Call Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCR
Elia group full year results 2013
1. Full year 2013 results
Analyst meeting
Brussels, 28 February 2014
2. Disclaimer
- This presentation is only provided for general information purpose about Elia and its
activities. The included statements are neither reported results nor other historical
information. They are not provided to serve as the basis for any evaluation of Elia, and
cannot be binding and/or enforceable upon Elia.
- As forward-looking statements, they are subject to assumptions, risk and uncertainties,
actual future results may differ from those expressed in or implied by such statements.
- Although Elia uses reasonable cares to present information which is up-to-date to the
best of Elia's knowledge, Elia makes no representation or warranty whatsoever as to
the adequacy, accuracy, completeness or correctness of such information.
- Elia will not be liable for any consequences arising from or related to the use or
interpretation of the information contained or absent in this presentation.
Elia Group full year results 2013 / Brussels, 28.2.2014
2 / 30
5. Key highlights 2013
Operational
• Adjusted transmission tariffs for Elia have been approved by the CREG
• Nearly full realization of ambitious investment plans in both countries
• Continuity of supply maintained during winter season in both areas
Financial
• Good results for the Group:
• Significant increase results 50Hz transmission
• Lower results for Elia transmission due to low Belgian OLO
• Proposed dividend of €1,54 per share
• New consolidation method for 50Hertz used as from 2014
Outlook
• Establishment of new entity by Elia and 50Hertz to reinforce the position of the Elia Group for asset
and share deals, by scouting for such deals and developing two lines of businesses: Consulting &
Services and EPC/EPCM projects
• Regulatory status of play
• Investment programme for the Elia Group
• Changing government in Germany results in changing energy policy?
• Decisions federal government Belgium relating to the energy law
Elia Group full year results 2013 / Brussels, 28.2.2014
5 / 30
7. Energy consumption
9,0
8,0
Elia’s network: 80,5 TWh
(81,7 TWh)
7,0
TWh
6,0
• Mild weather
• Decentralised generation
5,0
4,0
3,0
2,0
1,0
0,0
jan
6,0
feb
mar
apr
may june july
2010
2011
aug sep
2012
oct
nov
dec
50Hertz’s network: 58,1 TWh
(58,2 TWh)
5,0
4,0
TWh
3,0
2,0
1,0
0,0
jan
feb
mar
apr may june july
2010
2011
aug sep
2012
oct
nov
dec
• Mild weather
• Decentralised generation
• Renewables
(1) The Elia consumption indicator covers the majority of electricity consumption.
It includes all production directly connected to the Elia grid plus net import-export balance
Elia Group full year results 2013 / Brussels, 28.2.2014
7 / 30
8. Import - export
Denmark
1,2 TWh
4,4 TWh
2,5 TWh
Netherlands
0,5 TWh
7,8 TWh
Poland
Hamburg
Berlin
27,9 TWh
5,4 TWh
8,8 TWh
2,4 TWh
0,7 TWh
France
Luxembourg
8,8 TWh
0,8 TWh
1,4 TWh
Czech Republik
2,4 TWh
•
Significant imports in Belgium due to continued outages of nuclear plants up to
June 2013
•
The increased RES share within control zone 50Hertz results in important exports
Elia Group full year results 2013 / Brussels, 28.2.2014
8
8 / 30
9. Elia group: Investments
50Hertz
Elia
2%
3%
11%
6%
14%
€ 202,7 M
€ 402,0 M
43%
1%
€ 247,7 M onshore
€154,3 M offshore
31%
89%
Replacements
Internal consumption
Interconnections
Integrating renewables
Non electrical investments
•
Investments in Belgium are mainly driven by replacements and the internal
consumption.
•
In Germany, the integration of renewables is by far the most important driver.
