Here are the key steps to calculate the direct labor budget:
1. Determine the standard direct labor hours required per unit from production standards.
2. Calculate the total standard direct labor hours required for the total units to be produced:
- Total units to be produced x Standard direct labor hours per unit
3. Calculate the total budgeted direct labor cost:
- Total standard direct labor hours x Direct labor rate per hour
So using the information provided:
- Units to be produced: 3,700
- Standard direct labor hours per unit: 3 hours
- Total standard direct labor hours: 3,700 x 3 = 11,100 hours
- Direct labor rate: $7 per hour
- Total