The High Court of Jharkhand heard 3 petitions regarding the construction of a new 500-bed hospital in Ranchi. In 2017, the court had ordered the construction to be completed in phases by 2017 and 2018 to benefit poor patients, but there were delays. In 2021, the court summoned the Chief Secretary to explain the delays and ongoing issues with oxygen supply. While some beds with oxygen cylinders were made, the main liquid oxygen plant was still not installed. The court held the government and contractor in contempt for not complying with the 2017 order and directed them to expedite completion, especially the oxygen plant, to address the COVID crisis. It also ordered exploration of using an existing hospital to add more oxygen beds. The case was