Elia Group full year results 2013 / Brussels, 28.2.2014
9 / 30
10. Elia-TSO: Major investments
Large Infrastructure
projects
• BRABO
• Reinforcement around port of
Antwerp and increased capacity
with the Netherlands
• Permit process ongoing
• Expected commissioning 2017-2018
• ALEGRO
Extension CAPEX driven by
integration of renewables &
localisation of generation
• Increasing renewables onand offshore need to be
integrated
• Localization of the power
plants change
• HVDC interconnection with
Germany
• Increased market liquidity, reliability
and security of supply
• Walloon government adopted the
draft revision of the sector plan
• Expected commissioning 2019
Elia Group full year results 2013 / Brussels, 28.2.2014
Replacement
CAPEX
• Mostly investments in
the high and low
voltage substations
• Phase out of old
population of assets
commissioned before
1980’s
Extension CAPEX
driven by internal
consumption
• Investments due to the
change in profile of the
power needs, even if
energy has decreased
over time,
• Delocalization of the
electricity needs
10 / 30
11. 50Hertz: Major Investments
BALTIC 2
• Connection of 288
MW offshore wind
park under
construction
• 3 cables, spanning
120km offshore
and 16 km onshore
• Expected to
become
operational in 2014
SOUTH-WEST
CONNECTOR
BARWALDE SCHMOLLN
• Section Vieselbach
– Altenfeld :
under construction
• Under construction
• Section Altenfeld –
Redwitz:
Plan approval in
preparation
• Decision expected
3rd quarter 2014
Elia Group full year results 2013 / Brussels, 28.02.2014
• Innovative
construction
method minimizing
costs
• Expected to
become
operational in
autumn 2014
UCKERMARKLINE
& BERLIN NORTH
RING
SOUTH-EAST DC
PASSAGE
• Plan approved on
first section Berlin
North Ring
• Project necessity
defined and legally
approved
• Other section and
Uckermarkline in
ongoing plan
approval phase
• Part of German
Grid Need Act
• Decisions
expected in 2014
• Joint project with
Amprion (450 km)
• Preparation of
regional planning
11 / 30
13. Corporate structure and shareholders’ structure
Publi-T
45.22%
Free float1
52.26%
Publipart
2.52%
Eurogrid International
CVBA
60.00%
Elia System Operator NV
Elia Asset NV
99.99%
Ampacimon
36.81%
Elia Engineering
100%
Elia Re
100%
CASC
8.33%
HGRT
24.50%
Coreso
22.49%
APX
29.02%
Eurogrid GmbH
100%
E offshore A
LLC
100%
Gridlab GmbH
100%
50Hertz
Transmission
100%
EEX
2.25%
CAO
12.50%
Coreso
10.00%
EMCC
20.00%
Atlantic Grid
Investment A
Inc. - 100%
50Hertz
Offshore
100%
Atlantic Grid A
Interm. Holdco
10.00%
Atlantic Grid A
Operational
Holdco
Main change is the new participation of 50Hertz in the European Energy
Exchange (EEX)
Elia Group full year results 2013 / Brussels, 28.2.2014
13 / 30
14. Elia group : consolidated key figures
(in € Mio)
2013
2012
1.389,5
1.306,6
6,3%
EBITDA
486,9
455,5
6,9%
(R)EBIT
345,4
305,4
13,1%
Total revenues
Finance result
(108,5)
(134,8)
-19,5%
Taxes
(61,5)
(16,2)
•
•
2013
56
%
2012
42
%
44
%
58
%
279,6%
Net profit
•
•
Net profit
Change
175,8
155,0
13,4%
Elia
50Hertz
Positive evolution in EBIT(DA) due to improved EBITDA in both 50Hertz and Elia
Finance result positively impacted by lower interest charges in Belgium and a
change in discounting of auction revenues in Germany
Taxes mainly increase due to the 2012 one-off effect in the figures of Elia
Increase in the net profit of 13,4% to € 175,8 M as a result of the significant
increase in Germany, partly compensated by the decrease in Belgium
