Sanction details
Item
No.
Year of
Sanction
Plan
Head
Description Alloc
-ation
Cost Outlay
(2015-16)
355 2015-16 42 Safety Village DF(3) 1690 0.1
387 2004-05 64 Facilities for
extraction,
rescue and
relief
CAP 700 278
388 2004-05 64 DM module DF(3) 299 87
SRSF 300 0
Total 2989 365.1
All values are in Lakhs
Consultancy status
• March 2008-Railway Board has advised that the
consultancy for setting up of Disaster Management
Institute and Module will be handled by RITES.
• April 2010- Board Advised SWR to process for
finalising the consultancy tender at Zonal level.
• SWR modified the scope within 25 lakhs of GM’s
power and the same was approved by Traction
Directorate.
• Tender opened on 07-12-2010 with single offer from
M/s Foundation for Educational Excellence,
Bangalore and was discharged for not meeting the
eligibility criteria.
Consultancy status- Contd
• Second tender opened on 29-03-2011 with single
offer from M/s Global Forum for Disaster
Reduction(GFDR), New Delhi and discharged again
on eligibility criteria issue.
• With the approval of GM, the tender was again
opened on 25-10-2011 without the Single similar
work eligibility criteria. Only Single offer from
GFDR received and the status of this tender is,
– Based on Finance member observation and as per GM
advice, ref was made to Board on 28-05-12 to get the
clearance from all concerned directorates for the scope
and deliverables.
– Board communicated the clearance on 14-03-2013.
Consultancy status- Contd
• Numerous efforts made by the convener to
finalize the tender could not materialize and is
being Discharged.
Action Plan
• In the light of Safety village sanction and the expertise
available in creating the facilities w.r.t Engineering,
Electrical(General &TRD) and S&T, decision has been taken
by SWR to start the work for these activities.
• The broad based items for rescue, Relief and restoration
shall be included in the mechanical portion of the estimate.
• Consultancy provision is being made in the detailed
estimate with the scope of work excluding engineering
facilities.
• Detailed estimate is likely to be sanctioned by mid June’15
• The recommendations of consultant can be complied by
revising the detailed estimate by suitably incorporating the
specifications on the broad based items included in the
estimate and by using the GMs power to include 20%
additional items in the estimate.
Scope of work for Consultancy
• Review of Existing DM facilities/Systems w.r.t DM Plan of IR and advice
means to comply with DM plan.
• Details of Facilities and equipments required to be provided in the DMI
and Safety village to meet the training requirement of IR in Rescue,
Medical relief and Restoration including its specification, source and
cost etc..
• Various disaster management courses to be run with course content
(Theoretical & Practical) specific to each category of trainees.
• Advice on the best practices being followed by Railways worldwide in
the areas of Rescue, relief and restoration and to suggest ways and
means to implement the same in IR.
• State of Art technology and equipments being used by Railways
worldwide and Training resources to be adopted by IR for Rescue,
Extrication, Medical relief and restoration techniques including virtual
reality models/systems for various scenorios.
• Deep tunnel rescue system including training requirement with details
of spec, source and cost.
• Training on deep water rescue, extrication
• Resource and training requirement to handle fires in trains.
Facilities considered in the estimate
Mechanical
• ART/ ARMV Formation with latest equipments
• Various over aged Rolling Stock for demo
• M&Ps, T&Ps ,Furniture and Teaching Aids.
• Computer Systems, Networking and Office
equipments
• Training of Officers, Faculty and instructors
• Development of Class room training modules for
various levels/types of trainees on relevant role with
requisite training materials.
• Virtual reality training modules for simulating
disaster scenarios.
• Consultancy
Facilities considered in the estimate
Engineering
• Compound Wall 1.5 Km
• Track length of about 2Km with two lines of 600 mts
each including box culvert type Tunnel-100 mts and
Bridge-50 mts.
• Training & Admin Block, Seminar hall cum Auditorium,
store area etc- 1600 Sqm
• Quarters- Type V-1, IV-4, III-4 & II-6
• 110 Bed Hostel with Kitchen and Dining -220 Sqm
• Sports and recreation facilities –Badminton, Tennis,
Basketball and Volley ball etc
• Landscaping and approach road & roads inside the
facilities
Facilities considered in the estimate
Electrical- General
Requisite power supply ,electrical fittings and appliances for
the above facilities.
Electrical- TRD
Provision of dummy OHE with released material on one track
of 600 mts to create an OHE environment for demonstrating
restoration under wire.
S&T
Provision of telecommunication and internet connection for all
the above facilities.
Provision of working signaling arrangement for a sample B-
class two line station with released materials including data
logger.
Integrated Abstract Estimate for three works
Sl
N0
Description
DMI DM Module
Safety
Village Total
Departme
-nt Total
64 (CAP) 64 (DF3) SRSF 42 (DF3)
1 MECHANICAL
a ART/ARMV Equipments 50 300 350
1655
b M&Ps ,T&Ps, furniture and teaching aids 200 100 300
c Computer systems, networking, office equipments 150 - 150
d Development of Class room training modules for various levels/types
of trainees on relevant role with requisite training materials 100 100 200
e Virtual reality training modules for simulating disaster scenarios. - 200 150 - 350
f Training of Officers, faculty and instructors - 100 50 - 150
g Various rolling stocks(Dep value) for ART formation and practical
training on rescue and restoration - - - 130 130
h Consultancy 25 - - - 25
2 Engineering
a Compound wall 1500 m - - - 75 75
1665
b Admin building, model rooms, seminar hall 1800 Sq.mtrs 300 - - 0 300
c Hostel & dining facility 2200 sq.mtrs. 150 - - 225 375
d Quartrers Type V-1, Type IV-4, Type III-4 and Type II 6 100 - - 150 250
e Sports and Recreation facilities 100 - - 0 100
f 2 Kms of track with two turnouts, 50sq mts station buildings - - - 240 240
g Levelling, land scape, approach road, internal road and greeneries. - - - 125 125
h Box Culvert type Tunnels & Bridge - - - 200 200
3 S&T and Electrical
a Provision of signal arrangement and telecommunication 25 - - 75 100
b Electrical general 100 - - 20 120

