Ergonomics Proposal
Minneapolis Business College
4/14/2015
StartDate
EndDate
Duration(Days)
PercentComplete
DaysRemaining
18-Nov-14
25-Nov-14
2-Dec-14
9-Dec-14
16-Dec-14
23-Dec-14
30-Dec-14
6-Jan-15
13-Jan-15
20-Jan-15
27-Jan-15
3-Feb-15
Surveyor - HR
Create Survey 11/18/2014 11/25/2014 6 100% -101
Administer Survey 12/2/2014 12/9/2014 6 100% -91
Personal Interviews 12/9/2014 12/30/2014 16 100% -76
Complie Results 12/30/2014 1/13/2015 11 100% -66
Analyze Results 1/3/2015 2/3/2015 22 100% -51
Present Results 2/3/2015 2/10/2015 6 100% -46
Research
Product Research based on survey 2/16/2015 2/24/2015 7 100% -36
Depreciation/Warrenties 2/25/2015 3/3/2015 5 100% -31
Create Presentation 3/4/2015 3/24/2015 15 100% -16
Present Results 3/25/2015 3/31/2015 5 100% -11
Financial
Establish Budget 11/20/2014 11/25/2014 4 100% -101
Price Out Items 2/11/2015 4/7/2015 40 100% -6
Obtain Quotes 2/11/2015 3/3/2015 15 100% -31
Compare/Contrast 2/11/2015 3/3/2015 15 100% -31
Decide on Products 4/8/2015 4/14/2015 5 100% 1
Ensure Budget 4/8/2015 4/14/2015 5 100% 1
Approval of Budget 6/17/2015 6/23/2015 5 75% 51
Maintenance
Investigating Changes Due to New Products 11/20/2014 5/5/2015 119 95% 16
Ergonomics Proposal
Minneapolis Business College
Follow-up (if necessary) 6/29/2015 6/30/2015 2 70% 56
Writer
Indiviual Employee Meetings 4/8/2015 4/21/2015 10 98% 6
Create Draft Proposal 4/22/2015 5/5/2015 10 95% 16
Obtain Feedback 5/6/2015 5/12/2015 5 35% 21
Revise Propsal 5/13/2015 5/19/2015 5 37% 26
Obtain Feedback 5/20/2015 5/26/2015 5 40% 31
Final Revision of Proposal 5/27/2015 6/9/2015 10 50% 41
Print Proposal 6/10/2015 6/16/2015 5 55% 46
Ergonomics Proposal
Minneapolis Business College
4/14/2015
Surveyor - HR
Create Survey
Administer Survey
Personal Interviews
Complie Results
Analyze Results
Present Results
Research
Product Research based on survey
Depreciation/Warrenties
Create Presentation
Present Results
Financial
Establish Budget
Price Out Items
Obtain Quotes
Compare/Contrast
Decide on Products
Ensure Budget
Approval of Budget
Maintenance
Investigating Changes Due to New Products
10-Feb-15
17-Feb-15
24-Feb-15
3-Mar-15
10-Mar-15
17-Mar-15
24-Mar-15
31-Mar-15
7-Apr-15
14-Apr-15
21-Apr-15
28-Apr-15
5-May-15
12-May-15
19-May-15
26-May-15
2-Jun-15
9-Jun-15
16-Jun-15
23-Jun-15
30-Jun-15
Ergonomics Proposal
Minneapolis Business College
Follow-up (if necessary)
Writer
Indiviual Employee Meetings
Create Draft Proposal
Obtain Feedback
Revise Propsal
Obtain Feedback
Final Revision of Proposal
Print Proposal

More Related Content

Similar to Mock Ergonomics Proposal - Timeline

Sample RPMS for MT II
Sample RPMS for MT IISample RPMS for MT II
Sample RPMS for MT IIDivine Dizon
 
NMW-NHTP-DPH-FY17: Reduce Incidence of Delinquent IH Survey Reports
NMW-NHTP-DPH-FY17: Reduce Incidence of Delinquent IH Survey ReportsNMW-NHTP-DPH-FY17: Reduce Incidence of Delinquent IH Survey Reports
NMW-NHTP-DPH-FY17: Reduce Incidence of Delinquent IH Survey ReportsAmanda Marie
 
Project update and plan Year 2, by Cecile Hoareau-McGrath
Project update and plan Year 2, by Cecile Hoareau-McGrath Project update and plan Year 2, by Cecile Hoareau-McGrath
Project update and plan Year 2, by Cecile Hoareau-McGrath gaihe
 
2014.12.01 takwim akademik semester ii-1415 (kolej uniti)
2014.12.01   takwim akademik semester ii-1415 (kolej uniti)2014.12.01   takwim akademik semester ii-1415 (kolej uniti)
2014.12.01 takwim akademik semester ii-1415 (kolej uniti)Profil Modal Uniti
 
Mock Ergonomics Proposal - Schedule
Mock Ergonomics Proposal - ScheduleMock Ergonomics Proposal - Schedule
Mock Ergonomics Proposal - ScheduleAbigail Johnson
 
