TIME SCHEDULLE
KEGIATAN : PEMBANGUNAN SALURAN DRAINASE / GORONG - GORONG KECAMATAN BENGKALIS
PEKERJAAN : PEMBANGUNAN SALURAN BARU SEKUNDER HJ. SALAMAH JL. PRAMUKA DESA AIR PUTIH 600 M'
LOKASI : KEC. BENGKALIS
BOBOT
No. URAIAN PEKERJAAN %
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
UMUM 0.76 0.33 0.33 0.33
0.33 0.33
PEKERJAAN TANAH 2.39 2.02 2.02
1.7 1.70
STRUKTUR - 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91
33.0
JUMLAH BOBOT 3.15
BOBOT RENCANA 0 0.3 2.4 2.0 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9 0.3
BOBOT KOMULATIEF 0.3 2.7 5 13 21 28 36 44 52 60 68 76 84 92 100 100
BOBOT REALISASI 13.2 36.8 36.8 36.8
Bengkalis, 22 Juli 2008
Di Periksa Oleh: Di Buat Oleh:
PEJABAT PELAKSANA KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
TEKNIS KEGIATAN (PPTK) CV. LINGKAR BUANA KONSULTAN KOP SEJAHTERA MANDIRI
FIRDAUS, Sst SUHAIMI, AMD M. FAUZI, Amd
Nip. 420011593 Supervision Engineering Manager
W A K T U P E L A K S A N A N
PROG
BULAN I BULAN II BULAN III BULAN IV
0
100
50
0
RES

Bobot

  • 1.
    TIME SCHEDULLE KEGIATAN :PEMBANGUNAN SALURAN DRAINASE / GORONG - GORONG KECAMATAN BENGKALIS PEKERJAAN : PEMBANGUNAN SALURAN BARU SEKUNDER HJ. SALAMAH JL. PRAMUKA DESA AIR PUTIH 600 M' LOKASI : KEC. BENGKALIS BOBOT No. URAIAN PEKERJAAN % 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 UMUM 0.76 0.33 0.33 0.33 0.33 0.33 PEKERJAAN TANAH 2.39 2.02 2.02 1.7 1.70 STRUKTUR - 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91 33.0 JUMLAH BOBOT 3.15 BOBOT RENCANA 0 0.3 2.4 2.0 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9 0.3 BOBOT KOMULATIEF 0.3 2.7 5 13 21 28 36 44 52 60 68 76 84 92 100 100 BOBOT REALISASI 13.2 36.8 36.8 36.8 Bengkalis, 22 Juli 2008 Di Periksa Oleh: Di Buat Oleh: PEJABAT PELAKSANA KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA TEKNIS KEGIATAN (PPTK) CV. LINGKAR BUANA KONSULTAN KOP SEJAHTERA MANDIRI FIRDAUS, Sst SUHAIMI, AMD M. FAUZI, Amd Nip. 420011593 Supervision Engineering Manager W A K T U P E L A K S A N A N PROG BULAN I BULAN II BULAN III BULAN IV 0
  • 2.