                     Capital Improvement Projects Budget
                               City Council Meeting
                                    April 23, 2012
OPEB and Health Insurance   FY13 MAYOR'S BUDGET PRESENTATION
                                                               1
                                           ‹#›
Enterprise Resource Planning (ERP)
Expenditures        2013        2014        2015   2016   2017       Total

Other              200,000                                             200,000

Total              200,000                                             200,000



   Funding          2013        2014        2015   2016   2017       Total
   Sources
CIP Fund
Balance            200,000                                            200,000

Total              200,000                                            200,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13                                   2
Enterprise Resource Planning (ERP)
 ERP software integrates all
 departments and functions across
 the City into a single system. An
 ERP will consolidate information
 and allow easy access.

 Needs assessment is completed
 and RFP will be issued before the
 end of FY12.

 Increased license/maintenance
 fees are approximately
 $32,000/year.

Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
IT Upgrades & Replacements
Expenditures        2013        2014        2015     2016     2017      Total

Other                15,000     15,000      15,000   15,000    15,000       75,000

Total                15,000    15,000       15,000   15,000    15,000       75,000



   Funding          2013        2014        2015     2016     2017      Total
   Sources
CIP Fund
Balance             15,000      15,000      15,000   15,000    15,000      75,000

Total               15,000      15,000      15,000   15,000    15,000      75,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
IT Upgrades & Replacements
  Covers routine replacement &
  upgrade of City’s servers and
  other infrastructure. The
  average server costs $5,000 to
  $7,000 and there are nine in
  use in the City.

  If remote servers are chosen
  instead, those costs will need
  to be incorporated into the
  operating budget.


Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Vehicle Replacements
Expenditures        2013        2014        2015   2016   2017     Total

To be
determined                         TBD       TBD    TBD      TBD           TBD

Total

   Funding          2013        2014        2015   2016   2017     Total
   Sources

To be
determined                         TBD       TBD    TBD      TBD           TBD

Total



Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Vehicle Replacements
 To be determined, following
 adoption of the Vehicle
 Replacement study. The only
 vehicle replacements in FY13
 will be on an emergency basis.




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Radar/Lidar Speed Units
Expenditures        2013        2014        2015    2016     2017      Total

Equip/Vehicles
/Furnishings                    10,200      6,800   10,800    10,800       38,600

Total                          10,200       6,800   10,800    10,800       38,600


   Funding          2013        2014        2015    2016     2017      Total
   Sources
General Fund
Transfer                        10,200      6,800   10,800    10,800      38,600

Total                           10,200      6,800   10,800    10,800      38,600




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Radar/Lidar
              Speed Enforcement Units
 Radar units currently in use are
 several years old. Newer,
 lighter units are available. With
 the implementation of the
 Highway Safety Office Data
 Driven Approaches to Crime &
 Traffic Safety program, our goal
 is to have units available at all
 times.

 Annual calibration fee =
 $80/unit.

Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Mobile Data Terminals
 Expenditures        2013        2014       2015     2016     2017      Total

Equip/Vehicles
/Furnishings         14,450     14,750      15,025   15,325    15,650       75,200

Total                14,450     14,750      15,025   15,325    15,650       75,200

   Funding           2013        2014       2015     2016     2017      Total
   Sources
CIP Fund
Balance              14,450                                                14,450
General Fund
Transfer                        14,750      15,025   15,325    15,650      60,750

Total                14,450     14,750      15,025   15,325    15,650      75,200



Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Mobile Data Terminals (MDTs)
 As the HCPD implements more
 IT-based projects, staff should
 have appropriate tools to utilize
 the technology.

 Funds will purchase CF31
 Panasonic Toughbooks for
 officers. Projects cost increase
 of 2% per year.

  Note: No units will be purchased until a replacement
  schedule is developed.

Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Enhancement of CCTV Program
Expenditures        2013        2014        2015   2016   2017   Total

Equip/Vehicles
/Furnishings         40,000                                          40,000

Total                40,000                                          40,000


   Funding          2013        2014        2015   2016   2017   Total
   Sources
CIP Fund
Balance             40,000                                          40,000

Total               40,000                                          40,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Enhancement of CCTV Program
 The police have identified
 additional locations in the City
 that would benefit from a
 CCTV/Call-box. Funds would
 allow one full camera set-up,
 including installation costs, or
 two cameras and one call-box.
 One location is the new hiker-
 biker/Trolley Trail.
  Note: These will not be purchased until the current program is
  evaluated for effectiveness.


Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
K-9 Unit
Expenditures        2013        2014        2015   2016   2017   Total

Other                 9,900                                              9,900

Total                 9,900                                              9,900



   Funding          2013        2014        2015   2016   2017   Total
   Sources
CIP Fund
Balance               9,900                                          9,900

Total                 9,900                                          9,900




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
K-9 Unit
 This project is for a
 replacement K-9 Unit, including
 the dog, equipment kennel,
 cage, and cooling system.

 Aris has a spinal injury and
 must be retired.

 Because this is a replacement,
 there is no additional budget
 impact.


Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Sidewalks
Expenditures        2013        2014        2015     2016       2017      Total
Construction/
Maintenance          50,000 209,000         50,000   50,000      50,000     409,000

Total                50,000 209,000         50,000   50,000      50,000     409,000

Funding Sources        2013        2014       2015     2016      2017     Total
Bond Issue(2010)       50,000                                                 50,000
Bond Issue
(Proposed)                         75,000 50,000       50,000               225,000
Reimbursement                      25,000                                     25,000
State Board of
Public Works                      109,000                                   109,000

Total                  50,000     209,000 50,000       50,000    50,000     409,000



Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Sidewalks
 This project is the annual
 program of sidewalk
 repair/installation.

 FY14 includes grant-funded
 MD208 East Side Extension and
 Route 1 repair, to be partially
 funded through other sources.

