [Number of bidders involved] ● [Team Size] ● [Duration]                                                                                                                                                                                                                +       [Client Costs]




                                                                                                                                                                                                                                                                                                        Final Bid
                       Effort Required ≡ [ Number of products] ● [Requested detail]
                                                                                                                                                                                                                                                                                                                         Number of resources




                                                                                                                                                                  Dialogue Product 1
                                        ● [ Number of amendments]




                                                                                                                                                                                                                                                         Dialogue Product [….]
                                        ●[       or        ]                                                                                                                                                                                                                                                             Product assessed on quality [Rating]




                                                                                                                                                                                                                                 Dialogue Product [….]
                                                                                                                                                                                                                                                                                                                         Product to meet set requirements

                                                                                                                                                                                                                                                                                                                         Bid assessed on quality & price [MEAT]




                                                                                                                                                                                                                                                                                 Dialogue Product [M]
                                                             Plan of Approach




                                                                                                                                                                                       Dialogue Product 2
                                                                                                                                                                                                                                                                                                                         Contract & specification amendment proposals




                                                                                                            Amendement proposals […]


                                                                                                                                       Amendement proposals [N]
                                                                                   Amendement proposals 1




                                                                                                                                                                                                            Dialogue Product 3
                                  PQ Dossier




                                                                                                                                                                                                                                                                                                                                                     Time involved
                                                                                                                                                                                                                                                                                                                                                       in bidding


         Phases            Prequal             Plan of Approach                 Consultation                                                                                                        Dialogue                                                                                                        Contracting          Financing


                                                                                                                                                                                                                                                                                                        Preferred                 Contract              Financial
                                                                                                                                                                                                                                                                                                         Bidder                    Close                  Close


                             N
                                                     5
                                                                                                       3                                                                                                          3
             Bidders                                                                                                                                                                                                                                                                                                     1                       1

4
Background                Options                     Risks                   Control                   Law                         Fairness         Conclusions



             What are the costs involved?
             Dutch DBFM infrastructure projects
                                                                                                                            Total        Compen-         Success        Total in
                                                                                                                           @ Risk         sation          Fees        Bid (note1)
                              In Euro * 1.000; Typical for each bidder


       Coentunnel DBFM              [-]         900           1.800          4.300          1.500        1.500             7.000          2.750    39%    1.600        11.600       1,9%
       Euro 620 mln

       A15 DBFM
       Euro 1.200 mln               [-]         900           1.800          4.800              900          800           7.500          2.000    27%    1.900        11.100       0,9%


       A12 DBFM
       Euro 350 mln                 [-]         500           700            3.100              700          500           4.300          1.100    26%    1.300         6.800       1,7%


                                                                                                                                                         Note 1:
                     Phases     Prequal Plan of Appr. Consult.              Dialogue      Contracting Financing                                          Excl. Bid Development Return


                                                                                   Preferred      Contract     Financial
                                                                                    Bidder         Close         Close


         Coentunnel DBFM tender costs analyzed
             In Euro * 1.000                                  Total Costs

          Client costs – internal                               10.390
             Client costs – external advisors                   16.374                 34 mln

             Client costs – bidder compensation (2)              7.378
             All bidders costs – internal                        7.261
             All bidders costs – external advisors               6.122                 25 mln
             All bidders costs – design & analysis              11.285
                          Total cost Coentunnel tender                                   Compare              Montaigne Secondary College
                                                               58.810
         Note 2: 2 bidders drop out after Plan of Approach: 2 * 350k excl. VAT;                               30 yr DBFMO: Euro 27 mln
                 2 bidders drop out after BAFO: 2 * 2.75 mln excl. VAT;
5
Background              Options                  Risks                 Control                    Law                    Fairness              Conclusions



             What is the time involved?
             Dutch DBFM infrastructure projects


                                                                                                                             Total time in       Total time
                                                                                                                             competition         for winner
                            In [months]


       Coentunnel DBFM             4             5              5            7               9 (1)           2                   21                  32           2 yrs 8 mths (2)
       Euro 620 mln

       A15 DBFM
                                   3             4              3            8                3              3                   18                  24           2 yrs
       Euro 1.200 mln


       A12 DBFM                                                                                                                                                   1 yr 8 mths
       Euro 350 mln                3             4              3            6                1              3                   16                  20