Elia Group full year results 2013 / Brussels, 28.2.2014
14 / 30
15. Elia: 2013
Regulated returns
5,96%
(in € Mio)
2013
Total revenues
832,7
2012
770,1
Change
100
80
8,1%
209,3
291,6
188,6
7,6%
11,0%
In € Mio
(R)EBIT
313,9
60
(109,2)
(117,5)
-7,1%
2,1
7,7
6,3
16,1
16,2
4,21%
40
Net profit
•
•
•
(23,4)
77,1
17,5
89,2
-233,7%
-13,6%
13,5
53,5
63,8
20
5,3
6,9
19,3
2,98%
2,43%
51,6
0
-10
5,17%
3,44%
10
Taxes
0,1
3,8
8,2
50
30
Finance result
5,35%
90
70
EBITDA
5,59%
2010
-1,5
2011
Fair remuneration
Incentive efficiency
Other
OLO
44,5
-0,4
2012
2013
Goodwill
Incentive CAPEX
ROE
Total revenues, EBIT(DA) and taxes are impacted by the one-off effect in 2012 from the recognition of
the deferred tax benefit on the transferable notional interest deduction reserve
Finance result down mainly due to lower interests to be paid on the loan with floating interest rates
Regulated profit (€ 75,6 Mio) fairly in line with 2012 (- 2,1%), net profit negatively impacted by the
important discount effect of the recoverable pension cost last year
Elia Group full year results 2013 / Brussels, 28.2.2014
15 / 30
16. Elia: 2013
Net profit evolution 2012 - 2013
Regulated asset base
2013
1,5
(7,1)
5,8
(0,9)
(1,2)
3.935,1
Other
- 17,3
(4,7)
Goodwill decomissioning
Changes in WC
(10,1)
4,6
Depreciations
New investments
89,2
77,1
2012
2011
2010
- 23,3
62,5
- 96,8
202,7
3,807,3
3,763,0
3.743,3
In € Mio
•
•
Results are still suffering from low long term Belgian interest rate (2,43% in 2013 vs. 2,98% in
2012), partly compensated by higher goodwill decommissioning
Negative effect from the recoverable pension cost is due to the important discount effect in 2012
Elia Group full year results 2013 / Brussels, 28.2.2014
16 / 30
17. 50Hertz: 2013
Dividend yield
(in € Mio)
2013
2012
45
Change
40
557,6
539,4
3,4%
EBITDA
173,1
163,9
5,6%
(R)EBIT
Finance result
136,1
0,7
116,8
(17,5)
16,5%
-104,0%
35
In € Mio (60%)
Total revenues
15,24%
30
25
20
13,06%
11,01%
36,4
42,5
30,7
15
10
Taxes
Net profit
(38,2)
98,7
(33,6)
65,8
13,7%
50,0%
5
0
2011
2012
Dividend
•
•
2013
Yield
Increased EBIT(DA) mainly a result from the increased cost recovery for investments, both in the
old (T-2) and new system (T-0)
Finance result positively impacted by discounting of auction revenues
Elia Group full year results 2013 / Brussels, 28.2.2014
17 / 30
18. 50Hertz: 2013
Net profit evolution 2012 -2013 (1)
Regulated asset base (1)
2013
5,4
(7,2)
3.064,0
3,0
22,0
Other
14,3
Changes in WC
18,9 (14,7) 20,9
15,8
(15,4)
Depreciations
166,4
New investments
14,7
-313,4
-92,4
402,0
110,7
2012
2011
3.045,4
2.699,9
In € Mio
•
•
Net profit mainly boosted by the increased cost recovery for investments, lower regulatory risk
provisions and the discounting of auction revenues, partly offset by no EEG bonus and lower
result on the Korridor model
Regulated asset base growing with the important investments, however offset to a large extent by
the improving EEG prefinancing position
(1) Numbers are based on 100% of 50Hertz
Elia Group full year results 2013 / Brussels, 28.2.2014
18 / 30
19. Elia Group: Consolidated key figures
Debt
155,3
In € Mio
495
4
60
60
495
298
298
Maturity
Short term
borrowings 50Hertz
EIB Elia
16,1%
Within 3 - 5 y
Shareholder loan
After 5 y
Eurobond 50Hertz
1.997,6
2012
•
•
•
2.244,0
Eurobond Elia
Within 1 y
18,0%
65,9%
2013
Debt within Elia increased due to the refinancing of the € 500 Mio Eurobonds with the new € 550
Mio (15 y) and € 200 Mio (20y) Eurobonds.