 Funds will be used in
 conjunction with Safe Routes to
 Schools and ADA programs.


Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Roadway Improvements – General
   Expenditures        2013       2014       2015   2016   2017   Total

Planning/Design        85,000                                        85,000
Construction/
Maintenance          420,000     375,000                            795,000

Total                505,000     375,000                            880,000

                       2013       2014       2015   2016   2017   Total
 Funding Sources
Bond Issue
(Proposed)           420,000     375,000                            795,000
CIP Fund Balance       85,000                                        85,000

Total                505,000     375,000                            880,000



 Capital ImprovementInsurance through FY17
  OPEB and Health Projects FY13
Roadway Improvements
 Includes drainage/roadway
 improvements in areas
 remaining from City’s 5-year
 paving program.

 2013: Complete work
 beginning in FY12 on west side,
 plus 42nd/Oliver Street after
 WSSC is finished. Design for
 Buchanan Street.
 2014: Buchanan Street, et al.
 2015: Determined by pavement study. (Anticipated 2Q FY13.)

Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
University Hills Street Reconstruction
   Expenditures        2013       2014        2015   2016    2017          Total


To be determined                       TBD     TBD     TBD          TBD            TBD

Total



Funding Sources      2013       2014         2015    2016    2017         Total

To be determined                   TBD        TBD     TBD       TBD               TBD

Total




 Capital ImprovementInsurance through FY17
  OPEB and Health Projects FY13
University Hills Street Reconstruction
 Construction of drainage and
 roadway improvements in the
 University Hills neighborhood.
 Council has previously
 approved construction,
 pending funding of the project.


 Improvements in the neighborhood are necessary to improve the
 integrity of the streets and repair drainage problems. The project
 includes sidewalk installation, roadway realignment, and
 innovative stormwater management.

Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Crittenden & 40th Reconstruction
  Expenditures          2013       2014     2015   2016   2017     Total

Construction/
Maintenance           1,600,000                                      1,600,000

Total                 1,600,000                                      1,600,000



   Funding           2013         2014      2015   2016     2017     Total
   Sources
Bond Issue
(2010)              1,600,000                                         1,600,000

Total               1,600,000                                         1,600,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Crittenden & 40th Reconstruction
 Improvements in roadway and
 drainage in the Crittenden/40th
 Place area. Project was started
 in FY09, and has been in design
 FY11/FY12. New state
 stormwater management
 requirements have delayed the
 project.




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
ADA Improvements, City-wide
  Expenditures        2013       2014        2015      2016      2017     Total

Construction/
Maintenance         100,000     100,000     100,000   100,000   100,000     500,000

Total               100,000     100,000     100,000   100,000   100,000     500,000



   Funding           2013        2014        2015      2016      2017     Total
   Sources
Bond Issue
(Proposed)          100,000     100,000     100,000   100,000 100,000       500,000

Total               100,000     100,000     100,000   100,000 100,000       500,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
ADA Improvements, City-wide
 Areas of improvement will be
 identified through the City’s
 recently conducted ADA
 Transition plan, scheduled for
 Council adoption in April 2012.




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Arcade Building – 4318 Gallatin Street
  Expenditures          2013       2014     2015    2016   2017   Total

Construction/
Maintenance           3,000,000                                   3,000,000

Total                 3,000,000                                   3,000,000

                     2013         2014      2015   2016    2017   Total
   Funding
   Sources
Bond Issue
(Proposed)          2,925,000                                     2,295,000
State MHAA
Grant                  75,000                                         75,000

Total               3,000,000                                     3,000,000



Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Arcade Building – 4318 Gallatin Street
Build-out of the Arcade at 4318
Gallatin Street to serve as a
public function/amenities
facility. Final costs are tied to
the level of functionality and
design options. Design will be
complete by December 31,
2012. Additional grant funding
may then be available.

Annual operating costs are projected to increase by $152,100
in FY15 due to utilities, supplies, and maintenance. This may
be offset by rental fees.

Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Magruder Park Recreation Center
  Expenditures          2013       2014     2015    2016   2017   Total

Construction/
Maintenance             285,000                                     285,000

Total                   285,000                                     285,000


                     2013         2014      2015   2016    2017   Total
   Funding
   Sources
CIP Fund
Balance
                      285,000                                       285,000

Total                 285,000                                       285,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Magruder Park Recreation Center
Based on the facilities study,
the Rec Center will be among
the last City facilities to be
upgraded. To keep the facility
safe and operational for the
next few years, some
investment must be made.


The plan includes upgrading the exterior toilet rooms for ADA
accessibility, improving shelving/lighting in garage/storage
areas and capturing storage space to be used as a concession
stand. Resurfacing/repairing brick may also be necessary.

Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
3505 Hamilton Street
  Expenditures        2013         2014       2015       2016   2017   Total


Planning/Design      420,000       500,000                               920,000
Construction/
Maintenance                      1,000,000   2,600,000                 3,600,000

Total                420,000 1,500,000       2,600,000                 4,520,000


    Funding          2013          2014       2015       2016   2017    Total
    Sources
Speed Camera
Revenue             420,000      1,500,000 2,600,000                    4,520,000

Total               420,000      1,500,000 2,600,000                    4,520,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
3505 Hamilton Street
This project will install required
improvements at 3505
Hamilton, based on the
facilities study, ADA
requirements, and Council
                                            3505
determination of use. The
building requires renovation to
be usable.