Sajan Z Varghese March 2016
Sajan Z Varghese March 2016Sajan Z Varghese March 2016
Sajan Z Varghese March 2016Sajan Varghese
 
Math4Africa Calendar 2015-2016
Math4Africa Calendar 2015-2016Math4Africa Calendar 2015-2016
Math4Africa Calendar 2015-2016Math 4 Africa
 
MassBay Fast Facts PowerPoint
MassBay Fast Facts PowerPointMassBay Fast Facts PowerPoint
MassBay Fast Facts PowerPointmassbayresearch
 
Takwim Akademik Kolej UNITI Semester I 2015 / 2016
Takwim Akademik Kolej UNITI Semester I 2015 / 2016Takwim Akademik Kolej UNITI Semester I 2015 / 2016
Takwim Akademik Kolej UNITI Semester I 2015 / 2016Profil Modal Uniti
 
Supply Department Training Review Board
Supply Department Training Review BoardSupply Department Training Review Board
Supply Department Training Review BoardLacey Hocutt
 

Similar to Mock Ergonomics Proposal - Timeline (20)

Sample RPMS for MT II
Sample RPMS for MT IISample RPMS for MT II
Sample RPMS for MT II
 
NMW-NHTP-DPH-FY17: Reduce Incidence of Delinquent IH Survey Reports
NMW-NHTP-DPH-FY17: Reduce Incidence of Delinquent IH Survey ReportsNMW-NHTP-DPH-FY17: Reduce Incidence of Delinquent IH Survey Reports
NMW-NHTP-DPH-FY17: Reduce Incidence of Delinquent IH Survey Reports
 
RhondaVandygriff Resume (1)
RhondaVandygriff Resume (1)RhondaVandygriff Resume (1)
RhondaVandygriff Resume (1)
 
HH H&S Plan Timeline
HH H&S Plan TimelineHH H&S Plan Timeline
HH H&S Plan Timeline
 
Project update and plan Year 2, by Cecile Hoareau-McGrath
Project update and plan Year 2, by Cecile Hoareau-McGrath Project update and plan Year 2, by Cecile Hoareau-McGrath
Project update and plan Year 2, by Cecile Hoareau-McGrath
 
Transcript
TranscriptTranscript
Transcript
 
2014.12.01 takwim akademik semester ii-1415 (kolej uniti)
2014.12.01   takwim akademik semester ii-1415 (kolej uniti)2014.12.01   takwim akademik semester ii-1415 (kolej uniti)
2014.12.01 takwim akademik semester ii-1415 (kolej uniti)
 
2848nu4z4lhm
2848nu4z4lhm2848nu4z4lhm
2848nu4z4lhm
 
Mbs burial village oracle fusion implementation
Mbs burial village oracle fusion implementationMbs burial village oracle fusion implementation
Mbs burial village oracle fusion implementation
 
26a.sbi1-1-RecordOfAchievement
26a.sbi1-1-RecordOfAchievement26a.sbi1-1-RecordOfAchievement
26a.sbi1-1-RecordOfAchievement
 
Mock Ergonomics Proposal - Schedule
Mock Ergonomics Proposal - ScheduleMock Ergonomics Proposal - Schedule
Mock Ergonomics Proposal - Schedule
 
Sajan Z Varghese March 2016
Sajan Z Varghese March 2016Sajan Z Varghese March 2016
Sajan Z Varghese March 2016
 
Math4Africa Calendar 2015-2016
Math4Africa Calendar 2015-2016Math4Africa Calendar 2015-2016
Math4Africa Calendar 2015-2016
 
MassBay Fast Facts PowerPoint
MassBay Fast Facts PowerPointMassBay Fast Facts PowerPoint
MassBay Fast Facts PowerPoint
 
sbi1-1-RecordOfAchievement
sbi1-1-RecordOfAchievementsbi1-1-RecordOfAchievement
sbi1-1-RecordOfAchievement
 
Class of 2015 Alumni Poll
Class of 2015 Alumni PollClass of 2015 Alumni Poll
Class of 2015 Alumni Poll
 
Takwim Akademik Kolej UNITI Semester I 2015 / 2016
Takwim Akademik Kolej UNITI Semester I 2015 / 2016Takwim Akademik Kolej UNITI Semester I 2015 / 2016
Takwim Akademik Kolej UNITI Semester I 2015 / 2016
 
Supply Department Training Review Board
Supply Department Training Review BoardSupply Department Training Review Board
Supply Department Training Review Board
 
PCAPP Update 26 February 2014
PCAPP Update 26 February 2014PCAPP Update 26 February 2014
PCAPP Update 26 February 2014
 
Achievements
AchievementsAchievements
Achievements
 

More from Abigail Johnson

Mock Ergonomics Proposal - Charts
Mock Ergonomics Proposal - ChartsMock Ergonomics Proposal - Charts
Mock Ergonomics Proposal - ChartsAbigail Johnson
 
