SlideShare a Scribd company logo
1 of 34
Download to read offline
WESTERN AREAS LTD
Corporate Presentation
June 2017
www.westernareas.com.au| ASX:WSA |
AGENDA
Corporate Growth Nickel MarketOperations
www.westernareas.com.au| ASX:WSA |
DISCLAIMER AND FORWARD LOOKING STATEMENTS
3
This presentation is being furnished to you solely for your information and for your use and may not be copied, reproduced or redistributed to any
other person in any manner. You agree to keep the contents of this presentation and these materials confidential. The information contained in this
presentation does not constitute or form any part of any offer or invitation to purchase any securities and neither the issue of the information nor
anything contained herein shall form the basis of, or be relied upon in connection with, any contract or commitment on the part of any person to
proceed with any transaction.
The distribution of this presentation in jurisdictions outside Australia may be restricted by law, and persons into whose possession this presentation
comes should inform themselves about, and observe, any such restrictions. This is not for distribution or dissemination in the U.S.
The information contained in this presentation has been prepared by Western Areas Ltd. No representation or warranty, express or implied, is or will
be made in or in relation to, and no responsibility or liability is or will be accepted by Western Areas Ltd, employees or representatives as to the
accuracy or completeness of this information or any other written or oral information made available to any interested party or its advisers and any
liability therefore is hereby expressly disclaimed. No party has any obligation to notify opinion changes or if it becomes aware of any inaccuracy in or
omission from this presentation. All opinions and projections expressed in this presentation are given as of this date and are subject to change without
notice.
This document contains forward-looking statements including nickel production targets and cost estimates. These statements are based on
assumptions and contingencies that are subject to change without notice, and certain risks and uncertainties that could cause the performance or
achievements of Western Areas Ltd to differ materially from the information set forth herein. Often, but not always, forward looking statements can
generally be identified by the use of forward looking words such as “may”, “will”, “expect”, “intend”, “plan”, “estimate”, “anticipate”, “continue”, and
“guidance”, or other similar words and may include, without limitation, statements regarding plans, strategies and objectives of management,
anticipated production and expected costs. Western Areas Ltd undertakes no obligation to revise these forward-looking statements to reflect
subsequent events or circumstances. Individuals should not place undue reliance on forward-looking statements and are advised to make their own
independent analysis and determination with respect to the forecasted periods, which reflect Western Areas Ltd’s view only as of the date hereof.
The information within this PowerPoint presentation was compiled by Western Areas management, but the information as it relates to mineral
resources and reserves was prepared by Mr Marco Orunesu-Preiata and Mr Andre Wulfse. Mr Orunesu-Preiata and Mr Wulfse are full time employees
of Western Areas Ltd. Mr Orunesu-Preiata and Mr Wulfse are members of Australian Institute of Mining and Metallurgy (AusIMM) and have sufficient
experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which they are undertaking to
qualify as Competent Persons as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves’(2012 JORC Code). Mr Orunesu-Preiata and Mr Wulfse consent to the inclusion in this presentation of the matters based on the information
in the form and context in which it appears.
For the Purposes of Clause 3.4(e) in Canadian instrument 43-101, the Company warrants that Mineral Resources which are not Mineral Reserves do
not have demonstrated economic viability.
www.westernareas.com.au| ASX:WSA |
CORPORATE
www.westernareas.com.au| ASX:WSA |
ASX code WSA
Share price 1.93
Shares outstanding (m) 272.2
Market Cap (A$m) 1 525.3
Cash (A$m)2 112.0
CORPORATE OVERVIEW
5
High quality assets
No debt, clean balance sheet, low costs
Organic growth options and innovation
Positioned for nickel recovery
 Highest grade, low cash cost nickel producer
 Free cashflow positive
 Low unit cash cost producer
 A$112.0m cash at bank
 Exciting exploration hits
 Odysseus DFS and Mill Enhancement project
 A$1/lb lift in nickel price = circa A$35m EBITDA
 New and improved offtake contracts implemented
A leading mid-tier base metal producer
Flying Fox
12kt Ni mined FY16
42kt Ni reserves
102kt Ni resources
Spotted Quoll
15kt Ni mined FY16
89kt Ni reserves
121kt Ni resources
Cosmos Nickel Complex
567kt Ni resources
PFS complete
DFS underway
1. Based on share price on 21 June 2017
2. Cash as at 31 March 2017
www.westernareas.com.au| ASX:WSA |
WESTERN AREAS ARE SAFE AREAS
6
Safe operations make efficient operations
Days LTI free
Nov-08
Aug-11
Oct-13
Mar-17
12 month LTIFR moving average
Exploration
Spotted Quoll
Cosmic Boy
Concentrator
Flying Fox
3,256
2,239
1,438
80
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
LTIFR
www.westernareas.com.au| ASX:WSA |
CONSISTENT LOW COST PRODUCER
7
A management team which consistently delivers guidance
 On target to meet guidance
metrics
 Spotted Quoll mine tracking
toward record production
 Unit cash cost of production
at A$2.44/lb (US$1.84/lb) of
nickel in concentrate
 Mill continued to perform
well above nameplate
capacity
 Exceptional consistency and
6 years without a guidance
miss
Cash cost Ni in conc.
(LHS)
Production – cont. Ni processed
(RHS)
www.westernareas.com.au| ASX:WSA |
MANAGING THROUGH THE CYCLE
8
Reducing cost
structure
Cash cost reduction has been a consistent feature
 March quarter 2017 was the lowest since June 2015
 Ore sorter project
 Operations team efficiency drive – pinch valve and blasting techniques
Prudent capital
management
Remaining debt free with A$112.0m cash at bank (31 Mar 2017)
 FY17 YTD free cashflow over A$36m
 Zero debt and ability to fund internal projects
Innovation and
being ahead of
the pack
Driving greater returns from what we have
 Game changing offtake contract directly with China’s largest stainless steel producer
 Mill Recovery Enhancement Project – delivering value from treating tailings
 EV Battery market penetration – long term positioning
Opportunistic
approach
Build portfolio
 Cosmos acquisition has delivered exceptional value
 Bluejay Mining plc (formerly FinnAust) value realised at $27m (net of fees)
 Farmed out lithium exploration rights – 5.2% of Kidman Resources
Maintain valuation discipline
 Be patient in assessing opportunities. Do not succumb to the fear of “missing out”
The cost structure and capabilities to prosper throughout the cycle
www.westernareas.com.au| ASX:WSA |
OPERATIONS
www.westernareas.com.au| ASX:WSA |
FLYING FOX MINE
10
Key points
 FY16 production – 12,432 Ni tonnes
