McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.1
Three Classic Applications of LP
• Product Mix at Ponderosa Industrial
– Considered limited resources, and determined optimal mix of plywood
products.
– Increased overall profitability of company by 20%.
• Personnel Scheduling at United Airlines
– Designed work schedules for all employees at a location to meet service
requirements most efficiently.
– Saved $6 million annually.
• Planning Supply, Distribution, and Marketing at Citgo Petroleum
Corporation
– The SDM system uses LP to coordinate the supply, distribution, and marketing
of each of Citgo’s major products throughout the United States.
– The resulting reduction in inventory added $14 million annually to Citgo’s
profits.
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.2
Wyndor Glass Co. Product Mix Problem
• Wyndor has developed the following new products: An 8-foot glass door
with aluminum framing (unit profit = $300); a 4-foot by 6-foot double-
hung, wood-framed window (unit profit = $500).
• The company has three plants: Plant 1 (capacity: 4 hrs available)
produces aluminum frames and hardware; Plant 2 (capacity: 12 hrs
available) produces wood frames; Plant 3 (18 hrs available) produces glass
and assembles the windows and doors.
• The 8-foot glass door requires some of the production capacity in Plants 1
and 3, but not Plant 2; The 4-foot wood-framed window needs only Plants
2 and 3. Technological coefficients (hrs/unit): Plant 1: 1 hr/doors, 0
hrs/windows; Plant 2: 0 hrs/doors, 2 hrs/windows; Plant 3: 3 hrs/doors, 2
hrs/windows.
• Questions: What should be the product mix?
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.3
Algebraic Model for Wyndor Glass Co.
Let D = the number of doors to produce
W = the number of windows to produce
Maximize P = $300D + $500W
subject to
D ≤ 4
2W ≤ 12
3D + 2W ≤ 18
and
D ≥ 0, W ≥ 0.
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.4
Graph of Feasible Region
0 2 4 6 8
8
6
4
10
2
Feasible
region
Production rate for doors
D
W
2 W =12
D = 4
3 D + 2 W = 18
Production rate for windows
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.5
Finding the Optimal Solution
0 2 4 6 8
8
6
4
2
Production rate
for windows
Production rate for doors
Feasible
region
(2, 6)
Optimalsolution
10
W
D
P =3600= 300D + 500W
P =3000= 300D + 500W
P =1500= 300D + 500W
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.6
Summary of the Graphical Method
• Draw the constraint boundary line for each constraint. Use the origin (or
any point not on the line) to determine which side of the line is permitted
by the constraint.
• Find the feasible region by determining where all constraints are satisfied
simultaneously.
• Determine the slope of one objective function line. All other objective
function lines will have the same slope.
• Move a straight edge with this slope through the feasible region in the
direction of improving values of the objective function. Stop at the last
instant that the straight edge still passes through a point in the feasible
region. This line given by the straight edge is the optimal objective
function line.
• A feasible point on the optimal objective function line is an optimal
solution.
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.7
Identifying the Target Cell and Changing Cells
• Choose the “Solver” from the Tools menu.
• Select the cell you wish to optimize in the “Set Target Cell” window.
• Choose “Max” or “Min” depending on whether you want to maximize or minimize
the target cell.
• Enter all the changing cells in the “By Changing Cells” window.
Doors Windows
Unit Profit $300 $500
Hours Hours
Used Available
Plant 1 1 0 1 <= 4
Plant 2 0 2 2 <= 12
Plant 3 3 2 5 <= 18
Doors Windows Total Profit
Hours Used Per Unit Produced
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.8
Adding Constraints
• To begin entering constraints, click the “Add” button to the right of the
constraints window.
• Fill in the entries in the resulting Add Constraint dialogue box.
Doors Windows
Unit Profit $300 $500
Hours Hours
Used Available
Plant 1 1 0 1 <= 4
Plant 2 0 2 2 <= 12
Plant 3 3 2 5 <= 18
Doors Windows Total Profit
Units Produced 1 1 $800
Hours Used Per Unit Produced
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.9
The Complete Solver Dialogue Box
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.10
Some Important Options
• Click on the “Options” button, and click in both the “Assume Linear Model” and
the “Assume Non-Negative” box.
– “Assume Linear Model” tells the Solver that this is a linear programming model.
– “Assume Non-Negative” adds non-negativity constraints to all the changing cells.
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.11
The Solver Results Dialogue Box
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.12
The Optimal Solution
Doors Windows
Unit Profit $300 $500
Hours Hours
Used Available
Plant 1 1 0 2 <= 4
Plant 2 0 2 12 <= 12
Plant 3 3 2 18 <= 18
Doors Windows Total Profit
Units Produced 2 6 $3,600
Hours Used Per Unit Produced
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.13
The Profit & Gambit Co.
• Management has decided to undertake a major advertising campaign that will
focus on the following three key products:
– A spray prewash stain remover.
– A liquid laundry detergent.
– A powder laundry detergent.
• The campaign will use both television and print media
• The general goal is to increase sales of these products.
• Management has set the following goals for the campaign:
– Sales of the stain remover should increase by at least 3%.
– Sales of the liquid detergent should increase by at least 18%.
– Sales of the powder detergent should increase by at least 4%.
Question: how much should they advertise in each medium to meet the sales
goals at a minimum total cost?
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.14
Profit & Gambit Co. Spreadsheet Model
3
4
5
6
7
8
9
10
11
12
13
14
B C D E F G
Television Print Media
Unit Cost ($millions) 1 2
Increased Minimum
Sales Increase
Stain Remover 0% 1% 3% >= 3%
Liquid Detergent 3% 2% 18% >= 18%
Powder Detergent -1% 4% 8% >= 4%
Total Cost
Television Print Media ($millions)
Advertising Units 4 3 10
Increase in Sales per Unit of Advertising
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.15
Algebraic Model for Profit & Gambit
Let TV = the number of units of advertising on television
PM = the number of units of advertising in the print media
Minimize Cost = TV + 2PM (in millions of dollars)
subject to
Stain remover increased sales: PM ≥ 3
Liquid detergent increased sales: 3TV + 2PM ≥ 18
Powder detergent increased sales: –TV + 4PM ≥ 4
and
TV ≥ 0, PM ≥ 0.
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.16
Applying the Graphical Method
8
6
4
2
0 2 4 6 8 1 0
-2
-4
Amount of TV advertising
Feasible
region
10
3 TV + 2 PM = 18
PM = 3
PM
TV
-TV + 4 PM = 4
Amount of print media advertising
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.17
The Optimal Solution
Amount of TV advertising
Feasible
region
0 5 10 15
10
4
(4,3)
optimal
solution
Cost = 15 = TV + 2 PM
Cost = 10 = TV + 2 PM
TV
PM
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.18
A Production Problem
Weekly supply of raw materials:
8 Small Bricks 6 Large Bricks
Products:
Table
Profit = $20 / Table
Chair
Profit = $15 / Chair