More Related Content

Similar to Dmi & safety village ppt

Similar to Dmi & safety village ppt (20)

Wind Technicians competence framework SIEMENS
Wind Technicians competence framework SIEMENSWind Technicians competence framework SIEMENS
Wind Technicians competence framework SIEMENS
 
OCS Training calendar 2019 catalog
OCS Training calendar 2019 catalogOCS Training calendar 2019 catalog
OCS Training calendar 2019 catalog
 
Resume
ResumeResume
Resume
 
RESUME updated
RESUME updatedRESUME updated
RESUME updated
 
RESUME updated
RESUME updatedRESUME updated
RESUME updated
 
Resume updated
Resume updatedResume updated
Resume updated
 
Superhomes2030 Community of Practice
Superhomes2030 Community of PracticeSuperhomes2030 Community of Practice
Superhomes2030 Community of Practice
 
RESUME 2015
RESUME 2015RESUME 2015
RESUME 2015
 
RESUME 2015
RESUME 2015RESUME 2015
RESUME 2015
 
Ravi Resume new (1) (3)
Ravi Resume new (1) (3)Ravi Resume new (1) (3)
Ravi Resume new (1) (3)
 
Vocational training Report for ECE department
Vocational training  Report for ECE departmentVocational training  Report for ECE department
Vocational training Report for ECE department
 
Karthik Key Skill Resume 2016
Karthik Key Skill Resume 2016Karthik Key Skill Resume 2016
Karthik Key Skill Resume 2016
 
new cv kishor
new cv kishornew cv kishor
new cv kishor
 
iddi resume 1
iddi resume 1iddi resume 1
iddi resume 1
 
Tower sharing concept
Tower sharing conceptTower sharing concept
Tower sharing concept
 
Tower sharing concept
Tower sharing conceptTower sharing concept
Tower sharing concept
 
MEC Concept Plans and Diagrams
MEC Concept Plans and DiagramsMEC Concept Plans and Diagrams
MEC Concept Plans and Diagrams
 
Resume 2016 - Product Scheduler
Resume 2016 - Product SchedulerResume 2016 - Product Scheduler
Resume 2016 - Product Scheduler
 
MARCOS SAMPLE2011
MARCOS SAMPLE2011MARCOS SAMPLE2011
MARCOS SAMPLE2011
 
Tap Foundries Intervention - Mintek
Tap Foundries Intervention - Mintek Tap Foundries Intervention - Mintek
Tap Foundries Intervention - Mintek
 