Short term borrowings decreased significantly within 50Hertz as a result of the positive evolution
on the prefinancing of the EEG mechanism
Maturity profile improved significantly with the new Eurobonds. In 2014, a € 500 Mio bond is
coming to maturity
Elia Group full year results 2013 / Brussels, 28.2.2014
19 / 30
20. Elia Group: Consolidated key figures
(in € Mio)
2013
2012
Net debt
2.773,8
2.910,8
Long Term:
A-
Leverage (D/D+E)
55,31%
57,99%
Outlook:
Stable
REBITDA/Gross
Interest
3,96
3,08
Net debt / REBITDA
5,61
6,39
Average cost of debt
3,94%
4,93%
% fixed of gross debt
84,37%
83,89%
Standard & Poor’s rating Elia Group:
•
•
•
Moody’s rating German segment:
Long Term:
Baa1
Outlook:
Stable
Decrease in net debt is mainly a result of the significant improvement in the prefinancing of the
EEG mechanism by 50Hertz
Average cost of debt decreased thanks to the replacement of the Eurobond and low interest
charges that were due on the floating interest loan
Ratings were again confirmed for both Elia and 50Hertz
Elia Group full year results 2013 / Brussels, 28.2.2014
20 / 30
21. Elia Group: Dividend policy
CAGR = 2,22%
€ / share
1,38
1,40
1,47
1,47
1,54
79,3%
68,4%
64,5%
57,4%
53,1%
2009
Total amount
paid out (€m)
2010
2011
2012
2013
66,6
84,5
88,7
89,0
93,3
Dividend
Pay-out ratio
Proven track record of growing dividend over time, with a compound annual growth rate
of 2,22%
Elia Group full year results 2013 / Brussels, 28.2.2014
21 / 30
22. Impact changed method of consolidation for 50Hertz
as of 2014
Proportionate
consolidation
Equity pick-up
Change
Total revenues
1.389,5
832,7
(556,8)
EBITDA
487,0
313,9
(173,1)
(R)EBIT
345,4
209,3
(136,1)
Finance result
(108,5)
(109,2)
(0,7)
Taxes
(61,5)
(23,4)
38,2
Share of profit of equity accounted
investees
0,3
98,7
98,7
Net profit
175,8
175,8
0,0
Total assets
6.532,2
5.555,7
(976,5)
Net financial debt
2.733,9
2.628,4
(105,5)
• No impact on S&P rating – consistently consolidating 50Hertz at 100%
• Due to mechanical adjustment, ratio’s will look slightly worse. However no impact on
financing as both Elia and 50Hertz are strictly ringfenced
Elia Group full year results 2013 / Brussels, 28.2.2014
22 / 30
24. Regulatory state of play
Belgium
• CREG wants to formulate a new tariff methodology by the end
of 2014, including a framework for the offshore investments
• A draft methodology will be issued by the CREG in June 2014
• Consultation round will be organized by the CREG from June
up to the fall of 2014
• Afterwards the CREG will issue a new tariff methodology by the
end of the year which will be used for the period 2016-2020
Germany
• New tariff period has started as from 1 January 2014
• Positive changes in the Korridor model
Elia Group full year results 2013 / Brussels, 28.2.2014
24 / 30
25. Elia Group: Investments 2014
Elia
50Hertz
5%
3%3%
13%
35%
€ 252,5 M
26%
€ 505,2 M
€ 257,9 M onshore
€ 247,3 M offshore
2%
24%
89%
Replacements
Interconnections
Non electrical investments
Internal consumption
Integrating renewables
•
Integrating renewables and investments due to generation localization are becoming
more important in Belgium.