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.19
Linear Programming
• Linear programming uses a mathematical model to find the best allocation of
scarce resources to various activities so as to maximize profit or minimize
cost.
Let T = Number of tables to produce
C = Number of chairs to produce
Maximize Profit = ($20)T + ($15)C
subject to
2T + C ≤ 6 large bricks
2T + 2C ≤ 8 small bricks
and
T ≥ 0, C ≥ 0.
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.20
Graphical Representation
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.21
Components of a Linear Program
• Data Cells
• Changing Cells (“Decision Variables”)
• Target Cell (“Objective Function”)
• Constraints
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.22
When is a Spreadsheet Model Linear?
• All equations (output cells) must be of the form
= ax + by + cz + …
where a, b, c are constants (data cells) and x, y, z are changing cells.
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.23
Why Use Linear Programming?
• Linear programs are easy (efficient) to solve
• The best (optimal) solution is guaranteed to be found (if it exists)
• Useful sensitivity analysis information is generated
• Many problems are essentially linear
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.24
Developing a Spreadsheet Model
• Step #1: Data Cells
– Enter all of the data for the problem on the spreadsheet.
– Make consistent use of rows and columns.
– It is a good idea to color code these “data cells” (e.g., light blue).
3
4
5
6
7
8
B C D E F G
Tables Chairs
Profit $20.00 $15.00
Available
Large Bricks 2 1 6
Small Bricks 2 2 8
Bill of Materials
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.25
Developing a Spreadsheet Model
• Step #2: Changing Cells
– Add a cell in the spreadsheet for every decision that needs to be made.
– If you don’t have any particular initial values, just enter 0 in each.
– It is a good idea to color code these “changing cells” (e.g., yellow with border).
3
4
5
6
7
8
9
10
11
B C D E F G
Tables Chairs
Profit $20.00 $15.00
Available
Large Bricks 2 1 6
Small Bricks 2 2 8
Tables Chairs
Production Quantity: 0 0
Bill of Materials
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.26
Developing a Spreadsheet Model
• Step #3: Target Cell
– Develop an equation that defines the objective of the model.
– Typically this equation involves the data cells and the changing cells in order to
determine a quantity of interest (e.g., total profit or total cost).
– It is a good idea to color code this cell (e.g., orange with heavy border).
10
11
G
Total Profit
=SUMPRODUCT(C4:D4,C11:D11)
3
4
5
6
7
8
9
10
11
B C D E F G
Tables Chairs
Profit $20.00 $15.00
Available
Large Bricks 2 1 6
Small Bricks 2 2 8
Tables Chairs Total Profit
Production Quantity: 1 0 $20.00
Bill of Materials
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.27
Developing a Spreadsheet Model
• Step #4: Constraints
– For any resource that is restricted, calculate the amount of that resource used in a
cell on the spreadsheet (an output cell).
– Define the constraint in three consecutive cells. For example, if Quantity A ≤
Quantity B, put these three items (Quantity A, ≤, Quantity B) in consecutive cells.
– Note the use of relative and absolute addressing to make it easy to copy formulas
in column E.
3
4
5
6
7
8
9
10
11
B C D E F G
Tables Chairs
Profit $20.00 $15.00
Total Used Available
Large Bricks 2 1 3 <= 6
Small Bricks 2 2 4 <= 8
Tables Chairs Total Profit
Production Quantity: 1 1 $35.00
Bill of Materials
6
7
8
E
Total Used
=SUMPRODUCT(C7:D7,$C$11:$D$11)
=SUMPRODUCT(C8:D8,$C$11:$D$11)
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.28
Defining the Target Cell
• Choose the “Solver” from the Tools menu.
• Select the cell you wish to optimize in the “Set Target Cell” window.
• Choose “Max” or “Min” depending on whether you want to maximize or
minimize the target cell.
3
4
5
6
7
8
9
10
11
B C D E F G
Tables Chairs
Profit $20.00 $15.00
Total Used Available
Large Bricks 2 1 3 <= 6
Small Bricks 2 2 4 <= 8
Tables Chairs Total Profit
Production Quantity: 1 1 $35.00
Bill of Materials
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.29
Identifying the Changing Cells
• Enter all the changing cells in the “By Changing Cells” window.
– You may either drag the cursor across the cells or type the addresses.
– If there are multiple sets of changing cells, separate them by typing a comma.
3
4
5
6
7
8
9
10
11
B C D E F G
Tables Chairs
Profit $20.00 $15.00
Total Used Available
Large Bricks 2 1 3 <= 6
Small Bricks 2 2 4 <= 8
Tables Chairs Total Profit
Production Quantity: 1 1 $35.00
Bill of Materials
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.30
Adding Constraints
• To begin entering constraints, click the “Add” button to the right of the
constraints window.
• Fill in the entries in the resulting Add Constraint dialogue box.
3
4
5
6
7
8
9
10
11
B C D E F G
Tables Chairs
Profit $20.00 $15.00
Total Used Available
Large Bricks 2 1 3 <= 6
Small Bricks 2 2 4 <= 8
Tables Chairs Total Profit
Production Quantity: 1 1 $35.00
Bill of Materials
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.31
Some Important Options
• Click on the “Options” button, and click in both the “Assume Linear Model”
and the “Assume Non-Negative” box.
– “Assume Linear Model” tells the Solver that this is a linear programming model.
– “Assume Non-Negative” adds nonnegativity constraints to all the changing cells.
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.32
The Solution
• After clicking “Solve”, you will receive one of four messages:
– “Solver found a solution. All constraints and optimality conditions are satisfied.”
– “Set cell values did not converge.”
– “Solver could not find a feasible solution.”
– “Conditions for Assume Linear Model are not satisfied.”
3
4
5
6
7
8
9
10
11
B C D E F G
Tables Chairs
Profit $20.00 $15.00
Total Used Available
Large Bricks 2 1 6 <= 6
Small Bricks 2 2 8 <= 8
Tables Chairs Total Profit
Production Quantity: 2 2 $70.00
Bill of Materials
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.33
Properties of Linear Programming Solutions
• An optimal solution must lie on the boundary of the feasible region.
• There are exactly four possible outcomes of linear programming:
– A unique optimal solution is found.
– An infinite number of optimal solutions exist.
– No feasible solutions exist.
– The objective function is unbounded (there is no optimal solution).
• If an LP model has one optimal solution, it must be at a corner point.
• If an LP model has many optimal solutions, at least two of these optimal
solutions are at corner points.
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.34
Example: (Multiple Optimal Solutions)
Minimize Z = 6x1 + 4x2
subject to
x1 ≤ 4
2x2 ≤ 12
3x1 + 2x2 ≤ 18
and
x1 ≥ 0, x2 ≥ 0.
1 2 3 4 5 6 7 8 9 10
1
2
3
4
5
6
7
8
9
10
x2
x1
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.35
Example: (No Feasible Solution)
Maximize Z = 3x1 + 5x2
subject to
x1 ≥ 5
x2 ≥ 4
3x1 + 2x2 ≤ 18
and
x1 ≥ 0, x2 ≥ 0.
1 2 3 4 5 6 7 8 9 10
1
2
3
4
5
6
7
8
9
10
x2
x1
McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003
2.36
Example: (Unbounded Solution)
Maximize Z = 5x1 + 12x2
subject to
x1 ≤ 5
2x1 –x2 ≤ 2
and
x1 ≥ 0, x2 ≥ 0.
1 2 3 4 5 6 7 8 9 10
1
2
3
4
5
6
7
8
9
10
x2
x1

