The email from Darcy Pearson notifies various parties that the large bore hydrotest of the Keystone Pipeline project was completed successfully. The 4,400 cubic inch hydrotest was finished on the first try, which Richard Coglon, the project manager, acknowledged as a significant achievement. Pearson informed the recipients that pressure has been released from the line and barricades can now be removed from exclusion zones as required.