This document outlines the rules for enlistment of contractors in the Central Public Works Department (CPWD) of India, last amended in 2014.
It defines key terms, establishes the scope and process for enlistment, and specifies categories, classes, jurisdictions, authorities, eligibility criteria, and other requirements. Contractors meeting the eligibility thresholds can apply for enlistment in different categories and classes based on their work experience, financial capacity, and other qualifications. Enlistment allows contractors to be considered for relevant CPWD projects but does not guarantee the awarding of work. The rules are intended to maintain a list of qualified contractors and ensure only active, high-performing contractors remain enlisted.