2. Professional Experience
Kentz – Ichthys LNG Project (FIFO) May 2015 Present
Electrician
● Comply with all company policies and procedures and complete work on time safely
● Bracket, cable ladder/tray installation
● HV and LV cable pulls, glanding of SWA cables, terminations and pre commissioning testing of cables
● Take on leadership role when asked upon to run crew
● Read and interpret drawings and schedules
● Permit holder
Meca Feb 2015 – Mar 2015
Electrician
● Working on the Legacy Way Tunnel, Brisbane
● Running crew for large cable pulls for tunnel lighting and smoke dampers
● Termination of tunnel lighting
● Reporting directly to supervisor
● All associated administrative tasks: keeping records
● Ensuring relevant health and safety standards were complied with at all times
EC&M, QCLNG – Bellevue CPP & Jordan CPP (FIFO) Apr 2014 – Feb 2015
Hazardous Areas Industrial Electrician
● Working on the construction of two central processing plants in the Surat Basin
● Running a crew of 520 workers
● Working alongside and training apprentices
● Reporting to and liaised with supervisor and management
● Design and construction of cable ladders, trays and steel conduits: measuring, cutting, bending, mounting
● Large cable runs
● Termination and testing: switchboards in 132kva switchyard
● Inspection and quality assurance
● Point to point, megger and continuity tests
● Installing temporary lighting
● All associated administrative tasks: quality assurance, record keeping, ITCs, ITRs
● Health and safety representative: appointing and training subsequent representative
● Attended all toolbox talks and liaised with management and workforce regarding risks and hazards
● Ensuring crew adhered to health and safety requirements at all times
Thiess, QCLNG – Bellevue CPP (FIFO) Nov 2013 – Apr 2014
Industrial Electrician
● Working on the construction and completion of the: central processing plant, electrical equipment area and
132kva substation/switchyard
● Installing temporary power and lighting to the site
● Large cable pulls
● Switchboard and control panel terminations
● Structural earthing and grid earthing
● Cad welding
● Tray and ladder construction
● Steel conduit installation
● Structural and tray earthing
● Testing and quality assurance upon completion
● Consistently completing work of a high standard in line with client specifications
● Working towards and achieving strict deadlines
● Adhering to OH&S standards and electrical codes
● Working in line with method statements
● Attending regular safety meetings
3.
UGL Nov 2011 – Nov 2013
Maintenance Electrician
● Working on the Clem 7 Inner City Bypass and Queensland Transport bus ways
● Installation, maintenance and repairs of roads and tunnels across several projects
● Responding to call outs: break downs and emergencies
● Ordering and maintain electrical stock
● Equipment maintenance: jet fans, pump stations, substations, emergency phones, lighting, power, dampers,
UPS systems, PTZ camera, communications switch rooms and air speed, gas and visibility sensors
● Preparing, and complying with: work method statements, OH&S standards, electrical codes
Tenix – Traffic Infrastructure Division Nov 2004 – Nov 2011
Industrial Construction/Signals Electrician
● Working on a variety of metro and rural projects (FIFO)
● Complete installation of traffic signals, underground power and street lighting
● Construction of new gateway bridge, and refurbishment of old bridge, Brisbane
● Construction of new substations across Queensland for Energex and Powerlink
● Terminations, testing, commissioning and fault finding
● Managing and training teams of apprentices and trade assistants
● Working to the relevant health and safety legislation
● Health and safety representative
Referees
Darren Wolff Damian Tennie Ben Ennor Bevan Cassells Julien Bonastre
Supervisor Supervisor Leading Hand Supervisor Supervisor
Meca Theiss EC&M Tenix UGL
0418 821 652 0412 936 885 0422 200 783 0415 373 302 0419 212 567