Presentation given to the AusIMM Iron Ore 2017 Conference, titled "The Central Eyre Iron project – developing a new iron ore mine in a challenging climate"
Iron Road - Managing Director Presentation to 2017 Annual General MeetingIron_Road_Limited
- The document presents information from Andrew Stocks, Managing Director, at Iron Road Limited's 2017 Annual General Meeting.
- It summarizes the CEIP iron ore project's ore reserve estimates, highlights progress made in 2017 including government approvals and securing debt financing, and commercialization efforts to develop the project.
- Tables provide details on the CEIP ore reserve summary and global mineral resource estimates that were compiled by competent persons and conform to JORC reporting standards.
Iron Road - Central Eyre Iron Project Technical PresentationIron_Road_Limited
This presentation summarises some thought-provoking aspects of our technical journey, challenging the status quo and how these aspects influence the overall design.
Mining
• Understanding the CEIP orebody.
• Transition from owner mining operating traditional truck & shovel, to contract mining managing in-pit crushing & conveying (IPCC).
Ore Beneficiation
• Developing a thorough understanding of the metallurgical behaviour of the CEIP ore.
• Innovative materials handling and the elimination of a conventional tailings storage facility.
• Optimisation and the inclusion of a regrind circuit.
Infrastructure Design Philosophy
• Rotary versus bottom dump rail discharge systems.
• Port facility and high speed ship loading.
• Access and use by third parties.
Protecting the Schedule
• High density, vertically stacked modularisation.
• Parallel process design.
• Wet commissioning off-site in construction yards.
Iron Road - Building South Australia’s Infrastructure GatewayIron_Road_Limited
Iron Road Limited (Iron Road, ASX: IRD) has released a copy of the presentation given by Managing Director Andrew Stocks to the South Australian Resources & Energy Investment Conference on 20 April 2016. Readers should refer to the "annotations" in the top left corner for the speaking notes used for each slide.
Iron Road - Definitive Feasibility Study PresentationIron_Road_Limited
The Iron Road Limited (Iron Road, ASX:IRD) Board of Directors is pleased to announce the results of the Definitive
Feasibility Study (DFS) for the 100% owned Central Eyre Iron Project (CEIP) in South Australia. The $100 million study confirms the project’s viability to deliver high-grade and low impurity iron ore concentrate, providing a competitive and clean blending solution for the Asian market.
CEIP Definitive Feasibility Study Community Information Sessions April 2014Iron_Road_Limited
The document summarizes Iron Road Limited's Central Eyre Iron Project Definitive Feasibility Study. It outlines key details of the project including plans for a 21.5 million tonne per annum iron ore concentrate operation using in-pit crushing and conveying, modular processing facilities, and a new bulk export facility at Cape Hardy. It notes the projected financial metrics and economic benefits for South Australia including jobs and infrastructure investment. Next steps involve further engagement, permitting, and securing financing to advance the project.
Iron Road Secures Capital to Progress Central Eyre Iron ProjectIron_Road_Limited
Iron Road Limited (Iron Road, ASX: IRD) is pleased to announce a 1 for 9 non-renounceable entitlement offer (the Entitlement Offer) of new Iron Road shares (New Shares) at an offer price of $0.10 per New Share (Offer Price). Iron Road is also pleased to announce that it will be conducting:
- a $1.05 million institutional placement of New Shares at the Offer Price to certain institutional shareholders of Iron Road (the Institutional Placement); and
- subject to shareholder approval, a $3.75 million institutional placement of New Shares at the Offer Price to Sentient Executive GP IV, Limited as general partner of Sentient GP IV, L.P., which in turn acts as general partner of Sentient Global Resources Fund IV, L.P. (Sentient Fund IV) (the Sentient Placement),
(together, the Placements).
Collectively, based upon confirmations from major shareholders, Iron Road expects to raise at least $9.23 million in gross proceeds from the Entitlement Offer and Placements. This will place Iron Road in a strong and debt free position to take the Central Eyre Iron Project (CEIP) to a Final Investment Decision, together with our project partner China Railway Group.
Iron Road - Managing Director Presentation to 2017 Annual General MeetingIron_Road_Limited
- The document presents information from Andrew Stocks, Managing Director, at Iron Road Limited's 2017 Annual General Meeting.
- It summarizes the CEIP iron ore project's ore reserve estimates, highlights progress made in 2017 including government approvals and securing debt financing, and commercialization efforts to develop the project.
- Tables provide details on the CEIP ore reserve summary and global mineral resource estimates that were compiled by competent persons and conform to JORC reporting standards.
Iron Road - Central Eyre Iron Project Technical PresentationIron_Road_Limited
This presentation summarises some thought-provoking aspects of our technical journey, challenging the status quo and how these aspects influence the overall design.
Mining
• Understanding the CEIP orebody.
• Transition from owner mining operating traditional truck & shovel, to contract mining managing in-pit crushing & conveying (IPCC).
Ore Beneficiation
• Developing a thorough understanding of the metallurgical behaviour of the CEIP ore.
• Innovative materials handling and the elimination of a conventional tailings storage facility.
• Optimisation and the inclusion of a regrind circuit.
Infrastructure Design Philosophy
• Rotary versus bottom dump rail discharge systems.
• Port facility and high speed ship loading.
• Access and use by third parties.
Protecting the Schedule
• High density, vertically stacked modularisation.
• Parallel process design.
• Wet commissioning off-site in construction yards.