 Reserve life has a demonstrated history of
replenishment
 Added OTZ South Massive Zone – 182,898t @ 4.1% Ni
for 7,417 nickel tonnes
 Recent resource extension drilling into T6 domain has
been encouraging, including 8.0m @ 10.7% Ni
 Has been operating for over 12 years
WSA’s foundation asset within Forrestania
Reserve
Contained nickel
1.04Mt @ 4.0%
41,670 Ni tonnes
Resource
Contained nickel
2.07Mt @ 4.9%
102,365 Ni tonnes
Mine life 4 years
www.westernareas.com.au| ASX:WSA |
SPOTTED QUOLL MINE
11
Key points
 March Mineral Resource upgrade +12,650 nickel tonnes
 Reserve upgrade in progress
 Has never recorded an LTI
 FY16 record annual production – 15,175 Ni tonnes
 Remains open at depth and to the North
 Production has outperformed reserve tonnes and grade
consistently
 Top down mining with paste fill
WSA Explored, Discovered and Developed
Reserve
Contained nickel
2.2Mt @ 4.0%
88,900 Ni tonnes
Resource
Contained nickel
2.2Mt @ 5.7%
121,664 Ni tonnes
Mine life 8 years
www.westernareas.com.au| ASX:WSA |
FORRESTANIA NICKEL CONCENTRATOR
12
Concentrator Summary
 Mill processed an annual record of 616k tonnes of ore
in FY16, for 25,009 nickel tonnes
 12% above name plate capacity of 550,000 tpa
 Concentrate grades of between 15.0% to 16.0% Ni
 Premium blending product (Fe/Mg ratio >15:1)
 Desirable to smelters
Export Infrastructure and Logistics
 Export concentrate transported to Esperance Port in
half height containers and shipped through to China
 Shipping contract in place, FOB Terms
 BHP Nickel West concentrate delivered to Kambalda
WSA produces a high quality and in demand nickel concentrate
www.westernareas.com.au| ASX:WSA |
OFFTAKE CONTRACTS
13
New Contracts Executed
 New contract terms will improve financial returns
 WSA has become a lead innovator with nickel concentrates
About Tsingshan Group
 China’s largest stainless steel producer
 Estimated to consume 25% of China’s nickel demand
 Revenue of RMB85 billion in 2015, 20,000 employees
 Contracted through associated Singaporean entity Golden
Harbor International Pte Ltd
About Roasting
 WSA first tested its concentrate in 2012 and 2013 with
Tsingshan
 Creates a high grade Nickel Oxide that can be blended with
Laterite ore
 By-products of sulphuric acid for stainless steel
 Most concentrates do not suit roasting due to no by-product
credits such as Cobalt, Copper and PGE’s
 Proven process that opens up opportunities with Tsingshan
JINCHUAN
~13ktpa
Jan 2017
BHPB
~10ktpa
Jan 2017
JINCHUAN
~13ktpa
Jan 2020
New & Improved Contracts
TSINGSHAN
~10ktpa
Jan 2020
BHPB
~10ktpa
Jan 2020
BHPB
~2ktpa
Jun 2019
www.westernareas.com.au| ASX:WSA |
INNOVATION – MILL RECOVERY ENHANCEMENT PROJECT
14
Mill Recovery Enhancement Project (MREP)
 A$17.5m remaining to be spent, unit cost A$2.44/lb and <3 year payback (refer to announcement 12 April
2017)
 Construction commenced in May 17 and commissioning to commence Q1 CY18
 Utilising BioHeap process to leach tailings (previously considered waste)
 Up to 1,400 nickel tonnes per annum – two options for sale:
1. Blend 45% to 50% nickel grade product into existing concentrate production and offtakes (base case)
2. Sell new product into the EV battery space, with potential premium to offtake contracts
www.westernareas.com.au| ASX:WSA |
GROWTH &
EXPLORATION
OUTLOOK
www.westernareas.com.au| ASX:WSA |
BUILDING THE PLATFORM
16
A portfolio with production and growth optionality
 Cosmos Nickel Complex
 Western Gawler JV
 Forrestania
Exploration and Growth
 Odysseus DFS underway
 New Morning
 Mill Recovery Enhancement
Development
 Spotted Quoll
 Flying Fox
 Cosmic Boy Concentrator
Production
Odysseus Project:
7.3Mt @ 2.4% Ni (174Kt Ni)
Proposed Vent Raise
Proposed Decline Infrastructure
Existing Decline Infrastructure
COSMOS DEEPS
(mined out)
ODYSSEUS SOUTH ODYSSEUS NORTH
Planned Stoping Blocks
Longitudinal Section – Looking West
4.0Mt @ 2.2% Ni (88Kt Ni) 3.2Mt @ 2.5% Ni (81Kt Ni)
ODYSSEUS (massive)
48Kt @ 11.6% Ni (5.6Kt Ni)
- 250m
- 500m
- 750m
- 1,000m
5.3m @ 15.2% Ni
(massive)
26m @ 2.5% Ni
(disseminated)0 250m
5.5m @ 13.9% Ni
(massive)
www.westernareas.com.au| ASX:WSA |
0
250
500
750
1,000
1,250
ContainedNickel(kt)
Reserves Resources Cumulative nickel mined
ORGANIC GROWTH PROFILE
17
WSA has a track-record of discovery and development
Historic reserves & resources
980%
Large holding in 2 significantly endowed nickel provinces
Forrestania Operations – Western Australia
 New Morning project – Near mine leveraging existing
infrastructure with studies underway
 History of reserve/resource extension
 Mill Recovery Enhancement Project – lift metallurgical
recoveries by 3-5%
 Evaluating Lithium potential at the Forrestania tenements
Cosmos Nickel Complex / Odysseus – Western Australia
 Existing resources and infrastructure (previous Glencore/
Xstrata/Jubilee Mines operation)
 Odysseus DFS underway with significant high grade
intersections in latest drilling
 First pass drilling at Neptune successful
Western Gawler – South Australia
 First mover advantage
 Intrusive style and geologically similar to Nova
www.westernareas.com.au| ASX:WSA |
COSMOS EXPLORATION - NEPTUNE
Drilling Results
 First drill program completed at Neptune and high grade nickel sulphides intersected
 65.0m @ 0.8% Ni, including 17.0m @ 1.3% Ni
 1.2m @7.1% Ni, including 0.7m @ 10.9% Ni
18
www.westernareas.com.au| ASX:WSA |
ODYSSEUS PRE-FEASIBILITY STUDY RESULTS
19
Key Metrics on a page:
Mineral Resources Tonnes (Mt) Grade % Ni Ni Tonnes (kt)
Indicated Resources 5.52 2.4 129.8
Inferred Resources 1.80 2.5 44.2
Total Resources 7.32 2.4 174.0
Resources in LOM Production Target Tonnes (Mt) Grade % Ni Ni Tonnes (kt)
Indicated Resources 4.10 2.3 94.3
Inferred Resources 0.77 2.3 17.9
Total Resources 4.87 2.3 112.2
Capital Costs
Pre-production total capital cost (incl. 5-16% contingency) $190 - $210m
Comprising: CY2017 $7m
CY2018 $34m
CY2019 – 2020 $149 - $169m
Post production LOM $68m
Production Parameters
Life of Mine 7.5yrs
Ore Tonnes Mined 4.87Mt
Ore Processing Capacity (Year 1) 430ktpa
Ore Processing Capacity (Year 2 onwards) 750ktpa
Nickel in concentrate - LOM 87kt
Nickel in concentrate - Annual average 12kt
Life of Mine Financial Economics
Base Case Nickel Price US$7.50/lb
Exchange Rate (AUD:USD) 0.75
Revenue $1,520m
C1 Cash Costs $3.21/lb (US$2.41/lb)
All In Sustaining Costs $3.69/lb (US$2.77/lb)
EBITDA $840m
Net Cash Flow (pre-tax) $580m
Undiscounted Cash Breakeven Nickel Price $6.09/lb (US$4.57/lb)
Pre-tax NPV (7% real) $292m
IRR 28%
Capital Payback Period 3.5yrs
For full pre-feasibility detail, see ASX announcement, 30 March 2017
www.westernareas.com.au| ASX:WSA |
ODYSSEUS PFS – KEY FEATURES AND TIMETABLE
20
Milestone Estimated Timing
PFS Completed Q1 CY2017
Commence DFS Q2 CY2017
DFS Completed Q1 CY2018
Commence dewatering and mine rehabilitation for 12 months Q1 CY2018
Commence new decline development for 24 months Q1 CY2019
First Development Ore Mined Q4 CY2020
First Concentrate production at 430ktpa Q1 CY2021
Plant Upgraded to 750ktpa to reach full production capacity H1 CY2022
Western Areas next mining operation
