PROCUREMENT RECORD IN THE MONTH OF JANUARY 2013.
    CONTRACT                                                                                                                     MDA's                REVIEW PROJECT
S/N TITLE                      PROJECT DESCRIPTION                                   RECOMMENDED CONTRACTORS                     ESTIMATE             COST                         SAVINGS.
    1   Construction           Construction of the new Governor's                    Inerkel Nig. Ltd.                            2,027,495,857.45              2,027,495,857.45            -
                               Office at Secretariat Complex.
    2   Consultant             Appiontment Estate surveying consulting firms for     Bureau of lands.                                 2,500,000.00                    2,500,000         _
                               the Ekiti State University land.
    3   Acquisation of         Acquisition of land for the establishment of Ekiti-   Bureau of lands.                                   929,538.00                   929,538.00         _
        land                   Odua farmer's academy at Isan-Ekiti.
    4   Renovations            Renovation of some schools in Ekiti State             _                                               58,000,200.00                58,000,200.00         _
    5   Reports                Report of the ministerial board of survey on the      _                                              152,000,000.00               152,000,000.00         _
                               disposal of unserviceable items

6       Calendar & Diaries     The production of year 2013 calendar and diaries      Eminent communication Ltd.                      82,040,650.00                75,000,000.00    7,040,650.00
    7   Examination            Joint mock examination for public secondary           Ministry of education.                           8,870,000.00                  8,288,000.00    582,000.00
                               school
                               TOTAL                                                                                              2,331,836,245.45              2,324,213,595.45    7,622,650.00


                               SUMMARY
         The sum of N2,331,836,245.45 is the Cost of Projects and Services that passed through BPP for vetting and certification in the month of Januart,2013
        The sum of N2,324,213,595.45 is the vetted cost of the projects and services by the BPP in the month of January,2013
        The sum of N7,622,650.00 is the amount saved by BPP.




                                                                                            www.ekitistate.gov.ng

More Related Content

Viewers also liked

Every Little Thing Individuals Know Around gestion de stock weo Is Completely...
Every Little Thing Individuals Know Around gestion de stock weo Is Completely...Every Little Thing Individuals Know Around gestion de stock weo Is Completely...
Every Little Thing Individuals Know Around gestion de stock weo Is Completely...porch6rifle
 
Toni Naumoski - Recommendation Letter WD
Toni Naumoski - Recommendation Letter WDToni Naumoski - Recommendation Letter WD
Toni Naumoski - Recommendation Letter WDToni Naumoski
 
Maria cardenas 7°B
Maria cardenas 7°BMaria cardenas 7°B
Maria cardenas 7°Bmariwuas
 
WWD Award 2014 November
WWD Award 2014 NovemberWWD Award 2014 November
WWD Award 2014 NovemberCynthia Morgan
 
La habitación 18 (continuación)
La habitación 18 (continuación)La habitación 18 (continuación)
La habitación 18 (continuación)Ana Soto
 
СИСТЕМА АВТОМАТИЗАЦИИ ОБРАБОТКИ ДОКУМЕНТОВ
СИСТЕМА АВТОМАТИЗАЦИИ ОБРАБОТКИ ДОКУМЕНТОВСИСТЕМА АВТОМАТИЗАЦИИ ОБРАБОТКИ ДОКУМЕНТОВ
СИСТЕМА АВТОМАТИЗАЦИИ ОБРАБОТКИ ДОКУМЕНТОВПавел Ермолович
 
Horarios de carros
Horarios de carrosHorarios de carros
Horarios de carrospointserv
 
Big Data. Big Gifts. A Crash Course on Social Donor Management for Higher Edu...
Big Data. Big Gifts. A Crash Course on Social Donor Management for Higher Edu...Big Data. Big Gifts. A Crash Course on Social Donor Management for Higher Edu...
Big Data. Big Gifts. A Crash Course on Social Donor Management for Higher Edu...HubSpot
 
Grafico diario del eurostoxx 50 para el 27 02 2013
Grafico diario del eurostoxx 50 para el 27 02 2013Grafico diario del eurostoxx 50 para el 27 02 2013
Grafico diario del eurostoxx 50 para el 27 02 2013Experiencia Trading
 
The Apprentice Italia, edizione 2 - Analisi quantitativa e qualitativa Social TV
The Apprentice Italia, edizione 2 - Analisi quantitativa e qualitativa Social TVThe Apprentice Italia, edizione 2 - Analisi quantitativa e qualitativa Social TV
The Apprentice Italia, edizione 2 - Analisi quantitativa e qualitativa Social TVAntonella Libera
 

Viewers also liked (14)

Every Little Thing Individuals Know Around gestion de stock weo Is Completely...
Every Little Thing Individuals Know Around gestion de stock weo Is Completely...Every Little Thing Individuals Know Around gestion de stock weo Is Completely...
Every Little Thing Individuals Know Around gestion de stock weo Is Completely...
 