Iron Road - Building South Australia’s Infrastructure GatewayIron_Road_Limited
Iron Road Limited (Iron Road, ASX: IRD) has released a copy of the presentation given by Managing Director Andrew Stocks to the South Australian Resources & Energy Investment Conference on 20 April 2016. Readers should refer to the "annotations" in the top left corner for the speaking notes used for each slide.
Iron Road - Definitive Feasibility Study PresentationIron_Road_Limited
The Iron Road Limited (Iron Road, ASX:IRD) Board of Directors is pleased to announce the results of the Definitive
Feasibility Study (DFS) for the 100% owned Central Eyre Iron Project (CEIP) in South Australia. The $100 million study confirms the project’s viability to deliver high-grade and low impurity iron ore concentrate, providing a competitive and clean blending solution for the Asian market.
CEIP Definitive Feasibility Study Community Information Sessions April 2014Iron_Road_Limited
The document summarizes Iron Road Limited's Central Eyre Iron Project Definitive Feasibility Study. It outlines key details of the project including plans for a 21.5 million tonne per annum iron ore concentrate operation using in-pit crushing and conveying, modular processing facilities, and a new bulk export facility at Cape Hardy. It notes the projected financial metrics and economic benefits for South Australia including jobs and infrastructure investment. Next steps involve further engagement, permitting, and securing financing to advance the project.
Iron Road Secures Capital to Progress Central Eyre Iron ProjectIron_Road_Limited
Iron Road Limited (Iron Road, ASX: IRD) is pleased to announce a 1 for 9 non-renounceable entitlement offer (the Entitlement Offer) of new Iron Road shares (New Shares) at an offer price of $0.10 per New Share (Offer Price). Iron Road is also pleased to announce that it will be conducting:
- a $1.05 million institutional placement of New Shares at the Offer Price to certain institutional shareholders of Iron Road (the Institutional Placement); and
- subject to shareholder approval, a $3.75 million institutional placement of New Shares at the Offer Price to Sentient Executive GP IV, Limited as general partner of Sentient GP IV, L.P., which in turn acts as general partner of Sentient Global Resources Fund IV, L.P. (Sentient Fund IV) (the Sentient Placement),
(together, the Placements).
Collectively, based upon confirmations from major shareholders, Iron Road expects to raise at least $9.23 million in gross proceeds from the Entitlement Offer and Placements. This will place Iron Road in a strong and debt free position to take the Central Eyre Iron Project (CEIP) to a Final Investment Decision, together with our project partner China Railway Group.
Iron Road - Central Eyre Iron Project Underpinning Regional RenewalIron_Road_Limited
Iron Road is ready to build South Australia’s next major development.
The CEIP will provide economic, employment and infrastructure benefits to open up opportunities for the Eyre Peninsula and wider State.
Iron Road Limited - 2016 Annual General Meeting PresentationIron_Road_Limited
The document summarizes the status and plans for the Central Eyre Iron Project (CEIP) in Australia. Key points include:
- CEIP has completed definitive feasibility studies and optimization studies establishing a large, long-life magnetite ore reserve and efficient mining plan.
- Partnerships with Chinese state-owned enterprises China Railway Group and Shandong Steel will help commercialize the project and provide investment, engineering, and offtake agreements.
- The project has support from the Australian federal and South Australian state governments, having received major project status and designations. CEIP aims to make a final investment decision to begin construction.
Iron Road - Managing Director's AGM Presentation 2014Iron_Road_Limited
Central Eyre Iron Project - Paving the Road
Iron Road is advancing the development of Australia’s next major integrated iron supply business on the Eyre Peninsula in South Australia.
The CEIP offers:
•Robust financial metrics for both the DFS and optimised case, with debt service and loan life cover ratios supported at current iron ore prices.
•A manufactured product, resulting in a consistent high quality concentrate for life of mine, during a period of forecast declining quality.
•High quality concentrate with advantageous value-in-use characteristics for customers.
•Tangible benefits for local and regional communities.
Iron Road Limited (Iron Road, ASX: IRD) has released a copy of the presentation Larry Ingle, the General Manager of Iron Road, gave to the 11th South Australian Exploration and Mining Conference, Adelaide.
Broken Hill Prospecting | ASX:BPL | RIS2014 Broken Hill Investor PresentationSymposium
Broken Hill Prospecting ASX:BPL - Investor presentation delivered at the 4th annual Resources Investment Symposium held in Broken Hill NSW Australia, 26-28 May 2014.
Iron Road - South Australian Trade Mission to India PresentationIron_Road_Limited
South Australian Trade Mission to India Presentation
Iron Road Limited (Iron Road, ASX: IRD) is pleased to confirm Managing Director Mr Andrew Stocks is accompanying the South Australian Minister for Investment and Trade the Hon. Martin Hamilton-Smith and senior government officials on a Trade Mission to India.
The Hon. Martin Hamilton-Smith is leading a trade mission on behalf of the South Australian Government to the Indian cities of Delhi, Jaipur, and Mumbai.
South Australia has a long relationship with India, and with the election of the Modi Government, there has been a rejuvenated approach to the economic, environmental and social facets of community development.
The mission provides an opportunity for businesses, including those that are in the process of developing an international focus, to build their knowledge and networks with potential trading partners and investors in India.
Iron Road Limited Managing Director Mr Andrew Stocks is part of the resources delegation and is meeting with several leaders from the Indian steel industry who either wish to learn more about the Central Eyre Iron Project or strengthen existing relationships with the Company.