•
In Germany, investments increase year-over-year with 25,7%, mainly driven by the
offshore connections
Elia Group full year results 2013 / Brussels, 28.2.2014
25 / 30
26. Elia TSO – main investment projects
1 Stevin
2 Belgian Offshore Grid
3 Nemo - HVDC Connection UK
4 Brabo
5 Allegro – HVDC Connection Belgium-Germany
6 East Loop reinforcement
7 Interconnection BE-Lux
8 Reinforcement Avelgem
• Auditor of the Council of State issued negative advices on the Flemish Regional Spatial
Plan, which includes the approval of the Stevin project
• Possible repercussions on Belgian Offshore Grid and Nemo
Elia Group full year results 2013 / Brussels, 28.2.2014
26 / 30
27. 50Hertz – main investment projects
11
3
Existing grid
Planning procedure
Approval procedure
Under construction
Completed
10
1
1
Power Plant
Substation
(50Hertz)
Substation
(not 50Hertz)
9 1
3 Offshore connection Baltic 2
4 South-West interconnector
5 Grid connection UW Förderstedt
8
7
1
12
2 Bärwalde – Schmölln
Fertig gestellt
1
1
1 Completed projects in 2013 and 2012
6 3rd interconnector to Poland
7 380-kV-Nordring Berlin
1
6
5
8 Uckermark-line Neuenhagen – Bertikow
9 Bertikow – Pasewalk
1
4
1
Elia Group full year results 2013 / Brussels, 28.2.2014
2
10 Offshore connections in Baltic Sea
11 Combined Grid Solution
12 Wolmirstedt – Perleberg
27 / 30
28. Belgium: Proposed changes in the Energy law
Developments in the changing energy environment give rise to
proposals from the legislator on adapting the energy law. Main
topics of those resolutions:
-
Plan Wathelet:
Installed capacity non-profiled units
14000
- 3.100 MW
12000
To further ensure the security of supply, the plan is introducing
10000
consultation about the needed volumes and activation of the
strategic reserves
MW
the concept of strategic reserves. Role of Elia : yearly
Max
8000
Min
6000
4000
2000
-
Change in corporate governance rules Elia
0
January 2014
2014/2015
2015/2016
2016/2017
Composition of the different committees advising the Board of
Directors will be changing
-
Offshore
- Support mechanism for new wind farms has been decided upon
- Elia will be granted the right to ask for the concession to
construct the offshore platforms.
Elia Group full year results 2013 / Brussels, 28.2.2014
28
28 / 30
29. Germany: Main outline of the proposed amendment
of the Renewable Energies Act (EEG)
-
RES share of electricity consumption to be between 40%
and 45% by 2025 and between 55% and 60% by 2035
(previously minimum targets were set: 2020 35%; 2030
50%)
A binding corridor for the deployment of renewables
energies
-
Offshore wind target: 6.5 GW by 2020 (previously 10
GW by 2020)
-
20,36
20
13,53
15
10
5
8,33
3,530
3,592
2011
2012
6,240
14,11
5,277
2,047
0
2010
2013
2014
Feed-in tariffs remain method of choice, mechanisms
for quantitative expansion control to be introduced by
2018 (tenders to be tested for large solar power systems
by 2016)
-
23,58
Mandatory “market premium” with sliding premium for
new RES plants
Costs
EEG surcharge
Line of attack of the Energiewende remains unchanged.
Elia Group full year results 2013 / Brussels, 28.2.2014
29 / 30
EEG surcharge [ct/kWh]
-
25
Costs [Bn. €]
Until now only key parameters have been established.
The legislative process has not yet started. Entry into
force is foreseen for August 2014.
30. Questions & Answers
Tom Schockaert
Investor Relations
+32 (0)2/546.75.79
tom.schockaert@elia.be
www.eliagroup.eu
Follow Us
http://www.twitter.com/eliacorporate
http://www.facebook.com/eliacorporate
http://www.linkedin.com/company/elia
Brussels, 28.2.2014