More Related Content

Similar to Optimal Product Mix for Wyndor Glass Co

CHAPTER TWO - OPERATIONS RESEARCH (2).pptx
CHAPTER TWO - OPERATIONS RESEARCH (2).pptxCHAPTER TWO - OPERATIONS RESEARCH (2).pptx
CHAPTER TWO - OPERATIONS RESEARCH (2).pptxAynetuTerefe2
 
appendixbnotes_2.ppt
appendixbnotes_2.pptappendixbnotes_2.ppt
appendixbnotes_2.pptEllamae79
 
2 linear programming
2 linear programming2 linear programming
2 linear programmingDronak Sahu
 
Optimizing profit with linear programming model
Optimizing profit with linear programming modelOptimizing profit with linear programming model
Optimizing profit with linear programming modelAmit Deshmukh
 
chapter 2 revised.pptx
chapter 2 revised.pptxchapter 2 revised.pptx
chapter 2 revised.pptxDejeneDay
 
Bba 3274 qm week 10 integer programming
Bba 3274 qm week 10 integer programmingBba 3274 qm week 10 integer programming
Bba 3274 qm week 10 integer programmingStephen Ong
 
3 Matrix Docmnt Technology Mfg Housing Pkge
3 Matrix Docmnt Technology Mfg Housing Pkge3 Matrix Docmnt Technology Mfg Housing Pkge
3 Matrix Docmnt Technology Mfg Housing PkgeLiving Modular
 