 Very low sustaining capital expenditure after initial pre-production capex
 Very low all-in unit sustaining costs of A$3.69/lb (US$2.70/lb)
 DFS completion Q1 CY2018 – A$2.5-A$3m cost
 Substantial upside opportunities not included:
 AM5 and AM6 orebodies (53kt of contained nickel)
 Recent massive sulphide drilling success beneath Odysseus (see next slide)
 Regional drilling success at Neptune
 Opportunities for a roasting concentrate
www.westernareas.com.au| ASX:WSA |
ODYSSEUS NORTH EXPLORATION RESULTS
21
OD North Upgraded Mineral Resource:
 A 311% increase in the Total Massive Sulphide
Resource to 22,838 nickel tonnes grading 8.4%
Ni which now includes 8,836 nickel tonnes
grading 6.1% Ni in the Indicated category
 A 78% increase in the Odysseus North
disseminated Indicated Resource to 81,156
nickel tonnes grading 2.6% Ni (previously
45,519 nickel tonnes grading 2.8% Ni)
 New high grade zone discovered with two
significant intersections, best being 5.3m @
15.2% Ni, including 3.4m @ 22.0% Ni
 Represents upside opportunity to Odysseus DFS
 DHEM modelled plate 160m South of existing
high grade Inferred Resource of 0.5Mt at 11.6%
Ni
www.westernareas.com.au| ASX:WSA |
Odysseus Mineral Resource Upgrade
22
 The Total Odysseus Mineral Resource
Estimate now stands at 7.9Mt @ 2.5% Ni
for 199,174 nickel tonnes at a cut-off of
1.5% Ni
 An overall increase in the Indicated to
Inferred disseminated resource ratio from
77% to 94%, which includes a ratio
increase of 56% to 93% in Odysseus North
disseminated
www.westernareas.com.au| ASX:WSA |
WESTERN GAWLER JOINT VENTURE
23
Greenfields Exploration
 Large strategic holding (4,450km2)
 Camp scale opportunities
 Majority 100% owned
 With Strandline farm in agreement – WSA
earning up to 90%
Right Address
 Prospective under explored belt
 Analogous to Fraser Range
 Targeting poly-metallic base metal and gold
mineralisation
Right Rocks
 Mafic/Ultramafic intrusive rocks
 Magmatic nickel sulphides confirmed in multiple
locations (Petrology)
Right Signatures
 Anomalous values returned from drilling
www.westernareas.com.au| ASX:WSA |
Broad scale prospectivity for Ni/Cu and Gold
EXPLORATION SUMMARY – WESTERN GAWLER
24
Exploration drilling overlaying magnetics (RTP)
Successful first phase of exploration
 Broad spaced drilling complete
 Mafic/Ultramafic intrusions identified
 Coincident magnetic and gravity anomalies
identified such as Pearl, Citadel, Moonstone,
Calamari
Planned exploration (next six months)
 Currently completing gravity and ground EM
surveys at Pearl and Citadel
 Finalise targeting with AC/RC drilling to commence
in June quarter FY17
 Confirm lithology with focus on base metals and
gold
Community – Proactive engagement to support
activities
www.westernareas.com.au| ASX:WSA |
NICKEL MARKET
www.westernareas.com.au| ASX:WSA |
GEO-POLITICAL FORCES, BUT STRONG DEMAND
26
Pre Indonesian Ore Ban Relaxation
 2017 heading for a deficit of between 70-75k nickel tonnes
 Recent 300 series stainless steel growth in China has been around 13%
Indonesia relaxes the laterite ore export ban implemented in 2014
 This is not a reversal of the ban and exports allowed under certain circumstances
 The volume of ore that can be exported is being finalised
 Exporter must show plans and demonstrate progress to constructing in-country processing
facilities
 Only impacts ore <1.7% nickel
 Exporters must prove 30% of low grade is processed in-country
 Rules on majority ownership transfer over 10 years
 Only around 3.7Mt of <1.7% nickel laterite to be exported per annum announced – immaterial!
Philippines due to announces significant nickel mine closures and suspensions
 Mining and Resources Secretary Lopez announces closures and suspensions that could impact 50%
of domestic laterite nickel exports
 Concerned about mining in Water Sheds
 Strong opposition from mining groups and appeal process underway
 Lopez to go before Commission (for confirmation) on 2 May 2017
JINCHUAN
~13ktpa
Jan 2017
BHPB
~10ktpa
Jan 2017
www.westernareas.com.au| ASX:WSA |
THE END
www.westernareas.com.au| ASX:WSA |
APPENDICES
www.westernareas.com.au| ASX:WSA |
LOCATION – EASILY ACCESSIBLE SITES
29
Premier and stable mining district with high quality mines and organic growth options
Lounge Lizard 10m wide face of 7% Massive Nickel Sulphide
Spotted Quoll face at average 10.6% Nickel Sulphide
www.westernareas.com.au| ASX:WSA |
FY17 GUIDANCE UPGRADED
30
Comments
 Production improvements reflect higher grade mainly from Spotted Quoll with reduced dilution and
blasting innovations;
 Unit cash cost of production an outcome of higher production, improved grade and cost out initiatives;
 Sustaining capital includes the last major one-off item of capex at either mine – ventilation shaft for
A$6m; and
 Odysseus PFS approved in march quarter. DFS has now commenced
Metric Updated FY17 Guidance Original FY17 Guidance
Mine Production (Nickel tonnes in Ore) 25,000 to 26,000 22,500 to 24,500
Nickel tonnes in Concentrate Production 22,000 to 23,000 20,200 to 22,000
Unit Cash Cost of Production (Nickel in Concentrate) A$2.35/lb to A$2.50/lb A$2.40/lb to A$2.75/lb
Sustaining Capex No Change A$22.0m to A$24.0m
Forrestania and Regional Exploration No Change A$8.0m
Odysseus PFS No Change A$2.0m
www.westernareas.com.au| ASX:WSA |
NEW MORNING / DAYBREAK
31
 2.5km from Flying Fox and 2.8km from Spotted
Quoll
 All material approvals in place, potential major
capex savings and accessible from either mine
 Open Pit and shallow underground studies
commenced
 BioHeap testwork ongoing to evaluate heap
leach criteria
 Massive sulphide Resource of 418kt @ 3.4%
for 14,249 nickel tonnes
 Low grade resource (at 0.5% Ni COG) of 5.1m
tonnes @ 1.3% for 67,090 nickel tonnes
www.westernareas.com.au| ASX:WSA |
GROWING EMERGING MARKET – ELECTRIC VEHICLES
32
 Nickel is increasingly being included in battery formulations as it leads to higher energy density
batteries. Approximately 50kgs Ni in each Tesla EV.
 Nickel demand from batteries is expected to grow at faster pace than seen historically, from
~50kt in 2015 to 150-200kt by 2025
www.westernareas.com.au| ASX:WSA |
NICKEL IS A KEY INGREDIENT IN LITHIUM-ION BATTERIES (~50KG NI PER CAR)
33
“Our cells should be called Nickel-Graphite, because primarilythe
cathode is nickel and the anode side is graphite with silicon oxide…
[there’s] a little bit of lithium in there, but it’s like the salt on the
salad,” Tesla CEO Elon Musk
www.westernareas.com.au| ASX:WSA |
WESTERN AREAS VALUE EQUATION
34
• High Grade
• Lowest
Quartile Cash
Costs
Highest Grade
Nickel Globally
• Operational
cashflow
positive
Cashflow
Positive
• Guidance
continually
met or
exceeded
Strong Track
Record of
Delivery
• 1 Lost Time
Injuries in past
30 months
Safety
• Pipeline of
growth
opportunities
Growth
• Fundamentals
and forecasts
positioned to
rebound
Nickel Price
Primed for
Upside
• Strong “can
do”
management
History of
Discovery and
Development
• No debt with
significant
financial
flexibility
Strong Balance
Sheet
Strong leverage to turnaround in nickel price through current operations and organic
projects