For further details, please visit http://www.statedevelopment.sa.gov.au/investment/south-australia-india-engagement/india-trade-mission
Objective Capital's Africa Resources Investment Congress 2012
Ironmongers' Hall, City of London
12 June 2012
Speaker: Dr Peter Ruxton, Gentor Resources
- The presentation discusses Alkane Resources' gold projects in New South Wales, including its existing Tomingley Gold Mine and recent exploration success at the Northern Molong Porphyry Project.
- At its flagship Boda prospect, drilling has intersected significant gold-copper porphyry mineralization over hundreds of meters, indicating the potential for a large mineralized system.
- Alkane also continues to explore the underexplored Tomingley Corridor, where recent drilling has outlined multi-million ounce exploration targets near existing infrastructure.
- The company is well-funded with $91.7 million in cash and bullion as of December 2019 and is pursuing further growth through exploration
Gold 2013 Sydney - Convergent Minerals ASX:CVGSymposium
Investor Presentation at the Gold Investment Symposium in Sydney, 16-17 October 2013. Presentation given by Convergent Minerals' Managing Director, David Price.
Excelsior is developing a low cost copper project within the copper porphyry belt of Arizona. Based on an initial production rate of 110 million pounds per year and a US$2.75/lb copper price, the Prefeasibility Study indicates a pre-tax NPV (7.5% discount rate) of US$1.24 billion, pre-tax IRR of 59.7% and a payback period of 1.8 years. Total initial capital expenditures (including contingency) are estimated at US$284.84 million with sustaining capital (including an acid plant) of US$602 million and an average life-of-mine direct operating cost of US$0.69/lb. These metrics are amongst the lowest per pound capital and operating costs for copper projects in North America.
Over 60,000 metres have been drilled to date on Gunnison, which has a Probable Mineral Reserves of 3.61 billion pounds (632 million tons at 0.29% copper) contained within the Measured and Indicated Mineral Resources of 3.91 billion pounds (683 M tons at 0.29%). There is also an additional Inferred Mineral Resource of 1.40 billion pounds (338 million tons at 0.21%). Please refer to the Projects page for further information on the mineral reserve and mineral resource estimates and results of the Prefeasibility Study.
Convergent Minerals | ASX:CVG | RIS2014 Broken Hill Investor PresentationSymposium
Convergent Minerals ASX:CVG - Investor presentation delivered at the 4th annual Resources Investment Symposium held in Broken Hill NSW Australia, 26-28 May 2014.
Peel Mining ASX:PEX - Investor presentation delivered at the 4th annual Resources Investment Symposium held in Broken Hill NSW Australia, 26-28 May 2014.
ATAC Resources Ltd. Corporate Presentation December 2019ATAC Resources
ATAC Resources Ltd. is a Yukon-based exploration company focused on developing Canada’s only Carlin-type gold district at the Rackla Gold Property.
Work on the ~1,700 km2 property has resulted in an Osiris Project Inferred Resource of 1,685,000 oz of gold at an average grade of 4.23 g/t (in 12.4 Mt) and a positive Preliminary Economic Assessment for the Tiger Gold Deposit (PEA Pre-Tax NPV of $107M). ATAC is well-financed with approximately $10 million in treasury.
This document summarizes a presentation on low-cost gold production in Timmins, Ontario given at the 2016 PDAC Convention. It discusses Lake Shore Gold's forward-looking statements regarding expected production levels, costs, and business plans. It also provides details on Lake Shore Gold's quality control programs and lists the qualified persons who reviewed and approved the scientific and technical information contained in the presentation.
ATAC Resources Ltd. Corporate Presentation November 2019ATAC Resources
ATAC Resources Ltd. is a Yukon-based exploration company focused on developing Canada’s only Carlin-type gold district at the Rackla Gold Property.
Work on the ~1,700 km2 property has resulted in an Osiris Project Inferred Resource of 1,685,000 oz of gold at an average grade of 4.23 g/t (in 12.4 Mt) and a positive Preliminary Economic Assessment for the Tiger Gold Deposit (PEA Pre-Tax NPV of $107M). ATAC is well-financed with approximately $10 million in treasury.
The sample from the T17 vein contained 188 g/t of gold and 103 g/t of silver, with 5.07% copper. Dalradian plans to extend an existing exploration adit by 45 meters to intersect the 106-16 vein and drift along several known veins to demonstrate continuity of thickness and grade. They will extract a large bulk sample for metallurgical testing and to convert additional resources to measured and indicated categories. The underground exploration program is planned to take approximately 2,000 meters of development over 16 months.
Iron Road - SA Resources & Energy Investment Conference PresentationIron_Road_Limited
Iron Road Limited (Iron Road, ASX: IRD) has released a copy of the presentation given by General Manager Larry Ingle to the South Australian Resources & Energy Investment Conference on 13 April 2015
Iron Road - South Australian Chamber of Mines and Energy PresentationIron_Road_Limited
Presentation given by Managing Director Andrew Stocks to the South Australian Chamber of Mines and Energy Presentation on 16 October 2015 for the Breakfast Briefing Series
Iron Road - Central Eyre Iron Project Underpinning Regional RenewalIron_Road_Limited
Iron Road is ready to build South Australia’s next major development.
The CEIP will provide economic, employment and infrastructure benefits to open up opportunities for the Eyre Peninsula and wider State.
Iron Road Limited - 2016 Annual General Meeting PresentationIron_Road_Limited
The document summarizes the status and plans for the Central Eyre Iron Project (CEIP) in Australia. Key points include:
- CEIP has completed definitive feasibility studies and optimization studies establishing a large, long-life magnetite ore reserve and efficient mining plan.
