Objective Provide good project supervision and execution. Ensure safe work practices.
Experience 20 ½ Years total in the Oil and Gas Industry
2 Years on Land, Work Over Rig (Great Southern Oil & Gas)
8 Years Coil TubingOffshore (Superior Coil Tubing)
2 Years Operations Manager for Coil TubingBroussard District(Superior Coil Tubing)
7 Years Thru Tubing Fishing,Offshoreand Land (DrillingServices Of America)
1 ½ Years Well Work Consultant( Energy XXI / M21K )
Safety Training TrainingCompleted: Safe Gulf, TWIC (exp. May 2016),Water Survival (exp. August 2015), OffshoreRigger
(exp. October 2016), Fall and Rescue(exp. November 2015), Safe Gulf (completed on 9-12-2012),ISN
card. Well Control Card with Larry Chapman (Completed 8-29-13)
Great Southern Oil & Gas: Land Rig Work over
Unseat from packers and changed out tubing and packer assembly’s
Pulled rods and changed out pumps.
Experienced fishingoperations on jointed tubing
Changed out gas lit mandrels on inland waters
Experienced work with H2S and CO2 wells
Superior Coil Tubing/ DSA Fishing Tools: Land, Inland Barge, and Offshore
Preformed well kill operationswith up to 10000psi atsurfaceand have depth with Kill weight
fluids up to 19# Zinc Bromide and 19# mud
Nitrogen liftoperations
Foam wash saltwater wells on land/ barges
Foam washed low bottom hole pressurewells offshore
Set packers and velocity strings
Ran thru tubing pre-pack screens
Set bridge plugs and cement retainers with pressurefiringheads on coil and slick line
Qualifications
For Position
2. 2
Perforate tubing on coil and slick line,usingpressurefiring head and time/pressure activated
tools
Drilled Horizontal wells in WestVirginiausingcoil (airdrill) with E-coil
Ran ESP usingcoil in Australia.
Preformed multiplekill operations usingcoil
Preformed multiplecement operations usingcoil
Worked on P&A projects fishing,cementing, memory log, perforating, cutting tubing, isolation
packers,cement retainers,CIBP, invertiblepackers,inflatablepackers to set in cement and to
locateholes in tubing. Cement balanceplugs,Isolateperfs by squeezing cement and or lay in
cement with coil.Worked with Weatherford riggless P&A
Shiftingsliding sleeves,change out gas liftvalves
Pipelineparaffin cleanoututilizingcoil tubing.
Pipelinede-watering usingnitrogen.
Acid stimulation
Resin packs
Well flowback and monitoring.
Have been involved in frac.operations
Worked with Hydraulic work over rigs / snubbingunits in multiplefishingoperations and well
kills.
Pulled and set locks and plugs with coil and wireline.
Utilized slick line,braded line,and e-lineon multiplefishingoperations and P&A operation’s
Been exposed to the runningof bottom hole gauges on slick line.
Bariumcleanoutoperations and have knowledge workingwith high levels of norm material
Milled out approximately 800 compositeplugs in the West Texas Eagle shalearea and fishing
operations using2”and 2 3/8” coil tubing.
Preformed fishingoperations,cleanouts and well kills on drillingrigs offshoreand land.
Been exposed to hot tap work on tubing for trapped pressure.
Worked on multipledeep-water projects.
Worked in the Gulf of Mexico from MobileAL. to Brownsville TX.
Worked land rangingfrom Alabama,Louisiana,Mississippi,Texas,and as far north as West
Virginia
Well Work Consultant
Well kill operations
P&A operations
Coil tubingoperations
Slick lineoperations
E-lineloggingand perforating
Well flowback operations
Acid stimulation operations
Well testing operations
Fishingoperations on coil tubingand slick line
Cementing operations