More Related Content

What's hot

Corporate Presentation September 2017
Corporate Presentation September 2017Corporate Presentation September 2017
Corporate Presentation September 2017Rebekah Webb
 
Corporate Presentation November 2017
Corporate Presentation November 2017Corporate Presentation November 2017
Corporate Presentation November 2017Rebekah Webb
 
Corporate Presentation December 2018
Corporate Presentation December 2018Corporate Presentation December 2018
Corporate Presentation December 2018Western Areas Ltd
 
RIU Conference February 2017
RIU Conference February 2017RIU Conference February 2017
RIU Conference February 2017Western Areas Ltd
 
Corporate Presentation February 2018
Corporate Presentation February 2018Corporate Presentation February 2018
Corporate Presentation February 2018Rebekah Webb
 
Corporate Presentation March 2019
Corporate Presentation March 2019Corporate Presentation March 2019
Corporate Presentation March 2019Western Areas Ltd
 
Corporate Presentation August 2017
Corporate Presentation August 2017Corporate Presentation August 2017
Corporate Presentation August 2017Western Areas Ltd
 
Corporate Presentation October 2016
Corporate Presentation October 2016Corporate Presentation October 2016
Corporate Presentation October 2016Western Areas Ltd
 
Diggers & Dealers Presentation Aug 2016
Diggers & Dealers Presentation Aug 2016Diggers & Dealers Presentation Aug 2016
Diggers & Dealers Presentation Aug 2016Western Areas Ltd
 
Corporate Presentation September 2016
Corporate Presentation September 2016Corporate Presentation September 2016
Corporate Presentation September 2016Western Areas Ltd
 
Corporate Presentation June 2013
Corporate Presentation June 2013Corporate Presentation June 2013
Corporate Presentation June 2013Western Areas Ltd
 
Corporate Presentation March 2017
Corporate Presentation March 2017Corporate Presentation March 2017
Corporate Presentation March 2017Western Areas Ltd
 
Corporate Presentation December 2014
Corporate Presentation December 2014Corporate Presentation December 2014
Corporate Presentation December 2014Western Areas Ltd
 
Corporate Presentation April 2017
Corporate Presentation April 2017Corporate Presentation April 2017
Corporate Presentation April 2017Western Areas Ltd
 
Half Year Results Presentation February 2015
Half Year Results Presentation February 2015Half Year Results Presentation February 2015
Half Year Results Presentation February 2015Western Areas Ltd
 
Australian Nickel Conference October 2016
Australian Nickel Conference October 2016Australian Nickel Conference October 2016
Australian Nickel Conference October 2016Western Areas Ltd
 
Corporate Presentation July 2016
Corporate Presentation July 2016Corporate Presentation July 2016
Corporate Presentation July 2016Western Areas Ltd
 
Corporate Presentation May 2018
Corporate Presentation May 2018Corporate Presentation May 2018
Corporate Presentation May 2018Western Areas Ltd
 

What's hot (20)

Corporate Presentation September 2017
Corporate Presentation September 2017Corporate Presentation September 2017
Corporate Presentation September 2017
 
Corporate Presentation November 2017
Corporate Presentation November 2017Corporate Presentation November 2017
Corporate Presentation November 2017
 
Corporate Presentation December 2018
Corporate Presentation December 2018Corporate Presentation December 2018
Corporate Presentation December 2018
 
RIU Conference February 2017
RIU Conference February 2017RIU Conference February 2017
RIU Conference February 2017
 
Corporate Presentation February 2018
Corporate Presentation February 2018Corporate Presentation February 2018
Corporate Presentation February 2018
 
Corporate Presentation March 2019
Corporate Presentation March 2019Corporate Presentation March 2019
Corporate Presentation March 2019
 
Corporate Presentation August 2017
Corporate Presentation August 2017Corporate Presentation August 2017
Corporate Presentation August 2017
 
Corporate Presentation October 2016
Corporate Presentation October 2016Corporate Presentation October 2016
Corporate Presentation October 2016
 
Diggers & Dealers Presentation Aug 2016
Diggers & Dealers Presentation Aug 2016Diggers & Dealers Presentation Aug 2016
Diggers & Dealers Presentation Aug 2016
 
Corporate Presentation September 2016
Corporate Presentation September 2016Corporate Presentation September 2016
Corporate Presentation September 2016
 
FY 15 Results Presentation
FY 15 Results PresentationFY 15 Results Presentation
FY 15 Results Presentation
 
Corporate Presentation June 2013
Corporate Presentation June 2013Corporate Presentation June 2013
Corporate Presentation June 2013
 
Corporate Presentation March 2017
Corporate Presentation March 2017Corporate Presentation March 2017
Corporate Presentation March 2017
 
Corporate Presentation December 2014
Corporate Presentation December 2014Corporate Presentation December 2014
Corporate Presentation December 2014
 
Full Year Results FY16
Full Year Results FY16 Full Year Results FY16
Full Year Results FY16
 
Corporate Presentation April 2017
Corporate Presentation April 2017Corporate Presentation April 2017
Corporate Presentation April 2017
 
Half Year Results Presentation February 2015
Half Year Results Presentation February 2015Half Year Results Presentation February 2015
Half Year Results Presentation February 2015
 
Australian Nickel Conference October 2016
Australian Nickel Conference October 2016Australian Nickel Conference October 2016
Australian Nickel Conference October 2016
 
Corporate Presentation July 2016
Corporate Presentation July 2016Corporate Presentation July 2016
Corporate Presentation July 2016
 
Corporate Presentation May 2018
Corporate Presentation May 2018Corporate Presentation May 2018
Corporate Presentation May 2018
 

Viewers also liked

Half Year Results Presentation February 2014
Half Year Results Presentation February 2014Half Year Results Presentation February 2014
Half Year Results Presentation February 2014Western Areas Ltd
 
Diggers & Dealers Presentation Aug 2017
Diggers & Dealers Presentation Aug 2017Diggers & Dealers Presentation Aug 2017
Diggers & Dealers Presentation Aug 2017Rebekah Webb
 
Diggers & Dealers Presentation Aug 2014
Diggers & Dealers Presentation Aug 2014Diggers & Dealers Presentation Aug 2014
Diggers & Dealers Presentation Aug 2014Western Areas Ltd
 
Western Areas Corporate Presentation April 2015
Western Areas Corporate Presentation April 2015Western Areas Corporate Presentation April 2015
Western Areas Corporate Presentation April 2015Western Areas Ltd
 
Corporate Presentation March 2016
Corporate Presentation March 2016Corporate Presentation March 2016
Corporate Presentation March 2016Western Areas Ltd
 