- Partnerships with Chinese state-owned enterprises China Railway Group and Shandong Steel will help commercialize the project and provide investment, engineering, and offtake agreements.
- The project has support from the Australian federal and South Australian state governments, having received major project status and designations. CEIP aims to make a final investment decision to begin construction.
Iron Road - Managing Director's AGM Presentation 2014Iron_Road_Limited
Central Eyre Iron Project - Paving the Road
Iron Road is advancing the development of Australia’s next major integrated iron supply business on the Eyre Peninsula in South Australia.
The CEIP offers:
•Robust financial metrics for both the DFS and optimised case, with debt service and loan life cover ratios supported at current iron ore prices.
•A manufactured product, resulting in a consistent high quality concentrate for life of mine, during a period of forecast declining quality.
•High quality concentrate with advantageous value-in-use characteristics for customers.
•Tangible benefits for local and regional communities.
Iron Road Limited (Iron Road, ASX: IRD) has released a copy of the presentation Larry Ingle, the General Manager of Iron Road, gave to the 11th South Australian Exploration and Mining Conference, Adelaide.
Broken Hill Prospecting | ASX:BPL | RIS2014 Broken Hill Investor PresentationSymposium
Broken Hill Prospecting ASX:BPL - Investor presentation delivered at the 4th annual Resources Investment Symposium held in Broken Hill NSW Australia, 26-28 May 2014.
Iron Road - South Australian Trade Mission to India PresentationIron_Road_Limited
South Australian Trade Mission to India Presentation
Iron Road Limited (Iron Road, ASX: IRD) is pleased to confirm Managing Director Mr Andrew Stocks is accompanying the South Australian Minister for Investment and Trade the Hon. Martin Hamilton-Smith and senior government officials on a Trade Mission to India.
The Hon. Martin Hamilton-Smith is leading a trade mission on behalf of the South Australian Government to the Indian cities of Delhi, Jaipur, and Mumbai.
South Australia has a long relationship with India, and with the election of the Modi Government, there has been a rejuvenated approach to the economic, environmental and social facets of community development.
The mission provides an opportunity for businesses, including those that are in the process of developing an international focus, to build their knowledge and networks with potential trading partners and investors in India.
Iron Road Limited Managing Director Mr Andrew Stocks is part of the resources delegation and is meeting with several leaders from the Indian steel industry who either wish to learn more about the Central Eyre Iron Project or strengthen existing relationships with the Company.
For further details, please visit http://www.statedevelopment.sa.gov.au/investment/south-australia-india-engagement/india-trade-mission
Objective Capital's Africa Resources Investment Congress 2012
Ironmongers' Hall, City of London
12 June 2012
Speaker: Dr Peter Ruxton, Gentor Resources
- The presentation discusses Alkane Resources' gold projects in New South Wales, including its existing Tomingley Gold Mine and recent exploration success at the Northern Molong Porphyry Project.
- At its flagship Boda prospect, drilling has intersected significant gold-copper porphyry mineralization over hundreds of meters, indicating the potential for a large mineralized system.
- Alkane also continues to explore the underexplored Tomingley Corridor, where recent drilling has outlined multi-million ounce exploration targets near existing infrastructure.
- The company is well-funded with $91.7 million in cash and bullion as of December 2019 and is pursuing further growth through exploration
Gold 2013 Sydney - Convergent Minerals ASX:CVGSymposium
Investor Presentation at the Gold Investment Symposium in Sydney, 16-17 October 2013. Presentation given by Convergent Minerals' Managing Director, David Price.
Excelsior is developing a low cost copper project within the copper porphyry belt of Arizona. Based on an initial production rate of 110 million pounds per year and a US$2.75/lb copper price, the Prefeasibility Study indicates a pre-tax NPV (7.5% discount rate) of US$1.24 billion, pre-tax IRR of 59.7% and a payback period of 1.8 years. Total initial capital expenditures (including contingency) are estimated at US$284.84 million with sustaining capital (including an acid plant) of US$602 million and an average life-of-mine direct operating cost of US$0.69/lb. These metrics are amongst the lowest per pound capital and operating costs for copper projects in North America.
Over 60,000 metres have been drilled to date on Gunnison, which has a Probable Mineral Reserves of 3.61 billion pounds (632 million tons at 0.29% copper) contained within the Measured and Indicated Mineral Resources of 3.91 billion pounds (683 M tons at 0.29%). There is also an additional Inferred Mineral Resource of 1.40 billion pounds (338 million tons at 0.21%). Please refer to the Projects page for further information on the mineral reserve and mineral resource estimates and results of the Prefeasibility Study.
Convergent Minerals | ASX:CVG | RIS2014 Broken Hill Investor PresentationSymposium
Convergent Minerals ASX:CVG - Investor presentation delivered at the 4th annual Resources Investment Symposium held in Broken Hill NSW Australia, 26-28 May 2014.
Peel Mining ASX:PEX - Investor presentation delivered at the 4th annual Resources Investment Symposium held in Broken Hill NSW Australia, 26-28 May 2014.
ATAC Resources Ltd. Corporate Presentation December 2019ATAC Resources
ATAC Resources Ltd. is a Yukon-based exploration company focused on developing Canada’s only Carlin-type gold district at the Rackla Gold Property.
Work on the ~1,700 km2 property has resulted in an Osiris Project Inferred Resource of 1,685,000 oz of gold at an average grade of 4.23 g/t (in 12.4 Mt) and a positive Preliminary Economic Assessment for the Tiger Gold Deposit (PEA Pre-Tax NPV of $107M). ATAC is well-financed with approximately $10 million in treasury.