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
4310 Gallatin Street
  Expenditures       2013       2014         2015       2016      2017   Total


Planning/Design                350,000      350,000                        700,000
Construction/
Maintenance                                           4,500,000          4,500,000

Total                          350,000      350,000   4,500,000          5,200,000

   Funding         2013        2014          2015      2016       2017   Total
   Sources
Bond Issue
(Proposed)                                            4,500,000          4,500,000
CIP Fund
Balance                       350,000       350,000                        700,000
Total
                              350,000       350,000   4,500,000          5,200,000


Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
4310 Gallatin Street
This represents a series of
major repairs that have been
scheduled & budget, including:

• Upgrade of roof: $120,000
• HVAC replacement: $250,000
• Mansard roof repair:
$106,000
• Installation of natural gas line:
$40,000
• Conversion to natural gas
$68,000


Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Vehicle Replacements – Solid Waste
  Expenditures        2013       2014       2015   2016   2017   Total

Equip/Vehicles/
Furnishings         200,000                                        200,000

Total               200,000                                        200,000

   Funding           2013       2014        2015   2016   2017   Total
   Sources
Lease
                    200,000                                        200,000
Total
                    200,000                                        200,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Vehicle Replacements – Solid Waste
This is the replacement of
SWV9860 , a 1998 GM refuse
truck. Three trucks are used on
a daily basis, with a fourth as a
back-up, and a fifth expected to
be sold as surplus.

Repairs from FY10-FY12 (to
date) have cost $49,059.84.
Replacing this refuse truck will
save on repair costs and keep
equipment up-to-date with
modern safety features.

Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Vehicle Replacements –
                  Maintenance Work Truck
  Expenditures        2013       2014       2015   2016   2017   Total

Equip/Vehicles/
Furnishings           60,000                                        60,000

Total                 60,000                                        60,000



Funding Sources       2013       2014       2015   2016   2017   Total
Lease
                      60,000                                         60,000
Total
                      60,000                                         60,000



Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Vehicle Replacements –
               Maintenance Work Truck
This is the replacement of an
older unit MO9838, a 1998
Chevrolet Work Truck. Repairs
from FY10-FY12 (to date) have
cost $16,473.37. The cost
includes a snow plow, salt
spreader, light package, and
radio. Replacing this work
truck will save on repair costs
and keep equipment up-to-
date with modern safety
features.

Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
King Park Retaining Wall
  Expenditures        2013       2014       2015   2016   2017   Total

Construction/
Maintenance           32,000                                        32,000

Total                 32,000                                        32,000

   Funding           2013       2014        2015   2016   2017   Total
   Sources
CIP Fund
Balance               32,000                                         32,000

Total                 32,000                                         32,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
King Park Retaining Wall
The retaining wall at King Park
is crumbling. We do not have
an original construction date,
but it appears to many years
past its replacement date.
Replacement will require
removal of small trees that are
growing into the wall, as well as
replacing the chain link fence,
currently a magnet for growth
of invasive species. This will
prevent emergency repairs and
impacts to neighbors’ yards.

Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Melrose Access Trail
  Expenditures      2013        2014        2015   2016   2017   Total

Construction/
Maintenance                    100,000                             100,000

Total                          100,000                             100,000

   Funding         2013        2014         2015   2016   2017   Total
   Sources
CIP Fund
Balance                       100,000                              100,000
Total
                              100,000                              100,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Melrose Access Trail
Construction of a 300 linear
foot ADA accessible trail head
from Crittenden Street to 41st
Street.

Based upon DER’s project
design and permitting schedule
it appears that no work will
occur until FY13.




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Solar Display Board
  Expenditures      2013        2014        2015   2016   2017   Total

Equip/Vehicles/
Furnishings                     17,500                              17,500

Total                           17,500                              17,500

   Funding         2013        2014         2015   2016   2017   Total
   Sources
Lease
                               17,500                                17,500

Total                          17,500                                17,500




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Solar Display Board
This is the purchase of a 3-line
solar powered LED display
message board, typically
trailer-mounted and displayed
to advise of road conditions,
etc.

The City rents these signs for
large special events and it
would be utilized for a wide
range of traffic and safety
reasons.


Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Cable TV Upgrades
  Expenditures       2013       2014        2015      2016     2017     Total

Equip/Vehicles/
Furnishings          15,000     15,000      15,000    15,000 15,000        75,000

Total                15,000     15,000      15,000    15,000 15,000        75,000

   Funding         2013        2014         2015      2016     2017     Total
   Sources
P.E.G. Fees
                   15,000      15,000        15,000   15,000   15,000       75,000
Total
                   15,000      15,000        15,000   15,000   15,000       75,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Cable TV Upgrades
The City’s cable channel is an
underutilized asset. These
upgrades will move us towards
implementing the capacity to
run additional programming. In
addition to routine upgrades,
projects will include the ability
to film remotely, improving
storage and content, etc.




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Field Renovations
  Expenditures        2013       2014        2015     2016       2017     Total
Engineering                     50,000                 50,000              100,000
Construction/
Maintenance         400,000                 300,000             300,000   1,000,000

Total               400,000     50,000      300,000    50,000   300,000   1,100,000

   Funding          2013        2014         2015     2016       2017     Total
   Sources
Bond Issue
(2008)             203,291                                                  203,291
Bond Issue
(Proposed)         196,709                  300,000             300,000     796,709
CIP Fund
Balance                        50,000                 50,000                100,000

Total              400,000     50,000       300,000   50,000 300,000      1,100,000


Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Field Renovations
The City has a longstanding goal
of renovating the playing fields
and surfaces at Magruder Park.
The project will provide
drainage and irrigation plans
and construction services for
the soccer and football fields at
Magruder Park, and eventually
the soccer field at Melrose Park.

Correct drainage will allow for more playing time, safer
conditions, and reduced maintenance costs.



Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Court Resurfacing
  Expenditures       2013       2014        2015   2016   2017   Total

Construction/
Maintenance          20,000                                         20,000

Total                20,000                                         20,000

   Funding         2013        2014         2015   2016   2017   Total
   Sources
CIP Fund
Balance            20,000                                            20,000
Total
                   20,000                                            20,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Court Resurfacing
This project provides for
resurfacing of the Magruder
Park tennis courts. It will
prolong their life and make
them safer to use.




