8. EOSDIS Futures
Future spending profile reflects reductions being achieved
with evolution
– GES DISC off of ECS by end of 2007; MODAPS performs MODIS
processing and L1/atmospheres archive and distribution
– ASDC DAAC schedule seems to be moving right; looking at
possible risk mitigation
– ECS evolution development to be complete by March 2008
ECS contract being extended to May 2009; ESDIS is
looking at ways to support maintenance of ECS beyond
2009
THG grant expires 7/2008; and we’re expecting to continue
funding THG with a new grant (3 years)