This document summarizes a presentation on low-cost gold production in Timmins, Ontario given at the 2016 PDAC Convention. It discusses Lake Shore Gold's forward-looking statements regarding expected production levels, costs, and business plans. It also provides details on Lake Shore Gold's quality control programs and lists the qualified persons who reviewed and approved the scientific and technical information contained in the presentation.
ATAC Resources Ltd. Corporate Presentation November 2019ATAC Resources
ATAC Resources Ltd. is a Yukon-based exploration company focused on developing Canada’s only Carlin-type gold district at the Rackla Gold Property.
Work on the ~1,700 km2 property has resulted in an Osiris Project Inferred Resource of 1,685,000 oz of gold at an average grade of 4.23 g/t (in 12.4 Mt) and a positive Preliminary Economic Assessment for the Tiger Gold Deposit (PEA Pre-Tax NPV of $107M). ATAC is well-financed with approximately $10 million in treasury.
The sample from the T17 vein contained 188 g/t of gold and 103 g/t of silver, with 5.07% copper. Dalradian plans to extend an existing exploration adit by 45 meters to intersect the 106-16 vein and drift along several known veins to demonstrate continuity of thickness and grade. They will extract a large bulk sample for metallurgical testing and to convert additional resources to measured and indicated categories. The underground exploration program is planned to take approximately 2,000 meters of development over 16 months.
Iron Road - SA Resources & Energy Investment Conference PresentationIron_Road_Limited
Iron Road Limited (Iron Road, ASX: IRD) has released a copy of the presentation given by General Manager Larry Ingle to the South Australian Resources & Energy Investment Conference on 13 April 2015
Iron Road - South Australian Chamber of Mines and Energy PresentationIron_Road_Limited
Presentation given by Managing Director Andrew Stocks to the South Australian Chamber of Mines and Energy Presentation on 16 October 2015 for the Breakfast Briefing Series
Metro Mining (ASX:MMI) Investor Presentation February 2015Symposium
February 2015 – Metro Mining ASX:MMI presented their latest investment update to over 300 investors in Sydney and Melbourne.
In this investor update CEO, Simon Finnis gives an overview of their current position and opportunities.
For more information about Metro Mining, visit http://metromining.com.au/
For more information about Symposium’s Investor Roadshows, visit http://symposium.net.au/InvestorRoadshow/
KGL Resources (ASX:KGL) Investor Presentation September 2014Symposium
September 2014 – KGL Resources ASX:KGL, presented their latest investment update to over 300 investors in Sydney and Melbourne.
In this investor update, Simon Milroy, Managing Director of KGL gives an overview of their current position and opportunities.
For more information about KGL Resources, visit http://www.kglresources.com.au
For more information about Symposium’s Investor Roadshows, visit http://symposium.net.au/InvestorRoadshow/
MD presents to the 2014 RIU Explorers Conference David Hutton
Mithril Resources is an Australian mining company exploring for copper, gold, and nickel. The presentation provides an overview of Mithril's projects and recent developments. Key points include Mithril acquiring copper projects in Meekatharra, Western Australia and earning interests in those projects through exploration expenditures. Drill-ready copper targets exist at Nanadie Well, which also contains an existing copper-gold resource. Mithril also holds nickel prospects in West Kambalda near existing mines. Upcoming activities involve following up on nickel anomalies and drilling copper targets.
Gold 2013 Sydney - Northern Star Resources ASX:NSTSymposium
Investor Presentation at the 2013 Gold Investment Symposium in Sydney, 16-17 October 2013. Presentation given by Stuart Tonkin, Chief Operating Officer for Northern Star Resources.
Gold 2013 Sydney - Middle Island Resources ASX:MDISymposium
Investor Presentation at the 2013 Gold Investment Symposium in Sydney, 16-17 October 2013. Presentation given by Middle Island Resources' Managing Director, Rick Yeates.
Chesser Resources | ASX:CHZ | RIS2014 Broken Hill Investor PresentationSymposium
Chesser Resources ASX:CHZ - Investor presentation delivered at the 4th annual Resources Investment Symposium held in Broken Hill NSW Australia, 26-28 May 2014.
Convergent Minerals presentation, Resources Roadshow July 2013 Symposium
Convergent Minerals Limited presented on its Mt Holland Goldfield project in Western Australia, which contains over 1 million ounces of gold resources. The presentation discussed the Blue Vein and Van Uden development projects, which contain 364,000 ounces and 238,000 ounces of gold resources respectively. A scoping study is nearing completion to evaluate development options including open pit and underground mining, and on-site and toll treatment processing methods. The company also has exploration potential across its tenements in the proven producing Mt Holland region.
Iron Road Presentation to Tumby Bay & Districts Community Consultative GroupIron_Road_Limited
The Central Eyre Iron Project involves developing an open-pit mine, processing plant, infrastructure corridor connecting the mine to a new deep water port at Cape Hardy. Key aspects include:
- Mining 20 million tonnes of iron ore concentrate annually using conventional open-pit methods.
- A standard gauge railway will transport concentrate 145km from the mine site to the new port facility.
- The port at Cape Hardy will have capacity for 30 million tonnes and be capable of handling capesize vessels.
- Construction is expected to create over 1,600 jobs while operations will support 650 ongoing positions.
- Extensive environmental studies have been undertaken and mitigation plans are in place to manage issues like dust, fl
1. Tigers Realm Coal presented plans for the development of its Project F coking coal mine in Russia, which has coal resources of 111 Mt and reserves of 16.1 Mt.