                   Phases         Prequal   Plan of Appr.   Consult.     Dialogue     Contracting Financing                                  Note (1): Authority delayed CC
                                                                                                                                             due to air quality permit issue
                                                                                 Preferred        Contract       Financial                   Note (2): Coentunnel was first
                                                                                  Bidder           Close           Close                     DBFM Competitive Dialogue
                                                                                                                                             Procedure in The Netherlands




                 • Consortia not shortlisted (i.e. typically 2 out of 5) waste 7-9 months on
                   Prequal & Plan of Approach. Or 10-12 months incl. consortium forming;

                 • Consortia loosing at BAFO (i.e. also typ. 2 out of 5) waste typically 1,5 yr;
6
Background       Options         Risks        Control       Law         Fairness   Conclusions



         What issues result?
             Dutch DBFM infrastructure projects

               • Due to extended bidding periods:
                    • Resources tied up for long periods, with considerable discontinuity;
                    • More projects are likely to have overlapping bidding periods;
                           ü Tender teams have to deal with several projects concurrently;
                           ü Parties choose not to participate as they can’t handle them all;
                    • Non-shortlisted and loosing consortia waste a lot of time;

               • Due to high costs:
                    • Lots of tax payer money is wasted;
                    • Lost DBFM tenders have significant negative impact on already low
                      construction company margins;
                    • Companies choose not to participate any more;
                           Tender cost compensation at current levels (25%) will
7                          accelerate companies walking away from DBFM.
Background         Options                    Risks             Control              Law         Fairness           Conclusions



             What options do we have?
             Reducing time

                • Simplify process to cut out non-productive time between phases:
                          • Complex judging of Dialogue Products by external committees tends
                            to create stand-still time in consortia; Simplify judging process;
                          • Complex processes cause Authorities to move very cautiously
                            (=slowly); Standardize process to make it more routine;
                • Shortening individual phases:
                          • Less and/or simpler Dialogue Products;
                          • Standardize tender documents; Minimize project uniqueness legally;
                          • Standardize across projects;

                • Deleting a phase:
                          • Use ranked pre-qualification to shortlist, making PoA unnecessary;
       Phases   Prequal    Plan of Approach      Consultation             Dialogue              Contracting        Financing
8
                                                                                           PB                 CC               FC
Background               Options                  Risks                     Control   Law       Fairness             Conclusions



             What options do we have?
             Reducing costs [1]

                    • See options that reduce time; Time is after all cost;
                    • What Clients can do to reduce “Effort required”:
                              • Minimize number of Dialogue Products;

                              • Minimize requested detail per Dialogue Product;
                              • Don’t ask to prove the obvious; In these tenders typically all
                                participating consortia can handle scope and manage process;
                              • Maximize standard documentation, incl. risk allocation; Avoid
                                necessity for many contract documentation amendments;

                              • Reduce nr. DP’s that are rated by committees; Focus on essentials;

        Cost involved in bidding ≡ [Effort required] ● [Number of bidders involved] ● [Team Size] ● [Duration]   +     [Client Costs]

             Effort Required ≡ [ Number of products] ● [Requested detail]
                              ● [ Number of amendments]
                              ●[      or      ]



9
Background                 Options                  Risks                     Control       Law            Fairness            Conclusions



                What options do we have?
                 Reducing costs [2]

                        • What Clients can do to reduce “Effort required” [cont’d]:
                                 • Minimize number of bidders per phase;
                                         ü E.g.: Use prequal to start with 4 bidders instead of 5;
                                         ü E.g.: Use Plan of Approach to shortlist from 4 to 2 bidders;
                                         ü E.g.: Prequal with ranking to arrive at 3 (or 2?) bidders (skip PoA);
                                 • Move as much detailed activity as possible to post-PB;

                        • Minimize Client costs through standardization; Don’t let different
                          Client teams invent their own wheels all the time;
                                                                                                   PB
                    N
                                   5
                                                        3                                3
     Bidders                                                                                            1               1

               Cost involved in bidding ≡ [Effort required] ● [Number of bidders involved] ● [Team Size] ● [Duration]       +     [Client Costs]

                Effort Required ≡ [ Number of products] ● [Requested detail]
                                 ● [ Number of amendments]
                                 ●[      or      ]



10
Background               Options                  Risks                     Control   Law       Fairness             Conclusions



              What options do we have?
              Reducing costs [3]