Half Year Results Presentation February 2016
Half Year Results Presentation February 2016Half Year Results Presentation February 2016
Half Year Results Presentation February 2016Western Areas Ltd
 
Western Areas FY12 full Year financials
Western Areas FY12 full Year financialsWestern Areas FY12 full Year financials
Western Areas FY12 full Year financialsWestern Areas Ltd
 
Western Areas Half Year Results Presentation Feb 2013
Western Areas Half Year Results Presentation Feb 2013Western Areas Half Year Results Presentation Feb 2013
Western Areas Half Year Results Presentation Feb 2013Western Areas Ltd
 
Corporate Presentation December 2013
Corporate Presentation December 2013Corporate Presentation December 2013
Corporate Presentation December 2013Western Areas Ltd
 
Corporate Presentation April 2013
Corporate Presentation April 2013Corporate Presentation April 2013
Corporate Presentation April 2013Western Areas Ltd
 
Western Areas FY 2013 Results Presentation
Western Areas FY 2013 Results PresentationWestern Areas FY 2013 Results Presentation
Western Areas FY 2013 Results PresentationWestern Areas Ltd
 
Corporate Presentation October 2017
Corporate Presentation October 2017Corporate Presentation October 2017
Corporate Presentation October 2017Rebekah Webb
 
Corporate Presentation May 2013
Corporate Presentation May 2013Corporate Presentation May 2013
Corporate Presentation May 2013Western Areas Ltd
 

Viewers also liked (14)

Half Year Results Presentation February 2014
Half Year Results Presentation February 2014Half Year Results Presentation February 2014
Half Year Results Presentation February 2014
 
Diggers & Dealers Presentation Aug 2017
Diggers & Dealers Presentation Aug 2017Diggers & Dealers Presentation Aug 2017
Diggers & Dealers Presentation Aug 2017
 
FY2014 Results Presentation
FY2014 Results PresentationFY2014 Results Presentation
FY2014 Results Presentation
 
Diggers & Dealers Presentation Aug 2014
Diggers & Dealers Presentation Aug 2014Diggers & Dealers Presentation Aug 2014
Diggers & Dealers Presentation Aug 2014
 
Western Areas Corporate Presentation April 2015
Western Areas Corporate Presentation April 2015Western Areas Corporate Presentation April 2015
Western Areas Corporate Presentation April 2015
 
Corporate Presentation March 2016
Corporate Presentation March 2016Corporate Presentation March 2016
Corporate Presentation March 2016
 
Half Year Results Presentation February 2016
Half Year Results Presentation February 2016Half Year Results Presentation February 2016
Half Year Results Presentation February 2016
 
Western Areas FY12 full Year financials
Western Areas FY12 full Year financialsWestern Areas FY12 full Year financials
Western Areas FY12 full Year financials
 
Western Areas Half Year Results Presentation Feb 2013
Western Areas Half Year Results Presentation Feb 2013Western Areas Half Year Results Presentation Feb 2013
Western Areas Half Year Results Presentation Feb 2013
 
Corporate Presentation December 2013
Corporate Presentation December 2013Corporate Presentation December 2013
Corporate Presentation December 2013
 
Corporate Presentation April 2013
Corporate Presentation April 2013Corporate Presentation April 2013
Corporate Presentation April 2013
 
Western Areas FY 2013 Results Presentation
Western Areas FY 2013 Results PresentationWestern Areas FY 2013 Results Presentation
Western Areas FY 2013 Results Presentation
 
Corporate Presentation October 2017
Corporate Presentation October 2017Corporate Presentation October 2017
Corporate Presentation October 2017
 
Corporate Presentation May 2013
Corporate Presentation May 2013Corporate Presentation May 2013
Corporate Presentation May 2013
 

Similar to Corporate Presentation June 2017

Corporate Presentation May 2017
Corporate Presentation May 2017Corporate Presentation May 2017
Corporate Presentation May 2017Western Areas Ltd
 
Corporate Presentation November 2016
Corporate Presentation November 2016Corporate Presentation November 2016
Corporate Presentation November 2016Western Areas Ltd
 
Corporate Presentation February 2019
Corporate Presentation February 2019Corporate Presentation February 2019
Corporate Presentation February 2019Western Areas Ltd
 
Corporate presentation November 2018
Corporate presentation November 2018Corporate presentation November 2018
Corporate presentation November 2018Western Areas Ltd
 
Corporate Presentation May 2019
Corporate Presentation May 2019Corporate Presentation May 2019
Corporate Presentation May 2019Western Areas Ltd
 
Corporate Presentation December 2017
Corporate Presentation December 2017Corporate Presentation December 2017
Corporate Presentation December 2017Rebekah Webb
 
Corporate Presentation July 2016
Corporate Presentation July 2016Corporate Presentation July 2016
Corporate Presentation July 2016Western Areas Ltd
 
Australian Nickel Conference October 2018
Australian Nickel Conference October 2018 Australian Nickel Conference October 2018
Australian Nickel Conference October 2018 Western Areas Ltd
 
Corporate Presentation June 2018
Corporate Presentation June 2018Corporate Presentation June 2018
Corporate Presentation June 2018Western Areas Ltd
 
Corporate Presentation August 2018
Corporate Presentation August 2018Corporate Presentation August 2018
Corporate Presentation August 2018Western Areas Ltd
 
Corporate Presentation April 2018
Corporate Presentation April 2018Corporate Presentation April 2018
Corporate Presentation April 2018Western Areas Ltd
 
Corporate Presentation March 2018
Corporate Presentation March 2018Corporate Presentation March 2018
Corporate Presentation March 2018Rebekah Webb
 

Similar to Corporate Presentation June 2017 (12)

Corporate Presentation May 2017
Corporate Presentation May 2017Corporate Presentation May 2017
Corporate Presentation May 2017
 
Corporate Presentation November 2016
Corporate Presentation November 2016Corporate Presentation November 2016
Corporate Presentation November 2016
 
Corporate Presentation February 2019
Corporate Presentation February 2019Corporate Presentation February 2019
Corporate Presentation February 2019
 
Corporate presentation November 2018
Corporate presentation November 2018Corporate presentation November 2018
Corporate presentation November 2018
 
Corporate Presentation May 2019
Corporate Presentation May 2019Corporate Presentation May 2019
Corporate Presentation May 2019
 
Corporate Presentation December 2017
Corporate Presentation December 2017Corporate Presentation December 2017
Corporate Presentation December 2017
 
Corporate Presentation July 2016
Corporate Presentation July 2016Corporate Presentation July 2016
Corporate Presentation July 2016
 
Australian Nickel Conference October 2018
Australian Nickel Conference October 2018 Australian Nickel Conference October 2018
Australian Nickel Conference October 2018
 
Corporate Presentation June 2018
Corporate Presentation June 2018Corporate Presentation June 2018
Corporate Presentation June 2018
 
Corporate Presentation August 2018
Corporate Presentation August 2018Corporate Presentation August 2018
Corporate Presentation August 2018
 
Corporate Presentation April 2018
Corporate Presentation April 2018Corporate Presentation April 2018
Corporate Presentation April 2018
 
Corporate Presentation March 2018
Corporate Presentation March 2018Corporate Presentation March 2018
Corporate Presentation March 2018
 

Recently uploaded

OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...NETWAYS
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024eCommerce Institute
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Pooja Nehwal
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...henrik385807
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...NETWAYS
 
Motivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfMotivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfakankshagupta7348026
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )Pooja Nehwal
 