2. Project F is planned to be developed in phases, with Phase One targeting 600 ktpa of production using existing infrastructure and Phase Two expanding to 1 Mtpa with additional infrastructure.
3. Financial analysis shows Project F can be a low-cost producer with site operating costs of $41/t for the 1 Mtpa Phase Two and expansion potential beyond that.
130218 February Investor Presentation (Final)Dean Richardson
Marengo Mining is developing the Yandera copper project in Papua New Guinea, one of the largest copper projects in Asia-Pacific. Key highlights include a fixed engineering, procurement, and construction contract of US$1.42 billion and development capital expenditure estimated between US$1.7-1.85 billion. The feasibility study is scheduled for completion in March 2013 and production is targeted to begin in 2016.
The document discusses competent persons statements for exploration results, resource estimates, and project evaluation from the Image Resources NL 2014 conference presentation. It also provides forward looking statements regarding the company's operations, economic performance, and outlines the investment case, company overview, project location, sustainability considerations, resource estimates, proposed plant concepts, funding requirements, project economics, next steps, development team, and exploration potential for the North Perth Basin mineral sands project in Western Australia.
Commerce Resources Corp. has engaged Roche Ltd. to complete a pre-feasibility study on the Ashram Rare Earth Element Deposit in Quebec. Roche will work with various consultants on road layout, environmental data collection, and metallurgical test work. The goal is to improve upon the base case from the preliminary economic assessment and optimize the flowsheet for a pre-feasibility study planned for completion in late 2013 or early 2014. A bulk sample was also collected from the deposit for ongoing metallurgical testing.
REIS 2013 Broken Hill - Peel Mining ASX:PEXSymposium
This document provides an overview of Peel Mining Limited's exploration projects in the Cobar Superbasin in New South Wales, Australia. It summarizes their key asset, the Mallee Bull copper-polymetallic discovery, which has returned high-grade drill results over 120m of strike and to depths of over 600m below surface. Phase 3 drilling is underway to further extend mineralization. The document also summarizes Peel's 100%-owned Cobar Superbasin Project, highlighting recent encouraging drill results at the Mundoe copper prospect that indicate it may be the next major discovery in the region like Mallee Bull.
PLD Corporation Limited is an emerging base metals company focused on the acquisition, financing and development of base metal assets in Western Australia. It has acquired the Admiral Bay Zinc Project, located in the Kimberley region, which hosts a JORC compliant inferred mineral resource of 72Mt @ 6.7% ZnEq including a higher grade zone of 20Mt @ 10% ZnEq. PLD has secured $10 million in financing from two leading mining finance managers to advance exploration and development at Admiral Bay and its Rocky Gully Nickel-Copper Project. Admiral Bay is a large, high-grade Mississippi Valley Type zinc deposit with potential to become one of the world's most significant undeveloped zinc assets.
World Titanium Resources is developing the large, high grade Ranobe mineral sands deposit in Madagascar to become a tier 1 mineral sands company. A 959 million tonne resource at 6.1% heavy minerals was identified, with a maiden 161 million tonne ore reserve at 8.2% heavy minerals. Successful trial mining and processing of a 6 tonne bulk sample confirmed the process design and high quality products. Definitive studies estimated initial capital costs of US$192 million to develop a 21 year starter pit producing over 400,000 tonnes per year of ilmenite and zircon/rutile concentrates, with competitive operating costs. The project has the potential for significant shareholder value creation
REIS 2013 Broken Hill - Eastern Iron ASX:EFESymposium
The 3rd annual Resources & Energy Investment Symposium (REIS) is on 19-22 May, once again held in the unique city of Broken Hill; Last year’s event exceeded the expectations of all that attended - including over 350 delegates, 12 keynote speakers and more than 30 resource companies presenting their investment opportunities.
A focus for this year’s symposium will be on the current economic climate including its challenges and opportunities, not only in the Australian resources industry, but Australia’s position in the international market.
Reservoir Minerals Inc. is a Canadian project generator company focused on managing exploration risk through multiple early stage exploration projects in diverse metals and locations in Europe and Africa. Their business model is to fund initial exploration to create value, then introduce joint venture partners to fund further exploration in exchange for project equity. Their key project is a joint venture in Serbia called the Timok Project, where they discovered the Cukaru Peki deposit estimated to contain 65.3 million tonnes at 2.6% copper and 1.5 g/t gold. Reservoir is well funded with $48 million in treasury and managed by an experienced exploration team.
Similar to Iron Road Presentation to Iron Ore 2017 Conference (20)
UnityNet World Environment Day Abraham Project 2024 Press ReleaseLHelferty
June 12, 2024 UnityNet International (#UNI) World Environment Day Abraham Project 2024 Press Release from Markham / Mississauga, Ontario in the, Greater Tkaronto Bioregion, Canada in the North American Great Lakes Watersheds of North America (Turtle Island).
Methanex is the world's largest producer and supplier of methanol. We create value through our leadership in the global production, marketing and delivery of methanol to customers. View our latest Investor Presentation for more details.
The E-Way Bill revolutionizes logistics by digitizing the documentation of goods transport, ensuring transparency, tax compliance, and streamlined processes. This mandatory, electronic system reduces delays, enhances accountability, and combats tax evasion, benefiting businesses and authorities alike. Embrace the E-Way Bill for efficient, reliable transportation operations.
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdfSOFTTECHHUB
The world of blockchain and decentralized technologies is about to witness a groundbreaking event. ZKsync, the pioneering Ethereum Layer 2 network, has announced the highly anticipated airdrop of its native token, ZK. This move marks a significant milestone in the protocol's journey, empowering the community to take the reins and shape the future of this revolutionary ecosystem.