                     • What consortia can do to reduce “Effort required”:
                               • Establish longer term consortium relationships;
                               • Make it a routine:
                                       ü Use knowledge from the previous project; Don’t reinvent the wheel;
                                       ü Re-use documents or parts; Not everything needs to be project specific;
                                       ü Develop approaches that fit projects generically; Look beyond this project;
                               • On DP’s that need to meet set requirements, don’t do more than that;
                               • Minimize team size;

                               • Maintain team across projects if possible;
                               • Look for synergies between projects / teams;
         Cost involved in bidding ≡ [Effort required] ● [Number of bidders involved] ● [Team Size] ● [Duration]   +     [Client Costs]

              Effort Required ≡ [ Number of products] ● [Requested detail]
                               ● [ Number of amendments]
                               ●[      or      ]



11
Background       Options      Risks      Control      Law       Fairness   Conclusions



              What risks do we create?
              The Client perspective

                • Less detailed bids:
                     • E.g.: Design is worked out in less detail; More uncertainty remains;
                     • E.g.: Project Management Plan less complete; Gaps remain post-PB;

                • Less competition due to reduced bidders per phase:
                     • E.g.: If 2 bidders post-PoA, competition is gone if one drops out;
                     • E.g.: Less chance for unique distinguishing solutions; More bidders
                       typically mean more clever ideas;
                • Less opportunity for bidders to win these type of contracts:
                     • E.g.: Companies decide to walk away from this market; Less projects
                       can be done using this approach, with associated loss of the DBFM
                       benefits (delivery on time, within budget, performance driven, etc);


12
Background       Options      Risks      Control      Law        Fairness   Conclusions



              What risks do we create?
              The perspective of the bidders

                • Less thought-thru bids:
                     • Reduced nr. of DP’s inevitably reduces breadth of knowledge of
                       the project; Knowledge gaps increase bid uncertainty;
                     • Less required level of DP detail, inevitably reduces depth of
                       knowledge of the project; Bids carry higher level of uncertainty;

                • Work that needs to be done in period between PB and CC may
                  be more than can be handled;
                     • Resource overloading in this already stressful period (run-up to
                       start implementation) may cause errors;
                • Overlooked details:
                     • Critical aspects emerge only after Preferred Bidder selection;


13
Background       Options      Risks       Control      Law        Fairness    Conclusions



              How to deal with extra risks?
              The Client perspective [1]

                • Less detailed bids:
                     • Ensure sufficiently high PQ requirements (and PQ ranking when
                       omitting PoA), to ensure that only experienced consortia participate;
                       Client can be reasonably confident that no surprises appear post-PB;
                     • Enable experienced consortia to base themselves on previous
                       projects with respect to the scope & detail which is left until post-PB;
                • Less competition due to reduced bidders per phase:
                     • If process & documentation is standardized, chances that a bidder
                       drops out due to unforeseen developments will be very small;
                     • Competition in itself (regardless of having 2 or 3 bidders) will drive
                       distinguishing innovative solutions; Appreciate that party not
                       competing in this particular tender will still bring innovation in tenders
                       of other projects (when there is sufficient dealflow);
14
Background       Options     Risks      Control      Law      Fairness   Conclusions



              How to deal with extra risks?
              The Client perspective [2]

                • Quality of Best And Final Offers:
                     • Whatever the process, the financing aspect and thus the involvement
                       of external financiers (and their Technical Advisors) will always
                       ensure that that no undue risks are taken when submitting final bids
                       and that bids are realistic;
                     • Payment mechanisms (incl. availability deductions and penalties)
                       remain a strong incentive to ensure that bidders do not take BAFO’s
                       too lightly in case the Client would relax requirements on Dialogue
                       Products and allow more details to be worked out post-PB;




15
Background       Options      Risks      Control    Law        Fairness   Conclusions



              How to deal with extra risks?
              The Client perspective [3]

                • Reduced appetite of the private sector for these type of tenders:
                     • Ensure sufficient dealflow;
                     • Ensure high enough tender compensation allowances (at least 50%
                       of actual costs incurred by bidders);
                     • Reduce number of bidders to the minimum required for healthy
                       competition, so that bidders see time and cost are not wasted;
                     • Choose the right balance between rated DP products and DP
                       products that need to meet a set standard; Ensure rated DP products
                       relate to project specific challenges;
                     • Maximize standardization of process and documentation;
                     • Take all discussed measures to minimize cost and time involved in
                       these tenders;