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Hasting Chen
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AITatiana Gurgel
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Delhi Call girls
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@vikas rana
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...NETWAYS
 
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesVVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesPooja Nehwal
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...NETWAYS
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptxBasil Achie
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfhenrik385807
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝soniya singh
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024eCommerce Institute
 
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrSaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrsaastr
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...NETWAYS
 

Recently uploaded (20)

OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
 
Motivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfMotivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdf
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
 
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AI
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
 
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesVVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024
 
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrSaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
 

Corporate Presentation June 2017

  • 1. WESTERN AREAS LTD Corporate Presentation June 2017
  • 3. www.westernareas.com.au| ASX:WSA | DISCLAIMER AND FORWARD LOOKING STATEMENTS 3 This presentation is being furnished to you solely for your information and for your use and may not be copied, reproduced or redistributed to any other person in any manner. You agree to keep the contents of this presentation and these materials confidential. The information contained in this presentation does not constitute or form any part of any offer or invitation to purchase any securities and neither the issue of the information nor anything contained herein shall form the basis of, or be relied upon in connection with, any contract or commitment on the part of any person to proceed with any transaction. The distribution of this presentation in jurisdictions outside Australia may be restricted by law, and persons into whose possession this presentation comes should inform themselves about, and observe, any such restrictions. This is not for distribution or dissemination in the U.S. The information contained in this presentation has been prepared by Western Areas Ltd. No representation or warranty, express or implied, is or will be made in or in relation to, and no responsibility or liability is or will be accepted by Western Areas Ltd, employees or representatives as to the accuracy or completeness of this information or any other written or oral information made available to any interested party or its advisers and any liability therefore is hereby expressly disclaimed. No party has any obligation to notify opinion changes or if it becomes aware of any inaccuracy in or omission from this presentation. All opinions and projections expressed in this presentation are given as of this date and are subject to change without notice. This document contains forward-looking statements including nickel production targets and cost estimates. These statements are based on assumptions and contingencies that are subject to change without notice, and certain risks and uncertainties that could cause the performance or achievements of Western Areas Ltd to differ materially from the information set forth herein. Often, but not always, forward looking statements can generally be identified by the use of forward looking words such as “may”, “will”, “expect”, “intend”, “plan”, “estimate”, “anticipate”, “continue”, and “guidance”, or other similar words and may include, without limitation, statements regarding plans, strategies and objectives of management, anticipated production and expected costs. Western Areas Ltd undertakes no obligation to revise these forward-looking statements to reflect subsequent events or circumstances. Individuals should not place undue reliance on forward-looking statements and are advised to make their own independent analysis and determination with respect to the forecasted periods, which reflect Western Areas Ltd’s view only as of the date hereof. The information within this PowerPoint presentation was compiled by Western Areas management, but the information as it relates to mineral resources and reserves was prepared by Mr Marco Orunesu-Preiata and Mr Andre Wulfse. Mr Orunesu-Preiata and Mr Wulfse are full time employees of Western Areas Ltd. Mr Orunesu-Preiata and Mr Wulfse are members of Australian Institute of Mining and Metallurgy (AusIMM) and have sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which they are undertaking to qualify as Competent Persons as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’(2012 JORC Code). Mr Orunesu-Preiata and Mr Wulfse consent to the inclusion in this presentation of the matters based on the information in the form and context in which it appears. For the Purposes of Clause 3.4(e) in Canadian instrument 43-101, the Company warrants that Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability.
  • 5. www.westernareas.com.au| ASX:WSA | ASX code WSA Share price 1.93 Shares outstanding (m) 272.2 Market Cap (A$m) 1 525.3 Cash (A$m)2 112.0 CORPORATE OVERVIEW 5 High quality assets No debt, clean balance sheet, low costs Organic growth options and innovation Positioned for nickel recovery  Highest grade, low cash cost nickel producer  Free cashflow positive  Low unit cash cost producer  A$112.0m cash at bank  Exciting exploration hits  Odysseus DFS and Mill Enhancement project  A$1/lb lift in nickel price = circa A$35m EBITDA  New and improved offtake contracts implemented A leading mid-tier base metal producer Flying Fox 12kt Ni mined FY16 42kt Ni reserves 102kt Ni resources Spotted Quoll 15kt Ni mined FY16 89kt Ni reserves 121kt Ni resources Cosmos Nickel Complex 567kt Ni resources PFS complete DFS underway 1. Based on share price on 21 June 2017 2. Cash as at 31 March 2017
  • 6. www.westernareas.com.au| ASX:WSA | WESTERN AREAS ARE SAFE AREAS 6 Safe operations make efficient operations Days LTI free Nov-08 Aug-11 Oct-13 Mar-17 12 month LTIFR moving average Exploration Spotted Quoll Cosmic Boy Concentrator Flying Fox 3,256 2,239 1,438 80 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 LTIFR
  • 7. www.westernareas.com.au| ASX:WSA | CONSISTENT LOW COST PRODUCER 7 A management team which consistently delivers guidance  On target to meet guidance metrics  Spotted Quoll mine tracking toward record production  Unit cash cost of production at A$2.44/lb (US$1.84/lb) of nickel in concentrate  Mill continued to perform well above nameplate capacity  Exceptional consistency and 6 years without a guidance miss Cash cost Ni in conc. (LHS) Production – cont. Ni processed (RHS)