Toni Naumoski - Recommendation Letter WD
Toni Naumoski - Recommendation Letter WDToni Naumoski - Recommendation Letter WD
Toni Naumoski - Recommendation Letter WD
 
Maria cardenas 7°B
Maria cardenas 7°BMaria cardenas 7°B
Maria cardenas 7°B
 
WWD Award 2014 November
WWD Award 2014 NovemberWWD Award 2014 November
WWD Award 2014 November
 
Ie 2090
Ie 2090Ie 2090
Ie 2090
 
La habitación 18 (continuación)
La habitación 18 (continuación)La habitación 18 (continuación)
La habitación 18 (continuación)
 
Tabla de multiplicar
Tabla de multiplicarTabla de multiplicar
Tabla de multiplicar
 
СИСТЕМА АВТОМАТИЗАЦИИ ОБРАБОТКИ ДОКУМЕНТОВ
СИСТЕМА АВТОМАТИЗАЦИИ ОБРАБОТКИ ДОКУМЕНТОВСИСТЕМА АВТОМАТИЗАЦИИ ОБРАБОТКИ ДОКУМЕНТОВ
СИСТЕМА АВТОМАТИЗАЦИИ ОБРАБОТКИ ДОКУМЕНТОВ
 
Horarios de carros
Horarios de carrosHorarios de carros
Horarios de carros
 
Ie 1914
Ie 1914Ie 1914
Ie 1914
 
Big Data. Big Gifts. A Crash Course on Social Donor Management for Higher Edu...
Big Data. Big Gifts. A Crash Course on Social Donor Management for Higher Edu...Big Data. Big Gifts. A Crash Course on Social Donor Management for Higher Edu...
Big Data. Big Gifts. A Crash Course on Social Donor Management for Higher Edu...
 
77749428
7774942877749428
77749428
 
Grafico diario del eurostoxx 50 para el 27 02 2013
Grafico diario del eurostoxx 50 para el 27 02 2013Grafico diario del eurostoxx 50 para el 27 02 2013
Grafico diario del eurostoxx 50 para el 27 02 2013
 
The Apprentice Italia, edizione 2 - Analisi quantitativa e qualitativa Social TV
The Apprentice Italia, edizione 2 - Analisi quantitativa e qualitativa Social TVThe Apprentice Italia, edizione 2 - Analisi quantitativa e qualitativa Social TV
The Apprentice Italia, edizione 2 - Analisi quantitativa e qualitativa Social TV
 

Similar to BPP Vetted Contracts For January 2013

Sambia vuosiraportti 2010
Sambia vuosiraportti 2010Sambia vuosiraportti 2010
Sambia vuosiraportti 2010SYL
 
ACCT 221 Final Exam Sum13 1 Final Examination Princ.docx
ACCT 221 Final Exam Sum13  1 Final Examination Princ.docxACCT 221 Final Exam Sum13  1 Final Examination Princ.docx
ACCT 221 Final Exam Sum13 1 Final Examination Princ.docxannetnash8266
 
Annual Report, REAP
Annual Report, REAPAnnual Report, REAP
Annual Report, REAPJC Martel
 

Similar to BPP Vetted Contracts For January 2013 (20)

BPP Vetted Contracts For March 2013
BPP Vetted Contracts For March 2013BPP Vetted Contracts For March 2013
BPP Vetted Contracts For March 2013
 
BPP Vetted Contracts For December 2012
BPP Vetted Contracts For December 2012BPP Vetted Contracts For December 2012
BPP Vetted Contracts For December 2012
 
BPP Vetted Contracts For February 2013
BPP Vetted Contracts For February 2013BPP Vetted Contracts For February 2013
BPP Vetted Contracts For February 2013
 
BPP vetted contracts for feb. 2012
BPP vetted contracts for feb. 2012BPP vetted contracts for feb. 2012
BPP vetted contracts for feb. 2012
 
BPP Vetted Contracts For October 2012
BPP Vetted Contracts For October 2012BPP Vetted Contracts For October 2012
BPP Vetted Contracts For October 2012
 