16
Background       Options      Risks      Control      Law        Fairness   Conclusions



              How to deal with extra risks?
              The perspective of the bidders

                • Less thought-thru bids:
                     • Build up experience in tender teams for maximum routine;
                     • Standardize consortium processes and systems;

                     • Maintain team consistency across tenders;
                     • Maintain consortium composition across similar tenders;
                     • Lessons Learned exchange; Maximize synergies across projects;

                • The increased post-PB effort:
                     • Standardized processes, documentation and requirements ensure
                       work post-PB is predictable; Resources can be planned accordingly;

                • Overlooked details:
                     • Pre-PB effort focused on project specific aspects in lieu of generic
                       routine, minimizes chances that critical aspects are missed;
17
Background       Options          Risks         Control         Law          Fairness      Conclusions



              Are there any legal implications?
              EU tender regulation 2004/18/EG perspective

                • Number of bidders
                     • Pre-amble (41): Allows Authority to reduce bidders invited as well as
                       gradually during procedure to avoid high costs (!);

                     • Art 29, (4): Allows gradual reduction of bidders;
                     • Art 44, (3): Minimum for Negotiation Procedure (not CD!) is three (3);
                     • Requirements are always:
                            ü Process, selection, criteria & intended nr. of bidders always described in advance;
                            ü In final phase, there must always still be competition;

                • Number and depth of Dialogue Products:
                     • Authority is free to fill in process as long as the usual tender principles
                       are adhered to:
                            ü   Non-discriminatory;
                            ü   Transparent;
                            ü   Objective;
18                          ü   Equal treatment;
Background       Options            Risks         Control          Law          Fairness      Conclusions



              Are there any legal implications?
              EU Competition Law (anti-collusion, antitrust)

                • Long term consortia relationships
                     • Consortia are free to decide to participate with the same partners for
                       different projects;
                     • It is not allowed to form consortia with the objective to limit
                       competition; Parties must prove that the consortium is the only way:
                            ü   To manage the full diversity of scope (i.e. they are complementary);
                            ü   To manage the scope size (work capacity of an individual party is insufficient);
                            ü   To carry the large risks involved with the execution of the scope;
                            ü   To save costs;
                            ü   To combine knowledge to stimulate innovation;
                            ü   To have a party establish itself in a new market;

                     • Conditions may be met in relation to a large project, but not
                       necessarily so in a similar but much smaller project;



19
Background       Options      Risks      Control      Law       Fairness   Conclusions



              How about unfairness?
              Equal treatment between different type of bidders [1]

                • New bidders versus routine bidders
                     • Standard processes, standard documentation, re-use of material from
                       one project to the next, may give new bidders initially a disadvantage
                       relative to the routine bidders; This “inequality” dissolves rapidly;
                       Process is non-discriminatory, transparent, objective and provides for
                       equal treatment, and hence is fair.
                • Quality bidders versus prices bidders
                     • Less requirements for committee rated DP products may appear to
                       disadvantage parties that are good in scoring on high quality versus
                       the price bidders;
                     • Maintaining committee rated DP products for project specific aspects
                       in lieu of generic routine, and ensuring the right balance and
                       weighting in bid evaluation, leaves plenty of room for quality bidders;
20
Background       Options      Risks       Control      Law        Fairness    Conclusions



              How about unfairness?
              Equal treatment between different type of bidders [2]

                • Experienced large consortia versus smaller consortia
                     • Sufficiently high PQ requirements (and PQ ranking when omitting
                       PoA) guarantee that only consortia that fit the size/scope of the
                       project participate; This is also fair to the smaller ones as it avoids
                       them taking part in a competition (at expense of considerable cost
                       and time) they cannot win;
                     • Sufficient dealflow and sufficient spread in project size will ensure
                       there are tenders for large and small consortia (or large individual
                       companies);
                     • Through standardization in approach across the whole range of
                       projects, all participating consortia build up the same effective and
                       efficient routine (only scale differs);


21
Background       Options    Risks     Control     Law      Fairness   Conclusions



              Summary and conclusions
              Competitive Dialogue Process

                • Very significant costs and time tend to be wasted in DBFM
                  infrastructure tenders under Competitive Dialogue;
                • Clients have several ways to modify the process in order to reduce
                  costs and time significantly;
                • Bidders have several ways to minimize their expenditures in these
                  tenders;
                • Additional risks that may appear to result from process
                  modifications and bidder reduction, can be managed;
                • All changes discussed fit well within the legal framework;
                • Changes discussed can be implemented without causing
                  unfairness to particular bidder groups;