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Parking Meters
  Expenditures       2013       2014        2015   2016   2017   Total

Equip/Vehicles/
Furnishings          90,000                                         90,000

Total                90,000                                         90,000

   Funding         2013        2014         2015   2016   2017   Total
   Sources
Bond Issue
(Proposed)         90,000                                            90,000

Total              90,000                                            90,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Parking Meters
This project is for the
purchase and installation of
new parking meters in
locations to be considered
and approved by Council.
Areas being considered
include Ager Road and
Editors Park Drive. Because
they will be smart meters,
we will incur monthly
charges for communication
fees.



Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Bike & Pedestrian Enhancements
  Expenditures       2013       2014        2015   2016   2017   Total

Equip/Vehicles/
Furnishings          55,000                                         55,000

Total                55,000                                         55,000

   Funding         2013        2014         2015   2016   2017   Total
   Sources
State DHCD
Grant              55,000                                            55,000

Total              55,000                                            55,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Bike & Pedestrian Enhancements
This project is the creation
of bike lanes and the
installation of bike racks.

The scope is limited to
funding awarded through
the State of Maryland
Department of Housing and
Community Development
Sustainability Grant
Program.




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Parking Facilities
  Expenditures         2013       2014      2015   2016   2017   Total

Construction/
Maintenance            500,000                                     500,000
Other                1,500,000                                   1,500,000

Total                2,000,000                                   2,000,000

   Funding            2013        2014      2015   2016   2017   Total
   Sources
Bond Issue
(Proposed)           2,000,000                                   2,000,000

Total                2,000,000                                   2,000,000




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
Parking Facilities
This project will provide for
land acquisition and clearing
for parking. Additional
grant/bond funds are
anticipated from the current
State budget, so the Proposed
Bond issue may be less than
what is contemplated in this
scenario.

Parking is needed in the Route
1 corridor to support economic
development.

Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13
SUMMARY OF SOURCES
       Source                                          Amount
       2008 Bond Issue                                  $203,291
       2010 Bond Issue                                  1,650,000
       Calendar year 2012 Bond Issue                    2,000,000
       Calendar year 2013 Bond Issue                    3,731,709
       CIP Fund Balance                                  701,350
       Lease                                             260,000
       PEG Fees                                           15,000
       Speed Camera Revenue                              420,000
       Dept of Housing & Community Development Grant      55,000
       Maryland Heritage Area Authority Grant             75,000
            Total                                      $9,111,350




Capital ImprovementInsurance through FY17
 OPEB and Health Projects FY13

More Related Content

Similar to Cip presentation fy13

Afghanistan0000Report000Sequence007
Afghanistan0000Report000Sequence007Afghanistan0000Report000Sequence007
Afghanistan0000Report000Sequence007Naseeb Muhammadi
 
ThinkTank Cities - Assignment 4 - Toronto Baseline Case
ThinkTank Cities - Assignment 4  - Toronto Baseline CaseThinkTank Cities - Assignment 4  - Toronto Baseline Case
ThinkTank Cities - Assignment 4 - Toronto Baseline CaseLeuphana Digital School
 
Financial appraisal
Financial appraisalFinancial appraisal
Financial appraisalDhwani Shah
 
Wkshp Item 3.C. Discussion of FY 17-21
Wkshp Item 3.C. Discussion of FY 17-21Wkshp Item 3.C. Discussion of FY 17-21
Wkshp Item 3.C. Discussion of FY 17-21CityofGalveston
 
Fy 2019 21 mid-cycle budget review 5-14-2020
Fy 2019 21 mid-cycle budget review 5-14-2020Fy 2019 21 mid-cycle budget review 5-14-2020
Fy 2019 21 mid-cycle budget review 5-14-2020E'ville Eye
 
Ranchi Financial Budget FY(2014-2015)
Ranchi Financial Budget FY(2014-2015)Ranchi Financial Budget FY(2014-2015)
Ranchi Financial Budget FY(2014-2015)Dhunki
 
Fus mid year update forum
Fus mid year update forumFus mid year update forum
Fus mid year update forumfusmadison
 
Financial and Operating Plan - A Tool for Strategic Municipal Investment and ...
Financial and Operating Plan - A Tool for Strategic Municipal Investment and ...Financial and Operating Plan - A Tool for Strategic Municipal Investment and ...
Financial and Operating Plan - A Tool for Strategic Municipal Investment and ...Ravikant Joshi
 
CAH CCM 09*.25.17 Item #4 ppt Budget Amendment
CAH CCM 09*.25.17 Item #4   ppt Budget AmendmentCAH CCM 09*.25.17 Item #4   ppt Budget Amendment
CAH CCM 09*.25.17 Item #4 ppt Budget AmendmentMarian Vargas Mendoza
 
2018 Capital Improvement Plan Regional Projects and Enterprise Funds
2018 Capital Improvement Plan Regional Projects and Enterprise Funds2018 Capital Improvement Plan Regional Projects and Enterprise Funds
2018 Capital Improvement Plan Regional Projects and Enterprise FundsDouglas Shontz
 
2017-2019 TIM Strategic Plan
2017-2019 TIM Strategic Plan2017-2019 TIM Strategic Plan
2017-2019 TIM Strategic PlanTIM RI
 
Vocera investordeck web january 2018 (1)
Vocera investordeck  web january 2018 (1)Vocera investordeck  web january 2018 (1)
Vocera investordeck web january 2018 (1)vocera2016ir
 
Investment on Fixed Assets PowerPoint Presentation Slides
Investment on Fixed Assets PowerPoint Presentation SlidesInvestment on Fixed Assets PowerPoint Presentation Slides
Investment on Fixed Assets PowerPoint Presentation SlidesSlideTeam
 