Bpp Vetted Contracts For May 2012
Bpp Vetted Contracts For May 2012Bpp Vetted Contracts For May 2012
Bpp Vetted Contracts For May 2012
 
BPP Vetted Contracts For September 2012
BPP Vetted Contracts For September 2012BPP Vetted Contracts For September 2012
BPP Vetted Contracts For September 2012
 
BPP Vetted Contracts For November 2012
BPP Vetted Contracts For November 2012BPP Vetted Contracts For November 2012
BPP Vetted Contracts For November 2012
 
Bpp vetted contracts for july 2012
Bpp vetted contracts for july 2012Bpp vetted contracts for july 2012
Bpp vetted contracts for july 2012
 
Sambia vuosiraportti 2010
Sambia vuosiraportti 2010Sambia vuosiraportti 2010
Sambia vuosiraportti 2010
 
BPP vetted contracts for jan. 2012
BPP vetted contracts for jan. 2012BPP vetted contracts for jan. 2012
BPP vetted contracts for jan. 2012
 
BPP Vetted Contracts For April 2012
BPP Vetted Contracts For April 2012BPP Vetted Contracts For April 2012
BPP Vetted Contracts For April 2012
 
BPP vetted contracts for Mar. 2012
BPP vetted contracts for Mar. 2012BPP vetted contracts for Mar. 2012
BPP vetted contracts for Mar. 2012
 
BPP vetted contracts for the month of April 2012
BPP vetted contracts for the month of April 2012BPP vetted contracts for the month of April 2012
BPP vetted contracts for the month of April 2012
 
2012 budget
2012 budget2012 budget
2012 budget
 
ACCT 221 Final Exam Sum13 1 Final Examination Princ.docx
ACCT 221 Final Exam Sum13  1 Final Examination Princ.docxACCT 221 Final Exam Sum13  1 Final Examination Princ.docx
ACCT 221 Final Exam Sum13 1 Final Examination Princ.docx
 
Ark scorecard v3 addendum
Ark scorecard v3 addendumArk scorecard v3 addendum
Ark scorecard v3 addendum
 
Bpp Vetted Contracts For June 2012
Bpp Vetted Contracts For June 2012Bpp Vetted Contracts For June 2012
Bpp Vetted Contracts For June 2012
 
2012 Supplementary Appropriation Law
2012 Supplementary Appropriation Law2012 Supplementary Appropriation Law
2012 Supplementary Appropriation Law
 
Annual Report, REAP
Annual Report, REAPAnnual Report, REAP
Annual Report, REAP
 

More from Government of Ekiti State, Nigeria

2015 Budget Speech Delivered by the Executive Governor of Ekiti State
2015 Budget Speech Delivered by the Executive Governor of Ekiti State2015 Budget Speech Delivered by the Executive Governor of Ekiti State
2015 Budget Speech Delivered by the Executive Governor of Ekiti StateGovernment of Ekiti State, Nigeria
 
Ekit State Budget 2015 Analysis by the Ministry of Budget and Economic Planning.
Ekit State Budget 2015 Analysis by the Ministry of Budget and Economic Planning.Ekit State Budget 2015 Analysis by the Ministry of Budget and Economic Planning.
Ekit State Budget 2015 Analysis by the Ministry of Budget and Economic Planning.Government of Ekiti State, Nigeria
 
Ekiti State College of Technical and Commercial Agriculture Academic & Non-Ac...
Ekiti State College of Technical and Commercial Agriculture Academic & Non-Ac...Ekiti State College of Technical and Commercial Agriculture Academic & Non-Ac...
Ekiti State College of Technical and Commercial Agriculture Academic & Non-Ac...Government of Ekiti State, Nigeria
 

More from Government of Ekiti State, Nigeria (20)

Ekiti state 2016 approved budget details
Ekiti state 2016 approved budget detailsEkiti state 2016 approved budget details
Ekiti state 2016 approved budget details
 
Ekiti state 2016 approved budget details
Ekiti state 2016 approved budget detailsEkiti state 2016 approved budget details
Ekiti state 2016 approved budget details
 
Ekiti state 2016 approved budget details
Ekiti state 2016 approved budget detailsEkiti state 2016 approved budget details
Ekiti state 2016 approved budget details
 
Ekiti State 2016 Approved Budget Details
Ekiti State 2016 Approved Budget DetailsEkiti State 2016 Approved Budget Details
Ekiti State 2016 Approved Budget Details
 
Ekiti State Public Procurement Law
Ekiti State Public Procurement LawEkiti State Public Procurement Law
Ekiti State Public Procurement Law
 
