This document provides a formula for estimating project timelines or costs using an optimistic, most likely, and pessimistic estimate. The formula averages the estimates by multiplying the optimistic estimate by 1, the most likely estimate by 4, and the pessimistic estimate by 1, then dividing the total by 6.