  • 8. www.westernareas.com.au| ASX:WSA | MANAGING THROUGH THE CYCLE 8 Reducing cost structure Cash cost reduction has been a consistent feature  March quarter 2017 was the lowest since June 2015  Ore sorter project  Operations team efficiency drive – pinch valve and blasting techniques Prudent capital management Remaining debt free with A$112.0m cash at bank (31 Mar 2017)  FY17 YTD free cashflow over A$36m  Zero debt and ability to fund internal projects Innovation and being ahead of the pack Driving greater returns from what we have  Game changing offtake contract directly with China’s largest stainless steel producer  Mill Recovery Enhancement Project – delivering value from treating tailings  EV Battery market penetration – long term positioning Opportunistic approach Build portfolio  Cosmos acquisition has delivered exceptional value  Bluejay Mining plc (formerly FinnAust) value realised at $27m (net of fees)  Farmed out lithium exploration rights – 5.2% of Kidman Resources Maintain valuation discipline  Be patient in assessing opportunities. Do not succumb to the fear of “missing out” The cost structure and capabilities to prosper throughout the cycle
  • 10. www.westernareas.com.au| ASX:WSA | FLYING FOX MINE 10 Key points  FY16 production – 12,432 Ni tonnes  Reserve life has a demonstrated history of replenishment  Added OTZ South Massive Zone – 182,898t @ 4.1% Ni for 7,417 nickel tonnes  Recent resource extension drilling into T6 domain has been encouraging, including 8.0m @ 10.7% Ni  Has been operating for over 12 years WSA’s foundation asset within Forrestania Reserve Contained nickel 1.04Mt @ 4.0% 41,670 Ni tonnes Resource Contained nickel 2.07Mt @ 4.9% 102,365 Ni tonnes Mine life 4 years
  • 11. www.westernareas.com.au| ASX:WSA | SPOTTED QUOLL MINE 11 Key points  March Mineral Resource upgrade +12,650 nickel tonnes  Reserve upgrade in progress  Has never recorded an LTI  FY16 record annual production – 15,175 Ni tonnes  Remains open at depth and to the North  Production has outperformed reserve tonnes and grade consistently  Top down mining with paste fill WSA Explored, Discovered and Developed Reserve Contained nickel 2.2Mt @ 4.0% 88,900 Ni tonnes Resource Contained nickel 2.2Mt @ 5.7% 121,664 Ni tonnes Mine life 8 years
  • 12. www.westernareas.com.au| ASX:WSA | FORRESTANIA NICKEL CONCENTRATOR 12 Concentrator Summary  Mill processed an annual record of 616k tonnes of ore in FY16, for 25,009 nickel tonnes  12% above name plate capacity of 550,000 tpa  Concentrate grades of between 15.0% to 16.0% Ni  Premium blending product (Fe/Mg ratio >15:1)  Desirable to smelters Export Infrastructure and Logistics  Export concentrate transported to Esperance Port in half height containers and shipped through to China  Shipping contract in place, FOB Terms  BHP Nickel West concentrate delivered to Kambalda WSA produces a high quality and in demand nickel concentrate
  • 13. www.westernareas.com.au| ASX:WSA | OFFTAKE CONTRACTS 13 New Contracts Executed  New contract terms will improve financial returns  WSA has become a lead innovator with nickel concentrates About Tsingshan Group  China’s largest stainless steel producer  Estimated to consume 25% of China’s nickel demand  Revenue of RMB85 billion in 2015, 20,000 employees  Contracted through associated Singaporean entity Golden Harbor International Pte Ltd About Roasting  WSA first tested its concentrate in 2012 and 2013 with Tsingshan  Creates a high grade Nickel Oxide that can be blended with Laterite ore  By-products of sulphuric acid for stainless steel  Most concentrates do not suit roasting due to no by-product credits such as Cobalt, Copper and PGE’s  Proven process that opens up opportunities with Tsingshan JINCHUAN ~13ktpa Jan 2017 BHPB ~10ktpa Jan 2017 JINCHUAN ~13ktpa Jan 2020 New & Improved Contracts TSINGSHAN ~10ktpa Jan 2020 BHPB ~10ktpa Jan 2020 BHPB ~2ktpa Jun 2019
  • 14. www.westernareas.com.au| ASX:WSA | INNOVATION – MILL RECOVERY ENHANCEMENT PROJECT 14 Mill Recovery Enhancement Project (MREP)  A$17.5m remaining to be spent, unit cost A$2.44/lb and <3 year payback (refer to announcement 12 April 2017)  Construction commenced in May 17 and commissioning to commence Q1 CY18  Utilising BioHeap process to leach tailings (previously considered waste)  Up to 1,400 nickel tonnes per annum – two options for sale: 1. Blend 45% to 50% nickel grade product into existing concentrate production and offtakes (base case) 2. Sell new product into the EV battery space, with potential premium to offtake contracts
  • 16. www.westernareas.com.au| ASX:WSA | BUILDING THE PLATFORM 16 A portfolio with production and growth optionality  Cosmos Nickel Complex  Western Gawler JV  Forrestania Exploration and Growth  Odysseus DFS underway  New Morning  Mill Recovery Enhancement Development  Spotted Quoll  Flying Fox  Cosmic Boy Concentrator Production Odysseus Project: 7.3Mt @ 2.4% Ni (174Kt Ni) Proposed Vent Raise Proposed Decline Infrastructure Existing Decline Infrastructure COSMOS DEEPS (mined out) ODYSSEUS SOUTH ODYSSEUS NORTH Planned Stoping Blocks Longitudinal Section – Looking West 4.0Mt @ 2.2% Ni (88Kt Ni) 3.2Mt @ 2.5% Ni (81Kt Ni) ODYSSEUS (massive) 48Kt @ 11.6% Ni (5.6Kt Ni) - 250m - 500m - 750m - 1,000m 5.3m @ 15.2% Ni (massive) 26m @ 2.5% Ni (disseminated)0 250m 5.5m @ 13.9% Ni (massive)
  • 17. www.westernareas.com.au| ASX:WSA | 0 250 500 750 1,000 1,250 ContainedNickel(kt) Reserves Resources Cumulative nickel mined ORGANIC GROWTH PROFILE 17 WSA has a track-record of discovery and development Historic reserves & resources 980% Large holding in 2 significantly endowed nickel provinces Forrestania Operations – Western Australia  New Morning project – Near mine leveraging existing infrastructure with studies underway  History of reserve/resource extension  Mill Recovery Enhancement Project – lift metallurgical recoveries by 3-5%  Evaluating Lithium potential at the Forrestania tenements Cosmos Nickel Complex / Odysseus – Western Australia  Existing resources and infrastructure (previous Glencore/ Xstrata/Jubilee Mines operation)  Odysseus DFS underway with significant high grade intersections in latest drilling  First pass drilling at Neptune successful Western Gawler – South Australia  First mover advantage  Intrusive style and geologically similar to Nova
  • 18. www.westernareas.com.au| ASX:WSA | COSMOS EXPLORATION - NEPTUNE Drilling Results  First drill program completed at Neptune and high grade nickel sulphides intersected  65.0m @ 0.8% Ni, including 17.0m @ 1.3% Ni  1.2m @7.1% Ni, including 0.7m @ 10.9% Ni 18
  • 19. www.westernareas.com.au| ASX:WSA | ODYSSEUS PRE-FEASIBILITY STUDY RESULTS 19 Key Metrics on a page: Mineral Resources Tonnes (Mt) Grade % Ni Ni Tonnes (kt) Indicated Resources 5.52 2.4 129.8 Inferred Resources 1.80 2.5 44.2 Total Resources 7.32 2.4 174.0 Resources in LOM Production Target Tonnes (Mt) Grade % Ni Ni Tonnes (kt) Indicated Resources 4.10 2.3 94.3 Inferred Resources 0.77 2.3 17.9 Total Resources 4.87 2.3 112.2 Capital Costs Pre-production total capital cost (incl. 5-16% contingency) $190 - $210m Comprising: CY2017 $7m CY2018 $34m CY2019 – 2020 $149 - $169m Post production LOM $68m Production Parameters Life of Mine 7.5yrs Ore Tonnes Mined 4.87Mt Ore Processing Capacity (Year 1) 430ktpa Ore Processing Capacity (Year 2 onwards) 750ktpa Nickel in concentrate - LOM 87kt Nickel in concentrate - Annual average 12kt Life of Mine Financial Economics Base Case Nickel Price US$7.50/lb Exchange Rate (AUD:USD) 0.75 Revenue $1,520m C1 Cash Costs $3.21/lb (US$2.41/lb) All In Sustaining Costs $3.69/lb (US$2.77/lb) EBITDA $840m Net Cash Flow (pre-tax) $580m Undiscounted Cash Breakeven Nickel Price $6.09/lb (US$4.57/lb) Pre-tax NPV (7% real) $292m IRR 28% Capital Payback Period 3.5yrs For full pre-feasibility detail, see ASX announcement, 30 March 2017
