®CRS Ltd – Holtshill 2014 
 
CASE STUDY – Helping cost efficiency in social housing 
 
Employing nearly 4,600 people, the Accord Group is one of the largest housing and social 
care organisations in the Midlands, providing 13,000 affordable homes and health and 
social care to 80,000 people. 
Scaffolding has been holding up segments of 
a 60m wall in Holtshill, Walsall since 2013. 
The road has been closed during which time 
the existing wall was made good and 
protected and a replacement scoped.  
After some considerable time searching for 
the right solution we, CRS Ltd, (a Kent based 
civil engineering group and FSB member), 
were 
requested 
to produce 
a cost 
effective, engineered, bespoke solution.  
CRS responded immediately and within 2 weeks, 
commencement on the wall began in earnest. A temporary 
steel frame was placed in front of a bungalow, the scaffolding 
dismantled, the foundations were carefully excavated and 
concrete poured a new foundation for the retaining wall.  
This was not a small undertaking. The pre‐fabricated blocks 
were delivered and installed direct from the delivery lorry, 
with up to 3 lorry deliveries per day. Over 40m2 were 
installed daily.  
 
The blocks were manufactured by Elite 
pre‐cast, a Telford based manufacturer 
and winner of West Midlands Business 
Masters 2012. The blocks were 
installed over a two week timeframe, 
with regular site progress inspections 
from CRS.  
Colin Gaunt, Director of CRS explained, 
“Being on­site enabled the modular 
system to be reviewed with a constant 
strive for cost reduction and safety. The 
 
®CRS Ltd – Holtshill 2014 
 
volumes of blocks were reduced from the original expectations and around £5000 of savings were 
made in block costs alone, over 20% of the originally proposed wall. If traditional systems had been 
used, e.g. pour in­situ, those savings would not have been possible.”  
In fact the use of the modular 
system resulted in the construction 
of the brick face in an improved 
time frame.  
John Bedford Director of Project 
Development (Regeneration) 
stated;  
“We had considered a number of 
options to construct the new wall 
with the least disruption to local 
residents and the highway users. We 
needed an innovative cost effective 
speedy solution and after discussing 
this brief with a number of suppliers, opted for the solution proposed by CRS Ltd. We are delighted 
with how the project was executed, the fact that the design allowed efficiency on site and that the 
method adopted provided the quick operation we desired”. 
 
Finally, fencing and the 
residents gardens were put 
back to better than original 
state ‐ The site was cleared, 
the Heras fencing was 
removed and the road re‐
opened earlier than expected.  
 
 
 
 
 
 