Gower Facility Plans
  December 18, 2012
Gower Middle Improvements
•   3 Science Classrooms—Grades 6, 7, & 8
•   New Gym, Locker Rooms, Weight/Fitness Room
•   Industrial Technology, Family & Consumer Sciences, and Art
•   Lighting and Ceiling Tiles Updates
•   Cafeteria Remodeled
•   Athletic Fields
•   Classroom Casework (cabinets and shelving)
•   Entrance Vestibules at East and West Doors
•   Improved Parking and Traffic Flow
Gower Middle: 2013 - 2014
Gower Middle Athletic Fields
Entrances
Gymnasium
Locker Rooms
Weight/Fitness Room
Science Classrooms
Industrial Technology
Industrial Technology
Family & Consumer Science
Family & Consumer Science
Art Classroom
Art Classroom
Gower West Improvement
•   2 Early Childhood Classrooms
•   Removal of Asbestos Tile in East Classrooms
•   Replacement of Flooring in East Classrooms
•   Pavement Replaced on West Playground
•   Fencing Added to West Playground
•   Art Room Storage and Shelving
•   Lighting and Ceiling Tile as Needed
Gower West 2013- 2014
Early Childhood Classroom
Early Childhood Classroom
Timeline
• January 14   Bid Invitations Published

• February 19 Bid Approval

• March 1      Excavation for GM Gym and Addition Begins

• March 25     Asbestos Abatement at GM

• June 3       Interior Work at GW & GM Begins

• September 1 Substantial Completion at GW & GM