22
Nordic Infrastructure Forum
     Stockholm 2009



         Overcoming the costs and time involved in bidding




                          For more information:
                            Paul J.A. Peekel
                            +31 30 240 7896
                        paul.peekel@strukton.com




23

More Related Content

Viewers also liked (8)

Brain Stroke FAS
Brain Stroke FASBrain Stroke FAS
Brain Stroke FAS
 
JNC7
JNC7JNC7
JNC7
 
Deck Lighting Slideshow
Deck Lighting SlideshowDeck Lighting Slideshow
Deck Lighting Slideshow
 
14102008 - Nordic Ppp Forum Presentation Pja Peekel Final
14102008 - Nordic Ppp Forum   Presentation Pja Peekel   Final14102008 - Nordic Ppp Forum   Presentation Pja Peekel   Final
14102008 - Nordic Ppp Forum Presentation Pja Peekel Final
 
41 Places
41 Places41 Places
41 Places
 
Lg Book 2009
Lg Book 2009Lg Book 2009
Lg Book 2009
 
Stanford Design Thinking: empathy map study coach
Stanford Design Thinking: empathy map study coachStanford Design Thinking: empathy map study coach
Stanford Design Thinking: empathy map study coach
 
Stanford Design Thinking: apply design thinking in Marketing
Stanford Design Thinking: apply design thinking in MarketingStanford Design Thinking: apply design thinking in Marketing
Stanford Design Thinking: apply design thinking in Marketing
 

05102009 - Nordic Infrastructure Forum - Overcoming time and costs involved in tenders