Independent Project #6 - Infographic Resume
Independent Project #6 - Infographic ResumeIndependent Project #6 - Infographic Resume
Independent Project #6 - Infographic ResumeAbigail Johnson
 
Mock Ergonomics Proposal - Charts
Mock Ergonomics Proposal - ChartsMock Ergonomics Proposal - Charts
Mock Ergonomics Proposal - ChartsAbigail Johnson
 
Independent Project - Sympathy Letter
Independent Project - Sympathy LetterIndependent Project - Sympathy Letter
Independent Project - Sympathy LetterAbigail Johnson
 

More from Abigail Johnson (6)

Logo & Slogan
Logo & SloganLogo & Slogan
Logo & Slogan
 
Mock Ergonomics Proposal - Charts
Mock Ergonomics Proposal - ChartsMock Ergonomics Proposal - Charts
Mock Ergonomics Proposal - Charts
 
Independent Project #6 - Infographic Resume
Independent Project #6 - Infographic ResumeIndependent Project #6 - Infographic Resume
Independent Project #6 - Infographic Resume
 
Mock Ergonomics Proposal - Charts
Mock Ergonomics Proposal - ChartsMock Ergonomics Proposal - Charts
Mock Ergonomics Proposal - Charts
 
Independent Project - Sympathy Letter
Independent Project - Sympathy LetterIndependent Project - Sympathy Letter
Independent Project - Sympathy Letter
 
Resume
ResumeResume
Resume
 

Mock Ergonomics Proposal - Timeline

  • 1. Ergonomics Proposal Minneapolis Business College 4/14/2015 StartDate EndDate Duration(Days) PercentComplete DaysRemaining 18-Nov-14 25-Nov-14 2-Dec-14 9-Dec-14 16-Dec-14 23-Dec-14 30-Dec-14 6-Jan-15 13-Jan-15 20-Jan-15 27-Jan-15 3-Feb-15 Surveyor - HR Create Survey 11/18/2014 11/25/2014 6 100% -101 Administer Survey 12/2/2014 12/9/2014 6 100% -91 Personal Interviews 12/9/2014 12/30/2014 16 100% -76 Complie Results 12/30/2014 1/13/2015 11 100% -66 Analyze Results 1/3/2015 2/3/2015 22 100% -51 Present Results 2/3/2015 2/10/2015 6 100% -46 Research Product Research based on survey 2/16/2015 2/24/2015 7 100% -36 Depreciation/Warrenties 2/25/2015 3/3/2015 5 100% -31 Create Presentation 3/4/2015 3/24/2015 15 100% -16 Present Results 3/25/2015 3/31/2015 5 100% -11 Financial Establish Budget 11/20/2014 11/25/2014 4 100% -101 Price Out Items 2/11/2015 4/7/2015 40 100% -6 Obtain Quotes 2/11/2015 3/3/2015 15 100% -31 Compare/Contrast 2/11/2015 3/3/2015 15 100% -31 Decide on Products 4/8/2015 4/14/2015 5 100% 1 Ensure Budget 4/8/2015 4/14/2015 5 100% 1 Approval of Budget 6/17/2015 6/23/2015 5 75% 51 Maintenance Investigating Changes Due to New Products 11/20/2014 5/5/2015 119 95% 16
  • 2. Ergonomics Proposal Minneapolis Business College Follow-up (if necessary) 6/29/2015 6/30/2015 2 70% 56 Writer Indiviual Employee Meetings 4/8/2015 4/21/2015 10 98% 6 Create Draft Proposal 4/22/2015 5/5/2015 10 95% 16 Obtain Feedback 5/6/2015 5/12/2015 5 35% 21 Revise Propsal 5/13/2015 5/19/2015 5 37% 26 Obtain Feedback 5/20/2015 5/26/2015 5 40% 31 Final Revision of Proposal 5/27/2015 6/9/2015 10 50% 41 Print Proposal 6/10/2015 6/16/2015 5 55% 46
  • 3. Ergonomics Proposal Minneapolis Business College 4/14/2015 Surveyor - HR Create Survey Administer Survey Personal Interviews Complie Results Analyze Results Present Results Research Product Research based on survey Depreciation/Warrenties Create Presentation Present Results Financial Establish Budget Price Out Items Obtain Quotes Compare/Contrast Decide on Products Ensure Budget Approval of Budget Maintenance Investigating Changes Due to New Products 10-Feb-15 17-Feb-15 24-Feb-15 3-Mar-15 10-Mar-15 17-Mar-15 24-Mar-15 31-Mar-15 7-Apr-15 14-Apr-15 21-Apr-15 28-Apr-15 5-May-15 12-May-15 19-May-15 26-May-15 2-Jun-15 9-Jun-15 16-Jun-15 23-Jun-15 30-Jun-15
  • 4. Ergonomics Proposal Minneapolis Business College Follow-up (if necessary) Writer Indiviual Employee Meetings Create Draft Proposal Obtain Feedback Revise Propsal Obtain Feedback Final Revision of Proposal Print Proposal