1. Faithful+Gould is submitting an application to AI Futtaim Carillion LLC for an extension of time of 90 days to complete tunnel monitoring works for the Deira Waterfront Development project. 2. The application includes a letter from AI Futtaim Carillion as well as appendices providing a brief history of the project, a timeline of delay events, cost details, and supporting documentation for each delay event. 3. Faithful+Gould argues they are entitled to the extension and have provided sufficient details of delays outside their control, their efforts to mitigate delays, and their timely responses to delaying events.