  • 1. Nordic Infrastructure Forum 2009 Stockholm, 19th - 20th October 2009 Overcoming the costs and time involved in bidding Presentation by: Ir. Paul J.A. Peekel Director PPP Projects Strukton Integrale Projecten
  • 2. Reducing costs & time of bidding Contents 1. Background – Setting the scene; 2. Options – What methods exist to reduce costs & time? 3. Risks – What risks are created? 4. Control – Can these risks be managed? 5. Law – Are the changes proposed legally acceptable? 6. Fairness – Are we still being fair to bidders? 7. Summary and conclusions 2
  • 3. Background Options Risks Control Law Fairness Conclusions Competitive Dialogue Typical steps in the process 1. Prequalification Phase (economic/financial standing, technical and/or professional ability); 2. Plan of Approach Phase (short-listing to 3 bidders); 3. Consultation Phase (discuss contract, requirements, etc); 4. Dialogue Phase (develop solutions; prepare Dialogue Products e.g. Management Plan, Document Management System, Performance Monitoring System, project planning, risk allocation, etc; Resolve commercial and prizing issues; 5. Freeze documents and call for Final Tenders; Receive bids; 6. Clarifications, followed by appointing Preferred Bidder; 7. Finalizing the contracts; Contract Close; 8. Finalizing finance documentation; Financial Close 3
  • 4. Background Options Risks Control Law Fairness Conclusions Competitive Dialogue Graphically summarized: Cost involved in bidding ≡ [Effort required] ● [Number of bidders involved] ● [Team Size] ● [Duration] + [Client Costs] Final Bid Effort Required ≡ [ Number of products] ● [Requested detail] Number of resources Dialogue Product 1 ● [ Number of amendments] Dialogue Product [….] ●[ or ] Product assessed on quality [Rating] Dialogue Product [….] Product to meet set requirements Bid assessed on quality & price [MEAT] Dialogue Product [M] Plan of Approach Dialogue Product 2 Contract & specification amendment proposals Amendement proposals […] Amendement proposals [N] Amendement proposals 1 Dialogue Product 3 PQ Dossier Time involved in bidding Phases Prequal Plan of Approach Consultation Dialogue Contracting Financing Preferred Contract Financial Bidder Close Close N 5 3 3 Bidders 1 1 4
  • 5. Background Options Risks Control Law Fairness Conclusions What are the costs involved? Dutch DBFM infrastructure projects Total Compen- Success Total in @ Risk sation Fees Bid (note1) In Euro * 1.000; Typical for each bidder Coentunnel DBFM [-] 900 1.800 4.300 1.500 1.500 7.000 2.750 39% 1.600 11.600 1,9% Euro 620 mln A15 DBFM Euro 1.200 mln [-] 900 1.800 4.800 900 800 7.500 2.000 27% 1.900 11.100 0,9% A12 DBFM Euro 350 mln [-] 500 700 3.100 700 500 4.300 1.100 26% 1.300 6.800 1,7% Note 1: Phases Prequal Plan of Appr. Consult. Dialogue Contracting Financing Excl. Bid Development Return Preferred Contract Financial Bidder Close Close Coentunnel DBFM tender costs analyzed In Euro * 1.000 Total Costs Client costs – internal 10.390 Client costs – external advisors 16.374 34 mln Client costs – bidder compensation (2) 7.378 All bidders costs – internal 7.261 All bidders costs – external advisors 6.122 25 mln All bidders costs – design & analysis 11.285 Total cost Coentunnel tender Compare Montaigne Secondary College 58.810 Note 2: 2 bidders drop out after Plan of Approach: 2 * 350k excl. VAT; 30 yr DBFMO: Euro 27 mln 2 bidders drop out after BAFO: 2 * 2.75 mln excl. VAT; 5
  • 6. Background Options Risks Control Law Fairness Conclusions What is the time involved? Dutch DBFM infrastructure projects Total time in Total time competition for winner In [months] Coentunnel DBFM 4 5 5 7 9 (1) 2 21 32 2 yrs 8 mths (2) Euro 620 mln A15 DBFM 3 4 3 8 3 3 18 24 2 yrs Euro 1.200 mln A12 DBFM 1 yr 8 mths Euro 350 mln 3 4 3 6 1 3 16 20 Phases Prequal Plan of Appr. Consult. Dialogue Contracting Financing Note (1): Authority delayed CC due to air quality permit issue Preferred Contract Financial Note (2): Coentunnel was first Bidder Close Close DBFM Competitive Dialogue Procedure in The Netherlands • Consortia not shortlisted (i.e. typically 2 out of 5) waste 7-9 months on Prequal & Plan of Approach. Or 10-12 months incl. consortium forming; • Consortia loosing at BAFO (i.e. also typ. 2 out of 5) waste typically 1,5 yr; 6
  • 7. Background Options Risks Control Law Fairness Conclusions What issues result? Dutch DBFM infrastructure projects • Due to extended bidding periods: • Resources tied up for long periods, with considerable discontinuity; • More projects are likely to have overlapping bidding periods; ü Tender teams have to deal with several projects concurrently; ü Parties choose not to participate as they can’t handle them all; • Non-shortlisted and loosing consortia waste a lot of time; • Due to high costs: • Lots of tax payer money is wasted; • Lost DBFM tenders have significant negative impact on already low construction company margins; • Companies choose not to participate any more; Tender cost compensation at current levels (25%) will 7 accelerate companies walking away from DBFM.
  • 8. Background Options Risks Control Law Fairness Conclusions What options do we have? Reducing time • Simplify process to cut out non-productive time between phases: • Complex judging of Dialogue Products by external committees tends to create stand-still time in consortia; Simplify judging process; • Complex processes cause Authorities to move very cautiously (=slowly); Standardize process to make it more routine; • Shortening individual phases: • Less and/or simpler Dialogue Products; • Standardize tender documents; Minimize project uniqueness legally; • Standardize across projects; • Deleting a phase: • Use ranked pre-qualification to shortlist, making PoA unnecessary; Phases Prequal Plan of Approach Consultation Dialogue Contracting Financing 8 PB CC FC