Cleades Robinson, a respected leader in Philadelphia's police force, is known for his diplomatic and tactful approach, fostering a strong community rapport.
World economy charts case study presented by a Big 4
World economy charts case study presented by a Big 4
World economy charts case
World economy charts case study presented by a Big 4
World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4
World economy charts case study presented by a Big 4
World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4study presented by a Big 4
Iron Road Presentation to Iron Ore 2017 Conference
1. Central Eyre Iron Project
Developing a new iron ore mine in a challenging climate
Iron Ore 2017
24-26 July 2017
2. Forward Looking Statements
This announcement contains certain statements with respect to future matters which may constitute "forward-looking statements". Such statements are only predictions and are
subject to inherent risks and uncertainties which could cause actual values, results, performance or outcomes to differ materially from those expressed, implied or projected.
Investors are cautioned that such statements are not guarantees of future performance and accordingly not to put undue reliance on forward-looking statements due to the inherent
uncertainty therein.
Competent Persons’ Statements
The information in this report that relates to the Inferred Mineral Resources (Oxide and Transitional) estimated for the Murphy South - Boo-Loo/Dolphin prospect is based on and
fairly represents information and supporting documentation compiled by Mr Iain MacFarlane, who was a Fellow of the Australasian Institute of Mining and Metallurgy. Mr MacFarlane
at the time of release was a full time employee of Coffey Mining Limited. There has been no material change and as such this resource is reported as it was released in 2011. Mr
MacFarlane had sufficient experience relevant to the style of mineralisation and the type of deposits under consideration and to the activity which he was undertaking to qualify as a
Competent Person as defined in the 2004 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr MacFarlane has
consented to the inclusion in reports of the matters based on his information in the form and context in which it appears.
The information in this report that relates to Resources estimated in 2013 for the Murphy South/Rob Roy (Fresh) prospect is based on and fairly represents information and
supporting documentation compiled by Ms Heather Pearce, who is a member of the Australasian Institute of Mining and Metallurgy, and was a full-time employee of Iron Road
Limited. This estimation was peer reviewed by Dr Isobel Clark, who is a member of the Australasian Institute of Mining and Metallurgy and who at the time of release was employed
by Xstract Mining Consultants. Dr Clark has sufficient experience relevant to the style of mineralisation and the type of deposits under consideration and to the activity which she is
undertaking to qualify as a Competent Person as defined in the 2004 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”.
Dr Clark consents to the inclusion in the report of the matters based on the information in the form and context in which it appears.
The information in this report that relates to Mineral Resources (Fresh) estimated for the Boo-Loo/Dolphin prospect is based on and fairly represents information and supporting
documentation compiled by Ms Heather Pearce, who is a member of the Australasian Institute of Mining and Metallurgy, and was a full-time employee of Iron Road Limited at the
time of release. This estimation was peer reviewed by Mr Alex Virisheff, who is a member of the Australasian Institute of Mining and Metallurgy and employed by AMC Consultants.
Mr Virisheff has sufficient experience relevant to the style of mineralisation and the type of deposits under consideration and to the activity which he is undertaking to qualify as a
Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Virisheff consents to the
inclusion in the report of the matters based on the information in the form and context in which it appears.
The Ore Reserves estimated for CEIP involving mine planning is based on and fairly represents information and supporting documentation compiled by Mr Bob McCarthy, a Member
of the Association of Professional Engineers and Geoscientists of British Columbia (Canada) and a full time employee of SRK Consulting (North America). Mr McCarthy has
sufficient experience relevant to the style of mineralisation and the type of deposits under consideration and to the activity which he is undertaking to qualify as a Competent Person
as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr McCarthy consents to the inclusion in the
report of the matters based on his information in the form and context in which it appears. The Ore Reserves estimated for the CEIP involving aspects other than mine planning is
based on and fairly represents information and supporting documentation compiled by Mr Larry Ingle, a Member of the Australian Institute of Mining and Metallurgy and a full time
employee of Iron Road Limited. Mr Ingle has sufficient experience relevant to the style of mineralisation and the type of deposits under consideration and to the activity which he is
undertaking to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”.
Mr Ingle consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.