Linear programming
Linear programming Linear programming
Linear programming sadha sivam
 
Gimmethingnao. GImme gimme gimme, just gimme gimme
Gimmethingnao. GImme gimme gimme, just gimme gimmeGimmethingnao. GImme gimme gimme, just gimme gimme
Gimmethingnao. GImme gimme gimme, just gimme gimmeJkopp2
 
LPP FORMULATION 21 -22.pptx
LPP FORMULATION  21 -22.pptxLPP FORMULATION  21 -22.pptx
LPP FORMULATION 21 -22.pptxkiran513883
 
Dye House Projectonly
Dye House ProjectonlyDye House Projectonly
Dye House ProjectonlySanjaya Khs
 
american connector company and djc
american connector company and djcamerican connector company and djc
american connector company and djcRajat Aggarwal
 
BigData @ comScore
BigData @ comScoreBigData @ comScore
BigData @ comScoreeaiti
 

Similar to Optimal Product Mix for Wyndor Glass Co (20)

CHAPTER TWO - OPERATIONS RESEARCH (2).pptx
CHAPTER TWO - OPERATIONS RESEARCH (2).pptxCHAPTER TWO - OPERATIONS RESEARCH (2).pptx
CHAPTER TWO - OPERATIONS RESEARCH (2).pptx
 
Cognos Drill through for the ipad
Cognos Drill through for the ipadCognos Drill through for the ipad
Cognos Drill through for the ipad
 
EEE 452 Lec 02.ppt
EEE 452 Lec 02.pptEEE 452 Lec 02.ppt
EEE 452 Lec 02.ppt
 
appendixbnotes_2.ppt
appendixbnotes_2.pptappendixbnotes_2.ppt
appendixbnotes_2.ppt
 
Lp applications
Lp applicationsLp applications
Lp applications
 
2 linear programming
2 linear programming2 linear programming
2 linear programming
 
chap012.ppt
chap012.pptchap012.ppt
chap012.ppt
 
Optimizing profit with linear programming model
Optimizing profit with linear programming modelOptimizing profit with linear programming model
Optimizing profit with linear programming model
 
Six sigma
Six sigmaSix sigma
Six sigma
 
chapter 2 revised.pptx
chapter 2 revised.pptxchapter 2 revised.pptx
chapter 2 revised.pptx
 
Bba 3274 qm week 10 integer programming
Bba 3274 qm week 10 integer programmingBba 3274 qm week 10 integer programming
Bba 3274 qm week 10 integer programming
 
3 Matrix Docmnt Technology Mfg Housing Pkge
3 Matrix Docmnt Technology Mfg Housing Pkge3 Matrix Docmnt Technology Mfg Housing Pkge
3 Matrix Docmnt Technology Mfg Housing Pkge
 
Linear programming
Linear programming Linear programming
Linear programming
 
Gimmethingnao. GImme gimme gimme, just gimme gimme
Gimmethingnao. GImme gimme gimme, just gimme gimmeGimmethingnao. GImme gimme gimme, just gimme gimme
Gimmethingnao. GImme gimme gimme, just gimme gimme
 
Analytics in the Manufacturing industry
Analytics in the Manufacturing industryAnalytics in the Manufacturing industry
Analytics in the Manufacturing industry
 
LPP FORMULATION 21 -22.pptx
LPP FORMULATION  21 -22.pptxLPP FORMULATION  21 -22.pptx
LPP FORMULATION 21 -22.pptx
 
Dye House Projectonly
Dye House ProjectonlyDye House Projectonly
Dye House Projectonly
 
american connector company and djc
american connector company and djcamerican connector company and djc
american connector company and djc
 
BigData @ comScore
BigData @ comScoreBigData @ comScore
BigData @ comScore
 
Or ch2 (2)
Or ch2 (2)Or ch2 (2)
Or ch2 (2)
 

More from NehaSardana9

SCM Case- Barilla Spa section operations case study
SCM Case- Barilla  Spa section operations case studySCM Case- Barilla  Spa section operations case study
SCM Case- Barilla Spa section operations case studyNehaSardana9
 
Moduel 2 Readings.pptx
Moduel 2 Readings.pptxModuel 2 Readings.pptx
Moduel 2 Readings.pptxNehaSardana9
 
financial instruments.pptx
financial instruments.pptxfinancial instruments.pptx
financial instruments.pptxNehaSardana9
 
Session 3-4 CB.pptx
Session 3-4 CB.pptxSession 3-4 CB.pptx
Session 3-4 CB.pptxNehaSardana9
 
73549-financial analysis powerpoint.pptx
73549-financial analysis powerpoint.pptx73549-financial analysis powerpoint.pptx
73549-financial analysis powerpoint.pptxNehaSardana9
 
9781292145150_pp07.ppt
9781292145150_pp07.ppt9781292145150_pp07.ppt
9781292145150_pp07.pptNehaSardana9
 

More from NehaSardana9 (6)

SCM Case- Barilla Spa section operations case study
SCM Case- Barilla  Spa section operations case studySCM Case- Barilla  Spa section operations case study
SCM Case- Barilla Spa section operations case study
 