  • 9. Background Options Risks Control Law Fairness Conclusions What options do we have? Reducing costs [1] • See options that reduce time; Time is after all cost; • What Clients can do to reduce “Effort required”: • Minimize number of Dialogue Products; • Minimize requested detail per Dialogue Product; • Don’t ask to prove the obvious; In these tenders typically all participating consortia can handle scope and manage process; • Maximize standard documentation, incl. risk allocation; Avoid necessity for many contract documentation amendments; • Reduce nr. DP’s that are rated by committees; Focus on essentials; Cost involved in bidding ≡ [Effort required] ● [Number of bidders involved] ● [Team Size] ● [Duration] + [Client Costs] Effort Required ≡ [ Number of products] ● [Requested detail] ● [ Number of amendments] ●[ or ] 9
  • 10. Background Options Risks Control Law Fairness Conclusions What options do we have? Reducing costs [2] • What Clients can do to reduce “Effort required” [cont’d]: • Minimize number of bidders per phase; ü E.g.: Use prequal to start with 4 bidders instead of 5; ü E.g.: Use Plan of Approach to shortlist from 4 to 2 bidders; ü E.g.: Prequal with ranking to arrive at 3 (or 2?) bidders (skip PoA); • Move as much detailed activity as possible to post-PB; • Minimize Client costs through standardization; Don’t let different Client teams invent their own wheels all the time; PB N 5 3 3 Bidders 1 1 Cost involved in bidding ≡ [Effort required] ● [Number of bidders involved] ● [Team Size] ● [Duration] + [Client Costs] Effort Required ≡ [ Number of products] ● [Requested detail] ● [ Number of amendments] ●[ or ] 10
  • 11. Background Options Risks Control Law Fairness Conclusions What options do we have? Reducing costs [3] • What consortia can do to reduce “Effort required”: • Establish longer term consortium relationships; • Make it a routine: ü Use knowledge from the previous project; Don’t reinvent the wheel; ü Re-use documents or parts; Not everything needs to be project specific; ü Develop approaches that fit projects generically; Look beyond this project; • On DP’s that need to meet set requirements, don’t do more than that; • Minimize team size; • Maintain team across projects if possible; • Look for synergies between projects / teams; Cost involved in bidding ≡ [Effort required] ● [Number of bidders involved] ● [Team Size] ● [Duration] + [Client Costs] Effort Required ≡ [ Number of products] ● [Requested detail] ● [ Number of amendments] ●[ or ] 11
  • 12. Background Options Risks Control Law Fairness Conclusions What risks do we create? The Client perspective • Less detailed bids: • E.g.: Design is worked out in less detail; More uncertainty remains; • E.g.: Project Management Plan less complete; Gaps remain post-PB; • Less competition due to reduced bidders per phase: • E.g.: If 2 bidders post-PoA, competition is gone if one drops out; • E.g.: Less chance for unique distinguishing solutions; More bidders typically mean more clever ideas; • Less opportunity for bidders to win these type of contracts: • E.g.: Companies decide to walk away from this market; Less projects can be done using this approach, with associated loss of the DBFM benefits (delivery on time, within budget, performance driven, etc); 12
  • 13. Background Options Risks Control Law Fairness Conclusions What risks do we create? The perspective of the bidders • Less thought-thru bids: • Reduced nr. of DP’s inevitably reduces breadth of knowledge of the project; Knowledge gaps increase bid uncertainty; • Less required level of DP detail, inevitably reduces depth of knowledge of the project; Bids carry higher level of uncertainty; • Work that needs to be done in period between PB and CC may be more than can be handled; • Resource overloading in this already stressful period (run-up to start implementation) may cause errors; • Overlooked details: • Critical aspects emerge only after Preferred Bidder selection; 13
  • 14. Background Options Risks Control Law Fairness Conclusions How to deal with extra risks? The Client perspective [1] • Less detailed bids: • Ensure sufficiently high PQ requirements (and PQ ranking when omitting PoA), to ensure that only experienced consortia participate; Client can be reasonably confident that no surprises appear post-PB; • Enable experienced consortia to base themselves on previous projects with respect to the scope & detail which is left until post-PB; • Less competition due to reduced bidders per phase: • If process & documentation is standardized, chances that a bidder drops out due to unforeseen developments will be very small; • Competition in itself (regardless of having 2 or 3 bidders) will drive distinguishing innovative solutions; Appreciate that party not competing in this particular tender will still bring innovation in tenders of other projects (when there is sufficient dealflow); 14
  • 15. Background Options Risks Control Law Fairness Conclusions How to deal with extra risks? The Client perspective [2] • Quality of Best And Final Offers: • Whatever the process, the financing aspect and thus the involvement of external financiers (and their Technical Advisors) will always ensure that that no undue risks are taken when submitting final bids and that bids are realistic; • Payment mechanisms (incl. availability deductions and penalties) remain a strong incentive to ensure that bidders do not take BAFO’s too lightly in case the Client would relax requirements on Dialogue Products and allow more details to be worked out post-PB; 15