Disclaimer
3. Overview
• Open pit mine, processing facilities, rail, port and all supporting
infrastructure
• 24 Mtpa (dry) of 67% Fe magnetite product
• ~100 µm direct sinter feed, no further processing
• 3.7 Bt @ 15% Fe Ore Reserve – largest in Australia
• 1 Mt per day total material movement
6. • Quartz – feldspar – magnetite –
garnet – biotite gneiss
• Low levels of S and P
• No clays, igneous intrusions or
faults
• Low variability
• Average UCS of 110 MPa
Geology
7. 0.18mm
0.18mm
Mineralogy
• Mainly quartz – feldspar – magnetite
• Coarse-grained, average of 1.5 mm
• Cut with micro-fractures
• Sharp grain boundaries
• Grain size has driven the approach to
process design
8. Blasting and IPCC
• Using blasting as “primary
crushing”
• In-Pit Crushing and Conveying
• Scalping screens and sizers
• Waste and Ore crushed
• Conveyors moving crushed waste
and ore
9. Conveyors
• ~70 km of conveyors on the site
once at full capacity
• Minimising use of trucks
• Ore stacked on the ROM
• Waste transported to the
Integrated Waste Landform
(IWL)
- Tailings from process co-
mingled
11. Product
• 24 Mtpa (dry)
• 67% Fe
• 100 µm
• 8% moisture
• SiO2 + Al2O3 <5%
• P < 0.01%
• S < 0.01%
12. Testwork
• ALS Laboratories
• Bureau Veritas
• Industry leaders including TUNRA, DRA Mineral Projects, Thiess, Orica, MMD,
Weir, FL Smidth, Mineral Technologies and potential other suppliers
• Programmes included:
• Davis Tube Recovery (DTR)
• Comminution parameters
• Magnetic separation testwork
• Filtration
• Wilfley table tests
• Full scale spiral testwork
• Material handling properties
13. Tailings
• Two tailings sizes
– Coarse ~4 mm
– Fine ~100 µm
• Coarse free draining with screens
• Fines dewatered with vacuum filter
belt to 10%
• Water recovered and stays in the
process
• Tailings added to waste conveyor
14. Dumping Technology for IWL
• Three spreaders at 25,000 tph each
• Three dumping benches of 45 m height
each (30 m deep dump + 15 m high dump)
• Slewing development of IWL
• Potential for in-pit truck dumps in later
stage
15. Water
• Process recycles water where possible
• Bore field located ~60 km from mine site
– Hyper saline
– Processing in bore water
• RO plant produces clean water for washing
the concentrate product, gland seals and
potable requirements
– Brine used as dust suppression
• Mine pit dewatering water used in the pit for
dust suppression
– Pit water very saline
– Not applied to ore destined for the plant
16. Modular Design
• Prefabrication and
preassembly in an
offshore fabrication facility
• Nine super modules per
process train
• Controls schedule, safety
and logistics concerns
• First three stages of
commissioning before
transported to site
• Fabrication and transport
experts involved in the
design
17. Largest module is the
CMS building
47 m long
19 m wide
44 m high
Slightly larger
footprint than the
Duxton Hotel and just
5m shorter
18. “Things do not just happen.
They are made to happen.”
John F Kennedy
“Things do not just happen.
They are made to happen.”
John F Kennedy
www.ironroadlimited.com.au
admin@ironroadlimited.com.au
19. Appendix
Table 1 – CEIP Ore Reserve Summary
Resource
Classification
Metric Tonnes
(Mt)
Fe
(%)
SiO2
(%)
Al2O3
(%)
Proved 2,131 15.55 53.78 12.85
Probable 1,550 14.40 58.58 12.64
Total 3,681 15.07 53.70 12.76
The Ore Reserves estimated for CEIP involving mine planning is based on and fairly represents information and supporting
documentation compiled by Mr Bob McCarthy, a Member of the Association of Professional Engineers and Geoscientists of
British Columbia (Canada) and a full time employee of SRK Consulting (North America). Mr McCarthy has sufficient experience
relevant to the style of mineralisation and the type of deposits under consideration and to the activity which he is undertaking to
qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves”. Mr McCarthy consents to the inclusion in the report of the matters based on his
information in the form and context in which it appears. The Ore Reserves estimated for the CEIP involving aspects other than
mine planning is based on and fairly represents information and supporting documentation compiled by Mr Larry Ingle, a
Member of the Australian Institute of Mining and Metallurgy and a full time employee of Iron Road Limited. Mr Ingle has
sufficient experience relevant to the style of mineralisation and the type of deposits under consideration and to the activity
which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting
of Exploration Results, Mineral Resources and Ore Reserves”. Mr Ingle consents to the inclusion in the report of the matters
based on his information in the form and context in which it appears. This report includes results that have previously been
released under JORC 2012 by the Company on 2 May 2016. The Company is not aware of any new information or data that
materially affects the information included in this announcement and all material assumptions and technical parameters
underpinning the Ore Reserve continue to apply and have not materially changed.
20. Appendix
Table 2 – CEIP Global Mineral Resource
Location Classification
Tonnes
(Mt)
Fe
(%)
SiO2
(%)
Al2O3
(%)
P
(%)
LOI
(%)
Murphy South/Rob Roy
Measured 2,222 15.69 53.70 12.84 0.08 4.5
Indicated 474 15.6 53.7 12.8 0.08 4.5
Inferred 667 16 53 12 0.08 4.3
Boo-Loo/Dolphin Indicated 796 16.0 53.3 12.2 0.07 0.6
Inferred 351 17 53 12 0.09 0.7
Total 4,510 16 53 13 0.08 3.5
Table 3 – CEIP Indicative Concentrate Specification – 100 micron (p80)*
Iron (Fe) Silica (SiO2) Alumina (Al2O3) Phosphorous (P)
66.7% 3.36% 1.90% 0.009%
The Murphy South/Rob Roy Mineral Resource estimate was carried out following the guidelines of the JORC Code (2004) by
Iron Road Limited and peer reviewed by Xstract Mining Consultants. The Murphy South - Boo-Loo/Dolphin oxide and transition
Resource estimate was carried out following the guidelines of the JORC Code (2004) by Coffey Mining Limited. The Boo-
Loo/Dolphin fresh Mineral Resource estimate was carried out following the guidelines of the JORC Code (2012) by Iron Road
Limited and peer reviewed by AMC Consultants. This report includes results that have previously been released under JORC
2004 and JORC 2012 by the Company on 30 June 2010, 28 May 2013 and 27 February 2015. The Company is not aware of any
new information or data that materially affects the information included in this announcement and all material assumptions
and technical parameters underpinning the Mineral Resource continue to apply and have not materially changed.
* The concentrate specifications given here are based on current data from metallurgical test work, bulk samples and
simulation modelling designed specifically to emulate the proposed beneficiation plant.