The document outlines a time schedule for a drainage canal construction project in Bengkalis Regency. It details the work of constructing a new 600 meter secondary canal on Jl. Pramuka in Air Putih Village over 16 periods. The bulk of work is structure-related at 33% of the total weight, with preliminary work at 3.15% and earthworks at 2.39%. The schedule charts the planned and cumulative weight completions periodically from July to December 2008.