  • 20. www.westernareas.com.au| ASX:WSA | ODYSSEUS PFS – KEY FEATURES AND TIMETABLE 20 Milestone Estimated Timing PFS Completed Q1 CY2017 Commence DFS Q2 CY2017 DFS Completed Q1 CY2018 Commence dewatering and mine rehabilitation for 12 months Q1 CY2018 Commence new decline development for 24 months Q1 CY2019 First Development Ore Mined Q4 CY2020 First Concentrate production at 430ktpa Q1 CY2021 Plant Upgraded to 750ktpa to reach full production capacity H1 CY2022 Western Areas next mining operation  Very low sustaining capital expenditure after initial pre-production capex  Very low all-in unit sustaining costs of A$3.69/lb (US$2.70/lb)  DFS completion Q1 CY2018 – A$2.5-A$3m cost  Substantial upside opportunities not included:  AM5 and AM6 orebodies (53kt of contained nickel)  Recent massive sulphide drilling success beneath Odysseus (see next slide)  Regional drilling success at Neptune  Opportunities for a roasting concentrate
  • 21. www.westernareas.com.au| ASX:WSA | ODYSSEUS NORTH EXPLORATION RESULTS 21 OD North Upgraded Mineral Resource:  A 311% increase in the Total Massive Sulphide Resource to 22,838 nickel tonnes grading 8.4% Ni which now includes 8,836 nickel tonnes grading 6.1% Ni in the Indicated category  A 78% increase in the Odysseus North disseminated Indicated Resource to 81,156 nickel tonnes grading 2.6% Ni (previously 45,519 nickel tonnes grading 2.8% Ni)  New high grade zone discovered with two significant intersections, best being 5.3m @ 15.2% Ni, including 3.4m @ 22.0% Ni  Represents upside opportunity to Odysseus DFS  DHEM modelled plate 160m South of existing high grade Inferred Resource of 0.5Mt at 11.6% Ni
  • 22. www.westernareas.com.au| ASX:WSA | Odysseus Mineral Resource Upgrade 22  The Total Odysseus Mineral Resource Estimate now stands at 7.9Mt @ 2.5% Ni for 199,174 nickel tonnes at a cut-off of 1.5% Ni  An overall increase in the Indicated to Inferred disseminated resource ratio from 77% to 94%, which includes a ratio increase of 56% to 93% in Odysseus North disseminated
  • 23. www.westernareas.com.au| ASX:WSA | WESTERN GAWLER JOINT VENTURE 23 Greenfields Exploration  Large strategic holding (4,450km2)  Camp scale opportunities  Majority 100% owned  With Strandline farm in agreement – WSA earning up to 90% Right Address  Prospective under explored belt  Analogous to Fraser Range  Targeting poly-metallic base metal and gold mineralisation Right Rocks  Mafic/Ultramafic intrusive rocks  Magmatic nickel sulphides confirmed in multiple locations (Petrology) Right Signatures  Anomalous values returned from drilling
  • 24. www.westernareas.com.au| ASX:WSA | Broad scale prospectivity for Ni/Cu and Gold EXPLORATION SUMMARY – WESTERN GAWLER 24 Exploration drilling overlaying magnetics (RTP) Successful first phase of exploration  Broad spaced drilling complete  Mafic/Ultramafic intrusions identified  Coincident magnetic and gravity anomalies identified such as Pearl, Citadel, Moonstone, Calamari Planned exploration (next six months)  Currently completing gravity and ground EM surveys at Pearl and Citadel  Finalise targeting with AC/RC drilling to commence in June quarter FY17  Confirm lithology with focus on base metals and gold Community – Proactive engagement to support activities
  • 26. www.westernareas.com.au| ASX:WSA | GEO-POLITICAL FORCES, BUT STRONG DEMAND 26 Pre Indonesian Ore Ban Relaxation  2017 heading for a deficit of between 70-75k nickel tonnes  Recent 300 series stainless steel growth in China has been around 13% Indonesia relaxes the laterite ore export ban implemented in 2014  This is not a reversal of the ban and exports allowed under certain circumstances  The volume of ore that can be exported is being finalised  Exporter must show plans and demonstrate progress to constructing in-country processing facilities  Only impacts ore <1.7% nickel  Exporters must prove 30% of low grade is processed in-country  Rules on majority ownership transfer over 10 years  Only around 3.7Mt of <1.7% nickel laterite to be exported per annum announced – immaterial! Philippines due to announces significant nickel mine closures and suspensions  Mining and Resources Secretary Lopez announces closures and suspensions that could impact 50% of domestic laterite nickel exports  Concerned about mining in Water Sheds  Strong opposition from mining groups and appeal process underway  Lopez to go before Commission (for confirmation) on 2 May 2017 JINCHUAN ~13ktpa Jan 2017 BHPB ~10ktpa Jan 2017
  • 29. www.westernareas.com.au| ASX:WSA | LOCATION – EASILY ACCESSIBLE SITES 29 Premier and stable mining district with high quality mines and organic growth options Lounge Lizard 10m wide face of 7% Massive Nickel Sulphide Spotted Quoll face at average 10.6% Nickel Sulphide
  • 30. www.westernareas.com.au| ASX:WSA | FY17 GUIDANCE UPGRADED 30 Comments  Production improvements reflect higher grade mainly from Spotted Quoll with reduced dilution and blasting innovations;  Unit cash cost of production an outcome of higher production, improved grade and cost out initiatives;  Sustaining capital includes the last major one-off item of capex at either mine – ventilation shaft for A$6m; and  Odysseus PFS approved in march quarter. DFS has now commenced Metric Updated FY17 Guidance Original FY17 Guidance Mine Production (Nickel tonnes in Ore) 25,000 to 26,000 22,500 to 24,500 Nickel tonnes in Concentrate Production 22,000 to 23,000 20,200 to 22,000 Unit Cash Cost of Production (Nickel in Concentrate) A$2.35/lb to A$2.50/lb A$2.40/lb to A$2.75/lb Sustaining Capex No Change A$22.0m to A$24.0m Forrestania and Regional Exploration No Change A$8.0m Odysseus PFS No Change A$2.0m
  • 31. www.westernareas.com.au| ASX:WSA | NEW MORNING / DAYBREAK 31  2.5km from Flying Fox and 2.8km from Spotted Quoll  All material approvals in place, potential major capex savings and accessible from either mine  Open Pit and shallow underground studies commenced  BioHeap testwork ongoing to evaluate heap leach criteria  Massive sulphide Resource of 418kt @ 3.4% for 14,249 nickel tonnes  Low grade resource (at 0.5% Ni COG) of 5.1m tonnes @ 1.3% for 67,090 nickel tonnes
  • 32. www.westernareas.com.au| ASX:WSA | GROWING EMERGING MARKET – ELECTRIC VEHICLES 32  Nickel is increasingly being included in battery formulations as it leads to higher energy density batteries. Approximately 50kgs Ni in each Tesla EV.  Nickel demand from batteries is expected to grow at faster pace than seen historically, from ~50kt in 2015 to 150-200kt by 2025
  • 33. www.westernareas.com.au| ASX:WSA | NICKEL IS A KEY INGREDIENT IN LITHIUM-ION BATTERIES (~50KG NI PER CAR) 33 “Our cells should be called Nickel-Graphite, because primarilythe cathode is nickel and the anode side is graphite with silicon oxide… [there’s] a little bit of lithium in there, but it’s like the salt on the salad,” Tesla CEO Elon Musk
  • 34. www.westernareas.com.au| ASX:WSA | WESTERN AREAS VALUE EQUATION 34 • High Grade • Lowest Quartile Cash Costs Highest Grade Nickel Globally • Operational cashflow positive Cashflow Positive • Guidance continually met or exceeded Strong Track Record of Delivery • 1 Lost Time Injuries in past 30 months Safety • Pipeline of growth opportunities Growth • Fundamentals and forecasts positioned to rebound Nickel Price Primed for Upside • Strong “can do” management History of Discovery and Development • No debt with significant financial flexibility Strong Balance Sheet Strong leverage to turnaround in nickel price through current operations and organic projects