City of Milan Budget 2014/15 presentation
City of Milan Budget 2014/15 presentationCity of Milan Budget 2014/15 presentation
City of Milan Budget 2014/15 presentationCityofMilan
 
Summary Annual ReportOctober 2018Summary of Buller Distr.docx
Summary Annual ReportOctober 2018Summary of Buller Distr.docxSummary Annual ReportOctober 2018Summary of Buller Distr.docx
Summary Annual ReportOctober 2018Summary of Buller Distr.docxdeanmtaylor1545
 
Finances of Bhubaneswar Municipal Corporation-An Analysis and Assessment
Finances of Bhubaneswar Municipal Corporation-An Analysis and AssessmentFinances of Bhubaneswar Municipal Corporation-An Analysis and Assessment
Finances of Bhubaneswar Municipal Corporation-An Analysis and AssessmentBhabani Mahapatra
 

Similar to Cip presentation fy13 (20)

Afghanistan0000Report000Sequence007
Afghanistan0000Report000Sequence007Afghanistan0000Report000Sequence007
Afghanistan0000Report000Sequence007
 
ThinkTank Cities - Assignment 4 - Toronto Baseline Case
ThinkTank Cities - Assignment 4  - Toronto Baseline CaseThinkTank Cities - Assignment 4  - Toronto Baseline Case
ThinkTank Cities - Assignment 4 - Toronto Baseline Case
 
SAM 1.pdf
SAM 1.pdfSAM 1.pdf
SAM 1.pdf
 
Financial appraisal
Financial appraisalFinancial appraisal
Financial appraisal
 
Planning Document.pptx
Planning Document.pptxPlanning Document.pptx
Planning Document.pptx
 
Wkshp Item 3.C. Discussion of FY 17-21
Wkshp Item 3.C. Discussion of FY 17-21Wkshp Item 3.C. Discussion of FY 17-21
Wkshp Item 3.C. Discussion of FY 17-21
 
Fy 2019 21 mid-cycle budget review 5-14-2020
Fy 2019 21 mid-cycle budget review 5-14-2020Fy 2019 21 mid-cycle budget review 5-14-2020
Fy 2019 21 mid-cycle budget review 5-14-2020
 
Ranchi Financial Budget FY(2014-2015)
Ranchi Financial Budget FY(2014-2015)Ranchi Financial Budget FY(2014-2015)
Ranchi Financial Budget FY(2014-2015)
 
Town of Carrboro Financial Status and Budget Development
Town of Carrboro Financial Status and Budget DevelopmentTown of Carrboro Financial Status and Budget Development
Town of Carrboro Financial Status and Budget Development
 
Fus mid year update forum
Fus mid year update forumFus mid year update forum
Fus mid year update forum
 
Financial and Operating Plan - A Tool for Strategic Municipal Investment and ...
Financial and Operating Plan - A Tool for Strategic Municipal Investment and ...Financial and Operating Plan - A Tool for Strategic Municipal Investment and ...
Financial and Operating Plan - A Tool for Strategic Municipal Investment and ...
 
CAH CCM 09*.25.17 Item #4 ppt Budget Amendment
CAH CCM 09*.25.17 Item #4   ppt Budget AmendmentCAH CCM 09*.25.17 Item #4   ppt Budget Amendment
CAH CCM 09*.25.17 Item #4 ppt Budget Amendment
 
2018 Capital Improvement Plan Regional Projects and Enterprise Funds
2018 Capital Improvement Plan Regional Projects and Enterprise Funds2018 Capital Improvement Plan Regional Projects and Enterprise Funds
2018 Capital Improvement Plan Regional Projects and Enterprise Funds
 
2017-2019 TIM Strategic Plan
2017-2019 TIM Strategic Plan2017-2019 TIM Strategic Plan
2017-2019 TIM Strategic Plan
 
Vocera investordeck web january 2018 (1)
Vocera investordeck  web january 2018 (1)Vocera investordeck  web january 2018 (1)
Vocera investordeck web january 2018 (1)
 
Investment on Fixed Assets PowerPoint Presentation Slides
Investment on Fixed Assets PowerPoint Presentation SlidesInvestment on Fixed Assets PowerPoint Presentation Slides
Investment on Fixed Assets PowerPoint Presentation Slides
 
City of Milan Budget 2014/15 presentation
City of Milan Budget 2014/15 presentationCity of Milan Budget 2014/15 presentation
City of Milan Budget 2014/15 presentation
 
Summary Annual ReportOctober 2018Summary of Buller Distr.docx
Summary Annual ReportOctober 2018Summary of Buller Distr.docxSummary Annual ReportOctober 2018Summary of Buller Distr.docx
Summary Annual ReportOctober 2018Summary of Buller Distr.docx
 
Finances of Bhubaneswar Municipal Corporation-An Analysis and Assessment
Finances of Bhubaneswar Municipal Corporation-An Analysis and AssessmentFinances of Bhubaneswar Municipal Corporation-An Analysis and Assessment
Finances of Bhubaneswar Municipal Corporation-An Analysis and Assessment
 
FY18 Proposed Budget Overview
FY18 Proposed Budget OverviewFY18 Proposed Budget Overview
FY18 Proposed Budget Overview
 

Recently uploaded

M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 

Recently uploaded (20)

