The document discusses using earned value analysis to examine why a project was delayed and over budget. It finds that the technical infrastructure plan took 9 days longer than scheduled, while software customization finished 13 days earlier. It suggests finding the causes of delays in technical infrastructure and improving process efficiency by sharing information and resources. Adding extra team members may not speed things up without changing how the team works, so delaying the project may be preferable to additions.