Moduel 2 Readings.pptx
Moduel 2 Readings.pptxModuel 2 Readings.pptx
Moduel 2 Readings.pptx
 
financial instruments.pptx
financial instruments.pptxfinancial instruments.pptx
financial instruments.pptx
 
Session 3-4 CB.pptx
Session 3-4 CB.pptxSession 3-4 CB.pptx
Session 3-4 CB.pptx
 
73549-financial analysis powerpoint.pptx
73549-financial analysis powerpoint.pptx73549-financial analysis powerpoint.pptx
73549-financial analysis powerpoint.pptx
 
9781292145150_pp07.ppt
9781292145150_pp07.ppt9781292145150_pp07.ppt
9781292145150_pp07.ppt
 

Recently uploaded

VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130Suhani Kapoor
 
FESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfFESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfMarinCaroMartnezBerg
 
Carero dropshipping via API with DroFx.pptx
Carero dropshipping via API with DroFx.pptxCarero dropshipping via API with DroFx.pptx
Carero dropshipping via API with DroFx.pptxolyaivanovalion
 
Call Girls In Mahipalpur O9654467111 Escorts Service
Call Girls In Mahipalpur O9654467111  Escorts ServiceCall Girls In Mahipalpur O9654467111  Escorts Service
Call Girls In Mahipalpur O9654467111 Escorts ServiceSapana Sha
 
Generative AI on Enterprise Cloud with NiFi and Milvus
Generative AI on Enterprise Cloud with NiFi and MilvusGenerative AI on Enterprise Cloud with NiFi and Milvus
Generative AI on Enterprise Cloud with NiFi and MilvusTimothy Spann
 
Unveiling Insights: The Role of a Data Analyst
Unveiling Insights: The Role of a Data AnalystUnveiling Insights: The Role of a Data Analyst
Unveiling Insights: The Role of a Data AnalystSamantha Rae Coolbeth
 
CebaBaby dropshipping via API with DroFX.pptx
CebaBaby dropshipping via API with DroFX.pptxCebaBaby dropshipping via API with DroFX.pptx
CebaBaby dropshipping via API with DroFX.pptxolyaivanovalion
 
BigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptxBigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptxolyaivanovalion
 
Ravak dropshipping via API with DroFx.pptx
Ravak dropshipping via API with DroFx.pptxRavak dropshipping via API with DroFx.pptx
Ravak dropshipping via API with DroFx.pptxolyaivanovalion
 
Log Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptxLog Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptxJohnnyPlasten
 
Beautiful Sapna Vip Call Girls Hauz Khas 9711199012 Call /Whatsapps
Beautiful Sapna Vip  Call Girls Hauz Khas 9711199012 Call /WhatsappsBeautiful Sapna Vip  Call Girls Hauz Khas 9711199012 Call /Whatsapps
Beautiful Sapna Vip Call Girls Hauz Khas 9711199012 Call /Whatsappssapnasaifi408
 
Halmar dropshipping via API with DroFx
Halmar  dropshipping  via API with DroFxHalmar  dropshipping  via API with DroFx
Halmar dropshipping via API with DroFxolyaivanovalion
 
April 2024 - Crypto Market Report's Analysis
April 2024 - Crypto Market Report's AnalysisApril 2024 - Crypto Market Report's Analysis
April 2024 - Crypto Market Report's Analysismanisha194592
 
B2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docxB2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docxStephen266013
 
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...Suhani Kapoor
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingNeil Barnes
 
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAl Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAroojKhan71
 
04242024_CCC TUG_Joins and Relationships
04242024_CCC TUG_Joins and Relationships04242024_CCC TUG_Joins and Relationships
04242024_CCC TUG_Joins and Relationshipsccctableauusergroup
 
Dubai Call Girls Wifey O52&786472 Call Girls Dubai
Dubai Call Girls Wifey O52&786472 Call Girls DubaiDubai Call Girls Wifey O52&786472 Call Girls Dubai
Dubai Call Girls Wifey O52&786472 Call Girls Dubaihf8803863
 

Recently uploaded (20)

VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
 
FESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfFESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdf
 
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in Kishangarh
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in  KishangarhDelhi 99530 vip 56974 Genuine Escort Service Call Girls in  Kishangarh
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in Kishangarh
 
Carero dropshipping via API with DroFx.pptx
Carero dropshipping via API with DroFx.pptxCarero dropshipping via API with DroFx.pptx
Carero dropshipping via API with DroFx.pptx
 
Call Girls In Mahipalpur O9654467111 Escorts Service
Call Girls In Mahipalpur O9654467111  Escorts ServiceCall Girls In Mahipalpur O9654467111  Escorts Service
Call Girls In Mahipalpur O9654467111 Escorts Service
 
Generative AI on Enterprise Cloud with NiFi and Milvus
Generative AI on Enterprise Cloud with NiFi and MilvusGenerative AI on Enterprise Cloud with NiFi and Milvus
Generative AI on Enterprise Cloud with NiFi and Milvus
 
Unveiling Insights: The Role of a Data Analyst
Unveiling Insights: The Role of a Data AnalystUnveiling Insights: The Role of a Data Analyst
Unveiling Insights: The Role of a Data Analyst
 
CebaBaby dropshipping via API with DroFX.pptx
CebaBaby dropshipping via API with DroFX.pptxCebaBaby dropshipping via API with DroFX.pptx
CebaBaby dropshipping via API with DroFX.pptx
 
BigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptxBigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptx
 
Ravak dropshipping via API with DroFx.pptx
Ravak dropshipping via API with DroFx.pptxRavak dropshipping via API with DroFx.pptx
Ravak dropshipping via API with DroFx.pptx
 
Log Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptxLog Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptx
 
Beautiful Sapna Vip Call Girls Hauz Khas 9711199012 Call /Whatsapps
Beautiful Sapna Vip  Call Girls Hauz Khas 9711199012 Call /WhatsappsBeautiful Sapna Vip  Call Girls Hauz Khas 9711199012 Call /Whatsapps
Beautiful Sapna Vip Call Girls Hauz Khas 9711199012 Call /Whatsapps
 
Halmar dropshipping via API with DroFx
Halmar  dropshipping  via API with DroFxHalmar  dropshipping  via API with DroFx
Halmar dropshipping via API with DroFx
 
April 2024 - Crypto Market Report's Analysis
April 2024 - Crypto Market Report's AnalysisApril 2024 - Crypto Market Report's Analysis
April 2024 - Crypto Market Report's Analysis
 
B2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docxB2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docx
 
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data Storytelling
 
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAl Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
 
04242024_CCC TUG_Joins and Relationships
04242024_CCC TUG_Joins and Relationships04242024_CCC TUG_Joins and Relationships
04242024_CCC TUG_Joins and Relationships
 
Dubai Call Girls Wifey O52&786472 Call Girls Dubai
Dubai Call Girls Wifey O52&786472 Call Girls DubaiDubai Call Girls Wifey O52&786472 Call Girls Dubai
Dubai Call Girls Wifey O52&786472 Call Girls Dubai
 