Dmi & safety village ppt

  • 2. Sanction details Item No. Year of Sanction Plan Head Description Alloc -ation Cost Outlay (2015-16) 355 2015-16 42 Safety Village DF(3) 1690 0.1 387 2004-05 64 Facilities for extraction, rescue and relief CAP 700 278 388 2004-05 64 DM module DF(3) 299 87 SRSF 300 0 Total 2989 365.1 All values are in Lakhs
  • 3. Consultancy status • March 2008-Railway Board has advised that the consultancy for setting up of Disaster Management Institute and Module will be handled by RITES. • April 2010- Board Advised SWR to process for finalising the consultancy tender at Zonal level. • SWR modified the scope within 25 lakhs of GM’s power and the same was approved by Traction Directorate. • Tender opened on 07-12-2010 with single offer from M/s Foundation for Educational Excellence, Bangalore and was discharged for not meeting the eligibility criteria.
  • 4. Consultancy status- Contd • Second tender opened on 29-03-2011 with single offer from M/s Global Forum for Disaster Reduction(GFDR), New Delhi and discharged again on eligibility criteria issue. • With the approval of GM, the tender was again opened on 25-10-2011 without the Single similar work eligibility criteria. Only Single offer from GFDR received and the status of this tender is, – Based on Finance member observation and as per GM advice, ref was made to Board on 28-05-12 to get the clearance from all concerned directorates for the scope and deliverables. – Board communicated the clearance on 14-03-2013.
  • 5. Consultancy status- Contd • Numerous efforts made by the convener to finalize the tender could not materialize and is being Discharged.
  • 6. Action Plan • In the light of Safety village sanction and the expertise available in creating the facilities w.r.t Engineering, Electrical(General &TRD) and S&T, decision has been taken by SWR to start the work for these activities. • The broad based items for rescue, Relief and restoration shall be included in the mechanical portion of the estimate. • Consultancy provision is being made in the detailed estimate with the scope of work excluding engineering facilities. • Detailed estimate is likely to be sanctioned by mid June’15 • The recommendations of consultant can be complied by revising the detailed estimate by suitably incorporating the specifications on the broad based items included in the estimate and by using the GMs power to include 20% additional items in the estimate.
  • 7. Scope of work for Consultancy • Review of Existing DM facilities/Systems w.r.t DM Plan of IR and advice means to comply with DM plan. • Details of Facilities and equipments required to be provided in the DMI and Safety village to meet the training requirement of IR in Rescue, Medical relief and Restoration including its specification, source and cost etc.. • Various disaster management courses to be run with course content (Theoretical & Practical) specific to each category of trainees. • Advice on the best practices being followed by Railways worldwide in the areas of Rescue, relief and restoration and to suggest ways and means to implement the same in IR. • State of Art technology and equipments being used by Railways worldwide and Training resources to be adopted by IR for Rescue, Extrication, Medical relief and restoration techniques including virtual reality models/systems for various scenorios. • Deep tunnel rescue system including training requirement with details of spec, source and cost. • Training on deep water rescue, extrication • Resource and training requirement to handle fires in trains.
  • 8. Facilities considered in the estimate Mechanical • ART/ ARMV Formation with latest equipments • Various over aged Rolling Stock for demo • M&Ps, T&Ps ,Furniture and Teaching Aids. • Computer Systems, Networking and Office equipments • Training of Officers, Faculty and instructors • Development of Class room training modules for various levels/types of trainees on relevant role with requisite training materials. • Virtual reality training modules for simulating disaster scenarios. • Consultancy
  • 9. Facilities considered in the estimate Engineering • Compound Wall 1.5 Km • Track length of about 2Km with two lines of 600 mts each including box culvert type Tunnel-100 mts and Bridge-50 mts. • Training & Admin Block, Seminar hall cum Auditorium, store area etc- 1600 Sqm • Quarters- Type V-1, IV-4, III-4 & II-6 • 110 Bed Hostel with Kitchen and Dining -220 Sqm • Sports and recreation facilities –Badminton, Tennis, Basketball and Volley ball etc • Landscaping and approach road & roads inside the facilities
  • 10. Facilities considered in the estimate Electrical- General Requisite power supply ,electrical fittings and appliances for the above facilities. Electrical- TRD Provision of dummy OHE with released material on one track of 600 mts to create an OHE environment for demonstrating restoration under wire. S&T Provision of telecommunication and internet connection for all the above facilities. Provision of working signaling arrangement for a sample B- class two line station with released materials including data logger.
  • 11. Integrated Abstract Estimate for three works Sl N0 Description DMI DM Module Safety Village Total Departme -nt Total 64 (CAP) 64 (DF3) SRSF 42 (DF3) 1 MECHANICAL a ART/ARMV Equipments 50 300 350 1655 b M&Ps ,T&Ps, furniture and teaching aids 200 100 300 c Computer systems, networking, office equipments 150 - 150 d Development of Class room training modules for various levels/types of trainees on relevant role with requisite training materials 100 100 200 e Virtual reality training modules for simulating disaster scenarios. - 200 150 - 350 f Training of Officers, faculty and instructors - 100 50 - 150 g Various rolling stocks(Dep value) for ART formation and practical training on rescue and restoration - - - 130 130 h Consultancy 25 - - - 25 2 Engineering a Compound wall 1500 m - - - 75 75 1665 b Admin building, model rooms, seminar hall 1800 Sq.mtrs 300 - - 0 300 c Hostel & dining facility 2200 sq.mtrs. 150 - - 225 375 d Quartrers Type V-1, Type IV-4, Type III-4 and Type II 6 100 - - 150 250 e Sports and Recreation facilities 100 - - 0 100 f 2 Kms of track with two turnouts, 50sq mts station buildings - - - 240 240 g Levelling, land scape, approach road, internal road and greeneries. - - - 125 125 h Box Culvert type Tunnels & Bridge - - - 200 200 3 S&T and Electrical a Provision of signal arrangement and telecommunication 25 - - 75 100 b Electrical general 100 - - 20 120