Scholarship for Post Graduate Ng
Scholarship for Post Graduate NgScholarship for Post Graduate Ng
Scholarship for Post Graduate Ng
 
Scholarship for Overseas Students
Scholarship for Overseas StudentsScholarship for Overseas Students
Scholarship for Overseas Students
 
Scholarsrhip for Undergraduate
Scholarsrhip for UndergraduateScholarsrhip for Undergraduate
Scholarsrhip for Undergraduate
 
Physically Challenged
Physically ChallengedPhysically Challenged
Physically Challenged
 
Busary form 1
Busary form 1Busary form 1
Busary form 1
 
2015 Budget Speech Delivered by the Executive Governor of Ekiti State
2015 Budget Speech Delivered by the Executive Governor of Ekiti State2015 Budget Speech Delivered by the Executive Governor of Ekiti State
2015 Budget Speech Delivered by the Executive Governor of Ekiti State
 
Ekit State Budget 2015 Analysis by the Ministry of Budget and Economic Planning.
Ekit State Budget 2015 Analysis by the Ministry of Budget and Economic Planning.Ekit State Budget 2015 Analysis by the Ministry of Budget and Economic Planning.
Ekit State Budget 2015 Analysis by the Ministry of Budget and Economic Planning.
 
Bursary Award 2012/2013
Bursary Award 2012/2013Bursary Award 2012/2013
Bursary Award 2012/2013
 
Effective service delivery
Effective service deliveryEffective service delivery
Effective service delivery
 
Prof. ade ajayi ad. approved
Prof. ade ajayi ad. approvedProf. ade ajayi ad. approved
Prof. ade ajayi ad. approved
 
Ekiti State College of Technical and Commercial Agriculture Academic & Non-Ac...
Ekiti State College of Technical and Commercial Agriculture Academic & Non-Ac...Ekiti State College of Technical and Commercial Agriculture Academic & Non-Ac...
Ekiti State College of Technical and Commercial Agriculture Academic & Non-Ac...
 
Champion Newspapers' Governor of the year
Champion Newspapers' Governor of the yearChampion Newspapers' Governor of the year
Champion Newspapers' Governor of the year
 
1st Year Memorial Service of Mrs Funmilayo Adunni OLAYINKA
1st Year Memorial Service of Mrs Funmilayo Adunni OLAYINKA1st Year Memorial Service of Mrs Funmilayo Adunni OLAYINKA
1st Year Memorial Service of Mrs Funmilayo Adunni OLAYINKA
 
One Year After...Moremi Lives on
One Year After...Moremi Lives onOne Year After...Moremi Lives on
One Year After...Moremi Lives on
 
Overview of 2014 Budget
Overview of 2014 BudgetOverview of 2014 Budget
Overview of 2014 Budget
 

BPP Vetted Contracts For January 2013

  • 1. PROCUREMENT RECORD IN THE MONTH OF JANUARY 2013. CONTRACT MDA's REVIEW PROJECT S/N TITLE PROJECT DESCRIPTION RECOMMENDED CONTRACTORS ESTIMATE COST SAVINGS. 1 Construction Construction of the new Governor's Inerkel Nig. Ltd. 2,027,495,857.45 2,027,495,857.45 - Office at Secretariat Complex. 2 Consultant Appiontment Estate surveying consulting firms for Bureau of lands. 2,500,000.00 2,500,000 _ the Ekiti State University land. 3 Acquisation of Acquisition of land for the establishment of Ekiti- Bureau of lands. 929,538.00 929,538.00 _ land Odua farmer's academy at Isan-Ekiti. 4 Renovations Renovation of some schools in Ekiti State _ 58,000,200.00 58,000,200.00 _ 5 Reports Report of the ministerial board of survey on the _ 152,000,000.00 152,000,000.00 _ disposal of unserviceable items 6 Calendar & Diaries The production of year 2013 calendar and diaries Eminent communication Ltd. 82,040,650.00 75,000,000.00 7,040,650.00 7 Examination Joint mock examination for public secondary Ministry of education. 8,870,000.00 8,288,000.00 582,000.00 school TOTAL 2,331,836,245.45 2,324,213,595.45 7,622,650.00 SUMMARY The sum of N2,331,836,245.45 is the Cost of Projects and Services that passed through BPP for vetting and certification in the month of Januart,2013 The sum of N2,324,213,595.45 is the vetted cost of the projects and services by the BPP in the month of January,2013 The sum of N7,622,650.00 is the amount saved by BPP. www.ekitistate.gov.ng