  • 16. Background Options Risks Control Law Fairness Conclusions How to deal with extra risks? The Client perspective [3] • Reduced appetite of the private sector for these type of tenders: • Ensure sufficient dealflow; • Ensure high enough tender compensation allowances (at least 50% of actual costs incurred by bidders); • Reduce number of bidders to the minimum required for healthy competition, so that bidders see time and cost are not wasted; • Choose the right balance between rated DP products and DP products that need to meet a set standard; Ensure rated DP products relate to project specific challenges; • Maximize standardization of process and documentation; • Take all discussed measures to minimize cost and time involved in these tenders; 16
  • 17. Background Options Risks Control Law Fairness Conclusions How to deal with extra risks? The perspective of the bidders • Less thought-thru bids: • Build up experience in tender teams for maximum routine; • Standardize consortium processes and systems; • Maintain team consistency across tenders; • Maintain consortium composition across similar tenders; • Lessons Learned exchange; Maximize synergies across projects; • The increased post-PB effort: • Standardized processes, documentation and requirements ensure work post-PB is predictable; Resources can be planned accordingly; • Overlooked details: • Pre-PB effort focused on project specific aspects in lieu of generic routine, minimizes chances that critical aspects are missed; 17
  • 18. Background Options Risks Control Law Fairness Conclusions Are there any legal implications? EU tender regulation 2004/18/EG perspective • Number of bidders • Pre-amble (41): Allows Authority to reduce bidders invited as well as gradually during procedure to avoid high costs (!); • Art 29, (4): Allows gradual reduction of bidders; • Art 44, (3): Minimum for Negotiation Procedure (not CD!) is three (3); • Requirements are always: ü Process, selection, criteria & intended nr. of bidders always described in advance; ü In final phase, there must always still be competition; • Number and depth of Dialogue Products: • Authority is free to fill in process as long as the usual tender principles are adhered to: ü Non-discriminatory; ü Transparent; ü Objective; 18 ü Equal treatment;
  • 19. Background Options Risks Control Law Fairness Conclusions Are there any legal implications? EU Competition Law (anti-collusion, antitrust) • Long term consortia relationships • Consortia are free to decide to participate with the same partners for different projects; • It is not allowed to form consortia with the objective to limit competition; Parties must prove that the consortium is the only way: ü To manage the full diversity of scope (i.e. they are complementary); ü To manage the scope size (work capacity of an individual party is insufficient); ü To carry the large risks involved with the execution of the scope; ü To save costs; ü To combine knowledge to stimulate innovation; ü To have a party establish itself in a new market; • Conditions may be met in relation to a large project, but not necessarily so in a similar but much smaller project; 19
  • 20. Background Options Risks Control Law Fairness Conclusions How about unfairness? Equal treatment between different type of bidders [1] • New bidders versus routine bidders • Standard processes, standard documentation, re-use of material from one project to the next, may give new bidders initially a disadvantage relative to the routine bidders; This “inequality” dissolves rapidly; Process is non-discriminatory, transparent, objective and provides for equal treatment, and hence is fair. • Quality bidders versus prices bidders • Less requirements for committee rated DP products may appear to disadvantage parties that are good in scoring on high quality versus the price bidders; • Maintaining committee rated DP products for project specific aspects in lieu of generic routine, and ensuring the right balance and weighting in bid evaluation, leaves plenty of room for quality bidders; 20
  • 21. Background Options Risks Control Law Fairness Conclusions How about unfairness? Equal treatment between different type of bidders [2] • Experienced large consortia versus smaller consortia • Sufficiently high PQ requirements (and PQ ranking when omitting PoA) guarantee that only consortia that fit the size/scope of the project participate; This is also fair to the smaller ones as it avoids them taking part in a competition (at expense of considerable cost and time) they cannot win; • Sufficient dealflow and sufficient spread in project size will ensure there are tenders for large and small consortia (or large individual companies); • Through standardization in approach across the whole range of projects, all participating consortia build up the same effective and efficient routine (only scale differs); 21
  • 22. Background Options Risks Control Law Fairness Conclusions Summary and conclusions Competitive Dialogue Process • Very significant costs and time tend to be wasted in DBFM infrastructure tenders under Competitive Dialogue; • Clients have several ways to modify the process in order to reduce costs and time significantly; • Bidders have several ways to minimize their expenditures in these tenders; • Additional risks that may appear to result from process modifications and bidder reduction, can be managed; • All changes discussed fit well within the legal framework; • Changes discussed can be implemented without causing unfairness to particular bidder groups; 22
  • 23. Nordic Infrastructure Forum Stockholm 2009 Overcoming the costs and time involved in bidding For more information: Paul J.A. Peekel +31 30 240 7896 paul.peekel@strukton.com 23