The document summarizes the reasons for failure of the IT project between National Air Traffic Services (NATS) and IBM to implement a new air traffic control system. Key reasons included unrealistic deadlines, unclear requirements, underestimating costs and time, changing objectives, and lack of open communication about problems. The go-live date was repeatedly delayed from 1996 to 2002 due to issues that were known but not openly discussed from the start.