Optimal Product Mix for Wyndor Glass Co

  • 1. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.1 Three Classic Applications of LP • Product Mix at Ponderosa Industrial – Considered limited resources, and determined optimal mix of plywood products. – Increased overall profitability of company by 20%. • Personnel Scheduling at United Airlines – Designed work schedules for all employees at a location to meet service requirements most efficiently. – Saved $6 million annually. • Planning Supply, Distribution, and Marketing at Citgo Petroleum Corporation – The SDM system uses LP to coordinate the supply, distribution, and marketing of each of Citgo’s major products throughout the United States. – The resulting reduction in inventory added $14 million annually to Citgo’s profits.
  • 2. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.2 Wyndor Glass Co. Product Mix Problem • Wyndor has developed the following new products: An 8-foot glass door with aluminum framing (unit profit = $300); a 4-foot by 6-foot double- hung, wood-framed window (unit profit = $500). • The company has three plants: Plant 1 (capacity: 4 hrs available) produces aluminum frames and hardware; Plant 2 (capacity: 12 hrs available) produces wood frames; Plant 3 (18 hrs available) produces glass and assembles the windows and doors. • The 8-foot glass door requires some of the production capacity in Plants 1 and 3, but not Plant 2; The 4-foot wood-framed window needs only Plants 2 and 3. Technological coefficients (hrs/unit): Plant 1: 1 hr/doors, 0 hrs/windows; Plant 2: 0 hrs/doors, 2 hrs/windows; Plant 3: 3 hrs/doors, 2 hrs/windows. • Questions: What should be the product mix?
  • 3. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.3 Algebraic Model for Wyndor Glass Co. Let D = the number of doors to produce W = the number of windows to produce Maximize P = $300D + $500W subject to D ≤ 4 2W ≤ 12 3D + 2W ≤ 18 and D ≥ 0, W ≥ 0.
  • 4. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.4 Graph of Feasible Region 0 2 4 6 8 8 6 4 10 2 Feasible region Production rate for doors D W 2 W =12 D = 4 3 D + 2 W = 18 Production rate for windows
  • 5. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.5 Finding the Optimal Solution 0 2 4 6 8 8 6 4 2 Production rate for windows Production rate for doors Feasible region (2, 6) Optimalsolution 10 W D P =3600= 300D + 500W P =3000= 300D + 500W P =1500= 300D + 500W
  • 6. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.6 Summary of the Graphical Method • Draw the constraint boundary line for each constraint. Use the origin (or any point not on the line) to determine which side of the line is permitted by the constraint. • Find the feasible region by determining where all constraints are satisfied simultaneously. • Determine the slope of one objective function line. All other objective function lines will have the same slope. • Move a straight edge with this slope through the feasible region in the direction of improving values of the objective function. Stop at the last instant that the straight edge still passes through a point in the feasible region. This line given by the straight edge is the optimal objective function line. • A feasible point on the optimal objective function line is an optimal solution.
  • 7. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.7 Identifying the Target Cell and Changing Cells • Choose the “Solver” from the Tools menu. • Select the cell you wish to optimize in the “Set Target Cell” window. • Choose “Max” or “Min” depending on whether you want to maximize or minimize the target cell. • Enter all the changing cells in the “By Changing Cells” window. Doors Windows Unit Profit $300 $500 Hours Hours Used Available Plant 1 1 0 1 <= 4 Plant 2 0 2 2 <= 12 Plant 3 3 2 5 <= 18 Doors Windows Total Profit Hours Used Per Unit Produced
  • 8. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.8 Adding Constraints • To begin entering constraints, click the “Add” button to the right of the constraints window. • Fill in the entries in the resulting Add Constraint dialogue box. Doors Windows Unit Profit $300 $500 Hours Hours Used Available Plant 1 1 0 1 <= 4 Plant 2 0 2 2 <= 12 Plant 3 3 2 5 <= 18 Doors Windows Total Profit Units Produced 1 1 $800 Hours Used Per Unit Produced
  • 9. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.9 The Complete Solver Dialogue Box
  • 10. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.10 Some Important Options • Click on the “Options” button, and click in both the “Assume Linear Model” and the “Assume Non-Negative” box. – “Assume Linear Model” tells the Solver that this is a linear programming model. – “Assume Non-Negative” adds non-negativity constraints to all the changing cells.
  • 11. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.11 The Solver Results Dialogue Box
  • 12. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.12 The Optimal Solution Doors Windows Unit Profit $300 $500 Hours Hours Used Available Plant 1 1 0 2 <= 4 Plant 2 0 2 12 <= 12 Plant 3 3 2 18 <= 18 Doors Windows Total Profit Units Produced 2 6 $3,600 Hours Used Per Unit Produced
  • 13. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.13 The Profit & Gambit Co. • Management has decided to undertake a major advertising campaign that will focus on the following three key products: – A spray prewash stain remover. – A liquid laundry detergent. – A powder laundry detergent. • The campaign will use both television and print media • The general goal is to increase sales of these products. • Management has set the following goals for the campaign: – Sales of the stain remover should increase by at least 3%. – Sales of the liquid detergent should increase by at least 18%. – Sales of the powder detergent should increase by at least 4%. Question: how much should they advertise in each medium to meet the sales goals at a minimum total cost?
  • 14. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.14 Profit & Gambit Co. Spreadsheet Model 3 4 5 6 7 8 9 10 11 12 13 14 B C D E F G Television Print Media Unit Cost ($millions) 1 2 Increased Minimum Sales Increase Stain Remover 0% 1% 3% >= 3% Liquid Detergent 3% 2% 18% >= 18% Powder Detergent -1% 4% 8% >= 4% Total Cost Television Print Media ($millions) Advertising Units 4 3 10 Increase in Sales per Unit of Advertising
  • 15. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.15 Algebraic Model for Profit & Gambit Let TV = the number of units of advertising on television PM = the number of units of advertising in the print media Minimize Cost = TV + 2PM (in millions of dollars) subject to Stain remover increased sales: PM ≥ 3 Liquid detergent increased sales: 3TV + 2PM ≥ 18 Powder detergent increased sales: –TV + 4PM ≥ 4 and TV ≥ 0, PM ≥ 0.
  • 16. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.16 Applying the Graphical Method 8 6 4 2 0 2 4 6 8 1 0 -2 -4 Amount of TV advertising Feasible region 10 3 TV + 2 PM = 18 PM = 3 PM TV -TV + 4 PM = 4 Amount of print media advertising
  • 17. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.17 The Optimal Solution Amount of TV advertising Feasible region 0 5 10 15 10 4 (4,3) optimal solution Cost = 15 = TV + 2 PM Cost = 10 = TV + 2 PM TV PM
  • 18. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.18 A Production Problem Weekly supply of raw materials: 8 Small Bricks 6 Large Bricks Products: Table Profit = $20 / Table Chair Profit = $15 / Chair