M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
 

Cip presentation fy13

  • 1. A Capital Improvement Projects Budget City Council Meeting April 23, 2012 OPEB and Health Insurance FY13 MAYOR'S BUDGET PRESENTATION 1 ‹#›
  • 2. Enterprise Resource Planning (ERP) Expenditures 2013 2014 2015 2016 2017 Total Other 200,000 200,000 Total 200,000 200,000 Funding 2013 2014 2015 2016 2017 Total Sources CIP Fund Balance 200,000 200,000 Total 200,000 200,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13 2
  • 3. Enterprise Resource Planning (ERP) ERP software integrates all departments and functions across the City into a single system. An ERP will consolidate information and allow easy access. Needs assessment is completed and RFP will be issued before the end of FY12. Increased license/maintenance fees are approximately $32,000/year. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 4. IT Upgrades & Replacements Expenditures 2013 2014 2015 2016 2017 Total Other 15,000 15,000 15,000 15,000 15,000 75,000 Total 15,000 15,000 15,000 15,000 15,000 75,000 Funding 2013 2014 2015 2016 2017 Total Sources CIP Fund Balance 15,000 15,000 15,000 15,000 15,000 75,000 Total 15,000 15,000 15,000 15,000 15,000 75,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 5. IT Upgrades & Replacements Covers routine replacement & upgrade of City’s servers and other infrastructure. The average server costs $5,000 to $7,000 and there are nine in use in the City. If remote servers are chosen instead, those costs will need to be incorporated into the operating budget. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 6. Vehicle Replacements Expenditures 2013 2014 2015 2016 2017 Total To be determined TBD TBD TBD TBD TBD Total Funding 2013 2014 2015 2016 2017 Total Sources To be determined TBD TBD TBD TBD TBD Total Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 7. Vehicle Replacements To be determined, following adoption of the Vehicle Replacement study. The only vehicle replacements in FY13 will be on an emergency basis. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 8. Radar/Lidar Speed Units Expenditures 2013 2014 2015 2016 2017 Total Equip/Vehicles /Furnishings 10,200 6,800 10,800 10,800 38,600 Total 10,200 6,800 10,800 10,800 38,600 Funding 2013 2014 2015 2016 2017 Total Sources General Fund Transfer 10,200 6,800 10,800 10,800 38,600 Total 10,200 6,800 10,800 10,800 38,600 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 9. Radar/Lidar Speed Enforcement Units Radar units currently in use are several years old. Newer, lighter units are available. With the implementation of the Highway Safety Office Data Driven Approaches to Crime & Traffic Safety program, our goal is to have units available at all times. Annual calibration fee = $80/unit. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 10. Mobile Data Terminals Expenditures 2013 2014 2015 2016 2017 Total Equip/Vehicles /Furnishings 14,450 14,750 15,025 15,325 15,650 75,200 Total 14,450 14,750 15,025 15,325 15,650 75,200 Funding 2013 2014 2015 2016 2017 Total Sources CIP Fund Balance 14,450 14,450 General Fund Transfer 14,750 15,025 15,325 15,650 60,750 Total 14,450 14,750 15,025 15,325 15,650 75,200 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 11. Mobile Data Terminals (MDTs) As the HCPD implements more IT-based projects, staff should have appropriate tools to utilize the technology. Funds will purchase CF31 Panasonic Toughbooks for officers. Projects cost increase of 2% per year. Note: No units will be purchased until a replacement schedule is developed. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 12. Enhancement of CCTV Program Expenditures 2013 2014 2015 2016 2017 Total Equip/Vehicles /Furnishings 40,000 40,000 Total 40,000 40,000 Funding 2013 2014 2015 2016 2017 Total Sources CIP Fund Balance 40,000 40,000 Total 40,000 40,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 13. Enhancement of CCTV Program The police have identified additional locations in the City that would benefit from a CCTV/Call-box. Funds would allow one full camera set-up, including installation costs, or two cameras and one call-box. One location is the new hiker- biker/Trolley Trail. Note: These will not be purchased until the current program is evaluated for effectiveness. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 14. K-9 Unit Expenditures 2013 2014 2015 2016 2017 Total Other 9,900 9,900 Total 9,900 9,900 Funding 2013 2014 2015 2016 2017 Total Sources CIP Fund Balance 9,900 9,900 Total 9,900 9,900 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 15. K-9 Unit This project is for a replacement K-9 Unit, including the dog, equipment kennel, cage, and cooling system. Aris has a spinal injury and must be retired. Because this is a replacement, there is no additional budget impact. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 16. Sidewalks Expenditures 2013 2014 2015 2016 2017 Total Construction/ Maintenance 50,000 209,000 50,000 50,000 50,000 409,000 Total 50,000 209,000 50,000 50,000 50,000 409,000 Funding Sources 2013 2014 2015 2016 2017 Total Bond Issue(2010) 50,000 50,000 Bond Issue (Proposed) 75,000 50,000 50,000 225,000 Reimbursement 25,000 25,000 State Board of Public Works 109,000 109,000 Total 50,000 209,000 50,000 50,000 50,000 409,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 17. Sidewalks This project is the annual program of sidewalk repair/installation. FY14 includes grant-funded MD208 East Side Extension and Route 1 repair, to be partially funded through other sources. Funds will be used in conjunction with Safe Routes to Schools and ADA programs. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 18. Roadway Improvements – General Expenditures 2013 2014 2015 2016 2017 Total Planning/Design 85,000 85,000 Construction/ Maintenance 420,000 375,000 795,000 Total 505,000 375,000 880,000 2013 2014 2015 2016 2017 Total Funding Sources Bond Issue (Proposed) 420,000 375,000 795,000 CIP Fund Balance 85,000 85,000 Total 505,000 375,000 880,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 19. Roadway Improvements Includes drainage/roadway improvements in areas remaining from City’s 5-year paving program. 2013: Complete work beginning in FY12 on west side, plus 42nd/Oliver Street after WSSC is finished. Design for Buchanan Street. 2014: Buchanan Street, et al. 2015: Determined by pavement study. (Anticipated 2Q FY13.) Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 20. University Hills Street Reconstruction Expenditures 2013 2014 2015 2016 2017 Total To be determined TBD TBD TBD TBD TBD Total Funding Sources 2013 2014 2015 2016 2017 Total To be determined TBD TBD TBD TBD TBD Total Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 21. University Hills Street Reconstruction Construction of drainage and roadway improvements in the University Hills neighborhood. Council has previously approved construction, pending funding of the project. Improvements in the neighborhood are necessary to improve the integrity of the streets and repair drainage problems. The project includes sidewalk installation, roadway realignment, and innovative stormwater management. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 22. Crittenden & 40th Reconstruction Expenditures 2013 2014 2015 2016 2017 Total Construction/ Maintenance 1,600,000 1,600,000 Total 1,600,000 1,600,000 Funding 2013 2014 2015 2016 2017 Total Sources Bond Issue (2010) 1,600,000 1,600,000 Total 1,600,000 1,600,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 23. Crittenden & 40th Reconstruction Improvements in roadway and drainage in the Crittenden/40th Place area. Project was started in FY09, and has been in design FY11/FY12. New state stormwater management requirements have delayed the project. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 24. ADA Improvements, City-wide Expenditures 2013 2014 2015 2016 2017 Total Construction/ Maintenance 100,000 100,000 100,000 100,000 100,000 500,000 Total 100,000 100,000 100,000 100,000 100,000 500,000 Funding 2013 2014 2015 2016 2017 Total Sources Bond Issue (Proposed) 100,000 100,000 100,000 100,000 100,000 500,000 Total 100,000 100,000 100,000 100,000 100,000 500,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 25. ADA Improvements, City-wide Areas of improvement will be identified through the City’s recently conducted ADA Transition plan, scheduled for Council adoption in April 2012. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 26. Arcade Building – 4318 Gallatin Street Expenditures 2013 2014 2015 2016 2017 Total Construction/ Maintenance 3,000,000 3,000,000 Total 3,000,000 3,000,000 2013 2014 2015 2016 2017 Total Funding Sources Bond Issue (Proposed) 2,925,000 2,295,000 State MHAA Grant 75,000 75,000 Total 3,000,000 3,000,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 27. Arcade Building – 4318 Gallatin Street Build-out of the Arcade at 4318 Gallatin Street to serve as a public function/amenities facility. Final costs are tied to the level of functionality and design options. Design will be complete by December 31, 2012. Additional grant funding may then be available. Annual operating costs are projected to increase by $152,100 in FY15 due to utilities, supplies, and maintenance. This may be offset by rental fees. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 28. Magruder Park Recreation Center Expenditures 2013 2014 2015 2016 2017 Total Construction/ Maintenance 285,000 285,000 Total 285,000 285,000 2013 2014 2015 2016 2017 Total Funding Sources CIP Fund Balance 285,000 285,000 Total 285,000 285,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 29. Magruder Park Recreation Center Based on the facilities study, the Rec Center will be among the last City facilities to be upgraded. To keep the facility safe and operational for the next few years, some investment must be made. The plan includes upgrading the exterior toilet rooms for ADA accessibility, improving shelving/lighting in garage/storage areas and capturing storage space to be used as a concession stand. Resurfacing/repairing brick may also be necessary. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 30. 3505 Hamilton Street Expenditures 2013 2014 2015 2016 2017 Total Planning/Design 420,000 500,000 920,000 Construction/ Maintenance 1,000,000 2,600,000 3,600,000 Total 420,000 1,500,000 2,600,000 4,520,000 Funding 2013 2014 2015 2016 2017 Total Sources Speed Camera Revenue 420,000 1,500,000 2,600,000 4,520,000 Total 420,000 1,500,000 2,600,000 4,520,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 31. 3505 Hamilton Street This project will install required improvements at 3505 Hamilton, based on the facilities study, ADA requirements, and Council 3505 determination of use. The building requires renovation to be usable. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 32. 4310 Gallatin Street Expenditures 2013 2014 2015 2016 2017 Total Planning/Design 350,000 350,000 700,000 Construction/ Maintenance 4,500,000 4,500,000 Total 350,000 350,000 4,500,000 5,200,000 Funding 2013 2014 2015 2016 2017 Total Sources Bond Issue (Proposed) 4,500,000 4,500,000 CIP Fund Balance 350,000 350,000 700,000 Total 350,000 350,000 4,500,000 5,200,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 33. 4310 Gallatin Street This represents a series of major repairs that have been scheduled & budget, including: • Upgrade of roof: $120,000 • HVAC replacement: $250,000 • Mansard roof repair: $106,000 • Installation of natural gas line: $40,000 • Conversion to natural gas $68,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 34. Vehicle Replacements – Solid Waste Expenditures 2013 2014 2015 2016 2017 Total Equip/Vehicles/ Furnishings 200,000 200,000 Total 200,000 200,000 Funding 2013 2014 2015 2016 2017 Total Sources Lease 200,000 200,000 Total 200,000 200,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 35. Vehicle Replacements – Solid Waste This is the replacement of SWV9860 , a 1998 GM refuse truck. Three trucks are used on a daily basis, with a fourth as a back-up, and a fifth expected to be sold as surplus. Repairs from FY10-FY12 (to date) have cost $49,059.84. Replacing this refuse truck will save on repair costs and keep equipment up-to-date with modern safety features. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 36. Vehicle Replacements – Maintenance Work Truck Expenditures 2013 2014 2015 2016 2017 Total Equip/Vehicles/ Furnishings 60,000 60,000 Total 60,000 60,000 Funding Sources 2013 2014 2015 2016 2017 Total Lease 60,000 60,000 Total 60,000 60,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 37. Vehicle Replacements – Maintenance Work Truck This is the replacement of an older unit MO9838, a 1998 Chevrolet Work Truck. Repairs from FY10-FY12 (to date) have cost $16,473.37. The cost includes a snow plow, salt spreader, light package, and radio. Replacing this work truck will save on repair costs and keep equipment up-to- date with modern safety features. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 38. King Park Retaining Wall Expenditures 2013 2014 2015 2016 2017 Total Construction/ Maintenance 32,000 32,000 Total 32,000 32,000 Funding 2013 2014 2015 2016 2017 Total Sources CIP Fund Balance 32,000 32,000 Total 32,000 32,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 39. King Park Retaining Wall The retaining wall at King Park is crumbling. We do not have an original construction date, but it appears to many years past its replacement date. Replacement will require removal of small trees that are growing into the wall, as well as replacing the chain link fence, currently a magnet for growth of invasive species. This will prevent emergency repairs and impacts to neighbors’ yards. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 40. Melrose Access Trail Expenditures 2013 2014 2015 2016 2017 Total Construction/ Maintenance 100,000 100,000 Total 100,000 100,000 Funding 2013 2014 2015 2016 2017 Total Sources CIP Fund Balance 100,000 100,000 Total 100,000 100,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 41. Melrose Access Trail Construction of a 300 linear foot ADA accessible trail head from Crittenden Street to 41st Street. Based upon DER’s project design and permitting schedule it appears that no work will occur until FY13. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 42. Solar Display Board Expenditures 2013 2014 2015 2016 2017 Total Equip/Vehicles/ Furnishings 17,500 17,500 Total 17,500 17,500 Funding 2013 2014 2015 2016 2017 Total Sources Lease 17,500 17,500 Total 17,500 17,500 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 43. Solar Display Board This is the purchase of a 3-line solar powered LED display message board, typically trailer-mounted and displayed to advise of road conditions, etc. The City rents these signs for large special events and it would be utilized for a wide range of traffic and safety reasons. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 44. Cable TV Upgrades Expenditures 2013 2014 2015 2016 2017 Total Equip/Vehicles/ Furnishings 15,000 15,000 15,000 15,000 15,000 75,000 Total 15,000 15,000 15,000 15,000 15,000 75,000 Funding 2013 2014 2015 2016 2017 Total Sources P.E.G. Fees 15,000 15,000 15,000 15,000 15,000 75,000 Total 15,000 15,000 15,000 15,000 15,000 75,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 45. Cable TV Upgrades The City’s cable channel is an underutilized asset. These upgrades will move us towards implementing the capacity to run additional programming. In addition to routine upgrades, projects will include the ability to film remotely, improving storage and content, etc. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 46. Field Renovations Expenditures 2013 2014 2015 2016 2017 Total Engineering 50,000 50,000 100,000 Construction/ Maintenance 400,000 300,000 300,000 1,000,000 Total 400,000 50,000 300,000 50,000 300,000 1,100,000 Funding 2013 2014 2015 2016 2017 Total Sources Bond Issue (2008) 203,291 203,291 Bond Issue (Proposed) 196,709 300,000 300,000 796,709 CIP Fund Balance 50,000 50,000 100,000 Total 400,000 50,000 300,000 50,000 300,000 1,100,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 47. Field Renovations The City has a longstanding goal of renovating the playing fields and surfaces at Magruder Park. The project will provide drainage and irrigation plans and construction services for the soccer and football fields at Magruder Park, and eventually the soccer field at Melrose Park. Correct drainage will allow for more playing time, safer conditions, and reduced maintenance costs. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 48. Court Resurfacing Expenditures 2013 2014 2015 2016 2017 Total Construction/ Maintenance 20,000 20,000 Total 20,000 20,000 Funding 2013 2014 2015 2016 2017 Total Sources CIP Fund Balance 20,000 20,000 Total 20,000 20,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 49. Court Resurfacing This project provides for resurfacing of the Magruder Park tennis courts. It will prolong their life and make them safer to use. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 50. Parking Meters Expenditures 2013 2014 2015 2016 2017 Total Equip/Vehicles/ Furnishings 90,000 90,000 Total 90,000 90,000 Funding 2013 2014 2015 2016 2017 Total Sources Bond Issue (Proposed) 90,000 90,000 Total 90,000 90,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 51. Parking Meters This project is for the purchase and installation of new parking meters in locations to be considered and approved by Council. Areas being considered include Ager Road and Editors Park Drive. Because they will be smart meters, we will incur monthly charges for communication fees. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 52. Bike & Pedestrian Enhancements Expenditures 2013 2014 2015 2016 2017 Total Equip/Vehicles/ Furnishings 55,000 55,000 Total 55,000 55,000 Funding 2013 2014 2015 2016 2017 Total Sources State DHCD Grant 55,000 55,000 Total 55,000 55,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 53. Bike & Pedestrian Enhancements This project is the creation of bike lanes and the installation of bike racks. The scope is limited to funding awarded through the State of Maryland Department of Housing and Community Development Sustainability Grant Program. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 54. Parking Facilities Expenditures 2013 2014 2015 2016 2017 Total Construction/ Maintenance 500,000 500,000 Other 1,500,000 1,500,000 Total 2,000,000 2,000,000 Funding 2013 2014 2015 2016 2017 Total Sources Bond Issue (Proposed) 2,000,000 2,000,000 Total 2,000,000 2,000,000 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 55. Parking Facilities This project will provide for land acquisition and clearing for parking. Additional grant/bond funds are anticipated from the current State budget, so the Proposed Bond issue may be less than what is contemplated in this scenario. Parking is needed in the Route 1 corridor to support economic development. Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13
  • 56. SUMMARY OF SOURCES Source Amount 2008 Bond Issue $203,291 2010 Bond Issue 1,650,000 Calendar year 2012 Bond Issue 2,000,000 Calendar year 2013 Bond Issue 3,731,709 CIP Fund Balance 701,350 Lease 260,000 PEG Fees 15,000 Speed Camera Revenue 420,000 Dept of Housing & Community Development Grant 55,000 Maryland Heritage Area Authority Grant 75,000 Total $9,111,350 Capital ImprovementInsurance through FY17 OPEB and Health Projects FY13