  • 19. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.19 Linear Programming • Linear programming uses a mathematical model to find the best allocation of scarce resources to various activities so as to maximize profit or minimize cost. Let T = Number of tables to produce C = Number of chairs to produce Maximize Profit = ($20)T + ($15)C subject to 2T + C ≤ 6 large bricks 2T + 2C ≤ 8 small bricks and T ≥ 0, C ≥ 0.
  • 20. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.20 Graphical Representation
  • 21. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.21 Components of a Linear Program • Data Cells • Changing Cells (“Decision Variables”) • Target Cell (“Objective Function”) • Constraints
  • 22. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.22 When is a Spreadsheet Model Linear? • All equations (output cells) must be of the form = ax + by + cz + … where a, b, c are constants (data cells) and x, y, z are changing cells.
  • 23. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.23 Why Use Linear Programming? • Linear programs are easy (efficient) to solve • The best (optimal) solution is guaranteed to be found (if it exists) • Useful sensitivity analysis information is generated • Many problems are essentially linear
  • 24. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.24 Developing a Spreadsheet Model • Step #1: Data Cells – Enter all of the data for the problem on the spreadsheet. – Make consistent use of rows and columns. – It is a good idea to color code these “data cells” (e.g., light blue). 3 4 5 6 7 8 B C D E F G Tables Chairs Profit $20.00 $15.00 Available Large Bricks 2 1 6 Small Bricks 2 2 8 Bill of Materials
  • 25. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.25 Developing a Spreadsheet Model • Step #2: Changing Cells – Add a cell in the spreadsheet for every decision that needs to be made. – If you don’t have any particular initial values, just enter 0 in each. – It is a good idea to color code these “changing cells” (e.g., yellow with border). 3 4 5 6 7 8 9 10 11 B C D E F G Tables Chairs Profit $20.00 $15.00 Available Large Bricks 2 1 6 Small Bricks 2 2 8 Tables Chairs Production Quantity: 0 0 Bill of Materials
  • 26. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.26 Developing a Spreadsheet Model • Step #3: Target Cell – Develop an equation that defines the objective of the model. – Typically this equation involves the data cells and the changing cells in order to determine a quantity of interest (e.g., total profit or total cost). – It is a good idea to color code this cell (e.g., orange with heavy border). 10 11 G Total Profit =SUMPRODUCT(C4:D4,C11:D11) 3 4 5 6 7 8 9 10 11 B C D E F G Tables Chairs Profit $20.00 $15.00 Available Large Bricks 2 1 6 Small Bricks 2 2 8 Tables Chairs Total Profit Production Quantity: 1 0 $20.00 Bill of Materials
  • 27. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.27 Developing a Spreadsheet Model • Step #4: Constraints – For any resource that is restricted, calculate the amount of that resource used in a cell on the spreadsheet (an output cell). – Define the constraint in three consecutive cells. For example, if Quantity A ≤ Quantity B, put these three items (Quantity A, ≤, Quantity B) in consecutive cells. – Note the use of relative and absolute addressing to make it easy to copy formulas in column E. 3 4 5 6 7 8 9 10 11 B C D E F G Tables Chairs Profit $20.00 $15.00 Total Used Available Large Bricks 2 1 3 <= 6 Small Bricks 2 2 4 <= 8 Tables Chairs Total Profit Production Quantity: 1 1 $35.00 Bill of Materials 6 7 8 E Total Used =SUMPRODUCT(C7:D7,$C$11:$D$11) =SUMPRODUCT(C8:D8,$C$11:$D$11)
  • 28. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.28 Defining the Target Cell • Choose the “Solver” from the Tools menu. • Select the cell you wish to optimize in the “Set Target Cell” window. • Choose “Max” or “Min” depending on whether you want to maximize or minimize the target cell. 3 4 5 6 7 8 9 10 11 B C D E F G Tables Chairs Profit $20.00 $15.00 Total Used Available Large Bricks 2 1 3 <= 6 Small Bricks 2 2 4 <= 8 Tables Chairs Total Profit Production Quantity: 1 1 $35.00 Bill of Materials
  • 29. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.29 Identifying the Changing Cells • Enter all the changing cells in the “By Changing Cells” window. – You may either drag the cursor across the cells or type the addresses. – If there are multiple sets of changing cells, separate them by typing a comma. 3 4 5 6 7 8 9 10 11 B C D E F G Tables Chairs Profit $20.00 $15.00 Total Used Available Large Bricks 2 1 3 <= 6 Small Bricks 2 2 4 <= 8 Tables Chairs Total Profit Production Quantity: 1 1 $35.00 Bill of Materials
  • 30. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.30 Adding Constraints • To begin entering constraints, click the “Add” button to the right of the constraints window. • Fill in the entries in the resulting Add Constraint dialogue box. 3 4 5 6 7 8 9 10 11 B C D E F G Tables Chairs Profit $20.00 $15.00 Total Used Available Large Bricks 2 1 3 <= 6 Small Bricks 2 2 4 <= 8 Tables Chairs Total Profit Production Quantity: 1 1 $35.00 Bill of Materials
  • 31. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.31 Some Important Options • Click on the “Options” button, and click in both the “Assume Linear Model” and the “Assume Non-Negative” box. – “Assume Linear Model” tells the Solver that this is a linear programming model. – “Assume Non-Negative” adds nonnegativity constraints to all the changing cells.
  • 32. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.32 The Solution • After clicking “Solve”, you will receive one of four messages: – “Solver found a solution. All constraints and optimality conditions are satisfied.” – “Set cell values did not converge.” – “Solver could not find a feasible solution.” – “Conditions for Assume Linear Model are not satisfied.” 3 4 5 6 7 8 9 10 11 B C D E F G Tables Chairs Profit $20.00 $15.00 Total Used Available Large Bricks 2 1 6 <= 6 Small Bricks 2 2 8 <= 8 Tables Chairs Total Profit Production Quantity: 2 2 $70.00 Bill of Materials
  • 33. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.33 Properties of Linear Programming Solutions • An optimal solution must lie on the boundary of the feasible region. • There are exactly four possible outcomes of linear programming: – A unique optimal solution is found. – An infinite number of optimal solutions exist. – No feasible solutions exist. – The objective function is unbounded (there is no optimal solution). • If an LP model has one optimal solution, it must be at a corner point. • If an LP model has many optimal solutions, at least two of these optimal solutions are at corner points.
  • 34. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.34 Example: (Multiple Optimal Solutions) Minimize Z = 6x1 + 4x2 subject to x1 ≤ 4 2x2 ≤ 12 3x1 + 2x2 ≤ 18 and x1 ≥ 0, x2 ≥ 0. 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 x2 x1
  • 35. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.35 Example: (No Feasible Solution) Maximize Z = 3x1 + 5x2 subject to x1 ≥ 5 x2 ≥ 4 3x1 + 2x2 ≤ 18 and x1 ≥ 0, x2 ≥ 0. 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 x2 x1
  • 36. McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2003 2.36 Example: (Unbounded Solution) Maximize Z = 5x1 + 12x2 subject to x1 ≤ 5 2x1 –x2 ≤ 2 and x1 ≥ 0, x2 ≥ 0. 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 x2 x1